Plts and PLTMH Site Assessment Checklist: Endev Indonesia
Plts and PLTMH Site Assessment Checklist: Endev Indonesia
Purpose of this checklist is to assess the suitability of a site to accommodate PLTS or PLTMH facility. The
checklist also considers available resources and anticipated demand for electricity. The checklist highlights the
minimum data and information needed to make a first-level feasibility assessment.
Checklist is to be completed by the applicant for the PLTS or PLTMH infrastructure and submitted to the
relevant decision-making authority, along with all supplementary information (e.g. site photographs).
List of Abbreviations
km kilometers
l/s litres per second
m meter
PLN Perusahaan Listrik Negara
PLTS Pembangkit Listrik Tenaga Surya (Solar Power Plant)
PLTMH Pembangkit Listrik Tenaga Mikro Hidro (Micro Hydro Power Plant)
Telepon: (021) 39830077 Faksimile: (021) 31901097 Website: www.ebtke.esdm.go.id Email: info@ebtke.esdm.go.id
2. Ownership of the land for PLTS installation is (please tick) a. Private c. State
b. Community d. Other (Please specify):
3. Available area for PLTS installation Width (m) m Length (m) m
4. Access to village (please tick) a. by foot c. by motorcycle e. by car
b. by truck d. by boat f. by plane
Additional information:
d. From West b. From East
c. From South
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL REPUBLIK INDONESIA
DIREKTORAT JENDERAL ENERGI BARU, TERBARUKAN DAN KONSERVASI ENERGI
JALAN PEGANGSAAN TIMUR NO. 1A CIKINI JAKARTA – 10320
Telepon: (021) 39830077 Faksimile: (021) 31901097 Website: www.ebtke.esdm.go.id Email: info@ebtke.esdm.go.id
2. Ownership of the land for PLTMH installation is (please tick ) a. Private c. State
b. Community d. Other (Please specify ):
3. Available flat area for PLTMH power house: Width (m) m Length (m) m
4. Access to village (please tick ) a. by foot c. by motorcycle e. by car
b. by truck d. by boat f. by plane
11. Name of the River / Irrigation 12. Size of River (please tick) a. Big River (W> 20m)
b. Medium River (5m < W < 20m)
13. Is the water of the river / irrigation reduced much c. Small River (W <5 m)
during the dry season ? Yes No d. Irrigation channel
14. The rainy season is usually started in the month of: If d. Irrigation channel:
to Width cm Depth cm
15. Using the picture of PLTMH, please estimate of some key data below:
A. Water
flow (l/s)
A. Water flow: l/s (litres per second)
B. Length of
B. Length of channel: m
C. Head height: m
Additional information:
C. Head
height (m)