Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

CON4157 N10 CashFlowS-curve (2021S2)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

CON4157"AY2021

CASH FLOW ANALYSIS

What is the objective of cash flow 
analysis?

CON4157@VTC2021 CC BB‐NC‐ND 1

CASH FLOW ANALYSIS

The amount of money gain in and expend out day to 
day, month to month / quarter to quarter.

To ensure the project progress runs in correspondence 
with finance support.

Outline the amount of money to be required from 
time being.

CON4157@VTC2021 CC BB‐NC‐ND 2

CC BB‐NC‐ND 1
CON4157"AY2021

Example

Month        Expenses        Payment Received          
Balance        .      
HK$ HK$ HK$

January 30,000.00
February 40,000.00
March 10,000.00
April 60,000.00
Total 140,000.00

CON4157@VTC2021 CC BB‐NC‐ND 3

Example

Month        Expenses        Payment Received          
Balance        .      
HK$ HK$ HK$

January 30,000.00 0
February 40,000.00 20,000.00
March 10,000.00 100,000.00
April 60,000.00 40,000.00

Total 140,000.00 160,000.00


CON4157@VTC2021 CC BB‐NC‐ND 4

CC BB‐NC‐ND 2
CON4157"AY2021

Example
Month        Expenses        Payment Received          
Balance        .      
HK$ HK$ HK$

January 30,000.00 0 (30,000.00)


February 40,000.00 20,000.00 (20,000.00)
March 10,000.00 100,000.00 90,000.00
April 60,000.00 40.000.00 (20,000.00)

Total 140,000.00 160,000.00 20,000.00


CON4157@VTC2021 CC BB‐NC‐ND 5

Based upon the above example, we can have to consider 
that:

In January,
HK$30K has been paid without income.
It indicates a result of negative balance which means the 
contractor has to get HK$30K to cover the payment.

In February,
HK$40K and HK$20K have been expended and gained 
respectively.
So, the balance is ‐20K which means the contractor has to get 
HK$20K to cover the payment.
CON4157@VTC2021 CC BB‐NC‐ND 6

CC BB‐NC‐ND 3
CON4157"AY2021

In March,
HK$10K and HK$100K have been expended and gained respectively.
So the balance is HK$90K which means this is a surplus and could 
pay back the money which was borrowed to cover the previous 
months’ negative balance.

In April,
HK$60K and HK$40K have been expended and gained respectively.
It comes to a negative balance HK$20K and to be covered from the 
surplus of last month.

CON4157@VTC2021 CC BB‐NC‐ND 7

Summing up

HK$140K and HK$160K have been paid out and gained in 
respectively.

The final balance HK$20K indicates that there is a profit made 
from this project.

CON4157@VTC2021 CC BB‐NC‐ND 8

CC BB‐NC‐ND 4
CON4157"AY2021

Each month’s  Each month’s 
expenses is  receipts is 
added to  added to 
that of the  that of the  Each month’s 
previous  previous  balance 
month (A) month (B) Column (B) –
(A)
Refer to the previous table

Month Expenses Receipts Balance Accumulated  Accumulate Accumulated 


of  Expenses d Receipt of  Balance
Payment Payment
HK$(K) HK$(K) HK$(K) HK$(K) HK$(K)
HK$(K) 
JAN 30 0 ‐30 30 0 ‐30
FEB 40 20 ‐20 70 20 ‐50
MAR 10 100 +90 80 120 This  40
APR 60 40 ‐20 140 160 is the  20
profit

CON4157@VTC2021 CC BB‐NC‐ND 9

Each month’s  Each month’s 
expenses is  receipts is  Each 
added to  added to  month’s 
that of the  that of the  balance 
previous  previous  Column 
month (A) month (B) (B) – (A)

Refer to the previous table
Month Expenses Receipts Balance Accumulated  Accumulate Accumulated 
of  Expenses d Receipt of  Balance
Payment Payment
HK$(K) HK$(K) HK$(K) HK$(K) HK$
HK$(K) 
JAN 30 0 ‐30 30 0 ‐30
FEB 40 20 ‐20 70 20 ‐50
MAR 10 100 +90 80 120 40
This 
APR 60 40 ‐20 140 160 is the  20
profit

CON4157@VTC2021 CC BB‐NC‐ND 10

CC BB‐NC‐ND 5
CON4157"AY2021

Each month’s  Each month’s 
expenses is  receipts is 
added to  added to 
that of the  that of the  Each month’s 
previous  previous  balance 
month (A) month (B) Column (B) –
(A)
Refer to the previous table

Month Expenses Receipts Balance Accumulated  Accumulate Accumulated 


of  Expenses d Receipt of  Balance
Payment Payment
HK$(K) HK$(K) HK$(K) HK$(K) HK$
HK$(K) 
JAN 30 0 ‐30 30 0 ‐30
FEB 40 20 ‐20 70 20 ‐50
MAR 10 100 +90 80 120 40
This 
APR 60 40 ‐20 140 160 is the  20
profit

CON4157@VTC2021 CC BB‐NC‐ND 11

Question

What we could observe from the above?
From the above table, we observe that the picture payment out and in 
for a project.

Mainly, it give an overview to the site manager / quantity surveyor that 
there is a need to borrow money for the outstanding HK$30K and 
HK$20K in Jan and Feb respectively.  

The accumulated total is therefore HK$50K to be short.

CON4157@VTC2021 CC BB‐NC‐ND 12

CC BB‐NC‐ND 6
CON4157"AY2021

Consolidating Cash Flow with 
Programed Works
Activity Materials Labor Plant &  Total
Others
HK$(K) HK$(K) HK$(K) HK$(K)
Setting Up NIL NIL 30 30
Ground Work NIL 5 NIL 5
Formwork 10 12 NIL 22
Steel Work 15 9 NIL 24
Concreting 15 6 NIL 21
Cleaning Up &  NIL 3 NIL 3
Handover
Total 105

CON4157@VTC2021 CC BB‐NC‐ND 13

Consolidating Cash Flow with 
Programed Works

Activity JAN FEB MAR APR


Setting up
Ground 
Work
Formwork
Steelwork
Concreting
Cleaning up 
& Handover

CON4157@VTC2021 CC BB‐NC‐ND 14

CC BB‐NC‐ND 7
CON4157"AY2021

Consolidating Cash Flow with 
Programed Works
Activity JAN FEB MAR APR
Setting up
Ground 
Work
Formwork
Steelwork
Concreting
Cleaning up 
& Handover

CON4157@VTC2021 CC BB‐NC‐ND 15

Consolidating Cash Flow with 
Programed Works

Activity JAN FEB MAR APR


Setting up
Ground 
Work
Formwork
Steelwork
Concreting
Cleaning up 
& Handover
CON4157@VTC2021 CC BB‐NC‐ND 16

CC BB‐NC‐ND 8
CON4157"AY2021

Consolidating Cash Flow with 
Programed Works
Activity JAN FEB MAR APR
Setting up
Ground 
Work
Formwork
Steelwork
Concreting
Cleaning up 
& Handover

CON4157@VTC2021 CC BB‐NC‐ND 17

Consolidating Cash Flow with 
Programed Works
Activity JAN FEB MAR APR
Setting up
Ground 
Work
Formwork
Steelwork
Concreting
Cleaning up 
& Handover

CON4157@VTC2021 CC BB‐NC‐ND 18

CC BB‐NC‐ND 9
CON4157"AY2021

Consolidating Cash Flow with 
Programed Works

Activity JAN FEB MAR APR


Setting up 30
Ground 
5
Work
Formwork 7 15

Steelwork 12 12

Concreting 21

Cleaning up 
1.5 1.5
& Handover
42 27 34.5 1.5

CON4157@VTC2021 CC BB‐NC‐ND 19

Estimated Expenditures Allocation During Construction
• Setting up will be an expenditure in January since commencement

• Ground  will be an expenditure in January
Works
• Formwork half will be the expenditures in January and February 
respectively
• Steelwork half in February and March respectively
• Concreting will be completed in March
• Cleaning up  half in March and April respectively 
& Handover
• Overheads allocated over the construction period

CON4157@VTC2021 CC BB‐NC‐ND 20

CC BB‐NC‐ND 10
CON4157"AY2021

Additional Cost Data
Presume that there is an additional HK$20K to be paid for indirect costs as the 
company overheads.  
The total amount of construction will be HK$145K, so the profit margin is to be 
HK$20K indeed. 

Proposed / Agreed Payment Terms
The payment of work done will be scheduled as below:
HK$20K on completion of ground work.
HK$50K on completion of formwork.
HK$45K on completion of concreting.
HK$30K to be kept as retention money for one month after completion.

CON4157@VTC2021 CC BB‐NC‐ND 21

Projected Cash Flow Table

Accumulated Accumulated 
Receipt of  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 42
FEB 27
MAR 34.5
APR 1.5
MAY 0
Total 105

CON4157@VTC2021 CC BB‐NC‐ND 22

CC BB‐NC‐ND 11
CON4157"AY2021

Projected Cash Flow Table

Accumulated Accumulated 
Receipt of  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 42 20
FEB 27 50
MAR 34.5 45
APR 1.5 0
MAY 0 30
Total 105 145

CON4157@VTC2021 CC BB‐NC‐ND 23

Projected Cash Flow Table

Accumulated Accumulated 
Receipt of  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 46 20
FEB 31 50
MAR 38.5 45
APR 5.5 0
MAY 4 30
Total 125 145

CON4157@VTC2021 CC BB‐NC‐ND 24

CC BB‐NC‐ND 12
CON4157"AY2021

Projected Cash Flow Table
Accumulated Accumulated 
Receipt of  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 46 20 ‐26
FEB 31 50 19
MAR 38.5 45 6.5
APR 5.5 0 ‐5.5
MAY 4 30 26
Total 125 145 20

CON4157@VTC2021 CC BB‐NC‐ND 25

Projected Cash Flow Table

Receipt of  Accumulated Accumulated  Accumulated 


Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 46 20 ‐26 46 20
FEB 31 50 19 77 70
MAR 38.5 45 6.5 115.5 115
APR 5.5 0 ‐5.5 121 115
MAY 4 30 26 125 145
Total 125 145 20

CON4157@VTC2021 CC BB‐NC‐ND 26

CC BB‐NC‐ND 13
CON4157"AY2021

Projected Cash Flow Table

Accumulated Accumulated 
Receipt of  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 46 20 ‐26 46 20 ‐26


FEB 31 50 19 77 70 ‐7
MAR 38.5 45 6.5 115.5 115 ‐0.5
APR 5.5 0 ‐5.5 121 115 ‐6
MAY 4 30 26 125 145 20
Total 125 145 20

CON4157@VTC2021 CC BB‐NC‐ND 27

Projected Cash Flow Table

Accumulated Accumulated 
Receipt of  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 51 20
FEB 28 50
MAR 0 45
APR 6.5 0
MAY 0 30
Total 85.5 145

CON4157@VTC2021 CC BB‐NC‐ND 28

CC BB‐NC‐ND 14
CON4157"AY2021

Projected Cash Flow Table
Receipt of  Accumulated Accumulated  Accumulated 
Month Expenses Balance Receipt of 
Payment Balance
Expenses Payment

(HK$) (HK$) (HK$) (HK$) (HK$) (HK$)

JAN 51 20 ‐31 51 20 ‐31


FEB 28 50 22 79 70 ‐9
MAR 0 45 45 79 115 36
APR 6.5 0 ‐6.5 85.5 115 29.5
MAY 0 30 30 85.5 145 59.5
Total 85.5 145 59.5

CON4157@VTC2021 CC BB‐NC‐ND 29

Cash Flow Forecast / Analysis Diagram
160

140

120

100
HK$

80

60

40

20

0
1/1/2018 2/1/2018 3/1/2018 4/1/2018 5/1/2018
1/1/2018 2/1/2018 3/1/2018 4/1/2018 5/1/2018
Accumulated Expenses 51 79 79 85.5 85.5
Accumulated Payment 20 70 115 115 145

CON4157@VTC2021 CC BB‐NC‐ND 30

CC BB‐NC‐ND 15
CON4157"AY2021

Lengthen Payments from The Client

When it is known roughly at which dates the client is likely to 
pay the contractor, these are used in the analysis.  

Let us say that the dates of interim payments should be 20 
Sep, 20 Oct or 20 Dec.  

Then, if you know that the client is usually 2 months late, you 
put the expected payment dates to the end of Nov., end of 
Dec, and Jan, in your cash flow analysis.

CON4157@VTC2021 CC BB‐NC‐ND 31

Lengthen Payments from The Client

Payment terms from terms of agreement  

Even some government departments can be slow 
at making money available to their contractors, and 

the reputations of private clients for prompt 
payment can vary enormously.

CON4157@VTC2021 CC BB‐NC‐ND 32

CC BB‐NC‐ND 16
CON4157"AY2021

Credit Period
Wages are normally paid: 
hourly, daily, weekly, biweekly & monthly.

Materials are often paid:‐
By  installment
By credit account
Cash on delivery
Supply basis
Fixing basis
Supply incl. Fixing

CON4157@VTC2021 CC BB‐NC‐ND 33

Level of Accuracy

Preparing a complete and accurate cash flow 
analysis can be a time consuming process.

An estimate of the amounts to be paid out and 
received at the various stages can be made, if 
time is limited.

CON4157@VTC2021 CC BB‐NC‐ND 34

CC BB‐NC‐ND 17
CON4157"AY2021

Level of Accuracy

In some cases the contractor will know roughly, based on 
experience, how much money will out and in.
Of course, he could base the amounts which he anticipates 
in the cash flow analysis.

Beware that the previous experience is not always 
applying for different kinds of project (e.g. roadworks
instead of buildings) or different employers, they may have 
different policy and agreement of payment terms.

CON4157@VTC2021 CC BB‐NC‐ND 35

Site Costing Objectives
• Cost report in weekly, monthly or 
quarterly basis
• Comparison between the budget and 
actual expense
• Keep Updates from time to time

CON4157@VTC2021 CC BB‐NC‐ND 36

CC BB‐NC‐ND 18
CON4157"AY2021

Site Costing Objectives
• Comparison ./. budget and actual expense
• Keep Updates from time to time
• Identification the tolerance and take necessary remedies
• Control the actual expenditure in conjunction with 
scheduled
• Variances to be made against variance incurred 
unforeseeably and by disruption events
• Analysis to be made in correspondence with the impact 
of variances (i.e. claims)
• Feedback / result of increased cost for future reference

CON4157@VTC2021 CC BB‐NC‐ND 37

Pricing the Estimate
• the estimate is the predicted cost of construction
• the tender is the amount of money for which the contractor offers to 
carry out the works and normally include
• the estimate ( Predicted cost / Price)
• an allowance for the firm’s overheads (OH)
• the profit which the contractor wishes to make (mark up)
• allowance for any additional risks (unforeseeable matters).

CON4157@VTC2021 CC BB‐NC‐ND 38

CC BB‐NC‐ND 19
CON4157"AY2021

All‐in Rates
Labour

A contractor does not only has to pay for the labour
employed at the agreed rate of pay, 

They also have to calculate all the additional costs for 
employing them (i.e. holidays with pay, insurance, etc.)

CON4157@VTC2021 CC BB‐NC‐ND 39

Plants are often paid:
Daily, weekly, monthly, quarterly, yearly or 
Subject to the terms of agreement

CON4157@VTC2021 CC BB‐NC‐ND 40

CC BB‐NC‐ND 20
CON4157"AY2021

Plant
Rent rate / Life cycle cost / Operator cost

Material
Supply and installation cost

CON4157@VTC2021 CC BB‐NC‐ND 41

‐END‐

CON4157@VTC2021 CC BB‐NC‐ND 42

CC BB‐NC‐ND 21

You might also like