In The United States District Court For The Eastern District of Louisiana
In The United States District Court For The Eastern District of Louisiana
In The United States District Court For The Eastern District of Louisiana
Defendants.
Defendants Ken Salazar, the U.S. Department of the Interior, Michael R. Bromwich, and
(collectively “Defendants”), hereby request that the Court, pursuant to Federal Rule of Civil
Procedure 62(c), stay its Orders of February 17 and March 1, 2011 (“Orders”) (Dkt. # 229, 250),
pending Defendants’ appeal to the United States Court of Appeals for the Fifth Circuit. In the
alternative, Defendants request that the Court issue a temporary stay of those same Orders until
resolution by the Court of Appeals of an emergency motion by the United States for a stay
I. INTRODUCTION
As this Court is aware, the Secretary of the Interior directed BOEMRE on May 28, 2010, and
again on July 12, 2010, to issue a temporary suspension of certain pending, current, and approved
1
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 2 of 12
offshore drilling operations involving deepwater oil and gas wells. See PubIV000049;1
PubIV000081-109. This temporary suspension was intended, inter alia, to afford BOEMRE the time
it needed after the Deepwater Horizon incident to issue new safety and environmental protection
rules. PubIV000100. On October 12, 2010, the Secretary indicated that a suspension was no longer
needed because the issuance of new regulatory requirements, the killing of the Macondo well, and
the development of containment standards and technology had improved drilling safety, blowout
containment, and spill response capabilities. PubIV000196-200. The Secretary made clear,
however, that all operators would be required to comply with applicable regulations and notices to
Plaintiffs, who would prefer the immediate approval of all drilling permits, alleged pursuant
to 5 U.S.C. § 706(1) that BOEMRE had unreasonably delayed a final decision on nine applications
for permits to drill. Plaintiffs sought, and this Court granted, an injunction compelling BOEMRE to
(“Nexen”) and Cobalt International Energy, L.P. (“Cobalt”)—no later than March 19, 2011 (Dkt. #
229). Following that decision, Plaintiffs moved to supplement the Court’s injunction with two
additional applications pertaining to ATP Oil & Gas Corporation. The Court also granted that
motion, compelling BOEMRE to issue a decision on those two applications no later than March 31,
2011 (Dkt. # 250). On March 4, 2011, Defendants noticed an appeal of those orders to the United
Defendants now respectfully request that the Court stay its Orders pending Defendants’
appeal. The Court’s finding of unreasonable delay, and decision to compel action on the
applications, were made in error. And compliance with the Court’s Orders will greatly harm
1
This citation format references the unique page identifiers in the Department of the Interior’s
Administrative Record for Count IV of Plaintiffs’ Second Amended Complaint.
2
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 3 of 12
BOEMRE and the efficient development of oil and gas resources on the Outer Continental Shelf,
as well as potentially harm the near-term interests of the operators who submitted the subject
applications. The Orders only work to disrupt BOEMRE’s more efficient, iterative practice of
BOEMRE instead now may be required to deny the applications outright, which in turn would
frustrate Congress’ stated preference that the Outer Continental Shelf be made available for
1332(3). The Court should therefore stay its injunction pending appellate review.
In the alternative, if the Court decides against staying its Order pending appeal,
Defendants respectfully request that the Court issue a temporary stay until resolution by the
Court of Appeals of an emergency motion by the United States for a stay pending appeal of the
The Court is familiar with the factual background of this case, which is described in
Defendants’ Opposition to Plaintiffs’ Motion for Preliminary Injunction, filed on December 22,
2010 (Dkt. #161), Defendants’ Supplemental Brief, filed on January 20, 2011 (Dkt. #191), and
February 28, 2011 (Dkt. # 247). Those facts are incorporated herein by reference.
then-First Amended Complaint. Dkt. # 139. Count IV initially sought to compel programmatic,
Gulf-wide action on applications for permits to drill for oil and gas in the Gulf in Mexico. On
December 22, 2010, however, Plaintiffs moved for leave to file a Second Amended Complaint.
3
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 4 of 12
The proposed pleading amended Count IV to allege unreasonable delay only with respect to nine
permit applications. Plaintiffs thereafter clarified that their preliminary injunction motion sought
to compel a decision from BOEMRE on five of those nine applications. On January 13, 2011,
the Court granted Ensco’s motion for leave, now joined by Plaintiff ATP Oil & Gas Corporation,
to file a Second Amended Complaint narrowing the scope of Count IV to nine specific permits,
including the five that were subject to the then-pending motion for a preliminary injunction. See
Dkt. # 184, 185. On January 12, the Court denied, without prejudice, Ensco’s preliminary
On January 20, at the Court’s request, the parties filed supplemental briefs addressing the
Court’s ability to impose a timeframe for action on Plaintiffs’ permit applications, and what, if
any, evidence justified the granting of the preliminary injunction as opposed to ultimate
consideration of permanent relief at a later stage of these proceedings. See Dkt. # 188, 191.
On January 29, BOEMRE filed the administrative record for Plaintiffs’ Count IV. See Dkt. #
215, 218. On February 17, before the parties had the opportunity to brief on the merits on the basis
of the Administrative Record, the Court sua sponte rescinded its prior denial of Plaintiffs’ preliminary
injunction and issued an injunction requiring BOEMRE to issue a decision on each of the five
applications within thirty days. See Dkt. # 229. Upon Plaintiffs’ motion, the Court supplemented
that order on March 1, requiring BOEMRE to issue a decision on two additional permits within thirty
IV. ARGUMENT
Under Rule 62(c) of the Federal Rules of Civil Procedure, a district court may, in its
discretion, stay any interlocutory order, including one granting a preliminary injunction, during
the pendency of an appeal of that order. Fed. R. Civ. P. 62(c). In order to obtain a stay pending
4
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 5 of 12
appeal, the moving party must: (1) make a strong showing that it is likely to succeed on the
merits; (2) demonstrate that it would suffer irreparable injury if the stay were not granted; (3)
show that granting the stay would not substantially harm the other parties; and (4) show that
granting the stay would serve the public interest. Hilton v. Braunskill, 481 U.S. 770, 776 (1987).
Rather than apply these factors in a rigid, mechanical fashion, however, the Fifth Circuit has
adopted a “balance of equities approach in determining whether to grant a stay pending appeal.”
Ruiz v. Estelle, 650 F.2d 555, 565 (5th Cir. 1981). See also Nat’l Treasury Employees Union v.
Von Raab, 808 F.2d 1057, 1059 (5th Cir. 1987). Specifically, “the movant need only present a
substantial case on the merits when a serious legal question is involved and show that the balance
of the equities weighs heavily in favor of granting the stay.” Id. The Fifth Circuit’s approach
results from a common-sense interpretation of Rules 62(c) and Federal Rule of Appellate
If a movant were required in every case to establish that the appeal would
probably be successful, the Rule would not require as it does a prior presentation
to the district judge whose order is being appealed. That judge has already
decided the merits of the legal issue. The stay procedure of Fed.R.Civ.P. 62(c)
and Fed.R.App.P. 8(a) affords interim relief where relative harm and the
uncertainty of final disposition justify it.
650 F.2d at 565; see also Mazurek v. United States, No. 99-2003 C/W 99-2229, 2001 WL
260064 at *1 n.1 (E.D. La. Jan. 11, 2001) (Feldman, J.) (same); Wildmon v. Berwick Universal
Defendants are likely to succeed on the merits of their appeal. As a threshold matter,
Plaintiffs are not entitled to an order compelling BOEMRE to issue a final decision on any
permit applications because Plaintiffs have not yet succeeded on the merits of their unreasonable
delay claim. Count IV states nine separate claims, each of which asserts that BOEMRE’s review of
5
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 6 of 12
a particular application has been unreasonably delayed pursuant to 5 U.S.C. § 706(1). Through their
preliminary injunction motions, Plaintiffs sought to fully and finally resolve seven of those claims by
asking the Court to compel BOEMRE to reach final decisions on the applications pertaining to
Cobalt, Nexen, and ATP. To obtain an order compelling agency action under 5 U.S.C. § 706(1),
however, a plaintiff must achieve actual success on the merits; a mere likelihood of success is
insufficient. See Univ. of Tex. v. Camenisch, 451 U.S. 390, 395 (1981) (“it is generally inappropriate
for a federal court at the preliminary injunction stage to give a final judgment on the merits.”);
Dresser Rand Co. v. Virtual Automation, Inc., 361 F.3d 831, 847 (5th Cir. 2004) (“[F]or a permanent
injunction to issue the plaintiff must prevail on the merits of his claim”). That did not occur in this
case and, accordingly, the Court’s issuance of an order compelling agency action was improper. See
Wilson v. Zarhadnick, 534 F.2d 55, 57 (5th Cir. 1976) (finding reversible error where district court
issued permanent injunction after the hearing on a preliminary injunction motion without prior notice
to parties and without first consolidating the proceedings with a trial on the merits).
But even if a motion for a preliminary injunction were an appropriate means of seeking
relief under 5 U.S.C. § 706(1), the Court’s February 17 finding—which the Court extended to its
March 1 Order—was based upon its conclusion that the OCSLA requires Interior to act within
thirty days of receiving an application for a permit to drill. See Dkt. #229 at 5–15. The OCSLA,
however, imposes no such time limit. See Dkt. #161 at 11-12; Dkt. #191 at 5–7.2
Instead, the merits of Count IV must be assessed separately for each permit application
that Plaintiffs allege has been unreasonably delayed. The Administrative Record for Count IV
2
The Court’s Order appears to have relied at least in part on the OCSLA’s 30-day time limit for
review of Exploration Plans as its rationale for imposing the same time limit for review of APDs.
The 30-day period for Exploration Plans (and the 120-day period for approval of Development
Operations Coordination Documents) does not begin to run until the EP or DOCD is deemed
submitted. Declaration of Michael Saucier at ¶ 11.d. n. 2 (attached hereto as Exhibit A); see also
30 C.F.R. § 250.231; 250.233.
6
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 7 of 12
requiring a longer processing time than others and, accordingly, the reasonableness of
BOEMRE’s processing time cannot be “decided in the abstract, by reference to some number of
Wampanoag Tribal Council, Inc. v. Norton, 336 F.3d 1094, 1101-1102 (D.C. Cir. 2003); see also
Liberty Fund, Inc. v. Chao, 394 F Supp. 2d 105, 115 (D.D.C. 2005) (rejecting as unpersuasive
those decisions that have granted mandamus petitions based solely on the length of a processing
delay and without sufficient consideration of other TRAC factors); Vietnam Veterans of Am.,
2009 WL 6179013, at *2 (refusing argument that agency should render decisions on all claims for
benefits within 90 days of receipt, and recognizing that each claim may present unique “nature,
complexity, or status”).
The Court assessed the agency’s review time by applying the six “TRAC factors.” See Dkt.
#229 at 8–9. Applying those factors to this case, Defendants explained that regulatory requirements
for drilling permits have significantly evolved since April 20, 2010, thereby increasing the
amount of time needed to review each application. See Dkt. #161-6 ¶¶ 4, 7-10. Defendants also
explained that the applications BOEMRE receives frequently lack the information that
Finally, Defendants explained that BOEMRE had taken action on six of the seven permit
applications at issue here by identifying flaws in the applications and returning them to the
operator for correction. See Dkt. #161 at 12-14; Dkt. # 247 at 6-8. For example, with regard to
the Cobalt Energy application for GB 959 Well #1, BOEMRE has engaged in multiple
exchanges with the applicant seeking additional information to comply with the permitting
requirements. See, e.g., PubIV03833; 003835; 003844. Similarly, for ATP’s application for MC
7
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 8 of 12
941 Well #4, the Record reflects the same approach, including numerous email exchanges of
information and face-to-face meetings to discuss the application. See, e.g., PubIV005889-
BOEMRE representatives). BOEMRE has not unreasonably delayed its review where the
applications themselves are not complete. See Orion Reserves Ltd. P’ship v. Kempthorne, 516
F. Supp. 2d 8, 12-13 (D.D.C. 2007) (recognizing that a court’s calculation of the time elapsed
since an agency came under a “duty to act” with respect to an application does not include
periods during which the application is found to be void or incomplete). Defendants also
explained that BOEMRE had identified flaws in the seventh application that prevented
BOEMRE from approving it, and that the operator did not plan to begin drilling until June 2011.
Under those circumstances, Plaintiffs could not demonstrate that BOEMRE had
unreasonably delayed a decision on any of the five applications as of January 20, 2011 (the date
the parties were directed to submit supplemental briefing). Moreover, after briefing on the
preliminary injunction, but before the Court’s February 17 Order, Defendants submitted the
Administrative Record with respect to their processing of the nine permit applications at issue in
Count IV, which further demonstrates the reasonableness of BOEMRE’s review process.
Defendants are likely to succeed on the merits of their appeal and a stay of this Court’s Orders
The balance of harms in this case weighs strongly in favor of staying the Court’s Orders.
The regulatory requirements that govern the permitting process are designed to prevent further
loss of life and environmental and economic devastation such as occurred as a result of the
8
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 9 of 12
Deepwater Horizon incident. The Cobalt, Nexen, and ATP applications subject to the Court’s
Orders have not yet satisfied these requirements and, accordingly, they cannot be approved in
their current state. See Decl. of Michael J. Saucier at ¶ 10, Attached as Exhibit A to this Motion
(hereinafter “Saucier Decl.”). The present state of the seven applications, combined with the
Court’s imposed decision deadlines, will cause harm to BOEMRE, the public, and development
First, BOEMRE itself will be harmed in complying with the Court’s Orders. Consistent
with its normal practice, BOEMRE intends to assist the operators in meeting the regulatory
requirements in time to allow their permits to be approved under those regulations prior to the
Court’s deadlines. Saucier Decl. at ¶ 11.b. To accomplish that task, however, the agency will
have to refocus its permit review resources to heavily focus on these seven applications. Id. at ¶
11.c. This will pull agency staff away from other important tasks, including review of other
shallow and deepwater permit applications; correspondence and communication with other
operators regarding those other applications and their current state of compliance; and review of
weekly reports from active operations to ensure drilling is proceeding in accordance with
approved permit applications. Id. at ¶¶ 11.b. Moreover, “with respect to the seven applications
subject to the Court’s orders, if the applicable thirty-day deadline approaches and the
deficiencies in a given permit application have not been corrected, or if the information is
submitted without sufficient time for BOEMRE to complete its review prior to the deadline, the
application may have to be denied so that the agency can comply with the Court’s orders.” Id. at
¶ 12.d.
Second, compliance with the Court’s Orders will greatly impact other operators. Because
BOEMRE’s resources will be focused on the seven applications, the agency will be forced to
9
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 10 of 12
delay its review of other applications, including applications for shallow water drilling, which
may otherwise be ready for final review and approval. Id. at ¶ 12. This may delay resource
development at these other wells, potentially causing economic harm to the companies proposing
those operations. Id. at ¶ 12.b. That harm is underscored by the fact that shallow water drilling
companies generally maintain less capital than deepwater companies, and are thus not as well
Third, the resource reallocation that necessarily results from the Court’s Orders will harm
the public’s interest in the efficient development of oil and gas resources. Id. at ¶ 12.a.
Operations that may have otherwise been able to proceed in the coming weeks will be delayed;
all in the name of a making a final decision on the seven applications that both the operators and
BOEMRE know are not yet ready for final review. Id. at ¶¶ 11-12. The disruption to
BOEMRE’s developed iterative permit review process only frustrates Congress’s stated policy of
making the outer Continental Shelf available for “expeditious and orderly development subject to
environmental safeguards.” 43 U.S.C. § 1332(3). The Court should therefore stay its injunction
By contrast, Plaintiffs themselves will not be prejudiced by the granting of the stay,
because, consistent with the iterative process it follows in reviewing permit applications,
BOEMRE would continue to review Plaintiffs’ permit applications during a stay of the
preliminary injunction. Moreover, as Defendants noted in their Motion for Summary Judgment
on Counts II and III of Ensco’s Amended Complaint, Ensco lacks standing to challenge the
review of permits because it is not a lessee or operator. See Dkt. 42 at 6-8. In addition, Ensco
failed to demonstrate that it would be injured in the absence of injunctive relief. Accordingly, it
is abundantly clear that Ensco would also not be harmed by the granting of a stay. Ensco has
10
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 11 of 12
failed to show that it will suffer any compensable economic harm as a result of BOEMRE’s
orderly review of its permit applications. See Dkt. #161 at 22-23. In addition, Ensco’s only
other argument for injury, the loss of its skilled workforce, is similarly flawed. Id. at 23-24.
Ensco has not provided a single example of an employee who has lost skills or who has left
Should the Court decide against granting Defendants’ request that its Orders be stayed
pending appeal, then Defendants respectfully request that the Court temporarily stay the Orders
pending resolution by the Court of Appeals of an emergency motion by the United States under
Federal Rule of Appellate Procedure 8(a). See, e.g., Kouba v. Allstate Ins. Co., Civil Action No.
S-77-99 LKK, 1981 WL 278, *7 (E.D. Cal. Nov. 12, 1981) (“in order to facilitate defendant’s
Rule 8(a) application, this court grants defendant’s motion for a temporary stay”). A stay for this
purpose will not impose appreciable hardship upon the Plaintiffs, and will ensure that the Court
of Appeals has sufficient opportunity to review the parties’ competing positions on whether a
V. CONCLUSION
For the foregoing reasons, Defendants respectfully request that the Court enter a stay
pending appeal of its Orders granting Plaintiffs’ Motion for Preliminary Injunction, or in the
alternative, that it enter a temporary stay until resolution by the Court of Appeals of an
11
Case 2:10-cv-01941-MLCF-JCW Document 264-1 Filed 03/04/11 Page 12 of 12
IGNACIA S. MORENO
Assistant Attorney General
Environment and Natural Resources Division
PETER MANSFIELD
Assistant United States Attorney
Eastern District of Louisiana
Hale Boggs Federal Building
500 Poydras Street, Suite B-210
New Orleans, Louisiana 70130
Tel: (504)680-3000
CERTIFICATE OF SERVICE
I hereby certify that on March 4th, 2011, I caused a copy of the foregoing to be served
/s/Brian Collins__
Brian Collins
Attorney for Defendants
12