Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

IMS Checklist 4 - Mod 3-1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Reference Points in IMS

Module-3
QUALITY PLANNING AND DEVELOPMENT MATERIAL
&
SALES MANAGEMENT
No Topic Key Points
1 Role of project Project management is important because it ensures what is
management techniques being delivered, is right, and will deliver real value.

Network Analysis as the technique is used to solve projects


like one industrial, military etc. It is dividing complex job
Network analysis into small jobs and represent graphically to easily analysis
and solving it.
2 Critical Path Method: Activity: It is an individual operation which consumes
CPM Terms resource and time. It has beginning and end. An arrow
represents an activity

Event: Event represent a point in time where completion


of some activity and beginning of new activity.
A circle represents a node.

Successor event: An event which follows another event


is called successor event.

Predecessor event: The event which occurs before


another event is known as predecessor event.

Dummy activity: A dummy activity which is not


utilizing time or resource. It is an imaginary activity
represented by dotted arrow line.

VIVEKANAND K
EFT (Earliest finish time): This is the earliest possible time at
which an activity can finish. This is represented on the top
right corner outside operation in a rectangle.

LFT (Latest finish time): It is the total time by which and


activity should be completed. It is represented by triangle.

Critical path: The path in which a LFT and EFT are equal is
called critical path. It can be represented by double line

Slack or float: It is the difference between LFT and EFT. In


critical path slack or float will be zero.
.

3 Numbering an Event 1. Identify initial event and assign no 1


2. Number these initial events from 2,3,4 etc.
Fulkersons rule 3. Mark the arrow direction
4. Follow the procedure till end
4 Numbering an Event

5 CPM Vs PERT

VIVEKANAND K
6 Applications of CPM and CPM application
PERT 1. Construction of civil and mechanical projects
2. Electrical and electronic product manufacturing and
assembling
3. Equipment maintenance
4. Setting up new industry

PERT Application
1. Research and development activity
2. Military operations
3. Design and development of new product.
4. Weather forecasting.
5.
7 Program Evaluation and PERT requires three estimated activity times:
Review Technique:
1. Optimistic time (a minimum time)
PERT Terms 2. Most likely time (an average time)
3. Pessimistic time (a maximum time)

to = optimistic time
tm = most likely time
tp = pessimistic time

Statically Expected time te = [to+4 tm+ tp / 6]

Standard deviation St= [tp- to /6]

2 2
Variance V = St = [tp- to /6]

VIVEKANAND K
8 Linear Programming Question: A candy manufacturer has 130 kg of chocolate-
Problem (LPP) covered cherries and 170 kg of chocolate-covered mints in
stock. He decides to sell them in the form of two different
mixtures. One mixture will contain half cherries and half
mints by weight and will sell for Rs 2.00 per kg. The other
mixture will contain one-third cherries and two-thirds mints
by weight and will sell for Rs 1.25 per kg. How many pounds
of each mixture should the candy manufacturer prepare in
order to maximize his sales revenue?

Solution for forming LPP:

Let x be the number of pounds of A to be prepared and y the


number of pounds of B to be prepared.

Max Z= 2x+1.25y

Constraint of A

1/2 x+ 1/3 y ≤ 130

Constraint of B

1/2 x+ 2/3 y ≤ 170

LPP
Max Z= 2x+1.25y

Constraints

1/2 x+ 1/3 y ≤ 130


1/2 x+ 2/3 y ≤ 170

x ≥0 , y≥ 0

VIVEKANAND K
Graphical solution To get graphical solution of above problem
Max Z= 2x+1.25y

Constraints
1/2 x+ 1/3 y ≤ 130------1
1/2 x+ 2/3 y ≤ 170------2

Solution

Replace ≤ or ≥ with = in equations

1/2 x+ 1/3 y = 130------1

Put x=0 in eqn 1 x=0 then y= 390


Put y=0 in eqn 1 y=0 then x= 260

1/2 x+ 2/3 y = 170------2

Put x=0 in eqn 1 x=0 then y= 390


Put y=0 in eqn 1 y=0 then x= 260

Draw graph and find end points

Substitute the end points in max z


Extreme point Value of z=2x+1.25y
(0, 0) 0
(0, 255) 318.75
(180, 120) 510.00
(260, 0) 520.00
The table shows that the largest value for z is 520.00 and the
corresponding optimal solution is (260, 0). Thus the candy
manufacturer attains maximum sales of $520 when he
produces 260 pounds of mixture A and none of mixture B.

VIVEKANAND K
Transportation problem

VIVEKANAND K
VIVEKANAND K
Game theory Game theory is used for decision making under conflicting
situations ie where there are one or more opponents. In game
theory it’s called players.

Example: Election success of one person will lead failure of


other.
Min and min-max Min and min-max principle can be used for the selection of
principle. optimal strategy by the two players.

Saddle point Saddle point is position of such an element in the payoff


matrix which is the minimum in its row and max in its
column.

Problem to find value of game.

VIVEKANAND K

You might also like