Meeting Title: FM Service Provider – Weekly meeting (GMC23-C1, C9 & C12) MOM No.112
Date: 19th Dec 2019 Time: 1:00 pm Location: Madinat Zayed Office, WR
Attendees: MUSANADA – Abdelhalim Salih (AS), JUMA AL MAJID – Muthasim Hamed (MH), JUMA AL MAJID – Abdul Mohaisth (AM), JUMA AL MAJID – Jacqueline Bagang (JB)
Apologies: Circulation: NA
Meeting Aim: To discuss the operational issues and performance of the contract
DISCUSSION POINTS
No. Item Action Owner By
Added Facility MEP Services to commence on 1st Dec. 2019, external communication to be issued
2 JAM to submit Bldg Attributes, ACS/Asset Registry, Layout (Tamm Center vs. New facility ADDA), TAMM TBC
(ADDA – P004) Center ACS to be revised
3 KPI scorecards received for Oct’19 subject for further discussion on 26th Dec. 2019 JAM/MSDA 26th Dec. 2019
Variation Orders and Awaiting for Procurement’s feedback for the discrepancy of fixed fees in J1190 – C1 (ref no. JAM-MU-203) and
4 MSDA
Payments C1179 – C9 (ref. no. JAM-MU-204)
Suggest to replace the tank in B6201 – on-going.
5 Water Quality WQater tanks in Res. Compound on 06/09/19. Job has been completed. BOQ to be revised as per the newv JAM
SOR book 22nd Dec. 2019
Lift Entrapment traning for JAM staffs done and awaiting for the training certitficates from the lift service 3rd week
6 QHSE HSE JAM
provider - Done Oct.’19
Notes and Action points of Meeting
Meeting Title: FM Service Provider – Weekly meeting (GMC23-C1, C9 & C12) MOM No.112
Date: 19th Dec 2019 Time: 1:00 pm Location: Madinat Zayed Office, WR
Attendees: MUSANADA – Abdelhalim Salih (AS), JUMA AL MAJID – Muthasim Hamed (MH), JUMA AL MAJID – Abdul Mohaisth (AM), JUMA AL MAJID – Jacqueline Bagang (JB)
Apologies: Circulation: NA
Meeting Aim: To discuss the operational issues and performance of the contract
DISCUSSION POINTS
No. Item Action Owner By
Generator Breakdown: as instructed by MSDA JAM not eligible for claiming services labor charges until JAM
issue an official letter for the justification of Operation procedure of the existing genertor, Only SP’s - full
reimbursable.
ADNOC compliance for the diesel supply – Quote required after shifting of Tanks (on-going comprehensive
7 E9056 JAM
contractor QIAS)
Civil Defence compliance – to coordinate w/ SOS & engr. Ahmed Salah
Additional assets to be added after handover (generators)
PPM Done by the DLP contractor, JAM verified and awaiting PPM service report from the DLP Contractor
Unclaimed Cluster 1 Hosson Al Sarrah - rental generator (GMC23:19334 & GMC23:19477), Transpo (GMC23:19478) DOT MSDA
8 3rd Nov 2019
Issues/Pending WO cabling works (GMC23:24036) Scoping
Team
Updated
9 3rd ACS – received Master ACS file on 12/11/2019 . C1 – 61% C12 – 88% C9 – 22% JAM/MSDA
ACS/Tagging/Registry
10 Energy Conservation JAM to confirm the schedule of the presentation of energy conservation intitiaitives w/ Engr. Helal JAM Jan 2020
JAM to submit the Nov.’19 summary of absence 22nd Dec 2019
Requested status of SP for CCU in H8004 JAM
11 Others Fixing Wiring Test – Schedule shared on 19/08/2019 – in-progress
MSDA
ACB replacement in Al Falah School postpone til further notice
Awaiting for ZHO Estidama certification validation
12 D4, Breach penalty D4 – subject to MGT. decision MSDA
NEXT MEETING
Date: 26th Dec 2019 Time: Location: Musanada office – WR
Meeting Aim: GMC23 C1, C9 & C12 – Western Region Madinat Zayed, Delma Island and Ghayathi FM project – weekly meeting