Millennium Dome
Millennium Dome
Millennium Dome
“Construction”
ALPS played a major role in the constriction process of the Dome roof, initially working with
the mast & roof support contractor during bidding stage to develop a safe and effective lifting
& access system to “raise the roof” later to procure and implement the roof lifting & access
systems.
ALPS design was simple yet effective, to convert each of the 12 steel masts into a 36 Ton
multi-directional crane effectively generating a combined force of 432Tons.
The lifting system was used initially to raise the central hub followed by raising all support
radials into place to enable securing pins to be placed and the roof support to be competed.
ALPS supplied a “mast master” for each of the 12 masts all working as a team and each
controlling 3 linear winches during lifting.
Left: The central hub was ~30m dia’ and weigh some 80 tons, it had to be raised 50M
centrally in order to attach the support cable sockets to the top of each mast.
Right: To accelerate production ALPS equipped each mast with a wire guided powered access
& egress platform.
Once the steel wire roof support was installed ALPS continued working on the project for the
American roofing contractors supplying and installing special 24M long radial access
platforms, (as above), Engineered Access Systems & Specialist Rope Access labour.
Access Lifting Pulling & Safety Ltd: Stubley Hollow, Sheffield, S18 1PA UK.
t’ 01246 413111