STNW1165ver3 Generator
STNW1165ver3 Generator
STNW1165ver3 Generator
Abstract: This standard provides the requirement for connecting embedded generation to operate
in parallel with Ergon Energy’s distribution network not exceeding 5MW.
Foreword
This Standard has been prepared by Ergon Energy to provide owners and Proponents of
embedded generation installations information about their rights and obligations for the connection
to and interfacing with the Ergon Energy Distribution Network. Embedded generators are defined in
the National Electricity Rules as generators connecting directly to the distribution network and not
the transmission network.
The National Electricity Rules also identify the requirements for generating systems connected to
transmission and/or distribution systems and, in part, requires that a person must not engage in the
activity of owning, controlling or operating a generating system connected to the interconnected
transmission or distribution system unless:
AEMO has decided that small generating systems satisfying any one of the following criteria
cannot significantly affect market outcomes and/or impact on system security, and, therefore, the
person owning, controlling or operating such generating systems is automatically exempt from the
requirement to register as a generator/ registered participant.
A generating system that has a total nameplate rating at a connection point of less than
5MW
A generating system that is not capable of exporting to a transmission or distribution
system in excess of 5MW
the nameplate rating of the generator exceeds 5MW but exports less than 20GWh in any
12 month period, or if extenuating circumstances apply; or
The generating system has no capability to synchronise or to operate electrically connected
to a distribution system or transmission system.
Notwithstanding the automatic exemption from becoming a Registered Participant under the
National Electricity Rules, Ergon Energy as the Distribution Network Service Provider, has an
inherent obligation to ensure that such embedded generation facilities do not cause a material
degradation in the quality of supply to other network users and do not adversely affect operation of
the distribution network.
Contents
1. General.......................................................................................................................... 1
1.1 Purpose .............................................................................................................. 1
1.2 Scope .................................................................................................................. 1
1.3 Application .......................................................................................................... 1
1.4 Enquiries ............................................................................................................. 1
2. References .................................................................................................................... 1
2.1 Ergon Energy controlled documents ................................................................... 1
2.2 Other documents ................................................................................................ 1
3. Definitions, Acronyms and Abbreviations ................................................................. 2
3.1 Definitions ........................................................................................................... 2
3.2 Acronyms and Abbreviations .............................................................................. 4
4. Network Connection Overview ................................................................................... 5
4.1 Network Connection Agreement ......................................................................... 5
4.2 Network Connection Assets ................................................................................ 5
4.3 Technical Considerations .................................................................................... 7
4.4 Types of Embedded Generators ......................................................................... 7
4.4.1 Export Embedded Generation............................................................................. 7
4.4.2 Non-Export Embedded Generation ..................................................................... 8
4.5 Permissible Generator Connection Arrangements .............................................. 8
5. Connection Application Process ................................................................................ 9
5.1 General Requirements for Connection of Generators ......................................... 9
5.2 Connection Enquiry............................................................................................. 9
6. Technical Requirements and Performance Standards ........................................... 11
6.1 General ............................................................................................................. 11
6.2 Network Connection Arrangement and Voltage Level ...................................... 11
6.2.1 General ............................................................................................................. 11
6.2.2 Nominal Interconnection Voltage ...................................................................... 12
6.2.3 Power Frequency .............................................................................................. 12
6.2.4 Network Characteristics .................................................................................... 13
6.2.5 Equipment Ratings............................................................................................ 13
6.2.6 Fault Levels and Protection Impacts ................................................................. 14
6.3 Generator Control System ................................................................................ 15
6.3.1 General Requirements ...................................................................................... 15
6.3.2 Means of Isolation ............................................................................................. 15
6.3.3 Synchronising and Synchronising Check Facilities ........................................... 15
ii Standard STNW1165 Ver 3
1. General
1.1 Purpose
The purpose of this Standard is to provide owners and Proponents of embedded generation
installations information about their rights and obligations for connection to and interfacing with the
Ergon Energy Network.
1.2 Scope
This Standard outlines the requirements for embedded synchronous generators and inverter based
systems with a total nameplate rating of up to, but not exceeding 5MW at a single connection point;
that are intended to be connected to and operate in parallel with, any part of Ergon Energy’s
distribution network under normal operating conditions.
1.3 Application
This Standard does not apply to:
Micro scale parallel customer generation via Inverters in the range up to 30 kW (3ph) (refer
to Ergon Energy’s Inverter Energy Systems (IES) Network Agreement Form
Larger generation over 5MW
Non-parallel back-up generation
Ergon Energy Distribution Networks connected to Ergon Energy’s 33 Isolated Power
Stations.
This document does not cover issues associated with the sale of electricity exported into the Ergon
Energy distribution network. This is a matter between the proponent and their selected electricity
retailer.
1.4 Enquiries
Further information may be obtained by emailing: Majorconnections@ergon.com.au
2. References
2.1 Ergon Energy controlled documents
Copies of Ergon Energy Standards may be obtained from the following website –
http://www.ergon.com.au/contractors,-suppliers--and--developers/electrical-contractors/forms,-
manuals-and-standards
Australian Energy Regulator A Federal Government body responsible for the economic
(AER) regulation of electricity distribution services in the National
Electricity Market.
Connection Point The agreed point of supply established between Network Service
Provider(s) and another Registered Participant, Non-Registered
Connection Applicant or franchise Connection Applicant.
Customer Asset Electrical assets that are owned by the customer and are designed
and constructed in accordance with AS/NZS 3000.
Check this is the latest version before use. Page 2 of 62 Standard STNW1165 Ver 3
Embedded generating unit A generating unit connected within a distribution network and not
having direct access to the transmission network.
Generating unit The actual generator of electricity and all related equipment
essential to its function as a single entity.
Generator A person who engages in the activity of owning, controlling, or
operating a generating system that supplies electricity to, or who
otherwise supplies electricity to, a transmission or distribution
system and who is registered with NEMMCO in that capacity.
Inverter Energy System A system comprising one or more inverters together with one or
more energy sources (which may include batteries for energy
storage), controls and one or more grid protection devices.
Low Voltage Connection Point The low voltage terminals of the distribution transformer. The
DNSP is responsible for the operation and maintenance of the
transformer and other HV equipment and the Connection Applicant
is responsible for the installation, operation and maintenance of
the all low voltage equipment.
Multiple Earth Neutral (MEN) Multiple earth neutral system of earthing is one in which the LV
neutral conductor is permanently connected to earth.
Supervisory Control and Data The SCADA system is used by Ergon Energy to manage and
Acquisition (SCADA) operate the Distribution Network.
Small to Medium Scale For the purpose of this Standard a small scale embedded
Embedded Generation generator is up to a capacity of 1 MW and a medium scale
Installation embedded generator is up to a capacity of 5 MW.
Check this is the latest version before use. Page 3 of 62 Standard STNW1165 Ver 3
National Electricity Rules The National Electricity Rules govern the operation of the National
(NER): Electricity Market.
National Metering Identifier A National Metering Identifier as described in NER clause 7.3.1(d).
(NMI)
Network: The apparatus, equipment, plant and buildings used to convey,
and control the conveyance of, electricity to customers (whether
wholesale or retail) excluding any connection assets. In relation to
a Network Service Provider, a network owned, operated or
controlled by that Network Service Provider.
Network Coupling Point The point at which connection assets join a distribution network,
used to identify the distribution service price payable by a
Connection Applicant.
Network Augmentation Works: Augmentation works required on network assets to enable a new
project to be supplied or the increase in supply for an existing
Connection Applicant.
Network Islanded Operation: Generation is allowed to “back feed” into a portion of the
distribution network that is isolated from the rest of the electricity
supply network, typically as a result from a protection operation on
the transmission or distribution network.
Registered Participant: A person who is registered by AEMO in any one or more of the
categories listed in clauses 2.2 to 2.7 [of the NER] (in the case of a
person who is registered by AEMO as a Trader, such a person is
only a Registered Participant for the purposes referred to in clause
2.5A [of the NER]). However, as set out in clause 8.2.1(a1)[of the
NER], for the purposes of some provisions of clause 8.2 [of the
NER] only, AEMO and Connection Applicants who are not
otherwise Registered Participants are also deemed to be
Registered Participants.
Retailer: Means the holder of an electricity retail licence granted under the
Electricity Act, 1994, who is contracted to sell electricity to the
Customer at the Supply Address.
Service Provider (SP): A person or organisation authorised by the DNSP to carry out
design and/or construction of certain electrical works.
Check this is the latest version before use. Page 4 of 62 Standard STNW1165 Ver 3
The Proponent shall indemnify Ergon Energy and accept liability for safety and supply quality
issues that occur when the generator is operating. Ergon Energy will provide supply to local
customer loads on a no-risk basis. This requirement shall apply to all loads that are connected on
the customer side of the network Boundary and which can be supplied from the generator.
Where Connection Assets include transformers, the Network Coupling Point and low voltage
metering will normally be on the low voltage side of the transformer. HV metering will be installed
in situations where the customer owns and operates the HV assets.
Check this is the latest version before use. Page 5 of 62 Standard STNW1165 Ver 3
Network
(HV) Legend
NCP Network Coupling Point
CP Connection Point
MP Metering Point
NCP
NCP NCP MP
CP
Customer Owned
Connection Assets
Connection Assets
• HV
Connection Assets • HV
• HV & LV
MP
CP Customers
CP Electrical
Customers MP
Electrical Installation
Installation Customers
Electrical
Customer Facility or
Installation
Customer Facility or Development Site
Development Site
Customer Facility or Customer 3
Customer 1 Development Site
Customer 2
Check this is the latest version before use. Page 6 of 62 Standard STNW1165 Ver 3
Prior to the connection of an embedded generator to the distribution network Ergon Energy will
carry out a detailed analysis study of the network. The detailed analysis study and subsequent
engineering report will identify any network operating constraints, network reinforcement
requirements due to increases in fault levels, levels of VAR support, network voltage compensation
control, operating protocols and interface requirements between the Generator and Ergon Energy
for the proposed connection.
Ergon Energy will require information (as detailed later in the document) to perform the detail
analysis study and fees may apply.
A direct connected generation unit is directly connected to the distribution system. An export
embedded generating unit and a direct connected unit must have an agreement with a Retailer to
Check this is the latest version before use. Page 7 of 62 Standard STNW1165 Ver 3
All export embedded generating units may require communication links installed between Ergon
Energy and the embedded generating unit installation to provide SCADA monitoring and control.
This will be determined by Ergon Energy in accordance with Section 6.6.
To minimise the potential for adverse impact on the quality of electricity supply to other network
customers, the following limitations shall apply for this connection arrangement:
Ergon Energy will not provide LV circuit ties between the dedicated transformer / LV circuit
incorporating the embedded generator network connection point and adjacent transformers
or substations.
Only local load associated with the Proponent’s own installation shall be supplied from the
section of the customer’s installation that is supplied from the embedded generator. The
connection of other customer loads to the dedicated substation or transformer as applicable
shall not be permitted. Where this results in a requirement for additional network equipment
or infrastructure, the total cost of such equipment/infrastructure shall be borne by the
Proponent.
If the embedded LV generation facility is proposed to connect to the Ergon Energy
distribution network at an existing transformer or substation, any existing loads not related
to the local customer site must be relocated to other network supply sources or an
approved protection system installed. The total cost of such works shall be borne by the
Proponent.
Notwithstanding the above limitations, connection to, and parallel operation with, any part of Ergon
Energy’s network shall be subject to achieving compliance with the requirements outlined in this
document at each point capable of paralleling the generator with Ergon Energy’s LV distribution
network.
Furthermore, in accordance with this document and Qld Electricity Connections and Metering
Manual - Service and Installation Rules, the Proponent shall ensure that where an embedded LV
generator connects within the customer’s installation and supplies only part of the customer’s
installation:
Adequate mechanisms are provided to ensure that paralleling of Ergon Energy substation
transformers from within the customer’s installation cannot occur; and/or
The generator cannot be connected to the Ergon Energy LV distribution network without
synchronisation and the associated protection systems.
Check this is the latest version before use. Page 8 of 62 Standard STNW1165 Ver 3
Generators that are intending to export energy to the network must enter into a power purchase
arrangement with an Energy Retailer and have export and import metering installed.
Connection Applicants facilities shall comply with technical and performance standards as defined
in the NER and Ergon Energy’s Connection Agreement. (e.g. protection systems, disturbing loads,
harmonic emission limits, and power factor).
Detailed technical requirements for the connection of Generators are outlined in Section 6.2.
The enquiry must be submitted on the Ergon Energy Connection Enquiry form.
It is recommended that the Connection Applicant makes early contact with an Electricity Retailer.
The installation cannot be connected unless there is an electricity supply contract between the
Connection Applicant and an Electricity Retailer.
Additional information may be required by Ergon Energy and this will be advised as necessary.
Further information on the Connection Application is given in the Large Customer Connections
Process.
The Proponent shall submit the following technical information as part of their Connection
Application.
(a) Detailed description of the proposed embedded generation facility; including, but not
limited to:
(b) Anticipated 24 hour local customer load profiles (both summer and winter) for the local
customer loads that are to be normally supplied from the embedded generation facility.
The profiles shall include apparent power (S), active power (P) and reactive power (Q) for
both lightly loaded and maximum demand scenarios.
(c) Anticipated 24 hour power (import from network) / (export to network) profiles (both
summer and winter) at the network connection point. The profiles shall include apparent
power (S), active power (P) and reactive power (Q) for both lightly loaded and maximum
demand scenarios.
(d) Site Plan showing the precise physical location of the embedded generator, the location of
customer main switchboards and other relevant switchboards and the location of Ergon
Energy substations and associated infrastructure.
(e) Detailed electrical single line diagram(s) showing the configuration of all embedded
generation facility/customer equipment and circuits between the embedded generator(s)
and the network connection point; including as a minimum:
All primary circuit equipment such as main switchboards, other switchboards, circuit
breakers and isolators/load break switches. In particular, all points where the
customer embedded generation facility and the Ergon Energy distribution network can
be connected / disconnected must be clearly identified.
All secondary protection and control equipment associated with the generator’s
connection and parallel operation with the Ergon Energy distribution network
including:
Local customer load connections including any interconnections with other parts of
the customer’s installation. In particular, where interconnection with other parts of the
customer’s installation are proposed the means to prevent paralleling of Ergon
Energy substations/transformers and/or unsynchronised connection to the Ergon
Energy distribution network shall be clearly identified.
All metering equipment associated with the generator and the import and export of
power from/to the Ergon Energy distribution network.
All proposed power factor correction equipment that will be installed within the part of
the customer’s installation that is supplied directly from the embedded generator.
(f) Detailed functional block / schematic diagram of the protection and control systems
relevant to the generator’s connection to the Ergon Energy distribution network showing
the philosophy of the protection and control systems including all relevant relay current
circuits, relay potential circuits, alarm and monitoring circuits, back-up systems, auxiliary
Check this is the latest version before use. Page 10 of 62 Standard STNW1165 Ver 3
(g) Detailed schematic diagram of the proposed earthing system arrangements for the
embedded generation facility and associated customer electrical installation including all
proposed earth connections, MEN connections and relevant switchboard earthing
arrangements.
(h) Generator data for each generator proposed to be installed as listed in Annex B or C,
depending on generator type.
(i) Full details of the proposed metering equipment and associated current transformers.
Nomination of the Responsible Person for metering in accordance with the National Grid
Metering.
(j) Full details of any proposed power factor correction equipment including:
Sufficient detail must be provided to enable Ergon Energy to assess compliance with the minimum
requirements outlined in this document, and conduct protection and load flow studies to assess the
impact on plant fault ratings, protection scheme requirements and power export limits of existing
infrastructure; and assess generator power factor and voltage limit requirements.
The equipment associated with each generating unit must be designed to withstand without
damage the range of operating conditions which may arise consistent with the specified system
standard of NER (Schedule S5.1a).
Generators must comply with the performance standards and any attached terms or conditions of
the Connection Agreement in accordance with a relevant provision of NER Schedules S5.2.
The voltage level which an embedded generator will be connected depends primarily on the size of
the generator, and the availability of distribution network in the area concerned.
An investigation will need to be undertaken by Ergon Energy to determine the most appropriate
connection voltage.
The AEMC standards state that “The frequency operating standards require that, during periods
when there are no contingency events or load events, the frequency be maintained within the
normal operating frequency band (49.85 Hz to 50.15 Hz) for 99% of the time, with larger deviations
permitted within the normal operating frequency excursion band (49.75 Hz to 50.25 Hz) for no
more than 1% of the time.” (See Table 2)
AS/NZS61000.2.2 details that the frequency range is typically plus or minus 1 Hz, but it is usually much less where
1
synchronous interconnection is used on a continental scale. This requirement is overridden by the National Electricity
Rules.
Check this is the latest version before use. Page 12 of 62 Standard STNW1165 Ver 3
The frequency standards in Table 3 apply to where a part of the national grid becomes islanded.
This table does not strictly apply to isolated systems but will be used by Ergon Energy as no other
standard applies at this time.
Frequency Operating Standards published by the AEMC Reliability Panel Frequency Operating Standards
2
Typical distribution feeders are fed radially from a utility substation. In these feeders, all of the
short-circuit fault current for faults on the feeder, as well as the load current, will come from the
source substation. The magnitude of the fault current is determined by the impedances of the
utility source, the transformers, reactors and feeder conductors etc, and fault resistance.
Embedded synchronous generators, will increase the fault current level at the fault point and
reduce the current being supplied by the source substation to the point of actually causing a
reversal of fault current flow in some circuits.
The maximum and minimum values of fault current are an important consideration for any
protection scheme. Maximum values determine the interrupting rating needed for circuit breakers,
automatic circuit reclosers (ACRs), fuses, etc as well as the upper design limit for the protection
scheme performance. Minimum current values determine the lower limit settings of overcurrent,
earth fault relays and other protective devices to provide a satisfactorily high probability of
detecting all faults. .
On a radial feeder, all protective devices between the substation relays and the fault measure the
same current if the substation is the only source. This simplifies the coordination of overcurrent
tripping devices to interrupt the fewest number of customers. Earth fault coordination may be
affected if feeders have other sources of earth current.
Sources of feeder fault current due to embedded generation may affect relay, fuse and ACR
coordination, equipment rating, and safety of utility personnel and the general public. The
magnitude of fault current from these sources will depend upon the type, size, and number of
generators, their impedances, and their location with respect to the fault and utility substation.
If the embedded generation contribution is large, the operation of the relays at the substation may
be delayed due to a reduction in fault current from the source substation. A more likely case is
that of a relatively high impedance embedded generation source located near the source
substation. Such an arrangement contributes limited fault current until the utility circuit breaker
opens, which may result in slow detection and sequential clearing of the fault. These multiple
current source problems will apply to phase-to-earth faults if there is an earthed neutral
(transformer or generator) at the faulted network voltage level.
A fault study is essential for embedded generation proposals covering faults in the customer
installation and the utility network. This should recognise the presence of other embedded
generation installations that may be “electrically” nearby.
The fault levels shall not exceed the embedded generator equipment rating. Temporary fault
levels (less than 1 minute) above the equipment rating may be tolerable based on a case by case
risk assessment basis.
Where transformers operate in parallel, Ergon Energy has additional requirements as given in
Annex D.
Check this is the latest version before use. Page 14 of 62 Standard STNW1165 Ver 3
Note: Ergon Energy circuit breakers are not fitted with synchronising facilities.
All protection equipment must comply with the relevant Australian and International Standards. All
protection equipment must be tested and commissioned by a competent commissioning officer, to
the agreed settings, and a Certificate of Compliance for the complete generator installation must
be issued by the Proponent to Ergon Energy prior to connection to the network.
The Proponent must keep a written record of all protection settings and of test results. A copy of
this record should be available at the service point or as required by Ergon Energy.
The protection shall be designed in accordance with Ergon Energy standards, which require a
main and back-up set of protection to detect all credible fault types. The protection will include
sufficient redundancy to ensure that a faulted element within the protection zone is disconnected
from the network within the applicable fault clearance time with any single protection element
(including communications upon which that protection system depends) out of service.
The Generator must submit complete details of the generator protection system including the
proposed settings to Ergon Energy for review and agreement.
Embedded generators must not be able to operate in network islanded mode. To prevent the
generator operating in network island mode, an Ergon Energy approved protection scheme/s shall
be installed. These schemes may include:
Check this is the latest version before use. Page 16 of 62 Standard STNW1165 Ver 3
Proponents may propose other forms of loss of mains protection schemes which are commercially
available. These schemes need to be approved by Ergon Energy.
In addition to the protection installed for the generator, the generator proponent must install a
protection system so that:
The generator cannot connect onto the Ergon Energy Network unless all phases of the
Network are energised at the supply point. The connection must ensure synchronisation
before closure. If one or more phases of the Network are lost, then the generator must
disconnect from the Network;
The protective equipment is operating within the agreed protection settings;
If a system abnormality occurs that results in an unacceptable deviation of voltage or
frequency at the supply point, the generator must be disconnected from the Network; and
The generator is to automatically disconnect from the Network in the event of failure of any
auxiliary supplies to the protection equipment that would inhibit its correct operation.
When any of these conditions are detected the generator must be disconnected from the network
at an agreed circuit breaker within the embedded generator’s system that will ensure complete
disconnection. To detect these conditions, as set out above, the Proponent must install suitable
protection. Table 5 outlines the range of risk scenarios to the network and the protection
requirements to address the network risks.
The protection equipment shall be compliant with the relevant sections of IEC60255 and operate
the circuit breaker directly or through interposing equipment that is also compliant to the relevant
sections of IEC60255. Marshaling of protection trips through control equipment that is not
compliant to IEC60255 is not acceptable.
The instrument transformers used to interface the protection equipment to the proponents
installation must be compliant with the relevant sections of AS60044.
Check this is the latest version before use. Page 17 of 62 Standard STNW1165 Ver 3
A communication link may be required between the embedded generator and the Ergon Energy’s
substation. This link must be continuously monitored for integrity. In the event that the link fails the
generator must be automatically disconnected from the network until the communications link is
restored.
Check this is the latest version before use. Page 18 of 62 Standard STNW1165 Ver 3
Generator overcurrent and earth fault protection relays should have compensation for under
voltage field weakening unless the Proponent can demonstrate that voltage depression at the
generator during fault events will not adversely impact on protection scheme operation.
As this protection scheme will require the installation of voltage transformer(s) on the Ergon Energy
HV distribution network near the network connection point; the voltage transformer(s) will be
supplied and installed by Ergon Energy. The total cost of this VT and associated equipment will be
borne by the Proponent.
The voltage transformer(s) required for this protection scheme may be either 3 x single phase
voltage transformers or a single three phase 5 limb voltage transformer, with the primary winding
star point connected to earth and the secondary winding connected in broken delta supplying a
NVD protection relay. If Overvoltage/Undervoltage or Overfrequency/Underfrequency protection is
required, an additional star connected secondary winding shall be provided on the voltage
transformer.
Ergon Energy will provide the VT secondary wiring to the Generator Interface Cubicle. The
Proponent will be required to supply and install the NVD protection relay and associated equipment
/ wiring within the embedded generation facility.
Check this is the latest version before use. Page 19 of 62 Standard STNW1165 Ver 3
Similarly, where Ergon Energy has nominated a limit on the amount of power that can be exported
to the distribution network as a result of network infrastructure or performance constraints power
limit protection shall be installed at the network connection point.
Any power limit protection settings will be determined by Ergon Energy at the detailed design stage
after the detailed network studies have been undertaken.
The power protection must include three phase power monitoring relays installed at the Network
Coupling Point to prevent the embedded generating unit exporting power beyond the agreed power
limit to the distribution network.
Where no export operation is permitted the power monitoring protection is to be set to ensure
electricity is always imported from the distribution network; (typically a minimum threshold of 10%
of the nominal supply rating to the customer’s installation as determined by instrument transformer
and protection relay capabilities).
Where an export power limit has been provided by Ergon Energy the Proponent shall have a
protection system that is capable of operating within 10% of the nominated power limit.
Whenever the power protection limit is exceeded for more than 2 seconds, the embedded
generating unit must be disconnected from the distribution network.
Power protection shall be compliant with the relevant sections of IEC60255 and directly operate
the circuit breaker or operate through interposing equipment that is also compliant to the relevant
sections of IEC60255. In addition to the power protection specified by Ergon Energy the user may
manage their power export through their control system.
The instrument transformers used to interface the protection relaying equipment to the proponents
installation shall be compliant with the relevant sections of AS60044.
a) Interruption of the embedded generation fault current flow or energisation of all faults on the
interconnecting feeder detected by protection at the source substation.
b) Secure, quick and direct separation at the embedded generation installation for LoM
conditions. This can include manual or auto tripping all of the circuit breakers in the source
substations that could result in islanding.
Check this is the latest version before use. Page 20 of 62 Standard STNW1165 Ver 3
The communications link can also be used for monitoring or SCADA type services from the
embedded generation installation back to Ergon Energy. Where such a communications link is a
part of the primary protection scheme either for interconnecting circuit protection or LoM, then its
availability and integrity should be monitored. Depending on the level of risk accepted, it may be
necessary to prevent operation of the embedded generator, but not customer load, or not allow
parallel operation of the generation, should the communications link be out of service.
Figure 2 following shows a complete range of protection types superimposed on a low voltage
embedded generation installation configured according to Arrangement 2 from Annex A. The types of
protection and their function are summarized in
Table 6 and discussed below.
Check this is the latest version before use. Page 21 of 62 Standard STNW1165 Ver 3
The operating time of feeder protection can be relatively slow and may not clear faults fast enough
to prevent transient instability of embedded synchronous generation. In this scenario faults on
adjacent feeders, that is not the interconnecting feeder, may be cleared too slowly for the
embedded generator to maintain synchronism.
It is a general utility requirement that the earth fault protection be quite sensitive because as noted
above feeder phase-to-earth faults can involve hazards that need to be minimized.
The feeder protection P1a can send a remote trip via P2S (see below) where a protection signaling
quality communications link is available.
Live Line blocking (or Voltage Check) may be installed with the feeder auto-reclose to prevent a
reclose attempt should the feeder be back energised by the embedded generation. Unless this
feature is specifically requested by the generator proponent it will not be implemented. Clearly for
this a line-side voltage transformer would be required. Where this feature is specifically requested
a study will be carried out to determine if the VT can be retrofitted. The cost of the study and
installed solution will be on a fee-for-service basis and will be borne by the proponent.
Check this is the latest version before use. Page 22 of 62 Standard STNW1165 Ver 3
Zone Substation
Distribution Substation Customer Installation
P1b Internal
P3 P6 Customer
Load Embedded
Generation
CB2 CB3
M M G
BUS P5 P8 P9
P4 P7 P7
P1a
P11
Syn
Syn
P2S P2R
Aux
P10
Supply
Figure 2 – Protection for Low Voltage Embedded Generation with Dedicated Low Voltage Connection
Generation at low voltage with parallel low voltage load – Dedicated low voltage connection – Shared HV feeder
Check this is the latest version before use. Page 23 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 24 of 62 Standard STNW1165 Ver 3
PROTECTION
PROTECTION SCHEME and COMPONENTS TRIPPING COMMENTS
PROVIDED
Distribution Substation LV Protection CB3
LV bus - primary
Phase Overcurrent
Earth Fault
Main or Generator Circuit Breaker Synch Prevents closure of CB4 or CB5 as required
Check Interlock Prevent closing for
Phase angle difference network or
Voltage difference generation
Phase sequence abnormality
Slip frequency
Customer Incoming Protection CB4
Check this is the latest version before use. Page 25 of 62 Standard STNW1165 Ver 3
If a remote trip is the primary or only means ensuring separation for LoM or interrupting embedded
generation feeder fault energisation, then best practice would require that the communications link
be monitored and the generation be shut down if the link is not healthy. Therefore a good
reliability is necessary. Telco communications links are sometimes used but may not always be
reliable enough. Utility grade protection signaling using digital radio, supervisory cable, or optical
fibre cable are preferred. Power line communication (PLC) can also be used if it can successfully
signal through a feeder fault.
A direct remote trip can be the most secure method of providing LoM unless there is switchgear
installed between the source substation circuit breaker and the embedded generation. If this
switchgear can be automatically or manually opened then the remote trip would not ensure loss of
mains separation.
Note that if the communications link is suitably physically located then line differential protection
could be added for sole use feeders. Ergon Energy’s period contract for line differential protection
will be used to determine the relay types for line differential protection.
Check this is the latest version before use. Page 26 of 62 Standard STNW1165 Ver 3
This protection needs to be applied on the high voltage side of the connection transformer and a
suitable voltage transformer will be required. The voltage transformer needs to transform the zero
sequence voltage correctly and either three single phase voltage transformers with an earthed star
connected primary winding connection or a 5-limb three-phase voltage transformer with a residual
voltage winding is required. In the former case the voltage signal for the NVD protection is
obtained from a set of secondary windings connected in open delta, or from an appropriately
connected set of auxiliary voltage transformers connected to earthed star connected secondary
windings on the main voltage transformer.
Neutral Displacement Protection will be required for applications that have the ability to export
power and enough generation capacity to supply the minimum anticipated load on the smallest
adjacent network section.
The UV-OV Protection may be installed on the HV side as discussed in Section 6.5.7 (i.e. as P5) in
which case the protection here could be used as a backup if that was required.
The LoM protection may be backup to a remote trip system (P2) or the primary means of detecting
separation with the UV-OV and UF-OF possibly with reverse power as backup.
The generator protection would act as backup for failure of protection P8 or its associated circuit
breaker.
To facilitate the interface between the Generator and Ergon Energy, a communications system
may be required. The communication link will be assessed on a case by case basis but in general
is required where the embedded generator has the potential to operate as part of a network
support agreement.
Where the site has been provided with intertripping facilities the communications system shall
provide a two-channel communications link, one for protection inter-trip and the second for the
SCADA interface for the monitoring and control of the generator network access. This
communications link must be continuously monitored for integrity. In the event that the link fails the
generator must be automatically disconnected from the network until the communications link is
restored.
Ergon Energy will nominate both the type and amount of data, and the location of the SCADA
interface point in the distribution network SCADA system (typically a nearby zone substation).
The Proponent shall provide the following remote monitoring and control functions, for each
generator and/or network connection point, as applicable, to the Ergon Energy Network System
Control Centre. The minimum functionality to be provided is given in Annex F.
Subject to availability, Ergon Energy prefers the use of fibre optic telecommunications cable
between the generating unit and the nominated SCADA interface point, and the nominated
protection intertripping point. The Proponent shall provide and install telephone line isolation
equipment to comply with ACA, NEC and TC regulations. Where fibre optic telecommunication
cables are not readily available, Ergon Energy will investigate the suitability of alternative radio
options. This will be done on a case by case basis.
In the event of communications failure for the protection intertripping circuit, it will be responsibility
of the Generator’s protection equipment to trip the source of generation. The generation source
shall remain tripped until the protection intertripping communications circuit is operating.
Where the Ergon Energy feeder to the generating station is dedicated and the Connection
Application states that Ergon Energy is allowed to energise the distribution feeder at the local zone
substation without confirming that the generating unit has tripped, then a communications failure
on the SCADA circuit can be ignored. If this is not the case, then a communications failure on the
SCADA circuit must also cause the source of generation to trip and inhibit closure until the
communications fault clears.
Communications services must continue to operate when the Generator is off-line.
Selected components of Ergon Energy’s protection, SCADA, and communications systems will
need to be installed at the Generator’s facility to facilitate intertripping, SCADA and
communications interface requirements. Ergon Energy will provide the equipment in a panel.
Check this is the latest version before use. Page 29 of 62 Standard STNW1165 Ver 3
If a switch fuse is used instead of HV circuit breaker, the switch fuse shall meet the requirements of
the appropriate Australian Standard (AS 1033 - High voltage fuses) and provide short-circuit and
secondly overload protection. To be effective, fuses shall not operate for magnetising inrush
currents, cold-load pickup or sustained overloads. The HV fuse shall also coordinate with the
upstream protective devices and grade where possible, with the LV fuse for all possible values of
fault current.
Effective isolation of this neutral may be required to inhibit the flow of harmonic currents through
the neutral. The Proponent is to investigate and advise Ergon Energy on their proposed method to
limit harmonic currents through the neutral. The Proponents proposed scheme would be subject to
the proposed commissioning and testing.
G Distribution
Network
E/F
Figure 3 – Generator connected via a Star-Delta transformer with the neutral directly connected to earth
All metallic equipment housing and fixtures shall be connected to an earth point in accordance with
AS/NZS 3000.
Alternative earthing arrangements (eg connection to the network via a delta/star transformer with
the star on the network side with a high impedance earth) must be agreed by Ergon Energy on a
case by case basis.
Check this is the latest version before use. Page 30 of 62 Standard STNW1165 Ver 3
Permissible Range
Supply Voltage (Nominal) Power Factor Range
> 400 kV 0.98 lagging to unity
250 kV – 400 kV 0.96 lagging to unity
50 kV – 250 kV 0.95 lagging to unity
1 kV < 50 kV 0.90 lagging to 0.90 leading
Table 7 – Power Factor Requirements (Table S5.3.1 of NER)
Ergon Energy may specify alternative power factor ranges for the purposes of voltage
management.
Voltage Flicker
Voltage flicker refers to rapid fluctuations in the voltage level on the distribution system. These
fluctuations cause light bulbs to ‘flicker’ instead of producing a steady light.
Ergon Energy will specify customers’ emission limits for voltage flicker prior to the connection.
Harmonics
Harmonic distortions are mainly introduced by inverter-coupled embedded generation scheme.
Recommended limits of harmonic voltages permitted to inject into the Ergon Energy distribution
network at the point of common coupling will be specified by Ergon Energy prior to the connection.
Voltage Unbalance
The connection of unbalanced loads and generation to the distribution network can result in
unbalanced currents and voltages.
Check this is the latest version before use. Page 31 of 62 Standard STNW1165 Ver 3
a) For connections at 30kV or higher voltage, the current in any phase is not greater than
102% or less than 98% of the average of the average of the currents in the three phases;
and
b) For connection at voltages less than 30kV, that the current in any phase is not greater than
105% or less than 95% of the average of the currents in the three phases.
Customers must balance the current drawn in each phase at each of its connection points so as to
achieve average levels of negative sequence voltage at its connection points. The average voltage
unbalance, measured at a connection point, should not vary by more than the amount set out in
column 4 of Table 8 for the relevant nominal supply voltage, when determined over a 10-minute
averaging period.
Nominal supply
voltage Maximum negative sequence voltage (% of nominal voltage)
(kV)
Column 1 Column 2 Column 3 Column 4 Column 5
No contingency Credible General Once per
Event contingency event hour
30 minute average 30 minute average 10 minute 1 minute
average average
More than 100 0.5 0.7 1.0 2.0
More than 10 but 1.3 1.3 2.0 2.5
not more than
100
10 or less 2.0 2.0 2.5 3.0
Table 8 – Negative sequence voltage, Table S5.1a.1 of NER
The Proponent will conduct commissioning tests to demonstrate compliance of the embedded
generation plant and network connection with the Engineering Report and NER Schedule 5.2.
The Proponent must submit to Ergon Energy for approval, the proposed commissioning program
including test procedures and proposed test equipment to be used in the commissioning.
The generation unit’s commissioning program and test shall include all relevant tests to confirm the
embedded generation plant compliance with the Engineering Report.
Check this is the latest version before use. Page 32 of 62 Standard STNW1165 Ver 3
Does not adversely affect the security of the Network or the quality of supply of electricity
from the Network; and
Minimises any possible threat of damage to the Network, or any other plant, equipment or
installations of any other person that is connected to the Network.
1. A customer must not install generating plant for interconnection with a supplier’s network
without the supplier’s agreement
2. The agreement must include the conditions for securing safe and stable parallel operation
of the supply network and the generating plant
In respect of the ongoing operation of the embedded generator, the Proponent must maintain the
embedded generation plant protection and control systems and any other service provided by the
Proponent in connection with the embedded generation plant that impacts on the generator, its
safety or operation, or the safety or operation of the network.
Upon receipt of the written request, Ergon Energy will advise the Generator if it is necessary for
Ergon Energy to undertake a new network analysis and engineering report (at the Generator’s
cost) in order to ascertain the operational constraints of the embedded generation plant with the
proposed changes to the embedded generation plant.
Check this is the latest version before use. Page 33 of 62 Standard STNW1165 Ver 3
11. Maintenance
The Proponent shall notify Ergon Energy of scheduled and unscheduled protection, SCADA,
or Communications outages or failures.
Ergon Energy may require access to the generation unit’s site for maintenance and testing
purposes.
12. Disputes
A party may also have the right to access dispute resolution provisions under other
legislation e.g. the National Electricity Rules or Energy Ombudsman Act 2006 (Qld).
Check this is the latest version before use. Page 34 of 62 Standard STNW1165 Ver 3
NOTES:
The following single line diagrams (Arrangements 1 to 12) show a range of possible connection
arrangements for embedded generation operating in parallel with utility distribution networks.
The network voltage is 415/240V for low voltage (LV) or 11 or 33kV for the high voltage (HV)
distribution. Connection arrangements for sub-transmission or distribution networks are shown in
a separate document.
The variations considered are connection to a LV or HV network, whether the feeder is shared use
with 3rd party customers and transformer connection arrangements between customer load and
generation.
Network Coupling Point (NCP) is the point where power quality criteria would normally be
assessed and the Connection Point (CP) is the point of asset ownership change from utility to
customer.
The metering arrangements are indicative only. Metering may be Nett or Import/Export as
required and either metering arrangement can be used in any connection arrangement. Metering
may be on either side of the CP to suit utility requirements.
These diagrams apply regardless of the type of generator. The energy source or “generator” can
be synchronous, asynchronous (induction machine) or power electronic (inverter or converter)
coupled.
For protection and control requirements see the separate diagrams showing these.
Check this is the latest version before use. Page 35 of 62 Standard STNW1165 Ver 3
Ln
L3
HV LV
HV FEEDER
ZONE
SUBSTATION DISTRIBUTION L2
SUBSTATION
LEGEND
CP Connection Point L1
L1 Internal load for embedded generation Customer NCP M
L2 to Ln Third party customer low voltage load CP
M Metering G
NCP Network Common Point CUSTOMER INSTALLATION
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 36 of 62 Standard STNW1165 Ver 3
M L
HV LV M
HV FEEDER NCP CP
ZONE
M G
SUBSTATION
DISTRIBUTION CUSTOMER
SUBSTATION INSTALLATION
LEGEND
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 37 of 62 Standard STNW1165 Ver 3
Ln
L3
HV LV
HV FEEDER
ZONE
SUBSTATION DISTRIBUTION L2
SUBSTATION
LEGEND
CP Connection Point PCC M L1
CP
L1 Internal load for embedded generation Customer
L2 to Ln Third party customer low voltage load
M Metering NCP
HV LV M
CP
G
NCP Network Coupling Point
DISTRIBUTION CUSTOMER INSTALLATION
HV or LV fuse
SUBSTATION
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 38 of 62 Standard STNW1165 Ver 3
HV LV M L
HV FEEDER CP
ZONE
SUBSTATION HV LV M G
NCP CP
LEGEND
DISTRIBUTION CUSTOMER
CP Connection Point SUBSTATION INSTALLATION
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 39 of 62 Standard STNW1165 Ver 3
L
CP
M HV LV
HV FEEDER NCP
ZONE
M G
SUBSTATION
CUSTOMER INSTALLATION
LEGEND
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 40 of 62 Standard STNW1165 Ver 3
ZONE
SUBSTATION
L
NCP CP
M HV LV
HV FEEDER
M G
CUSTOMER INSTALLATION
LEGEND
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 41 of 62 Standard STNW1165 Ver 3
CP
M HV LV L
HV FEEDER NCP
ZONE
SUBSTATION M HV HV G
LEGEND
CUSTOMER INSTALLATION
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 42 of 62 Standard STNW1165 Ver 3
CP
M HV LV L
HV FEEDER NCP
ZONE
SUBSTATION M G
LEGEND
CUSTOMER INSTALLATION
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 43 of 62 Standard STNW1165 Ver 3
ZONE
SUBSTATION
NCP CP
M HV LV L
HV FEEDER
M HV HV G
CUSTOMER INSTALLATION
LEGEND
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 44 of 62 Standard STNW1165 Ver 3
ZONE
SUBSTATION
NCP CP
M HV LV L
HV FEEDER
M G
CUSTOMER INSTALLATION
LEGEND
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 45 of 62 Standard STNW1165 Ver 3
CP
M HV HV HV LV L
HV FEEDER NCP
ZONE
SUBSTATION M G
LEGEND
CUSTOMER INSTALLATION
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 46 of 62 Standard STNW1165 Ver 3
ZONE
SUBSTATION
NCP CP
M HV HV HV LV L
HV FEEDER
M G
CUSTOMER INSTALLATION
LEGEND
CP Connection Point
L Internal load for embedded generation Customer
M Metering – may be Nett or Import/Export type
NCP Network Coupling Point
HV or LV fuse
Circuit breaker, protection or switching device
Check this is the latest version before use. Page 47 of 62 Standard STNW1165 Ver 3
The following information shall be provided for each generator proposed to be installed:
Where the Data Item Unit is identified as PU it shall be the PU value calculated on a base of
the generator nominal terminal voltage and nominal generator kVA rating.
Check this is the latest version before use. Page 48 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 49 of 62 Standard STNW1165 Ver 3
This discussion pertains to the power system protection considerations associated with the
connection and parallel operation of synchronous generators with utility distribution networks, also
referred to as embedded generation.
The following issues relating to protection systems need to be considered when interconnecting an
embedded generator with a utility distribution network:
a) Safety: Interruption of the utility supply source may not de-energize a circuit if an
embedded generator is supplying power to the same circuit; therefore, safety for other utility
customers, the public and utility personnel is a key issue to consider
c) Detection of Faults: All faults and hazardous abnormalities must be detected and
cleared promptly within the limits of sensitivity that protection technology can provide. The
effects of changed short-circuit currents due to embedded generation on circuit protection
and coordination need to be considered. Fault detection performance and risk in the face
of protection relay or circuit breaker failure has to be considered.
e) Power Quality: Temporary, fluctuating or sustained over and undervoltages may also
occur. These effects need to be controlled within acceptable limits. Maintenance of
steady-state frequency level and frequency fluctuations within acceptable limits under all
operating conditions is also to be considered.
g) Neutral Earthing: Adequacy under all normal and sustained abnormal operating
conditions has to be ensured.
While the foregoing issues need to be resolved, and mostly they all have technical solutions
available, the cost of protection should be considered when evaluating the feasibility of a proposed
embedded generation installation. It is essential to ensure safe and reliable interconnections
Check this is the latest version before use. Page 50 of 62 Standard STNW1165 Ver 3
For the purposes of this document, the term “island” is used to describe the situation in which the
embedded generation is feeding un-faulted and isolated customer load or loads. Since
synchronous generators do not require interconnection with a utility system to operate, they may
be capable of supplying part of the utility load if separation occurs somewhere between the
embedded generation and the source substation. These installations can be divided into three
categories:
a) An installation, such as an industrial plant or hospital, where the primary purpose of the
generator is to feed continuous power to the facility when the tie to the utility is interrupted.
Operating such a facility as an island is desirable, but such plants must be designed so that
the voltage and frequency excursion is within acceptable limits when separation from the
utility occurs. Synchronising facilities, either automatic or manual are used whenever the
connection to the utility is re-established and are owned and operated by the embedded
generation owner.
Islanded operation can only be acceptable when there is no risk to 3rd party utility customers and
where they can receive the equivalent to utility service. This requires not only the same phase
configuration (three-phase generator for three-phase load), but the proper transformer connections
to supply the distribution load in the same manner as the utility. Islanded operation also would
require that the frequency and voltage stay within narrow limits set by the utility (with regulatory
body approval). Deviations beyond these limits should be detected by protection relays, which
would open the embedded generation interconnection.
However due to safety, power quality and liability concerns, most utilities will not permit embedded
generation to remain connected to isolated feeders under any circumstances. In some instances,
this may require installation of a transfer-trip (remote trip) system to make sure that an embedded
generator is promptly disconnected when the source substation circuit breaker opens.
Check this is the latest version before use. Page 51 of 62 Standard STNW1165 Ver 3
General
In designing protection associated with embedded generation interconnection, faults and
abnormalities to be considered will be:
In these notes the protection for generator faults is not considered in detail and only to the extent of
a suitable minimum standard and from the view of its use for interconnection or network faults.
Fault Currents
Typical distribution feeders are fed radially from a utility substation. In these feeders, all of the
short-circuit fault current for faults on the feeder, as well as the load current, will come from the
source substation. Non-radial distribution networks are considered in another document.
The magnitude of the fault current is determined by the impedances of the utility source, the
transformers, reactors and feeder conductors etc, and fault resistance. Embedded synchronous
generators, will increase the fault current level at the fault point and reduce the current being
supplied by the source substation to the point of actually causing a reversal of fault current flow
some circuits.
The maximum and minimum values of fault current are an important consideration for any
protection scheme. Maximum values determine the interrupting rating needed for circuit breakers,
automatic circuit reclosers (ACRs), fuses, etc as well as the upper design limit for the protection
scheme performance. Minimum current values determine the lower limit settings of overcurrent,
earth fault relays and other protective devices to provide a satisfactorily high probability of
detecting all faults.
On a radial feeder, all protective devices between the substation relays and the fault measure the
same current if the substation is the only source. This simplifies the coordination of overcurrent
tripping devices to interrupt the fewest number of customers. Earth fault coordination may be
affected if feeders have other sources of earth current.
Sources of feeder fault current due to embedded generation may affect relay, fuse and ACR
coordination, equipment rating, and safety of utility personnel and the general public. The
magnitude of fault current from these sources will depend upon the type, size, and number of
generators, their impedances, and their location with respect to the fault and utility substation.
If the embedded generation contribution is large, the operation of the relays at the substation may
be delayed due to a reduction in fault current from the source substation. A more likely case is
that of a relatively high impedance embedded generation source located near the source
substation. Such an arrangement contributes limited fault current until the utility circuit breaker
opens, which may result in slow detection and sequential clearing of the fault. These multiple
current source problems will apply to phase-to-earth faults if there is an earthed neutral
(transformer or generator) at the faulted network voltage level.
Check this is the latest version before use. Page 52 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 53 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 54 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 55 of 62 Standard STNW1165 Ver 3
Where a power limit has been set by Ergon Energy (either import or export) the customer shall
provide a power protection measurement at the connection point. This protection shall be used to
trip either the source of generation or the incoming circuit breaker.
For IES sites with nameplate rating <100kW where the power limit set by Ergon Energy is above
the nameplate rating of the Inverter Energy System, the customer may elect not to install a power
protection. Should Ergon Energy review the power limit to a value below the IES nameplate rating
the customer will be required to retrofit a power protection system. In instances where it is not
possible to operate the IES without a connected load at the customer premises, the value power
limit may be regarded as the IES rating minus the absolute minimum site load.
Where a customer expects to export power, Ergon Energy shall be notified of the desired power
export threshold at the time of the connection application. Ergon Energy will study the impact on
the system and agree or review the threshold. Under these arrangements Ergon Energy reserves
the right to reduce the power export threshold at any time in order to accommodate network
conditions. In some cases this may be reviewed and changed to an import power threshold.
Voltage and frequency protection shall be configured to values stated in AS4777 and the
connection agreement where applicable.
Relays providing these functions are expected to comply with the appropriate sections of IEC
60255. The instrument transformers used to interface these protection relaying equipment to the
proponents installation shall be compliant with the appropriate sections of AS60044.
Check this is the latest version before use. Page 56 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 57 of 62 Standard STNW1165 Ver 3
For export agreements the generation proponent is required to participate in the protection of the
distribution network. The generation proponent shall provide protection systems in addition to the
inherent inverter protections to ensure that systems can detect and clear all faults on the high
voltage network reliably. The protection requirements are those detailed as P4 and P8 above.
For generators with an export agreement a voltage transformer connected to the high voltage
network shall be utilised to provide a neutral voltage displacement protection. Operation of this
shall trip either the source of the generation at the site or circuit breaker at the customer
connection point. The circuit breaker that can be tripped is at the discretion of the customer and
would be decided on operational convenience.
In addition to the neutral voltage displacement protection an overcurrent protection shall be applied
to detect and clear all faults on the high voltage network. This shall be set to the rating of the
generation and maybe set directional looking towards the utility network.
Voltage and frequency protection shall be configured to values stated in AS4777 and the
connection agreement where applicable.
Relays providing these functions are expected to comply with the appropriate sections of IEC
60255. The instrument transformers used to interface the protection relaying equipment to the
proponents installation shall be compliant with the relevant sections of AS60044.
Check this is the latest version before use. Page 58 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 59 of 62 Standard STNW1165 Ver 3
Input/Output Function
Digital Status Signals
HV connection point tripped status
HV connection point closed status
LV CB tripped status
LV CB closed status
Analogue Status Signals
HV Voltage (V) three phases
HV Current (C) three phases
Bi-directional HV Power (MW)
Bi-directional HV Reactive Power (MVA)
Digital Control Signal
HV connection point trip
Alarm Signals:
Ergon Energy System Operator trip
Intertrip received from HV feeder CB
Intertrip communications failure (time delayed)
SCADA Interface Panel DC supply failure (fail safe contact)
The communication requirements will vary depending on the type, size and function of the
embedded generator.
Space Requirements for Ergon Energy’s Protection, SCADA and Communications Equipment are:
Check this is the latest version before use. Page 60 of 62 Standard STNW1165 Ver 3
Statement of Purpose
Fault level calculations
Equipment ratings
Protection schemes
Operational procedures for the customers network
Associated risk assessments
4. For each transformer, install an LV circuit breaker between the customers LV board and
Ergon Energy 415 isolator
7. Intertrip the LV circuit breaker following operation of the HV circuit breaker or switch fuse
8. Pay actual cost for the assessment and implementation of the above requirements.
These charges will be generally be payable up front but in some circumstances may be
included within ongoing network charges
Check this is the latest version before use. Page 61 of 62 Standard STNW1165 Ver 3
Check this is the latest version before use. Page 62 of 62 Standard STNW1165 Ver 3