JX Nippon Oil & Gas Exploration Inspection Test Record (Itr) - A

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

JX NIPPON OIL & GAS EXPLORATION

INSPECTION TEST RECORD (ITR) - A

HIGH VOLTAGE CABLE E22-A


Project No
Project Title
Facilities
INFORMATION
Tag No. System/ Sub System No.
Cable Core/ Size Cable From
Cable To Ref. Drawing Nos.
Voltage
INSPECTION / TEST OK N/A P/L NO
1 Documents required:
a) Cable layout drawing
b) Cable schedule and drum list
2 Verify to ensure that all construction / installation activities have been
completed.
3 Cable installed, identified, dressed and secured, cable rack / tray
segregation and bending radius as per project specifications and
design. Verify and confirm single core cables are using trefoil clamps,
cable gland and gland plate made of nonmagnetic material.
4 Glanding, phase identification and termination kits correctly installed
to vendors specifications.
5 Verify cable type and size in accordance with cable schedule.
6 Verify terminations are tight. Record torque if applicable.
7 Insulation Resistance Test. Measure and record insulation resistance
(IR) of each conductor with all other conductors and shields grounded.
Subsequently, measure IR for phase to phase conductor with other
conductor and shield grounded. Refer PTS 63.10.08.11 for suitable
test voltage and acceptable insulation reading.

Test Point Insulation Remarks


Resistance
R-YBE
Y-RBE
B-RYE

Discharge all conductors to ground for a minimum period of 1 minute.


(Note: Hi-pot test to be done during pre-commissioning and
commissioning only).

8 The cable continuity to be tested using a suitable multi-meter, set to


ohms. Measured resistance to be compared with the datasheet value.
Measured cable resistance ……………... Ω
9 Gland body to earth path resistance (Max 0.1Ω)
10 Cable joints, if any are completed, identified and the location is marked
in cable schedule and relevant layout drawings.
11 Cable joints, if any are completed, identified and the location is marked
in cable schedule and relevant layout drawings.
JX NIPPON OIL & GAS EXPLORATION

INSPECTION TEST RECORD (ITR) - A

HIGH VOLTAGE CABLE E22-A


INSPECTION / TEST OK N/A P/L NO
12 Cable joints, if any are completed, identified and the location is marked
in cable schedule and relevant layout drawings.
13 Record any defects/shortcomings in the system punch-list.
14 Verify no dust inside enclosure /cabinet / panel and insulation surfaces
are clean.
15 Verify instruments & its accessories /electrical equipment/panel
externally clean.
COMMENT(S) AND ADDITIONAL INFORMATION

COMPLETED BY VERIFIED BY ACCEPTED BY


DESIGNATION DESB Representative NIPPON Inspector Discipline Engineer
COMPANY JX NIPPON JX NIPPON
NAME
SIGNATURE
DATE