Notes and Action Points of Meeting: 1:00 PM Madinat Zayed Office, WR

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Notes and Action points of Meeting

Meeting Title: FM Service Provider – Weekly meeting (GMC23-C1, C9 & C12) MOM No.112
Date: 19th Dec 2019 Time: 1:00 pm Location: Madinat Zayed Office, WR
Attendees: MUSANADA – Abdelhalim Salih (AS), JUMA AL MAJID – Muthasim Hamed (MH), JUMA AL MAJID – Abdul Mohaisth (AM), JUMA AL MAJID – Jacqueline Bagang (JB)

Apologies: Circulation: NA
Meeting Aim: To discuss the operational issues and performance of the contract

DISCUSSION POINTS
No. Item Action Owner By

 KPI weekly Status (RM/CM Task) (01/12/19 – 18/12/19)


Corrective Reactive
Cluster
attend contain fixed attend contain fixed
Madinat Zayed 70% 74% 59% 91% 91% 88%
Ghayathi 92% 92% 85% 98% 98% 96%
Delma 82% 82% 64% 91% 91% 81%
Overall 82% 83% 68% 93% 93% 89%
1 RM/CM Tasks  Fixed status breakdown JAM
Corrective Reactive
Cluster Grand Total
late on time Overdue Total late on time Overdue Total
C1 10 16 1 27 9 86 3 98 125
C12 4 22 0 26 2 46 0 48 74
C9 3 25 11 39 4 26 2 32 71
Grand Total 17 63 12 92 15 158 5 178 270
 Time extension request are subject for CRM verification in the system.
 JAM to ensure that captured photos for attend, contain & fix are accurate.

Added Facility  MEP Services to commence on 1st Dec. 2019, external communication to be issued
2  JAM to submit Bldg Attributes, ACS/Asset Registry, Layout (Tamm Center vs. New facility ADDA), TAMM TBC
(ADDA – P004) Center ACS to be revised
3 KPI  scorecards received for Oct’19 subject for further discussion on 26th Dec. 2019 JAM/MSDA 26th Dec. 2019
Variation Orders and Awaiting for Procurement’s feedback for the discrepancy of fixed fees in J1190 – C1 (ref no. JAM-MU-203) and
4 MSDA
Payments C1179 – C9 (ref. no. JAM-MU-204)
 Suggest to replace the tank in B6201 – on-going.
5 Water Quality  WQater tanks in Res. Compound on 06/09/19. Job has been completed. BOQ to be revised as per the newv JAM
SOR book 22nd Dec. 2019
 Lift Entrapment traning for JAM staffs done and awaiting for the training certitficates from the lift service 3rd week
6 QHSE HSE JAM
provider - Done Oct.’19
Notes and Action points of Meeting
Meeting Title: FM Service Provider – Weekly meeting (GMC23-C1, C9 & C12) MOM No.112
Date: 19th Dec 2019 Time: 1:00 pm Location: Madinat Zayed Office, WR
Attendees: MUSANADA – Abdelhalim Salih (AS), JUMA AL MAJID – Muthasim Hamed (MH), JUMA AL MAJID – Abdul Mohaisth (AM), JUMA AL MAJID – Jacqueline Bagang (JB)

Apologies: Circulation: NA
Meeting Aim: To discuss the operational issues and performance of the contract

DISCUSSION POINTS
No. Item Action Owner By

 Generator Breakdown: as instructed by MSDA JAM not eligible for claiming services labor charges until JAM
issue an official letter for the justification of Operation procedure of the existing genertor, Only SP’s - full
reimbursable.
 ADNOC compliance for the diesel supply – Quote required after shifting of Tanks (on-going comprehensive
7 E9056 JAM
contractor QIAS)
 Civil Defence compliance – to coordinate w/ SOS & engr. Ahmed Salah
 Additional assets to be added after handover (generators)
 PPM Done by the DLP contractor, JAM verified and awaiting PPM service report from the DLP Contractor

Unclaimed  Cluster 1 Hosson Al Sarrah - rental generator (GMC23:19334 & GMC23:19477), Transpo (GMC23:19478) DOT MSDA
8 3rd Nov 2019
Issues/Pending WO cabling works (GMC23:24036) Scoping
Team
Updated
9  3rd ACS – received Master ACS file on 12/11/2019 . C1 – 61% C12 – 88% C9 – 22% JAM/MSDA
ACS/Tagging/Registry
10 Energy Conservation  JAM to confirm the schedule of the presentation of energy conservation intitiaitives w/ Engr. Helal JAM Jan 2020
 JAM to submit the Nov.’19 summary of absence 22nd Dec 2019
 Requested status of SP for CCU in H8004 JAM
11 Others  Fixing Wiring Test – Schedule shared on 19/08/2019 – in-progress
MSDA
 ACB replacement in Al Falah School postpone til further notice
 Awaiting for ZHO Estidama certification validation
12 D4, Breach penalty  D4 – subject to MGT. decision MSDA

NEXT MEETING
Date: 26th Dec 2019 Time: Location: Musanada office – WR
Meeting Aim: GMC23 C1, C9 & C12 – Western Region Madinat Zayed, Delma Island and Ghayathi FM project – weekly meeting