GP Template DPAR1
GP Template DPAR1
GP Template DPAR1
ITEM
Schedule a DPAR meeting with Supplier(s) and all key stakeholders.
Send the DPAR Agenda to the Suppliers.
Review with the Supplier(s) the relevant questions in each tab.
Save the DPAR file and all related documentation in the appropriate project location in Sharepoint.
Follow up with Suppliers as needed; a follow-up meeting may be required.
NOTE:
Camso and the Supplier must have the drawings available.
Camso will decide which parts require a DPAR.
We will go over each part identified in the DPAR.
Supplier(s) must review all items in advance of the meeting to be prepared for the DPAR.
COVERSHEET
Date:
Program:
Supplier:
Product Engineer
SPQD Engineer
Facility QA
Design, Process and Assembly Review
Action List
Date:
Program:
Supplier:
AGENDA
1-Design review
2-Process review
3-Quality control Requirements review (gaging)
4-Packaging review
5-Procurement
1. DESIGN REVIEW
ITEM WHO DATE REQUESTED STATUS
Does the supplier have the latest revision level Project Buyer - Camso
Review geometric dimensioning and tolerancing for finished and, if applicable, raw parts Engineering - Supplier
Review sub-system to acknowledge assembly relation and appearance importancy of different surface. (One example shows in Engineering - Supplier
below)
Identify cost reduction opportunities or potential cost impacts of any changes identified Project Buyer - Camso
COMMENTS
Details for
measurement
Measure-ment IPS [x if req. or
2-MEASUREMENT AGREEMENT method
MSA [X if required] [as defined for Sample Size
target Ppk]
Decision
PPAP, unless
otherwise defined]
Dimensions SPC Yes Yes Agreed
How supplier
Drawing information Expectations CAMSO Measurements/Verification for P3 Measurements/Verification for PPAP Control in serial production
manufactures it?
(Prepared by Engineering) (Prepared by Engineering/SPQD) (Supplier to prepare) (Supplier to prepare) (Supplier to prepare)
(Supplier to prepare)
100% check No No Not agreed ==> add action to Quality Review tab
Decision
(Camso SPQD function)
MSA Details for MSA [X Details for MSA [X Details for
ST/Key IPS [x if IPS [x if Observe
Dimension/ Serial production Measure-ment [Yes if measurement method Measurement tool Sample Measure-ment if measurement method Measurement tool Sample Measure-ment if measurement Measurement tool Sample
Pos. characte PPAP expectation req. or req. or Frequency Ppk
Tolerance expectation frequency require [Go/No Go gauge, accuracy Size frequency require [as defined for P3, unless accuracy Size frequency require [as defined for P3, unless accuracy Size
ristics target Cpk] target Cpk] [x if req.]
d] camera, CMM, caliper...] d] otherwise defined] d] otherwise defined]
Poka Yoke
Sampling
Special Processes
Remarks: Abbreviations: CMM=Coordinate Measurement Machine, DR=Dimensional Report, ref.=reference plane or line, req.=requested, SOP=start of production order, IPS=Initial process study, MSA=Measurement System Analysis, SPC: Statistical Process Control, Cpk: Process Capability Index, Ppk: Process Performance Index
Review all processes and the flow between processes as required to produce the part/assembly (extrusion, calendering, casting, Quality -
machining, grinding, stamping, assembly, plating, heat treatment, bonding, e-coating, painting, etc.)-- Attach initial (high level) Supplier
process flow/control plan
Project
List and Review specifications related to these processes Buyer -
Camso
Identify the production line (pouring/molding/stamping/extrustion, etc.) to be used; number of cavities in the mold, etc. Quality -
Supplier
Local
Review key process characteristics from design reviews, PFMEA's & other sources Quality -
Camso
Local Quality -
Camso
PPAP requirements (level, PSW, etc)
Local Quality -
PPAP report responsible---Who will sign PSW? Camso
Local Quality -
How many samples parts for PPAP Camso
4-PACKAGING REVIEW
ITEM WHO DATE REQUESTED STATUS COMMENTS
Project Buyer -
Review requirements for component packaging/returnable containers, shipping requirements in process (Ex: Foundry->Machine Shop, Heat Treater->Painter). Camso
Project Buyer -
Review requirements for component packaging/returnable containers, shipping requirements for delivery to Incoterms Named Place. Camso
Project Buyer -
Communicate Camso plan for final delivery from incoterms named place to Camso final destination (not applicable when Camso final destination=Incoterms Named Place). Camso
Project Buyer -
Review the need for temporary sealing for the wash or paint process, and/or any other measures to protect parts (rust preventatives, VCI bags, etc.). Camso
5- PROCUREMENT REVIEW
ITEM WHO DATE REQUESTED STATUS COMMENTS
Review cost target Project Buyer - Camso
Verify service requirements complete Project Buyer - Camso
Production tooling PO release date Project Buyer - Camso
Tooling owner (Please specify for each suppliers Camso requirements) Project Buyer - Camso
Validate lead time for tooling Project Buyer - Camso
Validate lead time for P3 parts and documentation Project Buyer - Camso
Validate lead time for PPAP parts and documentation Project Buyer - Camso
Is third party laboratory test required for P3 or PPAP testings? Project Manager - Camso
Validate lead time for production parts. Project Buyer - Camso
Tooling Declaration process Project Buyer - Camso
PPAP Submission Index for
Purchased Parts
o þ
Supplier Name
PPAP-contact-person at CAMSO:
1 2 3 4 5
Ordered PPAP-Level: þ o o o o
(Default)
documents
documents
Requested
Submitted
Comments
1. Design records
o o
9. Dimensional Results
o o
o o
o o
o o
Yes o No o
Comments
or CAMSO inspection.
e Supplier
þ o
Completed Engineering - Camso
In progress Project Manager - Camso
Not started Plant Buyer - Camso
To be confirmed Project Buyer - Camso
Strategic Buyer - Camso
Global Quality - Camso
Local Quality - Camso
Quality - Supplier
Engineering - Supplier