Tutorial Questions
Tutorial Questions
CME3034
Tutorial
Questions
Solutions
John Dalton
Room C527
1
CME3034: Exam Scope:
● (JD) Pressure Vessel Standards
● (JD) Pressure Relief Sizing
● (JG) Bio. Safety
● (MH) Maintenance and Safe Systems
● (MH) Management of Change
● (SB) Plant layout
● (SB) Instrumentation and Protective Systems
I am in Room C527, or
email: John.Dalton@ncl.ac.uk
2
Tutorial:
Q&A
Q 1
3
Question 1) Target Safety Integrity Level (SIL) Assessment
d) There are several methods for carrying out Target SIL Assessment:
- Describe the relative benefits and limitations of each method
- Describe under what circumstances each method would typically be
used
Q1) Answer
You may incur a business loss due to an upset in production due the
process safety hazard is not present
Should a demand occur the function would fail and this may lead to
safety or environmental consequences
4
Q1) Answer
If you do not functionally test then you will miss an unrevealed failure
and then you could have a process safety incident
Q1) Answer
c) Test interval
Too Long:
If the test interval is too long then a real demand on the function
may occur in between functional tests.
For example,
if your demand rate is 1 per year, and your
test interval is every 2 years,
… meaning demands are more frequent that your tests. You are at
increased risk of a process safety incident.
5
Q1) Answer
c) Test interval
Too Short:
A shorter test interval often means improved reliability of a function (a
lower PFDavg), but this is not always the case if the test interval
becomes too short. If the test interval is too short then you may not
get the reliability you require out of your function due to:
● More tests mean more chance of human error during a test as the
technician makes a mistake and leaves the function in a failed state
● To do a test you may need to defeat the function (this is to prevent
the function operating fully and tripping out the plant under test
conditions which is undesirable). Testing too often may mean the
time the function is in a failed (defeated) state during testing
becomes significant
● Testing too often also means you are wasting money in terms of
technician time and effort
Q1) Answer
d) “There are several methods for carrying out Target SIL Assessment:
- Describe the relative benefits and limitations of each method
- Describe under what circumstances each method would typically be
used”
i) Risk graph
6
Q1) Answer
Q1) Answer
7
Q1) Answer
Q 2
8
Question 2) Target Safety Integrity Level (SIL) Assessment
b) The Target SIL Assessment for the tank high level Safety Instrumented
Function has identified a required SIL1 target with a PFDavg of 0.025.
c) How could the reliability of the high level Safety Instrumented Function
be improved?
What do you understand by this and how would you change the design of
the function to achieve a Hardware Fault Tolerance of 1?
9
Q2) Answer
Should high level occur in the tank the function would not operate,
therefore if the operator does not detect the failure of the function
(which is unlikely) and intervene manually then the tank would overflow
Q2) Answer
b) PFDavg calculation
10
Q2) Answer
b) PFDavg calculation
(T/12) = 0.25
so, T = 3 months
Overall this function achieves SIL 1 (PFDavg between 0.1 and 0.01)
Q2) Answer
b) iii) “If the functional test lasts 1 hour, during which time the
function is deliberately placed in a defeated state to avoid a
spurious trip that causes an interruption to the transfer of
gasoline, comment on its significance”
b) PFDavg calculation
iii) The PFDavg should include the PFDavg for the instrumentation
hardware {as calculated in b) ii)} and also the PFDavg for the time
when the function is defeated during testing
11
Q2) Answer
c) Reliability improvement
Q2) Answer
This is how many faults a function can have and still operate correctly
The HFT of zero means one failure (either the valve, switch or level
instrument) and the function would fail to operate on demand, this is
typical of a SIL1 function
A HFT of 1 would mean that a single failure could occur and the
function would still operate (typical of a SIL2 function)
So that if one switch failed then there is still another switch left to
activate the function
12
Q 3
The complex is made up of 5 process units that have been qualitatively risk
ranked as follows based on material properties and inventory:
13
Q3) Plant Layout
A chemical plant complex is to be located on a green-field site. The site is
square and has an plot plan area of 1 km2. A short distance from the
eastern boundary of the site is a small town. All other sides of the site
face onto open farmland.
b) Using the principles of inherent safety describe how you would arrange
the process units on the site?
c) Describe how you could reduce the domino hazard due to vapour cloud
explosion events on Unit 2.
d) What should you consider when locating the Reaction Unit Control Room?
e) What should you consider when locating the office building for the Site
Sales and Administration Team?
Q3) Answer
14
Q3) Answer
● Install a low hazard unit between Unit 2 and Unit 3 to avoid the
domino effect
Q3) Answer
c)
● Ensure plant structure is open, well-ventilated and not congested
– this allows leaks to disperse and should an explosion occur then
the lack of congestion would means the force of the explosion
would be minimised
15
Q3) Answer
d)
Q3) Answer
e)
16
Q 4
To
Grid
From
Supply
17
Q4) Answer
“Develop a more detailed version of the above diagram to indicate the
basic layout of ‘isolations for maintenance’ for the pump station …”
Double block and bleed installations around each pump, combined with
slip-plate positions allow each pump to be safely isolated.
To
Grid
From
Supply
Slip Plates
Spectacle
Pieces
18
Q4) Answer
“ … and describe how, when maintenance is required, each pump can be:
● safely isolated in all necessary respects
● de-inventoried and prepared for safe maintenance
● prepared for service and de-isolated following maintenance
● re-inventoried for return to service
When a pump is taken out for required maintenance, the sequence is:
Q4) Answer
“ … and describe how, when maintenance is required, each pump can be:
● safely isolated in all necessary respects
● de-inventoried and prepared for safe maintenance
● prepared for service and de-isolated following maintenance
● re-inventoried for return to service
● Remove slip-plates
● Connect pressurised nitrogen to one of two bleed valves and purge
until pump and pipework is proven oxygen free
● Pressurise pump and pipework and then disconnect nitrogen
● Introduce propylene via gradual opening of one of the two isolation
valves
● Maintaining pressure, purge nitrogen from pump and pipework to flare
● Remove connections to flare and open pump isolations
● Reinstate electrical supply to pump
19
Q 5
The new installation will be fed from existing power supplies and will
include an auto-start / auto change-over facility, added to the
existing process control computer system, to ensure continuous
operation in the event of a single pump shutdown.
Describe four factors you would include in the EHS assessment within
the management of change process for the proposed modifications to
the process unit and in each case why the factor needs to be
considered?
20
Q5) Answer
Q 6
21
Question 6) PRV Sizing
Determine the flow area of a safety valve used on a vessel containing
nitrogen gas, where a set pressure of 55 barg is required. Coefficient
of discharge Kd = 0.87.
Q 6) Answer
Pressure
(barg) relieving
10% pressure
set pressure
= 55 barg
time (s)
Po = (1.1 55) + 1 = 61.5 bara
22
Q 6) Answer
Po = 61.5 bara k
2 k 1
Pb = 1 bara
Pc Po
k 1
1.4
2
1.4 1
61.5
1.4 1
32.5
Pb 1 32.5
PRV Criticality
PR k 1 P
1.4
2
1.4 1 PR
PC 61.5
1.4 1
32.5 bara
Pb>PC
distance
23
Q 6) Answer
m
So using the critical formula: A 1
PO 2
0.2883 C Kd
vg
1
k 1 2
2 k 1
where: C 3.948 k
k 1
Q 6) Answer
Po = 61.5 bara RT
R = 287 J/kg K vg
T = 293 K P
287 293
61.5 10 5
0.01367 m 3 kg
24
Q 6) Answer
Finally:
m
A 1
P 2
0.2883 C Kd o
v g
18000
A 1
61.5 2
0.2883 2.703 0.87
0.01387
395 .8 mm 2
Q 7
25
Question 7) PRV Sizing
Repeat the previous example, but this time with a back pressure
of: 36 barg.
reminder of Q6)
Q 7) Answer
Pressure
(barg) relieving
10% pressure
set pressure
= 55 barg
time (s)
Po = (1.1 55) + 1 = 61.5 bara
26
Q 7) Answer
Po = 61.5 bara k
2 k 1
Pb = 36+1 bara
Pc Po
k 1
1.4
2
1.4 1
61.5
1.4 1
32.5
Pb 37 32.5
PRV Criticality
PR k 1 P
1.4
2
1.4 1 PR
PC 61.5
1.4 1
Pb=37 bara
32.5 bara
Pb>PC
distance
27
Q 7) Answer
m
So using the sub-critical formula: A 1
P 2
0.2883 C Kd Kb O
vg
1
k 1 2
2 k 1
where: C 3.948 k
k 1
Q 7) Answer
For kb:
1
2k P 2 k P k 1 k 2
b b
k 1 o
P P
o
Kb k 1 k 1
2
k
k1
28
Q 7) Answer
Q 7) Answer
Po = 61.5 bara RT
R = 287 J/kg K vg
T = 293 K P
287 293
61.5 10 5
0.01367 m 3 kg
29
Q 7) Answer
Finally:
m
A 1
P 2
0.2883 C Kd Kb o
v g
18000
A 1
61.5 2
0.2883 2.703 0.87 0.988
0.01387
400 .6 mm 2
Q 8
30
Question 8) PRV
A safety valve is to be sized for the superheater outlet of a large power
station boiler. The valve will be expected to handle 27000 kg/hour of
steam when it is relieving pressure, which will discharge to the
atmosphere.
Q 8) Answer
Pressure
(barg) relieving
10% pressure
set pressure
= 1.1 57 10%
= 62.7 barg
Pop
57 barg Op Pressure
time (s)
Po = (68.97) + 1 = 69.97 bara
31
Q 8) Answer
Po = 69.97 bara k
2 k 1
Pb = 1 bara
Pc Po
k 1
1.3
2
1.3 1
69.97
1.3 1
38.2
Pb 1 38.2
PRV Criticality
PR k 1 P
1.3
2
1.3 1 PR
PC 69.97
1.3 1
38.2 bara
Pb>PC
distance
32
Q 8) Answer
m
So using the critical formula: A 1
PO 2
0.2883 C Kd
vg
1
k 1 2
2 k 1
where: C 3.948 k
k 1
Q 8) Answer
Po = 69.97 bara
T = 450 °C = 743 K
v g 0.0441 m 3
kg
33
Q 8) Answer
Finally:
m
A 1
P 2
0.2883 C Kd o
v g
27000
A 1
69.97 2
0.2883 2.634 0.71
0.0441
1257 mm 2
Q 9
34
Question 9) PRV
A pressure vessel with a volume of 3.99 m3 contains 73.5 kg of a gas
at 130 °C. A pressure relief valve has been sized for this vessel with a
throughput of 3700 kg/hour.
Q 9) ans
122.5 kg
+ add
49 kg
Po
Pset
Pnorm
73.5 kg
38 seconds
35
Q 9) ans
122.5 kg
max press
when prv
operates
Po
Pset
prv opens
here
Pnorm
73.5 kg
38 seconds
Q 9) ans
mRT
Pnorm
V
73.5 287 403
3.99
21.3 10 5 Pa
21.3bara
mass corresponding
Pset 1.1 21.3
to 23.43 bara is
23.43 bara
80.83 kg
PO 1.1 23.43
25.77 bara
36
Q 9) ans
122.5 kg
tinc=?
PO = 25.77 bara
Q 9) ans
During accumulation
we add:
49 kg
1.29 kg s 32.32 s 41.69 kg
38 s
During PRV operation
we discharge:
3700 kg hr
1.028 kg s 32.32 s 33.23 kg
3600 s
37
Q 9) ans
Viewing this:
122.5 kg
PRV disch’s
33.23 kg we add
41.69 kg
What’s left
8.47 kg
80.83 kg
32.23 seconds
73.5 kg
38 seconds
Q 9) ans
PV mRT
mRT
P
V
80.83 8.47 287 403
3.99
25.88 10 Pa,
5
or 25.88 bara
38
Q 10
Using the data supplied redesign the vessel to determine a nominal wall
thickness and size a safety valve suitable for releasing the excess pressure.
The safety relief system operates under back pressure.
Assume:
i) a Kd value of 0.71 for the safety valve, and
ii) an estimated life of 10 years for the pressure vessel, and
iii) a mass flow rate, ṁ, for the safety valve of 3500 kg/h
39
Pdes = 20 bar
Pnorm = 18 bar
Pb = 8.5 bar
De = 1.1 m
1.1 m
L = 4.2 m
Corrrate = 0.08 mm/year
Life span = 10 years
Mat. tol. = ± 0.2 mm
RT/M = 530 MPa
D 2
V L Kd = 0.71
4 Solvent = 1200 kg, 37.5 kMol
1.12 Reactant = 675 kg 5.11 kMol
4.2
4 ΔH = -13.2104 kJ/kMol
mass rate = 3500 kg/h
4 m3
Tmix = 40 °C
Cp = 4 kJ/kg K
40
Reaction 1200 kg Solvent 37.5 kMol
675 kg Reactant 5.11 kMol
Cp = 4 kJ/kg K
Q m C p T
Q
T
m Cp
675 10 3
1200 675 4
90 C
41
Reaction 1200 kg Solvent 37.5 kMol
675 kg Reactant 5.11 kMol
Cp = 4 kJ/kg K
Q m C p T
Q 22 bar
T
m Cp
675 10 3
1200 675 4
40 °C 130 °C
90 C
ΔT = 90 °C
PRV Criticality
42
PRV Criticality
k
PC 2 k 1
PR k 1
1.56
2 1.561
PC 22
1.56 1
11 bar
PRV Criticality
k
PC 2 k 1
P
PR k 1
PR
1.56
2 1.56 1
PC 22 Pb>PC
1.56 1
11 bar
Pb=PC PC=11 bar
distance
43
PRV Sizing
Po = 22 bar
k = 1.56
Kd = 0.71
T = 130 °C
m = 3500 kg/h
PRV Sizing
3500
kg
m
h
Po = 22 bar 1
k = 1.56
1.56 1 2
2 1.561
Kd = 0.71 C 3.948 1.56 2.8
1.56 1
T = 130 °C
m = 3500 kg/h
RT 287 130 273
vg 0.0526 m3 / kg
P 22 10 5
3500
A 1
22 2
0.2883 2.8 0.71
0.0526
A 298.6 mm2
44
PRV Sizing
3500
kg
m
h
Po = 22 bar 1
k = 1.56
1.56 1 2
2 1.561
Kd = 0.71 C 3.948 1.56 2.8
1.56 1
T = 130 °C
m = 3500 kg/h
RT 287 130 273
vg 0.0526 m3 / kg
P 22 10 5
3500
A 1
22 2
0.2883 2.8 0.71
0.0526
A 298.6 mm2
1 1
4 A 2 4 298.6 2
D
19.5 mm 20 mm
PV
RM / T 530 safety
De = 1.1 m fd factor
Po = 22 bar 2.4 2.4
= 2.2 MPa 220.8 MPa
Z = 0.9
UTS
Rm/T = 530 MPa
45
PV
RM / T 530 safety
De = 1.1 m fd factor
Po = 22 bar 2.4 2.4
= 2.2 MPa 220.8 MPa
Z = 0.9
UTS
Rm/T = 530 MPa
remember
http://www.masteel.co.uk/p355gh.htm
46
PV
RM / T 530
De = 1.1 m fd
Po = 22 bar 2.4 2.4
= 2.2 MPa 220.8 MPa
Z = 0.9
UTS Po D e
Rm/T = 530 MPa e
2f Z P
2.2 1100
2 220.8 0.9 2.2
6 mm
PV
RM / T 530
De = 1.1 m fd
Po = 22 bar 2.4 2.4
= 2.2 MPa 220.8 MPa
Z = 0.9
UTS Po D e
Rm/T = 530 MPa e
2f Z P
2.2 1100
2 220.8 0.9 2.2
6 mm
tol = ± 0.2 mm
e = 0.2 mm
en 6 10 0.08 0.2
Crate = 0.08 mm/year
7 mm
Life = 10 years
47
Q 11
48
Q 11) ans
A 4 r 2 A D2
Q 11) ans
1
SA: S A DL D 2
;i.e. 2hemispheres = 1 sphere
2
D2 D3
Vol: V L
4 6
49
Q 11) ans
Using 2 make L the subject
D2 D3
V L
4 6
4 D3
L V
D2 6
4V 4 D3
D2 D2 6
4V 2 3
L D
D2 3
Q 11) ans
4V 2
Using 3 L D
D2 3 put 3 into 1
and 1 S A DL D2
4V 2
S A D D D2
D 3
2
4 V D 2
D2 D2
D 2
3
4V D2 4
SA
D 3
50
Q 11) ans
To minimise SA, we simply differentiate 4
w.r.t. D 4V D2
SA
D 3
dS A 4V 2
2 D
dD D 3
For max or min this = 0
4V 2
D0
D2 3
2 4V or
D3
D 2 V
3 D 6
6V Volume of a sphere
D3
Q 12
51
Question 12) PV Sizing
A pressure vessel operating at 7.5 bar, 30 °C is to be designed for a
brewery to the BS EN13445 standard. The cylindrical vessel will be
vertical, requires a volume of 16m3 and will be made from:
304 Stainless Steel, to which the following properties apply:
1 .. 1.7 10 .. 15 35 .. 40
Pressure barg
52
Q 12) ans
Q 12) ans
Vtotal 4 Vtotal 3
D3 D
n 4 2 n 8
53
Q 12) ans
L
4
Vtotal 2 D3
D 2
Q 12) ans
L
4
16 2 0.13116 1.6753
1.675 2
6.7 m
54
Q 12) ans
Dimensions :
Rp 0.2 T Rm 20
fd min ;
3
6.6 Cast steel
1.9
Yield strength ReH may be used instead of Rp0.2 if this value is not available
55
Q 12) ans
Rp 1.0 T Rp 1.0 T Rm T
fd max
; min ;
1.5 1.2 3
235 235 530
max ; min ;
1.5 1.2 3
max156.7 ; min 195.8 ; 176.7
176.7 MPa
Q 12) ans
Dimensions :
Pressure : 0.75MPa
Weld coefficient : z = 1
56
Torispherical wall thickness
The maximum of:
PR
es
2 fz 0.5P
Q 12) ans
Wall thicknesses
PDi
cylinder: e
2 fz P
0.75 1675
e
2 176.7 1 0.75
e 3.563 mm 4 mm
PR R=0.8D for
end: e Korbbogen
2 fz 0.5P
0.75 0.8 1675
e
2 176.7 1 0.5 0.75
e 2.848 mm 3 mm
57
Minimum wall thickness
Pressure Vessel Min. thickness
Diameter (m) (mm)
1 5
1 to 2 6
2 to 2.5 9
2.5 to 3.0 10
3.0 to 3.5 12
Q 12) ans
3mm
Comment:
4mm This is a very large vessel
and the wall thicknesses
seem rather small.
6.7m Would need to check the
structural integrity
further to see if this would
‘stand up’!
1.675m
58
Q 13
59
Question 13) PV Sizing
The selected material for construction is CrMo4-5, which is suitable for
operation at high temperature. The material has a density of 7850kg/m3
and the following material properties.
Rp0.2/20 Rm/20 Elongation
MPa MPa A%
e16: 300
e>16: 290 450-600 19
You have not yet decided which type of end will go at the top.
Determine, from the following ends, which will give the least overall mass
for the vessel.
(i) ASME 6%,
(ii) Kloepper,
(iii) Korbbogen,
(iv) Ellipsoidal,
(v) Flat end with hub (uniform thickness)
Assume the plate is supplied from the manufacturer to the nearest mm.
1 .. 1.7 10 .. 15 35 .. 40
Pressure barg
60
Q 13) ans
Rp 0.2 T Rm 20
fd min ;
3
6.6 Cast steel
1.9
Yield strength ReH may be used instead of Rp0.2 if this value is not available
61
Q 13) ans
First job is to determine the design stress.
Material (e16mm) has: A% = 19
Rp0.2/20 = 300 MPa, and
Rm/20 = 450 MPa
Rp 0.2 T Rm 20
fd min ;
1.5 2.4
Using: -0.0011T+1.0623 Rp 0.2 350 0.001 350 1.0623 300
214 MPa
214 450
fd min ;
1.5 2.4
min 142 .5 ; 187.5
fd 142 .5 MPa
Q 13) ans
Operating parameters:
D: 1.5 m (1500 mm)
L: 3 m (3000 mm)
P: 15 bar (1.5 MPa)
T: 350 °C
fd: 142.5 MPa
z: 1 (assumption)
density : 7850 kg.m-3
62
Q 13) ans
Calculate wall thicknesses for cylinder and
hemispherical end
cylinder: e PDi
2 fz P
1.5 1500
e
2 142.5 1 1.5
e 7.939 mm 8 mm
hemi-end: e PDi
4 fz P
1.5 1500
e
4 142.5 1 1.5
e 3.959 mm 4 mm
Q 13) ans
cylinder: Di = 1.5 m
L = 3.0 m
e = 8 mm
Do = 1.5+20.008 = 1.516 m
D2o D2i
Vcyl L
4
1.5162 1.52 mcyl Vcyl
3
4 7850 0.1137
0.1137 m3 892.55 kg
63
Q 13) ans
hemi: Di = 1.5 m
e = 4 mm
Do = 1.5+20.004 = 1.508 m
D3o D3i
Vhemi
12
1.5083 1.53 mhemi Vhemi
12 7850 0.0142
0.0142 m3 111.57 kg
Q 13) ans
64
Q 13) ans
65
Ellipsoidal wall thickness
According to BS EN 13445-3: 2009 we treat ellipsoidal
ends the same as torispherical ends
Di
hi
4
Di
Conditions: Di Di
K 2
2hi 2D i 4
K is the shape
factor 1.7 K 2.2
Di
Designed as nominally equivalent torispherical
ends with: Di
K … so K = ???
2hi
0.5
r D i 0.08
K
R Di 0.44K 0.02
66
Q 13) ans Wall thicknesses
ASME 6% 1.5 1500
e 7.918 8 mm
2 142.5 1.5
Kloepper
1.5 1500
e 7.918 8 mm
2 142.5 1.5
Korbbogen
1.5 0.8 1500
e 6.334 7 mm
2 142.5 1.5
Ellipsodal 1.5 0.9 1500
e 7.126 8 mm
2 142.5 1.5
Flat end with hub (uni thickness) …
eaf
Deq
Lcyl
es Di
67
Flat end with hub
Required min thickness e, (eaf>e)
P
e C1D eq
f
D es e
C1 max 0.40825 A 1 i ; 0.299 1 1.7 s
Di Di
es
A 1 B1 1 B1
2D i es
3 P D i 3 e2s 2D i es
2 4
3 f D es
B1 1 i
P D i 16 f D i es 4 D i es
Uniform D D r Tapered 1
eq i D eq Di DF
Thickness Shell 2
Uniform ? Tapered
Thickness Shell
Deq=Di - r Deq=½(Di + DF)
C1={P,Di,f,es} inc(r)
e ={C1,Deq,P,f}
r < 1.3e
?
r 1.3e use e, r and lcyl 0.5 es Di es
68
Flat end, +hub Start with:
P 1.5MPa f 142.5MPa
es = 7.939 mm, and
Di 1500mm ecyl 7.939mm
r = 2 mm
D eq Di r
r>1.3e?
es r Deq A1 B1 C1 a C1 b max(C1) e
7.939 7.939 1492.1 0.9914 0.9940 0.4069 0.3017 0.4069 62.295
62.295 9.939 1490.1 0.5404 0.5463 0.2298 0.3201 0.3201 48.944
48.944 11.939 1488.1 0.7077 0.7158 0.2983 0.3156 0.3156 48.188
Korbbogen
1.5 0.8 1500
e 6.334 7 mm
2 142.5 1.5
Ellipsodal 1.5 0.9 1500
e 7.126 8 mm
2 142.5 1.5
Flat end with hub (uni thickness) e 46.447 47 mm
69
Q 13) ans Volumes & masses
ASME 6%
=7850 kg.m-3
V 0.081 1.5163 1.53 0.00844 m3 69.4 kg
Kloepper
V 0.09897 1.5163 1.53 0.01080 m3 84.8 kg
Korbbogen
V 0.13116 1.5143 1.53 0.01251 m3 98.2 kg
Ellipsodal
V 1.516 3
1.53 0.01429 m3 112.2 kg
24
Flat end with hub (uni thickness) - Approx
1.5162
V 0.047 0.08484 m3 666 kg
4
total
vessel
mass
kg
70