Engine Generator Set Inspection Checklist: Section A - Customer Data
Engine Generator Set Inspection Checklist: Section A - Customer Data
Engine Generator Set Inspection Checklist: Section A - Customer Data
For use of this form see TM 5-694; the proponent agency is COE.
13. CIRCUIT BREAKER SIZE/INTERRUPTING RATING 14. WET BULB TEMPERATURE 15. DRY BULB TEMPERATURE
POLARIZATION INDEX
RATIO = 10 MINUTE/1 MINUTE
DC OVERPOTENTIAL TEST
@ V
18. NOTES
1. PERFORM 5 MEASUREMENTS AT ONE MINUTE INTERVALS.
2. DC HIPOT MEASUREMENTS SHOULD BEGIN AT 20% OF MAXIMUM TEST VOLTAGE AND INCREASE IN EQUAL
INTERVALS.
MAX DC TEST VOLTAGE = R (2 x NAMEPLATE RATING) x 1.6
WHERE R = .8 FOR DC TEST ON INSTALLATION
WHERE R = .6 FOR DC TEST AFTER SERVICE
(TEST MEASUREMENTS SHOULD NOT EXCEED MANUFACTURER'S RECOMMENDATION)
A-N
B-N
C-N
A-B
B-C
C-A
21. NOTES
1. VOLTAGE MEASUREMENT TO BE MADE AFTER GENERATOR IS STARTED AND CONNECTED TO LOAD (CAN USE
LOAD BANK).
2. DURING COMMISSIONING OF GENERATOR SETS OR ANY EQUIPMENT, A REPRESENTATIVE OF THE
MANUFACTURING COMPANY OR SUPPLIER MUST BE PRESENT TO WITNESS AND/OR PERFORM THE TESTS.
3. ENGINE GENERATOR TESTING IS A VERY INTENSIVE PROCESS AND REQUIRES A 10 TO 14 HOUR DAY
DEPENDING ON THE EQUIPMENT BEING COMMISSIONED. SUPPLIER/MANUFACTURER NORMALLY SUPPLY
GENERATOR TESTING LOAD REQUIREMENTS.
4. VERIFY ALL SYSTEM CHECK POINTS DURING LOAD CHANGES AND RECORD PER SPECIFIED REQUIREMENTS
AND/OR EQUIPMENT MANUFACTURER.