EnDev Indonesia

GIZ Renewable Energy Programme Indonesia/ASEAN

PLTS and PLTMH Site Assessment Checklist

Purpose of this checklist is to assess the suitability of a site to accommodate PLTS or PLTMH facility. The
checklist also considers available resources and anticipated demand for electricity. The checklist highlights the
minimum data and information needed to make a first-level feasibility assessment.
Checklist is to be completed by the applicant for the PLTS or PLTMH infrastructure and submitted to the
relevant decision-making authority, along with all supplementary information (e.g. site photographs).

List of Abbreviations

km kilometers
l/s litres per second
m meter
PLN Perusahaan Listrik Negara
PLTS Pembangkit Listrik Tenaga Surya (Solar Power Plant)
PLTMH Pembangkit Listrik Tenaga Mikro Hidro (Micro Hydro Power Plant)

For more information: www.endev-indonesia.org; endev.indonesia@giz.de


KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI
JALAN PEGANGSAAN TIMUR NO. 1A CIKINI JAKARTA – 10320

Telepon: (021) 39830077 Faksimile: (021) 31901097 Website: www.ebtke.esdm.go.id Email: info@ebtke.esdm.go.id

PLTS Site Selection Checklist


Village Name Regency
Subdistrict Province
Date of initial survey Contact person: Contact number:

1. Number of connections: a. Private houses d. Health Centre


b. Warung and small businesses e. Religious Buildings
c. School f. Other (Please specify):

2. Ownership of the land for PLTS installation is (please tick) a. Private c. State
b. Community d. Other (Please specify):
3. Available area for PLTS installation Width (m) m Length (m) m
4. Access to village (please tick) a. by foot c. by motorcycle e. by car
b. by truck d. by boat f. by plane

5. Nearest PLN grid connection: Name: Distance: km


6. Nearest subdistrict capitol: Name: Distance: km
7. Distance of village to PLTS area km
8. Plan to connect village to PLN grid (please tick) a. in less than 5 years b. in more than 5 year c. no plan
9. Available electricity sources in the village (please tick) a. Diesel genset c. PLTS e. none
d. PLN d. PLTMH f. Other

10. The immediate area is (tick all that apply)


a. Surrounded by high trees f. Next to an ocean beach
b. Surrounded by tall buildings g. Next to a river bank
c. Situated in a small narrow valley h. Frequently very windy
d. Frequently flooded in the rainy season i. Located on a mountain with regular cloud cover and mist
e. Located on a slope with signs of soil erosion j. Other (Please specify):

11. Site photographs


• Minimum four (4) site photographs, each from different direction (North, East, South and West) aiming into centre of area.
• Place person in centre of area, for size reference a. From North

Additional information:

d. From West b. From East

c. From South
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI
JALAN PEGANGSAAN TIMUR NO. 1A CIKINI JAKARTA – 10320

Telepon: (021) 39830077 Faksimile: (021) 31901097 Website: www.ebtke.esdm.go.id Email: info@ebtke.esdm.go.id

PLTMH Site Selection Checklist


Village Name Regency
Subdistrict Province
Date of initial survey Contact person: Contact number:

1. Number of connections: a. Private houses d. Health Centre


b. Warung and small businesses e. Religious Buildings
c. School f. Other (Please specify ):

2. Ownership of the land for PLTMH installation is (please tick ) a. Private c. State
b. Community d. Other (Please specify ):
3. Available flat area for PLTMH power house: Width (m) m Length (m) m
4. Access to village (please tick ) a. by foot c. by motorcycle e. by car
b. by truck d. by boat f. by plane

5. Nearest PLN grid connection: Name: Distance: km


6. Nearest subdistrict capitol: Name: Distance: km
7. Distance of village to PLTMH power house km
8. Plan to connect village to PLN grid (please tick ) a. in less than 5 years b. in more than 5 year c. no plan
9. Available electricity sources in the village (please tick) a. Diesel genset c. PLTS e. none
d. PLN d. PLTMH f. Other
10. Other sub-villages to connect:
Name: Distance: m
Name: Distance: m

11. Name of the River / Irrigation 12. Size of River (please tick) a. Big River (W> 20m)
b. Medium River (5m < W < 20m)
13. Is the water of the river / irrigation reduced much c. Small River (W <5 m)
during the dry season ? Yes No d. Irrigation channel
14. The rainy season is usually started in the month of: If d. Irrigation channel:
to Width cm Depth cm

15. Using the picture of PLTMH, please estimate of some key data below:
A. Water 
flow (l/s)
A. Water flow: l/s (litres per second)
B. Length of 
B. Length of channel: m
C. Head height: m

Additional information:
C. Head 
height (m)