Testing & Commissioning Checklist - HVAC Pumps
Testing & Commissioning Checklist - HVAC Pumps
Testing & Commissioning Checklist - HVAC Pumps
DOCUMENTS REQUIRED PRIOR TO TESTING AND COMMISSIONING OF CHILLED AND CONDENSER PUMPS
1 Calibration certificate of clampmeter, tachometer and insulation tester
2 Testing and commissioning form.
1 Conduct megger reading for each pump motor. (Isolate if the controller is VFD)
2 Configure the motor data to the VFD, once completed, start-the pump based on
the desired speed.
3 Obtain pressure reading by means of suction and discharge gauges (psi), first at
fully-closed valve then at fully open valve
4 Obtain a reading on line voltage: Line 1-2, Line 2-3, Line 3-1 by the aid of a clamp meter
to verify the voltage rating.
5 Obtain ampere reading: Line 1-2, Line 2-3, Line 3-1 by the aid of a clamp meter to check if it is
within the range of the FLA of the motor.
6 Obtain capacity in terms of gpm by plotting the acquired TDH in the pressure gauges
to the performace curve of each pump.
NG & COMMISSIONING PROCEDURE