Systimization and Circuitization Creation Case Study
Systimization and Circuitization Creation Case Study
Stream Number 0015 0016 0017 0018 0019 0020 0021 0023 0024 0025
WASH WATER OVHD VAPOR OVHD VAPOR LIQUID EXCESS REFLUX OFFGASES REBOILER REBOILER LEAN AMINE
TO FROM FROM FROM WATER TO TO TO (2-EA-002) (2-EA-002) FROM
2-DA-002 2-DA-002 2-EC-002 2-FA-001 OSBL 2-DA-002 INCINERATOR INLET OUTLET 2-EA-004
Case 1A 1A 1A 1A 1A 1A 1A 1A 1A 1A
Phase LIQUID VAPOR MIXED LIQUID LIQUID LIQUID VAPOR LIQUID MIXED LIQUID
mole %
METHANE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ETHANE 0.00 0.06 0.06 0.00 0.00 0.00 0.16 0.00 0.00 0.00
PROPANE 0.00 0.01 0.01 0.00 0.00 0.00 0.02 0.00 0.00 0.00
BUTANE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CARBON DIOXIDE 0.00 35.19 35.19 0.05 0.05 0.04 90.71 1.67 3.39 1.35
HYDROGEN SULFIDE 0.00 0.02 0.02 0.00 0.00 0.00 0.05 0.00 0.00 0.00
STEAM/WATER 99.99 64.69 64.69 99.91 99.91 99.92 9.05 88.11 96.56 86.52
DIGLYCOL AMINE 0.01 0.02 0.02 0.04 0.04 0.03 0.00 10.21 0.06 12.13
Mass Flow kg/hr 2,004 40,247 40,247 16,370 424 17,950 23,876 253,575 253,575 377,623
Molar Flow kg-mol/hr 111.15 1,479.72 1,479.72 906.18 23.48 993.85 573.53 9,270.43 9,270.43 13,049.04
Molecular Weight 18.03 27.19 27.19 18.07 18.07 18.06 41.62 27.35 18.94 28.94
Temperature °C 50.1 107.7 57.0 57.0 57.0 57.0 57.0 123.2 124.7 52.0
Pressure kg/cm2g 3.950 0.820 0.570 0.570 1.000 0.830 0.570 0.950 0.920 6.400
Vapor
Flow, mass kg/hr 0 40,247 23,876 0 0 0 23,876 0 50,712 0
Am3/hr 0 25,801 10,078 0 0 0 10,078 0 41,212 0
Molecular Weight 0.00 27.19 41.62 0.00 0.00 0.00 41.62 0.00 18.95 0.00
Density kg/m3 0.00 1.56 2.37 0.00 0.00 0.00 2.37 0.00 1.23 0.00
Viscosity cP 0.000 0.016 0.016 0.000 0.000 0.000 0.016 0.000 0.014 0.000
Cp/Cv 0.000 1.310 1.280 0.000 0.000 0.000 1.280 0.000 1.280 0.000
Compressibility 0.000 0.991 0.993 0.000 0.000 0.000 0.993 0.000 0.985 0.000
Liquid
Flow, mass kg/hr 2,004 0 16,370 16,370 424 17,950 0 253,575 202,863 377,623
m3/hr 2.03 0.00 16.58 16.58 0.43 18.67 0.00 260.07 209.29 363.79
Molecular Weight 18.03 0.00 18.07 18.07 18.07 18.06 0.00 27.35 29.01 28.94
Density kg/m3 986.0 0.0 987.2 987.2 987.2 961.7 0.0 975.0 969.3 1,038.0
Viscosity cP 1.01 0.00 0.52 0.52 0.52 0.52 0.00 0.39 0.40 1.67
Surface Tension dyne/cm 69.280 0.000 67.790 67.790 66.470 66.930 0.000 45.200 45.200 48.100
Refer Appendix 9.5 for detailed interlock description of Ethylene Plant &
utilities.
3.2.1 Description
prevent DGA carryover, and then sent to the Cracking Heaters. The feedstock
leaves the absorber with the CO2 reduced down to a level of 100 ppmw and
saturated with water at the absorber temperature and pressure. The rich DGA
solution leaving the bottom of the absorber is heat exchanged with lean DGA,
stripped of CO2 and H2S in the Amine Stripper (2-DA-002), cooled and recycled
back to the absorber. The Amine Stripper operates at the lowest possible
pressure based on the operating pressure of the incinerator. The tower utilizes
air as the condensing medium and low pressure steam as the heating medium.
The desorbed light hydrocarbons and steam are routed to the incinerator
where they are burned. Provisions are included to remove any contaminants in
the DGA solution via the Amine Reclaimer (2-EA-003). This exchanger is used
to perform batch evaporation of the lean DGA, leaving behind the
contaminants to be disposed.
Make-up DGA is available to replace any DGA losses in the system. In order to
insure the stable operation of the system over the required plant run length,
antifoam injection will be used and a 20% slipstream of the lean amine solution
will be continuously filtered.
The C2/C3 fresh feed coming from OSBL is send to mercury removal bed
(2-FD-201A/B) in order to remove traces of mercury. The inlet and outlet
mercury in the feed will be analysed by 2-AI-2013A/B. C2/C3 feed free from
mercury at ambient temperature, enters the bottom of the Acid Gas Absorber
(2-DA-001) on pressure control (2-PC-1077) to maintain the feedstock header
pressure. It passes first through the Feed K.O. Drum (2-FA-002) where any
condensate present will be separated and sent to the Wet Flare Drum on level
control (2-LC-0003). It then flows up through the column which is two beds
packed column. CO2 and H2S in the C2/C3 feedstock are removed by
countercurrent contact with 45 wt. % DGA solution recycled from the Amine
The heat of absorption raises the temperature of the solution as it flows down
the tower. The treated feedstock is passed through a demister pad and enters
the wash section at the top of the tower. The water wash section has three
bubble cap trays. Phosphate free boiler feed water (BFW) enters the top tray
on flow control (2-FC-0001) and flows countercurrent to the upward feedstock
flow to remove trace amounts of amine from it. The liquid from the water wash
section sump is sent on level control (2-LC-0001) to the Amine Stripper,
entering at the reflux line. In order to recover trace amounts of DGA in the
water, the C2/C3 vapor saturated with water is passed through a second
demister pad before going to the Ethane Feed Preheater (2-EA-130). A CO2
analyzer (2-AI-0003) is provided on this stream and another CO2 analyzer
(2-AI-0001) is provided on the C2/C3 feed line to the Acid Gas Absorber to
monitor the absorber performance.
Rich amine solution, containing up to 0.40 moles of CO2 per mole of DGA is
drawn from the sump of the Acid Gas Absorber on level control (2-LC-0005).
The pressure of the solution is reduced across the absorber level control valve
immediately before entering the Amine Stripper above the inlet distributor.
The rich amine solution increases in temperature as it passes through the
Lean/Rich amine Interchanger (2-EA-001A/B), entering the stripper at
101.7°C. As the solution flows down through the column, it contacts up flowing
steam stripping. This section of the stripper consists of two packed beds. Below
packed beds, lean amine solution is collected and drawn off to the Amine
Stripper Reboiler (2-EA-002A/B/C) which operates under thermosyphon
action. The Reboiler heating medium is desuperheated LP steam, which enters
The lean amine solution from the bottom of the Amine Stripper flows through
the Lean/Rich Amine Interchanger (2-EA-001,A,B) is pumped back to the Acid
Gas Absorber on flow control (2-FC-0006) and cooled down to 57°C in the Lean
Amine Cooler (2-EC-001A/B) where the cooling medium is air, and then is
cooled further to 52°C in the Lean Amine Trim Cooler (2-EA-004) where the
cooling medium is cooling water.
The stripper overhead product, CO2 and water vapor, is cooled and partially
condensed in the Amine Stripper Condenser (2-EC-002A/B), then enters the
Amine Stripper Reflux Drum (2-FA-001). The liquid from this reflux drum is
returned as reflux on flow control (2-FC-0011) with reset from the reflux drum
level controller (2-LC-0010) to the Amine Stripper top liquid distributor, which
is located above the top tray. The excess condensate is sent to waste water
treatment on flow control (2-FC-0014). The stripper overhead pressure is
controlled by venting the CO2 to the incinerator through the "B" pressure
controller (2-PC-0023) on high pressure, or drawing in nitrogen through the
"A" pressure controller (2-PC-0023) on low pressure. The Amine Reclaimer
(2-EA-003) is a kettle type heat exchanger which removes solution heat stable
salts, along with decomposition and degradation products from the circulating
amine. The reclaimer processes, in a semi-continuous operation, a slip stream
The operator should never change the set point of PC-0049 below the
maximum back pressure of wet flare header.
Pressure,
Service Temperature, °C Flow, kg/hr
kg/cm2g
Total Reflux to
57 57 0.83 17,950 17,408
2-DA-002
Lean/Rich Amine
Interchanger 2-EA-001 96.0 130 0.52 377,623 377,787
A/B Lean Amine (Out)
Nitrogen Mercury
Removal Bed 20 20 36.59 117,521 114,493
2-FD-201A/B
3.3.1 Description
The purpose of this section is to insure a continuous, controllable flow of C2/C3
vapor feed to the Cracking Heaters at the conditions specified in the process
design. Treated fresh C2/C3 feed saturated with water, along with back-up
ethane feed and ethane recycle are preheated with quench water in the Ethane
Feed Preheater (2-EA-130) to a temperature of 60 °C, before entering the
preheat section of the cracking heaters. Sulfur as DMDS is injected individually
to each heater feed after the preheater.
Recycle ethane from the Ethylene Fractionator that has been vaporized in the
Ethane Vaporizer (2-EA-301), is preheated in off-gas exchangers of the cold
box and combined with the treated fresh C2/C3 feed from the Acid Gas
Absorber (2-DA-001).The combined C2/C3 stream is heated in the Ethane Feed
Preheater (2-EA-130) with quench water on temperature control (2-TC-1003)
to 60° C. The fresh feed from battery limit is introduced on pressure control
through the pressure control valve (2-PC-1077). Back-up ethane feed will be
supplied through the (2-PV-1001A) if the pressure in the feed line to the
Cracking Heaters is too low. The back-up ethane feed can be supplied for up to
48 hours of continuous operation in case there is no fresh feed available. The
ethane recycle from the Ethylene Fractionator is on flow control (2-FC-4018),
reset by level (2-LC-4013).
Case 1 Case 2