CIR RT-500 Final
CIR RT-500 Final
CIR RT-500 Final
Right:
Weigh bridge
calibration and
bitumen pump
calibration.
Left:
BearCat 3785 L /
1000 gallon liquid
calibration trailer.
Widths and Depths of CIR
• Variable widths are easy to do
with this system. On this job,
material is placed to the side
by the Roadtec RX-60 (2.2 m
width/86”) where the RX-900
(3.8 m/150”) can walk over the
top of it and incorporate the
material into the next milling
pass.
• Precut and final cut could be
variable to 6 m width (20’).
Shown here is about 4 m (13’
4”).
• Depth of cut has to do with
ability to compact the material
to design specification.
Normal depths are between 50
and 125 mm (2” to 5”).
Mix Designs
• The mix design can be as
varied as the conditions
require, in this instance, the
emulsion was 2.2% with 2.5%
lime slurry solids by weight.
• The slurry was approximately
30% solids to water by weight.
500 lbs of gypsum was added
per 10,000 gallons of slurry to
slow down the reaction time.
• Various materials can be
added to an existing roadway
to create a new layer of
recycled pavement.
• The Bearcat system is shown
to the right.
Slaking Plant
• The lime slurry is
prepared at a slaking
plant and sent to the train
by tanker truck.
• On this project, lime and
emulsion were the main
additives along with
water.
• Bituminous emulsion,
lime, Portland cement, fly
ash, foamed asphalt or
other stabilization
materials can also be
used in this process.
Tank trailers deliver the asphalt emulsion
and lime slurry to the job site
• Tankers stay with the train
during work and tank trailers
shuttle to the supply point
and return with materials.
• The production of the train is
dependent upon the timing of
these materials and the
careful planning of transport
to the supply point.
• Material can be laid on the The “construction” job required
surface ahead of this water, emulsion and lime slurry. This
job was on Highway 93 south of
process as well by using a Lages Station, Nevada (USA) and on
dry material spreader. Hwy 93 between Lages Station and
Curie.
Roadway Grade and Slope
The milling machine
rebuilds the proper grade
and slope to the roadway
using state of the art
automated grade and
slope controls.
The mill can work in either direction and has 950 HP diesel power.
Front or rear loading, UP or DOWN cutting, widths from 2.2 m to 3.8 m.
Shown here is a 3.8 m (12’6”) drum down cutting and rear loading to
the RT-500.
The RX-900 tows the RT-500 Screening, Mixing and Blending Trailer
as well as the emulsion trailer and pushes the additive trailer.
RX-900 and the Train
The Screen Deck
• The RT-500 has a JCI
5142-24 Screen (5’ x 14’
– 1.5 m x 4.27 m) Double
Deck Screen with 120mm
bearings to give a uniform
size to the milled
material.
• Uniform size will yield a
more uniform mixture.
• A crusher and conveyor
circuit reduces the
oversize.
Over size material crusher
• Telsmith Crusher – 3048
Impactor
• 152 mm mainshaft and
110 mm bearings for
maximum service life
• Shaft and Rotor Assembly
feature Ring-Feders™ to
provide lock of shaft and
rotor without press-fits or
keys (allows for easy •Precision machined surfaces provide 100%
removal of shaft from backing for hammers
rotor) •Two - Moveable Aprons to allow for proper
• 2 Rows of Massive sizing of material
Hammer Bars •Spring Return on Moveable Aprons to
• Patented Hammer and eliminate shear bolts for tramp iron relief
Wedge Design provides 4 •1” (25 mm) Thick AR400 Liners on Aprons, ½”
wear surfaces for (13 mm) AR400 frame or wall liners
maximum life •Hydraulically Lifted Upper Frame - Opens for
• Hammer Bars are 28% complete internal access
Chrome Iron Alloy •150 hp (112 kW) electric motor drive.
•Fully enclosed belt guard
Crusher Circuit back to Screen
• Two Return Conveyors
• 24”(610 mm) return
conveyors
• Cleated belt for maximum
production
• Covered for safety and to
prevent roll-off
• Lagged head pulleys for
non-slip traction
• Water sprays to prevent
rap dust build-up on
rollers
Weigh Bridge and Mixer
• Under the Screen
deck there is a 48”
(1.22m) wide belt and
belt scale system to
provide accuracy ±1%
• JCI/KPI Model 52
Pugmill 48” (1.2 M)
Wide Box with Twin
24” Shaft mixers x 6’-
0” (1.83M) long or (9
cu. yards.) 600 TPH
Bearcat™ Emulsion System
• Full display and input screens
both Metric and Imperial
measures.
• Variable speed electric motor
driven 3" (7.62 mm) positive
displacement asphalt pump (240
gal/min or 908 liter/min) with
reverse capability.
• Positive displacement gear type
flow meter.
•Dual 8" (20cm) X 18" (45cm) spray bar
• Optional Mass flow meter
strainers with a pair 3-way valves allowing the
• Full circulating system to prevent selection of either canister so the other one
plugging in spray bar circuit while
in non-spray (circulate) mode. can be cleaned while in operation.
•Automated flushed system with onboard
• Thermostatically controlled electric flush solvent recovery tank.
heat in asphalt circulating circuit to
prevent material from cooling •System is capable of spraying paving grade
while circulating. asphalt.
• Pneumatic spray valve operation, •Optional foam system can be added.
computer controlled. •Hydraulic 3” (7.62 mm) variable drive positive
• Spray valves submersed poppet displacement asphalt pump (240 gal. or 908
style. liter/min) with reversing capability
RT-500 Generator Power
• Caterpillar C-9
Generator Set
• Caterpillar C-9 Tier III
Diesel Engine at 375
hp
• 250kw Output on
Marathon Generator
• The RT-500 is run by
electric motors.
Discharge to Roadway
• The material is mixed in
the pugmill and dropped
onto the roadway.
• Roadtec drops the
material as close to the
milling drum as possible
to keep the open areas to
a minimum aiding start up
and shut down of work
each day.
Windrow and Windrow Loader
The cold recycled material is left
in a windrow for three reasons:
– Drying & curing effect
– Surge control – if there is a
dip or hump you are correcting
with the milling process you
can move the material to
compensate and allow a
uniform lift of recycled mix to
be placed.
– Allows for maximum
production, the paving and
compaction progresses at is
own optimum rate.
– The recycling and supply of
additives go at their
optimum rate.
Paver and Placement
• The windrow loader is
pushed by the asphalt
paver and placed onto
the roadway.
• The paver uses an
automated grade
control to place a
uniform lift of material.
• There will be a new lift of
material placed on top of
this material after the
curing period. Normally
about two weeks.
Nevada Maintenance - Mix design