Lifting Plan
Lifting Plan
Lifting Plan
TERMINOLOGY
1. INTRODUCTION
1.1 PURPOSE
1.2 SCOPE
2.2 PLANNING
2.3 EXECUTION
3.1 APPLICATION
APPENDICES
Abbreviation/Term Meaning
The net capacity is the gross crane capacity minus deductions.
The deductions differ from manufacturer to manufacturer as well
as between crane types.
Deductions normally are:
Weight of main hook block
Net Capacity
Weight of slings and rigging
Weight of auxiliary hook block
Weight of all wire rope from boom tip and the block
Weight of any stowed jib
The gross capacity is the capacity shown in the crane’s load or
Gross Capacity
capacity charts.
A person who has appropriate practical and theoretical
knowledge and experience of the lifting operations to enable
Lift Planner
him to prepare a full working lift plan and who is approved by the
lifting equipment engineer.
Competent Authorised Person is a person who is appointed by
CAP the production co-ordinator (site-manager) to undertake the day-
to-day control of lifting equipment.
A unique number given to an item of lifting equipment for
Equipment Tag Number
registration purposes and to facilitate traceability.
Text English.
A person from a third party certification authority who has the
appropriate practical and theoretical knowledge and experience
of the lifting accessories to be thoroughly inspected against the
Lifting Inspector
applicable lifting equipment standards in relation to the safety
and continued use of the lifting tackle and who is approved by
the lifting equipment engineer.
A person from a third party certification company who has the
appropriate practical and theoretical knowledge and experience
Lifting Engineer of the lifting equipment to be thoroughly inspected as will enable
(surveyor) him to detect defects or weaknesses and to assess their
importance in relation to the safety and continued use of the
lifting equipment.
The term NDT inspector is used to describe any person carrying
out NDT inspection on lifting equipment. In all cases, the
NDT Inspector inspector shall have experience and training suitable to the NDT
inspection being performed. (min level 2 as per ASNT Tc 1a or
equivalent)
1 INTRODUCTION
1.1 PURPOSE
This document provides the procedure to be used for crane operational practices.
The key to safe crane operation is having qualified personnel using the correct
equipment in a safe manner. This procedure will outline the issues relating to the
selection of the correct people for the task. It will describe the operational practices to
be used by these people as part of a safe and effective crane and rigging program.
1.2 SCOPE
This procedure applies to all lifting operations.The lift planning process describes the
systematic assessment of important load factors and site factors. It is as applicable to
“simple” routine lifts as well as ”heavy” non-routine lifts. Planning a non-routine lift
requires considerable effort. In a lift determined to be non-critical, many of the
elements can be determined "by inspection"; and the depth involved in a non-routine
lift will not be required. Nevertheless, the planning process must be followed.
This procedure prohibits a person from riding or travelling on the load, lifting hook,
sling, platform or other lifting medium.
1.3 ROLES AND RESPONSIBILITIES
WHO WHAT
Project Manager To identify the need for a crane based on his/her workscope requirement.
To identify lifting parameters needed to execute the work.
To constantly monitor the approved plan and identify improvement for future
work.
To establish crane capacity and boom length in order to carry out the given
Contractor/Crane supplier
workscope safely and in accordance with this procedure.
To review and approve lifting plan and operation submitted by
contractor/crane supplier via the Executing Department as and when
Lifting Engineer required.
To constantly monitor the approved plan and identify improvement for
future.
To control the crane operations as per approved liftplan.
To participate in JHA/risk assessment/toolbox talk for the lift.
To perform pre-use crane inspections.
Crane Operator
To maintain crane operation logbook comprising manuals, pre-use
inspection lists, crane/lifting gear certificates, wire rope certificate and
hook block certificate.
To co-ordinate the lifting movements and maintains radio- and/or visual
communication with crane operator and persons close to the load.
To inspect the rigging, select rigging to suit the load, install the equipment.
When a lifting operation has to be carried out, it has to be checked if this particular
lifting operation has been carried out before on that site. A risk assessment and Lift
Plan might already exist.
If a risk assessment and Lift Plan do exist then they shall be assessed to confirm that
they are still applicable (e.g. changes to personnel, equipment, site layout or work
environment could all result in the need for re-assessment of hazards). Assuming that
significant changes have not taken place then lifting operations may proceed under the
requirements of the Lift Plan subject to approval by the lifting engineer.
If the lifting operations have not been carried out before, a competent person will
prepare a Lift Plan. This has to be initiated by the executing department.
Load weight, shape, centre of gravity and availability of adequate lifting points
Initial and final load positions and how it will get there
The environment in which the Lifting Equipment will be used
2.2 PLANNING
For every lifting operation the risks have to be assessed and controlled.
The risk assessment addresses a.o. the following aspects and activities:
As an aid to identifying risks and suitable controls, lifting operations are categorised to
reflect increasing risk and increasing level of control required as per categorisation
scheme as given below:
Routine Lifts
A generic risk assessment and Lift Plan may be used for Routine Lifts. However,
classifying a lifting operation as ‘routine’ does not automatically make it a ‘safe’ lifting
operation – most incidents associated with lifting occur during routine operations. The
risk assessments and Lift Plans shall always be reviewed during the Toolbox Talk for
continued applicability.
Non-Routine Lifts
A Lift Plan is prepared or identified for every lift. The Lift Plan comprises ao:
2.3 EXECUTION
Prior to starting of lifting operations a competent person shall hold a Toolbox Talk with
all personnel assigned to carry out the lift. Application of the ‘10 questions for a safe lift’
to the lift shall be covered during the Toolbox Talk (Appendix 5).
The Person-in-Charge (PIC) shall be clearly identified and made known to all members
of the lift team and personnel in the proximity.
All personnel involved in the lifting operation shall have their individual responsibilities
clearly allocated.
All personnel should have the opportunity to review the findings of the risk assessment
and the details of the Lift Plan to ensure that everyone clearly understands and agrees
with the methods and control measures to be used.
Lifting operations shall be conducted in strict accordance with the approved Lift Plan.
Any variation from the agreed Lift Plan shall result in the job being stopped and
reassessed to ensure continued safe operation.
The Lifting Appliance Operator shall obey an emergency stop signal at all times, no
matter who gives it.
Load to be lifted shall be confirmed to be within the rated capacity of the Lifting
Equipment and attached by means of suitable Lifting Accessories.
The Operator of the Lifting Appliance shall not leave the operating controls while the
load is suspended.
Prior to lifting the PIC shall be satisfied that the load is secure and properly
balanced and that the load path is clear of obstructions and personnel
At commencement of the first lift the Lifting Appliance Operator shall carefully
check the operation of the hoist brake to ensure no slippage occurs
Take up sling slack to confirm that the Lifting Appliance hook has been
positioned centrally over the load lifting point, adjust the Lifting Equipment as
necessary to minimise any ‘drift’ of the load as it is lifted
No external forces shall be applied to the load that create significant side
loading of the Lifting Equipment
For crane operations appropriate tag lines shall be used to control the load–
large or long loads with flat sides that could act as a ‘sail’ are particularly prone
to spinning and tag lines shall be used – tag lines shall be secured to the load
and not to the rigging slings
Cranes shall not be used for dragging a load
No fewer than five (5) full wraps of rope must remain on the winch drum in any
operating conditions.
All critical lifting parameters (e.g. weather, sea state, visibility, terrain stability and
slope, surrounding operations and installations, site access and egress, Lifting
Equipment, personnel) shall be identified during the risk assessment and preparation
of the Lift Plan.
The PIC shall ensure that these conditions are monitored as lifting operations proceed
to ensure continued safety.
If, as part of the operation and maintenance of equipment, the computer system shuts
down the operation, the load must be placed on the ground and a new lift plan must be
developed, eliminating the condition that caused the shut down.
Procedures for recovering and landing the load in the event of the lift being aborted
shall be clearly identified.
After completing the lifting operation, everyone involved in the lift should have the
opportunity to discuss and make improvements to the Lift Plan. Any learning points
noted on the plan must be reviewed by a competent person and, where appropriate,
action taken. Learning points may include feedback on equipment effectiveness, lifting
techniques, personnel, etc.
2.6 APPLICATION
This Lift planning procedure is applicable to all lifting operations / lifting equipment. As
such, this document is mandatory and shall be adhered to by all parties, involved in
lifting operations.
Any step-out from this procedure shall be addressed to the lifting equipment engineer
in writing. He will review and authorise the deviation in exceptional circumstances.
APPENDICES
For different applications different overlays of the Risk Assessment Matrix can be used.
Consequences Increasing likelihood
A B C D E
Never Happens
Environment
Severity
Reputation
Heard
heard Happens several
of in Incident
People
Assets
of in several times
E&P has
E&P times per year
Industr occurred
Industr per year in a
y
y location
No
injury or No
0 health damage
No effect No impact
effect
Slight
injury or Slight Slight
1 health damage effect
Slight impact
effect
Minor
injury or Minor Minor Limited
2 health damage effect impact
effect
3 Major Localised Localised Considerable
injury or damage effect impact
health
effect
4
PTD* or
Major Major National
1
damage effect impact
fatality
Multiple Extensiv
Massive International
5 fatalitie e
effect impact
s damage
Risk Assessment
…A scale of consequences from “0” to “5” is used to indicate increasing severity…
The potential consequences, rather than the actual ones, are used….
…After assessing the potential outcome, the likelihood on the horizontal axis is estimated on
the
basis of historical evidence or experience that such consequences have materialised within the
industry, the company or a smaller unit. Note that this should not be confused with the
likelihood
that the hazard is released: it is the likelihood of the estimated consequences occurring.
…In Operating Units or new ventures where experience is limited, it is recommended that the
probability be assessed on the basis of knowledge from similar operations in other Operating
Units….
The following interpretations may assist in determining likelihood when assessing risks
specific to lifting and hoisting operations:
Low Risk May be acceptable but review task to see if risk can be reduced further.
Medium Risk Task should only be undertaken with appropriate management
authorisation after consultation with specialist personnel and assessment
team. Where possible, the task should be redefined to take account of
the hazards involved or the risk should be reduced further prior to task
commencement.
High Risk Task shall not proceed. It should be redefined or further control
measures put in place to reduce risk. The controls should be reassessed
for adequacy prior to task commencement.
APPENDIX 2 - SAMPLE LIFT PLAN
LIFTING OPERATION PLAN PAGE 1 of
Location: Area:
Lifting Equipment & Accessories to be used (specify type ,SWL and colour code)
All Lifting Operations Require The Following To Be Considered But This List Is Not Exhaustive.
Cultural, communication and language difficulties Conflicting tasks in area
Weight, size, shape and centre of gravity of load
Availability of approved lifting points on load Environmental conditions including weather and
Method of slinging/attaching/detaching the load permissible limits
Overturning/load integrity/need for tag lines Lighting in the pick-up and lay-down areas;
Suitability and condition of lifting equipment to be used Proximity hazards, obstructions, path of load
Initial and final load positions and how it will get there Working under suspended loads
Ground and underground considerations Access and emergency escape routes
Lifting over live equipment Experience, competence and training of personnel
Number and duration of lift(s) Number of personnel required for task
Pre-Use Inspection of equipment by operator
Visibility of the load
Transportation
Certified transportation frames are considered best practice for chrome casings to
avoid/reduce body to body contact
In preparing tubulars for transportation it is good practice to pick up the tubing bundle
for a second time to see if more slack can be taken out using clamps or bulldog clips
Storage
Tubular ‘stacks’ should be segregated by pipe posts
The bottom stow of tubulars should be individually ‘chocked’ or secured by other
mechanical means to stop movement
The PIC shall obtain information on wind conditions prior to starting a lifting operation. The
lifting
operation shall be stopped, or the mobile crane secured in an out-of-service condition, as
appropriate, when the wind speed limits, as indicated by the manufacturer, are exceeded.
The PIC shall ensure that the ground (soil test), or any means of support, can sustain loads
imposed by the crane and is suitable for the crane to operate within the levels and other
parameters specified by the crane manufacturer. Side loads shall be avoided.
When siting a crane, point loads through the outrigger / stabiliser beams and jack pads shall
be
spread over a sufficient area to support the outrigger pad and to prevent the crane overturning
or becoming unstable. The PIC shall ensure that the siting can accommodate the crane with
the
outriggers extended and set as specified in the load chart. The mobile crane shall only be
operated in level position.
Danger to and from underground services (gas, electricity, water) shall be taken into
consideration and precautions taken to ensure that the crane foundation is clear of such
services or that they are adequately protected.
On-site travel of fully rigged wheeled cranes, whether loaded or unloaded, shall not be
allowed.
While in transit the boom shall be retracted and carried in line with the direction of motion and
the superstructure secured against rotation (or the boom placed in a boom rack mounted on
the
carrier). The empty hook shall be lashed or otherwise restrained so that it cannot swing freely.
If
the crane has a telescopic boom it shall be set to the fully closed position.
Do not exceed the rated capacity of the crane, hoist, chain, sling or any other component.
Slings, load chains and other accessories shall be fully and securely seated in the hook before
moving a load. Remove slack from the sling, chain or cable before lifting a load.
When lifting loads at or near the crane rated capacity test the hoist brakes by returning the
master switch or push button to the “OFF” position after raising the load a few centimetres off
the floor. If the brakes do not hold, lower the load to the floor slowly and do not continue with
the lifting operation. Report the situation immediately and DO NOT USE the crane until repairs
have been carried out.
Ensure that all loads are lifted high enough to clear obstructions before moving the bridge or
trolley. Whenever possible, maintain a minimum clearance of 300mm above obstacles and to
the sides of the load. Raise the load only to the height necessary to clear lower objects.
Never pull a hoist by the pendant cable. Never leave the controls unattended while a load is
suspended. If it becomes necessary to leave the controls, lower the load to the floor.
If loss of power occurs, place controls in the “OFF” position to prevent unexpected start-up
upon restoration of power. Disconnect power to a hoist that is unsafe or in need of repair –
follow the ‘Lock-Out’ procedure.
Cranes shall not be used to handle materials stored under electric power lines unless any
combination of boom, load, load line or machine component cannot enter the prohibited zone.
Overhead lines and other electrical apparatus shall be considered live unless declared ‘dead’
and ‘safe’ by the Line Operator. Crane Operators shall not rely on the coverings of wires for
their protection.
Where the possibility of contact with energised power lines exists then durable signs shall be
installed at the operator’s station and on the outside of the crane warning that electrocution or
serious bodily injury may occur unless minimum clearances are maintained between the crane
or the load being handled and energised power lines.
See also SP-1242 Activities within vicinity of overhead powerlines, which have to be strictly
adhered to.
5. Tandem Lifting
Tandem lifts for weight reasons alone (because a load is too heavy for a single crane) shall
only be considered as a last option.
All tandem lifts shall only be authorised by the lifting engineer and Site Manager and, based on
a risk assessment demonstrating that other alternatives are not technically feasible.
Tandem lifts shall only be carried out with lifting devices equipped with a load indicator.
Tandem lifts shall always be classified as Non-Routine Lift and should at least follow the
preparations outlined for this type of lift.
In addition, the following controls shall always be in place:
Positions of cranes and loads to be carefully assessed in the Lift Plan, documented in
drawings, and verified by the PIC prior to commencing the lift
Loads for both cranes to be calculated, including the range of permitted tolerances, and
documented. Speeds of raising / lowering the load and slewing of the cranes shall be
documented in the Lift Plan
The lift area to be fenced off and a permit-to-work system in operation, the load shall
not be transferred over personnel at any time
A full function test of all power, transmission, control, and safety systems to be carried
out prior to the commencement of the lift, by competent personnel
Only one person giving signals to be appointed for both cranes and shall have direct
sight vision (and permanent radio contact) to the Crane Operators
Prior to the lift, the PIC to ascertain that both load lines are vertical without side / off
loading of the boom
Upon signal, both cranes to lift slowly, to either the calculated weight tolerance limit or
until the load is free, and STOP
The PIC to confirm that the full load has been transmitted prior to authorizing the lift to
continue. The safe load indicator accuracy and the integrity of the braking mechanism
to be verified before the lift continues
Raising or lowering the lift, or slewing of the crane, to only be undertaken at the signal
from the signalman and at the previously agreed speeds
Be aware that if the load is moved from horizontal to vertical the weight on each crane
will change significantly
6 Powered Industrial Trucks including Fork Lift Trucks (FLTs)
Daily / Pre-Use Inspections
These inspections must be performed and documented by the qualified operator prior to first
use each day or shift the truck is used. These checks ensure that audible and visual
warning equipment is working correctly by carrying out function tests prior to any lifting
operations.
Operations
Key elements and practices for the safe operation of powered industrial trucks shall include,
but may not be limited too, dependent on local legislation and conditions, the following:
Before each operation or series of operations, the Operator shall:
- Perform a pre-operational check to demonstrate operational readiness of the
truck. If controls do not operate properly, the Operator is responsible for
notifying the supervisor. Repairs and adjustments are made before operations
begin
- Ensure the equipment is within inspection and testing intervals by examination
of the periodic re-certification tags and/or documentation
- Adhere to all tags on the controls
- Ensure, if fitted, that seat belts are worn when operating a powered industrial
truck equipped with a roll over protection device
During operations, the Operator shall:
- Drive at speeds appropriate for the existing conditions (space, load, lighting,
surface conditions, etc.) and at or below posted limits
- Keep all parts of the body inside the Operator compartment during operations
- Not start or operate the truck or any of its attachments from any place other
than from the Operators position
- Ensure other personnel are not in the swing radius prior to performing turning
manoeuvres
- Sound the horn when approaching cross aisles, doorways and other locations
where pedestrians may step into the path of truck travel
- Verify sufficient headroom under overhead installations, lights, wiring, pipes,
sprinkler systems etc
- Ensure they are driven on suitable surfaces. Road humps and rough or soft
surfaces are to be avoided
- Movement with loads in excessively raised positions shall not be carried out to
avoid the danger of toppling, especially on uneven surfaces and while cornering
- Shall only be used for loads, which can be carried safely on the forks or
attachments fitted. Non-standard, unpackaged and excessively wide loads shall
be avoided wherever possible. In particular, long tubes shall be carried using
appropriate attachments
- They are not to be operated on excessive gradients or across gradients (In
general they should be driven forwards up a slope, backwards down a slope
and in line with the incline. It may be necessary to raise the forks slightly at the
bottom of a slope to avoid grounding)
No personnel shall:
- Put any part of the body into the mast structure or between the mast and truck
- Be allowed to stand or pass under the elevated portion of any truck, empty or
loaded
Unauthorised personnel shall not be permitted to ride on powered industrial trucks
A safe place to ride (i.e. another seat) should be provided where riding of trucks is
authorised
Equipment shall not be loaded beyond its rated load (capacity) except for required
testing
Trucks should not be driven up to anyone standing in front of an object
Only approved industrial trucks shall be used in areas classified as hazardous locations
When parked:
- The engine shall be switched off, the key removed and the hand-brake applied
- The keys shall be kept in a secure place and only issued to authorised
operators for the duration of the duty period or task
- They shall be parked in secure areas to deter access by unauthorised
personnel
- They do not block access to fire aisles, stairways, or fire equipment
While refueling, the engine shall be stopped and the Operator shall not be on the truck
Lifting personnel with a powered industrial truck is not allowed, and alternative methods
have to be used (e.g. mobile aerial platform)
Rough Terrain Operations for FLTs
The operation of rough terrain FLTs involves special hazards, which require additional care
and
consideration:
Care shall be taken at all times to ensure that traction is retained. Loss of traction due
to the nature of the terrain or weight transfer taking load off the driving wheels is to be
avoided
Care shall be taken and speeds minimised to reduce the risk of load toppling caused by
the imbalance induced when operating on rough terrain
Operators shall ensure that the parking brake is capable of holding the FLT stationary
on an incline (some rough terrain vehicles are capable of climbing inclines steeper than
those on which the parking brake will hold the vehicle)
Checks for overhead obstructions shall be made before lifting and transporting loads
Special care shall be taken near power lines and other materials handling vehicles such
as mobile cranes
Driving rough terrain FLTs on public roads shall be kept to a minimum. When public
roadtravel is necessary, fork arms shall be removed, folded or protected in some way
so that they do not present a hazard to other road users. Where this is not possible,
forks shall be painted or otherwise made highly visible
Rough terrain FLT Operators shall wear seat belts while operating their vehicles.
Repairs
If repairs or part replacement is required then the following guidelines shall be followed:
Immediately take the truck out of service if an unsafe condition is identified or restrict its
operation to eliminate the unsafe condition
Repair or replace all critical components promptly by or under supervision of a qualified
mechanic
An original equipment manufacturer or other approved vendor should supply spare
parts or components
Document in writing all repairs or replacements as per the PM program
Personnel shall:
- Keep all parts of the body, tools, and equipment inside the work platform
periphery during raising, lowering, and travelling operations
- Hold onto a moving platform using both hands
- Secure tools and other objects in canvas bags or by other methods so that both
hands are free and do not present a snagging hazard. Alternate methods of tool
delivery beside personnel lifting devices should be investigated
- Wear fall protection with a lanyard attached to an authorised lanyard anchorage
point. Attach only one (1) lanyard per lanyard anchorage point
- Detailed technical operating procedures describing personnel lifting device
operation, emergency steps, communication requirements, and special
requirements should be prepared
- Personnel lifting device or mobile aerial platforms shall not be loaded beyond its
rated load (capacity) except for required testing
Electrocution Hazards
- For work on or near electrical distribution and transmission lines, mobile aerial
platforms shall be operated in accordance with the applicable national and or
local standard e.g. ANSI/SIA ASME standard
Note: for non-insulated platforms it is recommended that the following sign is
posted: ‘This machine is not insulated and does not provide protection from
contact or proximity to electrical current’
- Maintain safe distance from electrical lines, apparatus, or any energized
(exposed or insulated) parts according to the Minimum Safe Approach Distance
(MSAD) as shown in Table 1-1;
Tipping Hazards:
- The user shall be familiar with the surface before driving. Do not exceed the
allowable side slope and grade while driving
- Personnel Platforms/Carriers should not be elevated whilst on a sloping,
uneven, or soft surface. Personnel shall not be driven with the platform elevated
- Before driving on floors, bridges, trucks, and other surfaces, check allowable
capacity of the surfaces
- Never exceed the maximum platform capacity. Distribute loads evenly on
platform floor
- Do not raise the platform or drive from an elevated position unless the machine
is on firm, level surfaces and evenly supported
- Keep the chassis of the machine at least 2 ft. (0.6m) from holes, bumps, drop-
offs, obstructions, debris, concealed holes, and other potential hazards on the
floor/surface
- Do not push or pull any object with the boom
- Never attempt to use the machine as a crane. Do not tie-off machine to any
adjacent structure
- Do not operate the machine when wind conditions exceed 12.5 m/s or as
prescribed by manufacturer, local legislation and or procedures
- Do not increase the surface area of the platform or the load. Increase of the
area exposed to the wind will decrease stability
- Do not increase the platform size with unauthorised deck extensions or
attachments
- If boom assembly or platform is in a position that one or more wheels are off the
ground, all persons shall be removed before attempting to stabilize the machine.
Use cranes, forklift trucks, or other appropriate equipment to stabilize machine
and remove personnel
Crushing and Collision Hazards
- All operating and ground personnel shall wear approved headgear
- Check work area for clearances overhead, on sides, and bottom of platform
when lifting or lowering platform, and driving
- During operation, keep all body parts inside platform railing
- Use the boom functions, not the drive function, to position the platform close to
obstacles
- Always post a lookout when driving in areas where vision is obstructed
- Keep non-operating personnel at least 6 ft. (1.8m) away from machine during all
driving and swing operations
- Limit travel speed according to conditions of ground surface, congestion,
visibility, slope, location of personnel, and other factors, which may cause
collision or injury to personnel
- Be aware of stopping distances in all drive speeds. When driving in high speed,
switch to low speed before stopping
- Travel grades in low speed only
- Do not use high-speed drive in restricted or close quarters or when driving in
reverse
- Exercise extreme caution at all times to prevent obstacles from striking or
interfering with operating controls and persons in the platform
- Be sure that operators of other overhead and floor level machines are aware of
the aerial work platform’s presence
- Disconnect power to overhead cranes
- Warn personnel not to work, stand, or walk under a raised boom or platform
- Position barricades on floor if necessary
The following additional requirements shall be followed for man riding baskets
operations:
- Man baskets are only to be used in exceptional circumstances, when there are
no alternatives and has to be approved by the site manager in writing.
- The suitability of the mobile crane has to be checked carefully. Use check list
from NSL Aberdeen (Link: http://www.nsl-aberdeen.com/downloads.php )
- The lifting and supporting to be made under controlled conditions and under the
direction of one appointed person
- A crane driver always to be present at the normal crane control station when the
basket is occupied
- Visible and audible communication is there to be between the persons in the
basket and the crane driver at all times during the lifting operation
- The required equipment necessary to perform an emergency rescue to be
available throughout the lifting operation
- During operation the crane driver and signaller are not to do other work at the
same time, or direct a second crane and/or basket
- Lifting slings for suspended baskets not to be used for any other purpose
- People in the basket shall wear a harness with lanyard. A safety lanyard to be
attached to crane hook or basket anchoring point
- Suspended baskets not to be used in wind in excess of 7m/s, or other adverse
weather conditions that could affect the safety of personnel
- Machines which can be operated simultaneously in the same place with risks of
collision have to be stopped
- Unintended movement of the basket should, where possible, to be prevented
e.g. by means of guide ropes or anchoring
- The crane, suspended baskets, hook, catch, and fixed load lifting attachment to
be inspected prior to each use
- The hook must have a safety catch
- The lifting capacity of the crane employed is reduced to 10% at any given radius
- The basket to be positioned on a firm surface when entering or exiting
- Before employees exit or enter a suspended basket that is not landed, it is to be
secured to the structure where the work is to be performed
- Stay away from power lines unless all necessary precautions have been taken.
See also here above.
APPENDIX 4 - SAMPLE OF JOB HAZARDS
ANALYSIS (JHA) FORM
APPENDIX 5 - 10 QUESTIONS FOR A SAFE LIFT