RBU Operation Manual
RBU Operation Manual
RBU Operation Manual
Operation Manual
z Thank you very much for your buying RBU series regenerative break unit.
z Before use, please read this manual thoroughly to ensure proper usage. Keep this
manual at an easily accessible place so that can refer anytime as necessary.
Safety Precautions
Please read this operation manual carefully before installation, operation, maintenance or
inspection.
In some cases, even the contents of “CAUTION” still can cause serious accident.
Please follow these important precautions in any situation.
★ NOTE indicate the necessary operation to ensure the device run properly.
I
TABLE OF CONTENTS
II
LIST OF FIGURES
III
Introduction
1. INTRODUCTION
1.1 Technology Features
Break Moment 60s with 100% of rated torque (25% Duty cycle), can
continuously run with 80% of rated torque.
AC Voltage Range +10% to -15%, the imbalance between phases less than
2%.
1
Introduction
Rated
Input DC rated DC rated
Model No. Power Size
voltage current (A) current (A)
(KW)
RBU-011-4 380V 11 19 15
RBU-015-4 380V 15 26 20
RBU-022-4 380V 22 37 30
RBU-030-4 380V 30 51 40
RBU-037-4 380V 37 64 50
RBU-045-4 380V 45 77 60
RBU-055-4 380V 55 96 75
2
Introduction
A B L W D
Installation
Power (mm) (mm) (mm) (mm) (mm)
Hole
(kW) Installation
External Dimension (mm)
Dimension
7.5-22 In developing
3
Inspection
2. INSPECTION
CAUTION
● Don’t install or use any RBU that is damaged or have fault part, otherwise may
cause injury.
1. Inspect the entire exterior of the RBU to ensure there are no scratches or other
damage caused by the transportation.
2. Ensure there is operation manual and warranty card in the packing box.
3. Inspect the nameplate and ensure it is what you ordered.
4. Ensure the optional parts are what you need if have ordered any optional parts.
Please contact the local agent if there is any damage in the RBU or optional parts.
4
Installation
3. INSTALLATION
WARNING
● The person without passing the training manipulate the device or any rule in the
“Warning” being violated, will cause severe injury or property loss. Only the person,
who has passed the training on the design, installation, commissioning and
operation of the device and gotten the certification, is permitted to operate this
equipment.
● Input power cable must be connected tightly, and the equipment must be grounded
securely.
● Even if RBU is not running, the following terminals still have dangerous voltage:
- Power Terminals: R, S, T
● When power off, should not install the RBU until 5 minutes after, which will ensure the
device discharge completely.
● The section area of grounding conductor must be no less than that of power supply
cable.
CAUTION
●When moving the RBU please lift by its base and don’t lift by the panel. Otherwise
may cause the main unit fall off which may result in personal injury.
● Install the RBU on the fireproofing material (such as metal) to prevent fire.
● When need install two or more RBU in one cabinet, cooling fan should be provided to
make sure that the air temperature is lower than 45°C. Otherwise it could cause fire
5
Installation
3.1.1 Temperature
Environment temperature range: -10°C ~ +40°C. RBU will be derated if ambient
temperature exceeds 40°C.
3.1.2 Humidity
Less than 95% RH, without dewfall.
3.1.3 Altitude
RBU can output the rated power when installed with altitude of lower than 1000m. It will
be derated when the altitude is higher than 1000m. For details, please refer to the
following figure:
(m)
Figure 3.1 Relationship between output current and altitude.
3.1.4 Impact and Oscillation
It is not allowed that the RBU falls down or suffers from fierce impact or the RBU installed
at the place that oscillation frequently.
3.1.5 Electromagnetic Radiation
Keep away from the electromagnetic radiation source.
3.1.6 Water
Do not install the RBU at the wringing or dewfall place.
3.1.7 Air Pollution
Keep away from air pollution such as dusty, corrosive gas.
3.1.8 Storage
Do not store the RBU in the environment with direct sunlight, vapor, oil fog and vibration.
6
Installation
7
Installation
3.4 Disassembly
8
Wiring
4. WIRING
WARNING
● Wiring must be performed by the person certified in electrical work.
● Forbid testing the insulation of cable that connects the RBU with high-voltage
insulation testing devices.
● Cannot install the RBU until discharged completely after the power supply is switched
off for 5 minutes.
● Be sure to ground the ground terminal.
400V class: Ground resistance should be 10Ω or less,
Otherwise, it might cause electric shock or fire.
● Connect input terminals (R, S, T) and output terminals (U, V, W) correctly.
Otherwise it will cause damage the inside part of RBU.
● Do not wire and operate the RBU with wet hands.
Otherwise there is a risk of electric shock.
CAUTION
●Check to be sure that the voltage of the main AC power supply satisfies the rated
voltage of the RBU.
Injury or fire can occur if the voltage is not correct.
● Connect power supply cables and regenerative cables tightly.
9
Wiring
Main circuit terminal functions are summarized according to the terminal symbols in the
following table. Wire the terminal correctly for the desired purposes.
Terminal Description
ON-OFF signal input, optical coupling with +24V and COM. Short
connect with COM.
S1: When terminal control is valid, automatical input;
S1~S4
S2: When terminal control is un-valid, manual input;
S3: Multi-function terminal (Default is external fault input)
S4: Multi-function terminal (Default is fault reset input)
10
Wiring
Terminal Description
Common ground terminal for digital signal and +24V (or external
COM
power supply).
Open collector output terminal, The corresponding common
ground terminal is COM.
Y
External voltage range: 0~24V
Output current range: 0~50mA
Provide output power supply of +24V.
+24V
Maximum output current: 150mA
AO Analog output terminal. Output range: 0~10V
Common ground terminal of analog signal and AO.
GND
GND must isolated from COM.
RO1A、 RO1 relay output: RO1A—common; RO1B—NC; RO1C—NO.
RO1B、RO1C Contact capacity: AC 250V/3A, DC 30V/1A.
11
Wiring
AC Reactor U
R
Electromagnetism contactor V M
S INVERTER
W
T (+)/P (-)/N
PE
Suggest to use FU
(+) (-)
R
S RBU
T
Automatic running S1
Manual running S2
Interface for
CN9 external keyboard
External fault S3
COM
Y
+24V Open collector
output
COM
PE
ROA1
ROB1 Relay
output 1
ROC1
12
Operation
5. OPERATION
5.1 Keypad Description
Programming
Entry or escape of first-level menu.
Key
UP Increment
Progressively increase data or function codes.
Key
DOWN
Progressive decrease data or function codes.
Decrement Key
13
Operation
3) Digital Display
Have 5 digit LED , which can display all kinds of monitoring data and alarm codes such as
mains voltage, bus voltage, output current and so on.
0~1
0: Keyboard control
P0.00 Control mode 1: Terminal control 1 0
S1 valid: automatical mode
S2 valid: manual mode
14
Operation
Regenerative voltage
P0.04 400.0~760.0V 650.0V O 4
of start
Regenerative voltage
P0.05 0.0~60.0V 12.0V O 5
range
Regenerative stop
P0.06 0.1~10.0S 1.0S O 6
time
0~1
P0.07 Input frequency 0: 50HZ 0 7
1: 60HZ
1~15
3: Valid when short connect S3 and 3 (External
P0.08 S3 terminal function 8
COM fault))
Others, reserved
1~15
2: Valid when short connect S4 and
P0.09 S4 terminal function 2 (Fault reset)) 9
COM
Others, reserved
P0.10 Reserved 1 O 10
0~8
0: DC bus line voltage (0~1000V)
P0.11 AO function selection 1 O 11
1: Output current (0~200.0%)
2~8: Reserved
AO lower limit
P0.13 0.00V ~10.00V 0.00V O 13
corresponding output
AO upper limit
P0.15 0.00V ~10.00V 10.00V O 15
corresponding output
0~1
Cooling fan running 0: Run after start
P0.16 1 O 16
mode 1: Start when temperature higher
than 45℃
15
Operation
Under voltage
P0.19 300.0V ~400.0V 380.0V O 19
protection
AC 0~1
P0.22 input phase-failure 0: Unvalid 1 22
protection 1: Valid
AC
P0.23 input phase-failure 0.5~10.0S 1.0S 23
protection time
0~2
Restore function
0: no change
P0.25 parameters, 0 25
1: Restore factory setting
clear fault record
2: Clear fault record
16
Operation
5: Reserved
6: Over-current (OC3)
7: Reserved
8: Reserved
9: Over-voltage (OV3)
10: DC bus Under-voltage(UV)
11: Reserved
12: Inverter overload (OL2)
13: Reserved
14: Input phase failure (SPI)
Latest 15: Reserved
P0.30 ● 30
fault type 16: IGBT overheat (OH2)
17: External fault (EF)
18: Reserved
19: Current detection fault (ITE)
20: Reserved
21: EEPROM fault (EEP)
22: Reserved
23: Reserved
24: Reserved
25: Control power fault (CP)
26: Parameter setting wrong (PEr)
Output current at
P0.31 ● 31
current fault
DC bus voltage at
P0.32 ● 32
current fault
0~1
P0.33 Parameter locked 0: No locked 0 O 33
1: Locked
0~1
0: Keyboard control
P0.00 Control mode 1: Terminal control 1 0
S1 valid: automatical mode
S2 valid: manual mode
17
Operation
Automatical mode:
When in automatical mode, RBU detects the bus line voltage and realizes start and stop
automatically.
When the bus voltage is higher than P0.04, start the regeneration.
When the bus voltage is lower than P0.04, stop the regeneration.
Manual mode:
When start the running command, RBU regenerates all the time.
18
Trouble Shooting
6. TROUBLE SHOOTING
Fault
Fault Type Reason Solution
Code
1. Inspect external
1. IGBT module fault.
equipment and eliminate
2. Malfunction caused by
OUT IGBT fault interference. Press
interference.
STOP/RST to reset
3. Grounding is not properly.
2. Ask for support.
1. Set
1. Sundden change of 2. Decrease
regenerative power regenerative voltage
Over-voltage
OV 2. More higher threshold threshold
when running
setting of RBU 3. Use RBU with higher
3. No enough capacity of RBU power
4. Ask for support
1. Select variable
1. More lower threshold frequency motor.
setting of RBU 2. Check and adjust V/F
OL RBU overload 2. Sundden change of curve.
regenerative power 3. Check and adjust
3. More lower power of RBU PB.03
4. Check the load.
1. Check AC input
Input phase
SPI Power off at AC input power supply.
failure
2. Ask for support
S3: External fault input Inspect external
EF External fault
terminal take effect. equipment.
19
Trouble Shooting
20
Maintenance
7. MAINTENANCE
WARNING
● Maintenance must be performed according to designated maintenance
methods.
● Maintenance, inspection and replacement of parts must be performed only by
certified person.
● After turning off the main circuit power supply, wait for 10 minutes before
maintenance or inspection.
● DO NOT directly touch components or devices of PCB board. Otherwise
inverter can be damaged by electrostatic.
● After maintenance, all screws must be tightened.
In order to prevent the fault of RBU to make it operate smoothly in high-performance for a
long time, user must inspect the RBU periodically (within half year). The following table
indicates the inspection content.
Oil mist and dust Ensure there are no oil mist and dust in the RBU.
Inspect RBU to ensure whether there are abnormity
RBU heat and vibration.
Fan Ensure the fan is running well, nothing inside to block it.
Ensure the input power voltage and frequency is in
Input Power allowed range.
21
Maintenance
Fans and electrolytic capacitors are wearing part, please make periodic replacement to
ensure long term, safety and failure-free operation. The replacement periods are as
follows:
◆Fan: Must be replaced when using up to 20,000 hours;
22