Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

5.23 Weld Profiles: AWS D1.1/D1.1M:2015 Clause 5. Fabrication

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

AWS D1.1/D1.1M:2015 CLAUSE 5.

FABRICATION

mutually agreed upon by the Contractor and the Owner of the joint and then deposited along a spiral path to the
with proper regard for erection requirements. center of the hole, fusing and depositing a layer of weld
metal in the root and bottom of the joint. The arc shall
then be moved to the periphery of the hole and the proce-
5.23 Weld Profiles dure repeated, fusing and depositing successive layers to
fill the hole to the required depth. The slag covering the
All welds shall meet the visual acceptance criteria of weld metal should be kept molten until the weld is fin-
Tables 6.1 and 9.16, and shall be free from cracks, over- ished. If the arc is broken or the slag is allowed to cool,
laps, and the unacceptable profile discontinuities exhib- the slag must be completely removed before restarting
ited in Figure 5.4, Table 5.8, and Table 5.9, except as the weld.
otherwise allowed in 5.23.1, 5.23.2, and 5.23.3.
5.24.1.2 Vertical Position. For welds to be made in
5.23.1 Fillet Welds. The faces of fillet welds may be the vertical position, the arc is started at the root of the
slightly convex, flat, or slightly concave as shown in Fig- joint at the lower side of the hole and is carried upward,
ure 5.4 and as allowed by Tables 5.8, 5.9, 6.1, and 9.16. fusing into the face of the inner plate and to the side of
5.23.2 Exception for Intermittent Fillet Welds. Ex- the hole. The arc is stopped at the top of the hole, the slag
cept for undercut, as allowed by the code, the profile re- is cleaned off, and the process is repeated on the opposite
quirements of Figure 5.4 shall not apply to the ends of side of the hole. After cleaning slag from the weld, other
intermittent fillet welds outside their effective length. layers should be similarly deposited to fill the hole to the
required depth.
5.23.3 Groove Welds. Groove weld reinforcement shall
comply with Tables 5.8, and 5.9 and with the provisions 5.24.1.3 Overhead Position. For welds to be made in
below. Welds shall have a gradual transition to the plane the overhead position, the procedure is the same as for
of the base metal surfaces. the flat position, except that the slag should be allowed to
cool and should be completely removed after depositing
5.23.3.1 Flush Surfaces. Welds required to be flush each successive bead until the hole is filled to the re-
shall be finished so as to not reduce the thicknesses of the quired depth.
thinner base metal or weld metal by more than 1/32 in
[1 mm]. Remaining reinforcement shall not exceed 1/32 in 5.24.2 Slot Welds. Slot welds shall be made using tech-
[1 mm] in height and shall blend smoothly into the base niques similar to those specified in 5.24.1 for plug welds,
metal surfaces with transition areas free from undercut. except that if the length of the slot exceeds three times
However, all reinforcement shall be removed where the the width, or if the slot extends to the edge of the part, the
weld forms part of a faying or contact surface. technique requirements of 5.24.1.3 shall apply.

5.23.3.2 Finish Methods and Values. Where surface


finishing is required, surface roughness values (see ASME
B46.1) shall not exceed 250 microinches [6.3 microme- 5.25 Repairs
ters]. Chipping and gouging may be used provided these The removal of weld metal or portions of the base metal
are followed by grinding or machining. For cyclically may be done by machining, grinding, chipping, or goug-
loaded structures, finishing shall be parallel to the direction ing. It shall be done in such a manner that the adjacent
of primary stress, except final roughness of 125 micro- weld metal or base metal is not nicked or gouged. Oxy-
inches [3.2 micrometers] or less may be finished in any gen gouging shall only be permitted for use on as-rolled
direction. steels. Unacceptable portions of the weld shall be re-
5.23.4 Shelf Bars. Shelf bars shall conform to the re- moved without substantial removal of the base metal.
quirements of 5.9.1.1 through 5.9.1.5. Shelf bars may be The surfaces shall be cleaned thoroughly before welding.
left in place only for statically loaded members. Weld metal shall be deposited to compensate for any de-
ficiency in size.
5.25.1 Contractor Options. The Contractor has the op-
5.24 Technique for Plug and Slot Welds tion of either repairing an unacceptable weld or remov-
ing and replacing the entire weld, except as modified by
5.24.1 Plug Welds. The technique used to make plug
5.25.3. The repaired or replaced weld shall be retested by
welds when using SMAW, GMAW (except GMAW-S),
the method originally used, and the same technique and
and FCAW processes shall be as follows:
quality acceptance criteria shall be applied. If the Con-
5.24.1.1 Flat Position. For welds to be made in the tractor elects to repair the weld, it shall be corrected as
flat position, each pass shall be deposited around the root follows:

177

You might also like