Fat - Functional Factory Acceptance Test Procedure For Flare and Burn Pit Packages 2600-PK-001 / 2600-PK-002 / 2600-PK-003
Fat - Functional Factory Acceptance Test Procedure For Flare and Burn Pit Packages 2600-PK-001 / 2600-PK-002 / 2600-PK-003
Fat - Functional Factory Acceptance Test Procedure For Flare and Burn Pit Packages 2600-PK-001 / 2600-PK-002 / 2600-PK-003
QC comment
The below items shall be considered:
-Introduction , general description , definition of terms
-General instrumentation
-Air fan and duct
-Factory acceptance test certificate form
Issued for
V00 DR AL VT SH T MB 10/08/2017
comment
Page V00 V01 V02 V03 V04 Page V00 V01 V02 V03 V04
1 X 34
2 X 35
3 X 36
4 X 37
5 X 38
6 X 39
7 X 40
8 X 41
9 42
10 43
11 44
12 45
13 46
14 47
15 48
16 49
17 50
18 51
19 52
20 53
21 54
22 55
23 56
24 57
25 58
26 59
27 60
28 61
29 62
30 63
31 64
32 65
33 66
Azar Oil Field Development
Central Processing Facilities
FAT – FUNCTIONAL FACTORY ACCEPTANCE
TEST FOR FLARE AND BURN PIT PACKAGES
Contract No.:
ARCP F260TA PMQC PRTS 0005 V00 Page 3 of 8
AP-1-92-92
Table of Content
1. SCOPE ..................................................................................................................................... 4
2. OVERVIEW ............................................................................................................................. 4
3. METHODS............................................................................................................................... 4
3.1. FUNCTION TEST IN REAL CONDITIONS ....................................................................................... 4
3.2. FUNCTION TEST IN SIMULATED CONDITIONS ............................................................................ 5
4. QUALIFIED PERSONNEL ......................................................................................................... 5
5. APPROVALS ............................................................................................................................ 6
6. PERFORMING TESTS............................................................................................................... 7
7. CROSSCHECK OF THE TESTED PRODUCTS ............................................................................. 7
8. COMPLIANCE CRITERIA .......................................................................................................... 7
9. CERTIFICATION ....................................................................................................................... 7
Azar Oil Field Development
Central Processing Facilities
FAT – FUNCTIONAL FACTORY ACCEPTANCE
TEST FOR FLARE AND BURN PIT PACKAGES
Contract No.:
ARCP F260TA PMQC PRTS 0005 V00 Page 4 of 8
AP-1-92-92
1. SCOPE
The scope of this procedure is to provide general criteria to organize, perform and evaluate
function tests on final products or on particular specially manufactured prototypes.
This procedure is written according with THERMOENGINEERING Operating Instructions
IO7.2.7 – Rev 1.
2. OVERVIEW
This procedure can be applied to all equipment manufactured by THERMOENGINEERING
which could undergo function tests, in scale or in real operating conditions.
This procedure can also be used as a general guideline for the criteria to be adopted to carry
out function tests.
If not otherwise specified, the acceptance values must be the same contained in the test
report to be submitted to the customer or to the certification authority for approval, as
indicated in this procedure.
In the same way, measurement and control equipment for results verification must also be
approved in order to ascertain that the required technical standards are met.
The conditions in which the test will be carried out must be the most suitable to allow valid
results and data corresponding to the test pattern to be obtained.
This procedure does not include function tests for equipment and products for which a
particular specification and test procedure has been issued.
3. METHODS
Electrical panels, general electronic instruments and pneumatic equipment generally belong
to this category because they can be easily be brought to normal operating conditions to
verify their efficiency and functionality.
To complete examination, measurement and control equipment can be used.
4. QUALIFIED PERSONNEL
The personnel carrying out all activities related to the test must have a sufficient knowledge
of the manufacturing process and the operating conditions of the system or the parts
undergoing test procedures, in order to be able to verify and state the suitability of the parts
under verification.
The actual qualifications of the personnel are verified and tested according to document POI
6.1 “Personnel training”
Azar Oil Field Development
Central Processing Facilities
FAT – FUNCTIONAL FACTORY ACCEPTANCE
TEST FOR FLARE AND BURN PIT PACKAGES
Contract No.:
ARCP F260TA PMQC PRTS 0005 V00 Page 6 of 8
AP-1-92-92
5. APPROVALS
All the function tests belonging to the group described in paragraph 3.2 of this procedure
must be accurately examined and verified for approval by the customer or by the certification
authority.
The Technical Department together with the Quality Control office should issue a testing
procedure to this purpose, containing at least the following:
6. PERFORMING TESTS
All the tests will be performed according to the approved test report.
Should additional tests prove to be necessary, they will be discussed and agreed upon with
the functions in charge and involved in the test.
Function tests on equipment described in specific procedures must be carried out according
to the above mentioned documents.
8. COMPLIANCE CRITERIA
As a general rule, deviations in the expected results for the operating conditions established
in the purchase order and/or in the technical specifications, cannot not be accepted.
During the test, the level of compliance to the above mentioned rules will be stated, and the
possible release of a Non-conformity certificate be evaluated if defects or lack of performance
of the material under testing has been ascertained.
9. CERTIFICATION
The Quality Control function will issue certificates stating that FUNCTION TESTING has been
carried out and reporting the characteristics of the test and its results.
Azar Oil Field Development
Central Processing Facilities
FAT – FUNCTIONAL FACTORY ACCEPTANCE
TEST FOR FLARE AND BURN PIT PACKAGES
Contract No.:
ARCP F260TA PMQC PRTS 0005 V00 Page 8 of 8
AP-1-92-92
The certificate must be signed by the Quality Assurance manager of the secondary supplier
and by the person in charge of the testing for the Customer, if present.
In case an official certification authority is due to take part in the tests, the latter must issue
the necessary documentation to confirm test results.