Hugh Donovan, Eight-Year Review of The Full Depth Reclamation Process in The City of Edmonton
Hugh Donovan, Eight-Year Review of The Full Depth Reclamation Process in The City of Edmonton
Hugh Donovan, Eight-Year Review of The Full Depth Reclamation Process in The City of Edmonton
200-300mm
Hot Mix 150 - 300mm
Asphalt Granular Base 150-200mm
or or Portland
Oil Mix Soil Cement Cement
Base Concrete
City of Edmonton Roadway
2007-2011 Construction Budget
2007 - 2011 CPP Funded Projects
175
Dollars (X 000,000)
150
125
100
75
50
25
0
2007 2008 2009 2010 2011
Year
900
2009
2009
800
700
600
•500By the end of the 2009 construction season it has
been estimated that we had used an additional 505
400
Million tonnes of sand and gravel in the Edmonton
300
region;
200
100
• By0 2026 given current growth we estimate that we
will have used an additional 400 to 550 Million
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
tonnes of sand and gravel in the Edmonton region,
taking us to almost 1 Billion
Year tonnes
Gravel & Asphalt Combined Concrete Sand
Aggregate Supply Issues
• Current Local Aggregate Sources:
Are of poorer quality;
Have smaller rock fraction
maximum size;
More costly to process;
Secondary processing to remove
deleterious materials;
Further aggregate haul distances
Pavement Distresses Treated
Cracking, in the form of:
Age;
Fatigue;
Block;
Longitudinal;
Reflective;
Discontinuity
Legend:
0 - 25 mm
26 - 50 mm
50 - 100 mm
101 - 150 mm
151 - 200 mm
201 - 250 mm
251 - 300 mm
Granular
Asphalt Fulton Place Neighbourhood 2010 Project
Deflection Testing Pre & Post
Construction
0.0
0.5
1.0
1.5
2.0
2.5
3.0
0+000
0+040
0+090
0+140
0+190
0+240
0+290
0+340
0+390
0+440
0+490
0+540
0+590
0+640
0+690
0+740
Station
Ebound
0+790
Dynaflect
0+840
0+890
0+940
0+990
Existing Roadway Prior to Construction
1+040
1+090
1+140
1+190
1+240
Ellerslie Road Deflection Profile - 142 to 156 Street
1+290
1+340
1+390
Pavement Design
City of Edmonton’s asphalt overlay
design is based on deflection models
“Mix Design
Procedures of
Stabilized Materials”;
Samples obtained
utilizing WR2500;
Mix Design Laboratory Testing
SIEVE ANALYSES;
PLASTICITY;
MOISTURE DENSITY RELATIONSHIP;
BITUMEN FOAMING CHARICTERISTICS;
PREPARATION OF SAMPLES;
MIX WITH STABILIZING AGENTS;
CURING OF SAMPLES;
INDIRECT TENSILE STRENGTH TESTING
FOAM MIX DESIGN REPORT
Indirect Tensile
Client: City of Edmonton
Project : Ellerslie Road
Sample Number : 1
Material to be foamed
Strength Testing/
Location :
Asphalt content :
Insitu/Camron50/50 blend
Mix Design
Optimum moisture content : 5.5
Maximum dry density :
Asphalt cement used for foaming Foam requirements
Supplier : Husky Energy 2 Percentage "foaming" water :
Type: 150-200 pen 160 C Temperature of asphalt cement :
1% cement Additive and percentage :
Foamed asphalt treated material characteristics
Foamed asphalt added : 2.0 2.5 3.0 3.5
Actual foamed asphalt added : 2.00 2.50 3.00 3.50
Diameter of specimen (mm) 101.0 101.0 101.0 101.0
Height of specimen (mm) : 64.0 64.7 65.2 64.7
Mass of specimen (g) : 1086.5 1105.0 1105.5 1104.5
Bulk density (kg/m3): 2118 2132 2117 2131
Relative density (kg/m3) :
ITS dry (kPa): 427 355 358 325
ITS soaked (kPa): 262 327 280 291
Retained ITS (%): 61 92 78 90
Resilient modulus (Mpa):
Foamed asphalt vs ITS dry Foamed asphalt vs ITS soaked
450 340
300
350 280
300 260
240
250
220
200 200
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 1.50 2.00 2.50 3.00 3.50 4.00
100
80
2150
20 2050
0 2000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 0.00 1.00 2.00 3.00 4.00
Foamed asphalt content
Equipment Used - WR2500 or WR2500S
The Recycling Train
Asphalt Tanker
Wirtgen 2500 S
Water Truck
Place 100 mm
New Hot Mix
50 - 100mm
Asphalt
Hot Mix Asphalt Existing Structure
Reconstructed Roadway
150 – 300mm
Place 300mm
Granular Base3-20 or 3-25
Granular Base
or
Soil Cement Base
50 - 100mm
Hot Mix Asphalt Existing
Foaming Structure
& Final
Pre-pulverization Overlay
Process
Prepulverize
125-250mm
Foam and
Existing HotMix
Mix Asphalt &
150 –
125-250mm 300mm
Granular/Soil Cement
Granular
Pre-pulverizedBase
Materials
Materials
or
Soil Cement Base
50-75mm Remaining
Granular materials
Cost Comparison Example 2009$
Project 20,000 M2 Residential Reconstruction/FDR with Foamed Asphalt
Existing Structure – 50mm AC over 175mm SC
Item Description unit Unit Cost Quantity Total Cost
Reconstruction Option – 100mm ACR, 300mm 3-20mm Granular Base on Stabilized Subgrade
11.032 Remove Asphalt Course (50mm) m2cm $ 0.97 1000 $ 970.00
11.034 Remove Soil Cement Course m2cm $ 0.90 3500 $ 3,150.00
16.021 Gravel 3-20 Base tonne $ 71.76 13200 $ 947,232.00
31.010 150 Cement Stabilized Subgrade m2 $ 7.28 20000 $ 145,600.00
31.030 Cement for Stabilizing Subgrade 10Kg $ 2.14 20000 $ 42,800.00
40.421 Asphalt Overlay (ACR) Mass tonne $ 114.00 5082 $ 579,348.00
Foamed Asphalt Option – Prepulverize & Foam 150mm Depth with 75mm ACR Surface
31.047 Pre-pulverized Road Base m2 $ 3.91 20000 $ 78,200.00
31.048 Add/Delete 0.2% Oil m2 $ 0.46 20000 $ 9,200.00
31.049 Add/Delete 0.5% Cement m2 $ 0.66 20000 $ 13,200.00
31.051 150mm FDR using Foamed Asphalt m2 $ 13.49 20000 $ 269,800.00
40.421 Asphalt Overlay (ACR) Mass tonne $ 114.00 3811 $ 434,454.00
2010 Nine Contracts 3 neighbourhoods & Total not yet Does not include 2010
locations
~15 locations available
156 Street, 137 to St. Albert Trail
– Rural Granular Cross-Section
3.5
3.3
3.0
2.8
Deflection (mils)
2.5
2.3
2.0
1.8
1.5
1.3
1.0
0.8
0.5
0.3
0.0
Station
Pre - 2001 Post - 2001 Aug -02 May-05 May-07 May-09
Some Cracking
93 Avenue, 146 to 149 Street
2,175
y = -43.909Ln(x) + 2168.2
2,150 R
2
= 0.7616
Maximum Allowable loss 11%
Density (kg/m3)
2,125
2,100
2,075
2,050
2,025
2,000
1,975
1,950
1,925
1,900
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80
% Loss
Freeze-Thaw Testing
Freeze Thaw Testing (Density vs. % Loss)
2,275
2,250
y = -127.24Ln(x) + 2237.4
2,225 R2 = 0.7112
2,200
Density (kg/m3)
2,175
2,150
Maximum Allowable loss 11%
2,125
2,100
2,075
2,050
2,025
2,000
1,975
1,950
1,925
1,900
0 1 2 3 4 5 6 7 8 9 10
% Loss
Wet/Dry - Freeze/Thaw
Resiliant Modulus FWD Backcalculation
Foamed Stabilized
Subgrade
Asphalt Materials
Resiliant
Resiliant modulus
Modulus Resilient Modulus
(Backcalculated)
(Backcalculated)
75
9,500 (Backcalculated)
3,500
70
9,250
65
(MPa)
Modulus (MPa)
3,250
9,000
60
8,750
3,000
55
8,500
2,750
50
Resiliant Modulus
8,250
45
2,500
8,000
40
2,250
7,750
35
7,500
2,000
30
Resiliant
7,250
Resilient
1,750
25
7,000
20
1,500
6,750
15
1,250
6,500
10
6,250
1,000
5
6,000
0
750
2000
2000
2000 2001
2001
2001 2002
2002
2002 2003
2003
2003 2004
2004
2004 2005
2005
2005 2006
2006
2006
Construction
ConstructionYear
Construction Year
Year
Benefits Of Cold Recycling
Reuse of the material in the existing pavement
generally better quality materials than are
currently available.
Derive maximum benefit of existing pavement
structure as a stabilized base course material
Simultaneous addition of “make-up (granular)”
material and/or stabilizing agent(s)
Speed of construction - one or two pass
operation vs. a multi-pass operation
Accommodation of traffic - roadway is never
closed to traffic
Economics ($) 30 to 50% saving
Conclusions
Cold Recycling utilizing Foamed Bitumen is a viable
technology for use on many different types of
roadways;
The structural capacity of Foamed Bitumen treated
materials approaches 85% of hot laid asphalt mixes
Granular Base Equivalency of between 1.6 and 1.8;
The full depth pulverization completely eliminates any
possibility of reflective cracking;
There is no requirement for lengthy curing periods
prior to overlay of Foamed bitumen treated
materials;
Pre-engineering work by the owner is critical;
Imported granular material is definitely an option to
cover any material gradation problem.
Questions ?