OPN-501 Individual Assignment-18264019
OPN-501 Individual Assignment-18264019
OPN-501 Individual Assignment-18264019
Dr Md Abdul Haque
OPN-501
Assignment-04 (Individual)
Name ID
Answer:
ii) Find the completion time of the project and the critical path.
Answer:
1. A-B-E-F=28
2. A-B-D-F=31
3. A-B-E-D-F=37*
4. A-B-D-G=30
5. A-B-E-D-G=36
6. A-C-D-G=29
7. A-C-D-F=30
The Project completion time is 37 weeks and the critical path is A-B-E-D-F=37weeks.
iii) Find the slack time (delay time) of each of the activities, the critical and the non-critical
activities.
Answer
Activity LS ES LF EF Slack
A 0 0 5 5 0
B 5 5 12 12 0
C 12 5 18 11 7
D 18 18 27 27 0
E 12 12 18 18 0
F 27 27 37 37 0
G 28 27 37 36 1
So, the critical activity= A-B-E-D-F=37weeks and Non Critical activity = C,G
iv) Find the minimum possible completion time of the project by considering the crashed
completion times and the minimal total cost of that crashing the project.
f. Crash activity D is on the both path and crashing cost is $800 per week
g. Project duration is 32 weeks and we crash D
h. Can be crash F or G the project duration will be 31 weeks
i. Maximum number crashing is done
j. Minimum possible completion time of the project is 31 weeks.
Path N=0 1 2 3 4 5 6
A-B-E-D-F 37 36 36 34 33 32 31
A-B-E-D-G 36 35 34 33 33 32 32
A-B-E-F 29 27 26 25 24 24 23
A-B-D-F 31 31 31 30 29 28 27
A-B-D-G 30 30 30 29 29 28 28
A-C-D-F 30 30 30 29 28 27 26
A-C-D-G 29 29 29 28 28 27 27
Activity E E A F D F
crushed
Cost $400 $400 $500 $500 $800 $500
v) Highlight the critical and non-critical activities of the finally completed project by taking into