Risk Identification
Risk Identification
Risk Identification
Risks are to be identified and dealt with as early as possible in the project. Risk identification is
done throughout the project life cycle, with special emphasis during the key milestones.
Risk identification is one of the key topics in the regular project status and reporting meetings.
Some risks may be readily apparent to the project team—known risks; others will take more rigor
to uncover, but are still predictable.
The medium for recording all identified risks throughout the project is the risk register, which is
stored in the central project server.
The following tools and guidelines are used to identify risks in a structured and disciplined way,
which ensures that no significant potential risk is overlooked.
1. Risk Sources
2. Risk Category
Risk category provides a list of areas that are prone to risk events. The organization
recommends high-level, standard categories, which have to be extended based on the project
type.
Exhibit 3 – Organization-Provided Standard Risk Categories
Risk Analysis
Risk analysis involves examining how project outcomes and objectives might change due to the
impact of the risk event.
Once the risks are identified, they are analysed to identify the qualitative and quantitative impact
of the risk on the project so that appropriate steps can be taken to mitigate them. The following
guidelines are used to analyse risks.
4. Risk Impact
5. Risk Exposure
Risk Exposure or Risk Score is the value determined by multiplying the Impact Rating with Risk
Probability as shown in Exhibit 5.
The timeframe in which this risk will have an impact is identified. This is classified into one of the
following:
There may not be quick solutions to reduce or eliminate all the risks facing a project. Some risks
may need to be managed and reduced strategically over longer periods. Therefore, action plans
should be worked out to reduce these risks. These action plans should include:
For each risk, a risk response must be documented in the risk register in agreement with the
stakeholders. This should be ensured by the project manager.
Risk response plans are aimed at the following targets:
2. Risk Triggers
For each risk a trigger must be documented in the risk register. The trigger identifies the risk
symptoms or warning signs. It indicates that a risk has occurred or is about to occur. The risk
trigger also gives an indication of when a certain risk is expected to occur.
Examples:
3. Risk Ownership
The ground rule is that responsibility for managing all risks in the project lies with the project
manager.
Based on this ground rule a Risk Owner (who is not necessarily the project manager) must be
determined and named in the Risk Register. The Risk Owner is normally the one who can best
monitor the risk trigger, but can also be the one who can best drive the defined
countermeasures. The Risk Owner is responsible for immediately reporting any changes in the
risk trigger status and for driving the defined countermeasures.
Examples:
Monitor any risks that could become more critical over time
Tackle the remaining risks that require a longer-term, planned, and managed approach with
risk action plans
Risk reclassification
For the risks that cannot be closed, the criticality has to go down over a period of time due to
implementing the action plan. If this is not the case then the action plan might not be effective
and should be re-examined.
Risk reporting
The risk register is continuously updated, from risk identification through risk response planning
and status update during risk monitoring and control. This project risk register is the primary risk
reporting tool and is available in the central project server, which is accessible to all
stakeholders.
Risk monitoring and controlling or risk review is an iterative process that uses progress status
reports and deliverable status to monitor and control risks. This is enabled by various status
reports, such as quality reports, progress reports, follow-up reports, and so forth.
Risk Reviews are a mandatory item of milestone meetings and/or regular project meetings, but
they can also be executed during separately planned risk review meetings. These risk reviews
must be held regularly. The frequency could also be determined based on the overall risk level of
a project.
Risk Threshold
The risk priorities have to be set to direct focus where it is most critical. The risks with the highest
risk exposure rating are the highest priority.
Risks with Exposure Low can be dropped from the mitigation plans, but may need to be revisited
later in the project.
The organizational mandate is that if the projects have at least one “Very High” risk or more than
3 “High” risks, guidance should be sought from management and stakeholders, as the project
may be at high risk of failure. This is the recommended risk threshold. Projects can customize
the threshold based on project needs.
Risk Metrics
The efficiency of risk analysis and management is measured by capturing the following metrics
during project closure. The analysis results are used to decipher lessons learned, which is
updated in the organization's lessons learned database.
Risk Audit