Model Bill PLUMBING
Model Bill PLUMBING
Model Bill PLUMBING
N/S SUBCONTRACT
FOR
2010J027
PROVISIONAL BILLS OF QUANTITIES
FOR
FOR
IN
15 ON ORANGE
CAPE TOWN
FOR
SEPTEMBER 2010
2010J027
PLUMBING AND DRAINAGE
FOR
IN
15 ON ORANGE
CAPE TOWN
FOR
PAGE NO.
PRELIMINARIES
FINAL SUMMARY
ANNEXURES
ANNEXURE E : DRAWINGS
GENERAL TO INDEX
The tenderer is required to check the numbers of the pages and should any pages be found to be
missing or in duplicate, or should any of the typing be indistinct, or any doubt or obscurity arises
as to the meaning of any description of particulars of any item, or if this Tender Enquiry contains
any obvious errors, then the Tenderer must immediately inform the Architect/Quantity Surveyor
and have them rectified or explained in instructions whatsoever will be admitted by reason of the
Contractor having failed to comply with the foregoing writing as the case may be. No liability No
alteration, erasure, omission or addition is to be made in the text and conditions of this Tender
Enquiry. Should any such alteration, amendment, note or addition be made, it will not be
recognised and the wording of this Tender Enquiry, as prepared by the Quantity Surveyor, will be
adhered to. This Tender Enquiry is not to be used for ordering purposes. Any ordering based on
this Tender. Enquiry shall be at the sole risk of the Contractor.
SECTION A
NOTES TO TENDERERS
NOTES TO TENDERERS
1. SCOPE OF WORKS
The description hereunder is a general guide only and the Tenderer is referred to the
Architect’s drawings for tender purposes. No liability will be accepted should the
information provided be misconstrued.
The work consists of the design, supply and installation of Plumbing and drainage to the
gym for Planet Fitness.
2. COMPLETE INFORMATION
The pages of these Bills of Quantities are numbered consecutively. The Tenderer shall
check the numbers of the pages and should any be missing or duplicated, or the
reproduction be indistinct, or if any doubt exists as to the full intent or meaning of any
description or these Bills of Quantities contain any obvious errors, the Tenderer shall
notify the Principal Agent forthwith who shall promptly give a written directive. No liability
whatsoever will be admitted in respect of errors in any tender due to the
abovementioned causes. On no account should the document be used for placing
orders for materials, the Tenderer does so at his own risk and shall not be reimbursed
for additional costs incurred.
3. CONTRACT DRAWINGS
In order to assist Tenderers, the following contract drawings are issued with the bills of
quantities.
These drawings illustrate only the broad scope of the work to be done. The drawings do
not purport to show the exact nature of the work and no claims in this connection will be
entertained.
By submission of a tender, the Tenderer will be deemed to have acquainted himself fully
with the tender documents, local authority requirements and by-laws, and all aspects of
the work envisaged in the documents prior to pricing and submission of his tender.
5. STAMP DUTY
If applicable, all stamp duties in connection with the contract shall be paid by the
contractor.
The Tenderer must allow in his tender for all labour, material, transport, handling,
construction plant, temporary works, or method of construction where the method of
payment allows for various methods of construction, value added tax and everything
else necessary for the execution and completion of the works in accordance with the
tender documents. (NHBRC levies excluded).
7. SIGNING OF TENDER
The tender must be signed by a representative of the Tenderer being duly authorised to
do so and the Tenderer is to attach a company resolution if applicable.
The Employer will not be responsible to pay for expenses or losses, which may be
incurred by the Tenderer in the preparation of the tender or in visiting the site in
connection herewith.
9. ARITHMETICAL ERRORS
The Quantity Surveyor reserves the right to correct arithmetical or other errors in the
extention of rates and totals in the tender. The Tenderer will be informed of the effect of
any corrections prior to the signing of the contract.
In the event of there being any rate or rates which are declared to be unacceptable by
the Quantity Surveyor for the reasons which the Quantity Surveyor will indicate, the
Tenderer will be requested to:
a) Either justify and specify rate or rates, i.e. to give a financial breakdown on how
such a rate or rates were obtained or calculated, or
b) Consider amending and adjusting such rate or rates while retaining the tender
amount.
No site inspection will be held. The tenderer is to familiarize himself with conditions on
site.
The tenderer shall take note that the site is located in an existing functioning 5 Star Hotel
with construction activities involving hammering, breaking etc. to be restricted to hours
between 10:00 – 16:00. Also take note that limited access and parking on site exist for
contractor’s vehicles. Own arrangements should be made for deliveries to co inside with
the main contractor’s arrangements
The tendered price must include for value-added Tax (VAT). All rates in these Bills of
Quantities must however be nett with VAT calculated and added to the value thereof in
the Final Summary.
Contractor’s All Risk, Public Liability and SASRIA Insurances shall be affected by the
Contractor.
The Model Preambles for Trades (1999 edition) as recommended and published by the
Association of South African Quantity Surveyors, shall be read in conjunction with and
shall apply to all items in these provisional bills of quantities. Where descriptions or
supplementary preambles in these provisional bills of quantities differ from clauses
contained in these Model Preambles for Trades, the descriptions or supplementary
preambles in these provisional bills of quantities shall take precedence.
Tenderers must take note that the abovementioned document is not bound in these
provisional bills of quantities, and are referred to it for the full intent and meaning of
the clauses. This document is however available for inspection at the offices of the
quantity surveyor by appointment and the tenderer is advised to be fully acquainted
with it prior to submitting his tender.
CONTRACT DATA - EMPLOYER (EC)
N/S SUBCONTRACT DATA – EMPLOYER
1.0 CONTRACTING AND OTHER PARTIES
Tel 011 884 2536 Fax 011 884 7301 E-mail chaim@quantumprops
.co.za
Tax/VAT registration No.
4030207866
th
19 Floor, Sandton City Main Office Tower
Physical address th
C/o 5 Street & Rivonia Road, Sandton 2196
Tel 011 252 0700 Fax 011 447 1459 E-mail tc@tcdesign.co.za
Tel 011 252 0700 Fax 011 447 1459 E-mail tc@tcdesign.co.za
Tel 012 807 2500/1 Fax 086 661 3241 E-mail pete@dmsqs.co.za
Tel 012 663 9010 Fax 012 663 5259 E-mail etjan@inglplan.co.za
1.6 Agent (4) Mekan Consulting Engineers
Tel 011 318 0111 Fax 011 318 0114 E-mail jose@mekan.co.za
Tel 021 481 8700 Fax 021 481 8799 E-mail neil.smith@wspgroup.
co.za
1.10 The principal agent named [1.2] or agent [1.3-8] is responsible for the preparation of the
contract data and must be contacted should the subcontractor be uncertain of the information
provided or to be provided.
2.0 CONTRACT AND SITE INFORMATION
RSA
2.1 The law applicable to this agreement (country/state)
[1.7]
2.2 Works identification Complete plumbing and drainage installation on three levels,
approximately
1400 m² in extent for Planet Fitness, consisting of Wet Services,
[1.1]
Electrical, HVAC, finishes and sundry fittings
2.4 Defined restrictions to the n/s works area. Where “yes” the specific Requirements are Yes
[16.1] detailed in the n/s documents (yes/no)
As approved by Principal Agent
2.5 Geotechnic investigation of the site has been undertaken where appropriate results are
[16.2] included in the n/s contract documents (yes/no)
No
2.6 Existing premises will be occupied. Where “yes” the specific the specific requirements are
[16.4] described below or detailed in the n/s contract documents
Yes
The site is located in a building accommodating an operational five star hotel, thus
necessitating restrictions to noise and delivery of materials, as well as work outside of
working hours which
The building that will not be allowed. Noisy work limited to 10:00 – 16:00
– refer “Notes to Tenderers”
2.7 Prior work has been undertaken on the site. Where “yes” the specific requirements are
[16.5] detailed in the n/s contract documents No
3.0 PRACTICAL COMPLETION DATES AND PENALTIES
Note: The penalty per calendar day that is applicable to the contractor is provided for the
[30.1-2] information of the subcontractor. The amount has no direct relationship to the damages
that may be due either of the contracting parties to the other
3.1 For the works as a whole: The date for the practical completion and penalty per calender day
[24.3.1]
28 February 2011 R7, 000.00
3.2 For the works in sections: The date for practical completion and the penalty per calender day
[24.3.1]
[28.1] Date Penalty amount
Section 1
Section 2
Section 3
Section 4
Section 5
Section 6
4.1 Construction document copies to be supplied to the contractor free of charge (No. of) 3
[3.7]
No
4.2 The n/s priced document may be used as a specification of materials and goods
[3.9] and work methods (yes/no)
No N/A
4.3 The subcontractor shall provide a schedule of rates (yes/no) (Addendum No.)
[3.10]
2
4.4 On acceptance of the tender the n/s priced document is to be submitted within
[15.1] the stated working days (No. of).
4.6 On achievement of practical completion the contractor is to hand over manuals, warranties,
guarantees etc. related to the works as listed below.
[24.9]
1 2
3 4
5 6
7 8
5.1 Note all changes in detail must be listed below or provided in (Addendum No.)
[3.11]
Changes to definitions and content as indicated in the Bills of Quantities
I, the principal agent named in 1.2 above, declare that the information provided above is complete and
accurate at the time of calling for tenders. Where necessary, should any of the above information need to be
varied, tenderers will be forthwith informed thereof in writing.
_______________________________________
Principal Agent
_______________________________________
Date
BILL OF QUANTITIES
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
PRELIMINARIES
NOTES
iii) The 1999 edition of the model preambles for trades shall be deemed to be
incorporated herein.
iv) Tenderers are referred to the abovementioned documents for the full intent
and meaning of each clause thereof. These clauses are hereinafter referred
to by heading and clause number only. Where standard clauses or
alternatives are not applicable to this contract, they are marked "N/A". Any
modifications to these clauses are given as far as possible under each
relevant clause heading.
vi) Allowance is made opposite each of the clauses for whatever costs
andcharges necessary for the carrying out, complying with and due
observance of the provisions, conditions and requirements set out herein.
Only priced ite will be considered in respect of any adjustment in this
section. Any items left unpriced will be understood to be included at no
charge and no claim whatsoever for extras arising out of the omission to price
items will beconsidered.
vii) If Alternative A as set out in clause B10.3 hereinafter is to be used for the
adjustment of the preliminaries each item priced is to be allocated to one or
more of the three categories, where "F" denotes a fixed amount (amount not
to be varied), "V" denotes an amount variable in proportion to value and "T"
denotes an amount in proportion to time
-------------------------
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-1-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
SECTION A:
The terms and conditions of the principal agreement will form part of this
contract.This clause shall be deemed to be read in line with clause 3.0 of the
principal agreement. Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-2-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Clause 10.0 is amended by the addition of the following clause: "10.4 The
subcontractor shall be liable for and pay the deductibles" Item
Clause 11.0 is amended by the addition of the following clause: "11.3 The
subcontractor shall be liable for and pay the deductibles" Item
14 14.0 SECURITY
(iii) The guarantor shall be provided with a copy of the preliminaries to these bills
of quantities to enable him to acquaint himself of any and all amendments to
the standard documentation
(iv) The following shall be deemed to be included as clause 14.9 The construction
guarantee shall be accompanied by a signed power of authority issued on the
guarantor's letterhead. In addition the construction guarantee document shall
be stamped with the guarantor's official stamp.
v) In the event that the value of the works (excluding adjustments in terms of the
CPAP if applicable) were to increase by an amount of 15% or more of the
contract sum, upon request from the principal agent the subcontractor shall
immediately arrange to have the construction guarantee "guaranteed sum"
increased accordingly, the verified cost of which shall be added to the
contract value. Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-3-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
EXECUTION (A15-A22)
COMPLETION (A23-A30)
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-4-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
29.10 ACCELLERATION
29.10.1 Irrespective of whether or not the principal agent rules that the sub-contractor
is entitled to an extension of time or a revision of the date for interim
completion, the contractor shall nevertheless at any time, be entitled to
instruct the sub-contractor, in writing, to accelerate the progress of the
remaining n/s works, to ensure that the works are completed timeously.
29.10.2 Upon receipt of such instruction, the subcontractor shall take all necessary
steps to ensure that the works are completed timeously, including the
provision by him of additional resources, plant, manpower, etc and the
working overtime or additional overtime beyond that contemplated at the time
of tender (at all times adhering to the regulations and requirements of all
authorities) and by all other adequate and proper means and methods.
Thesubcontractor shall prove that such steps are being taken if called upon to
do so." Item
Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-5-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
TERMINATION (A36-A39)
DISPUTE (A40)
CONTRACTUAL AGREEMENT(A42)
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-6-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-7-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
SECTION B: PRELIMINARIES
The items in these bills of quantities are to be read and priced in conjunction
with and the descriptions regarded as amplified by the Model Preambles for
Trades as recommended and published by the Association of South African
Quantity Surveyors, 1997 edition, and no claim arising from brevity of
description of items fully described in the said Model Preambles for Trades
will be entertained
The area of the works to be occupied by the contractor, any restriction on the
area and the limit of access or exit will be pointed out to the contractor by the
principal agent/Main contractor on handing over of the site Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-8-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
N/A. Item
No claims for extras arising from the contractor having failed to comply with
this clause will be entertained. Item
The contract shall be programmed by the contractor taking into account the
availability of construction documentation for contracts based on provisional
bills of quantities. Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-9-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
The term 'scaffolding' shall mean all scaffolding including 'special scaffolding'
and shall be deemed to include all scaffolding internally and externally
required for the execution of the Works, mobile scaffolds and all external
swing and/or pipe scaffolding to all facades of the Works required.
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-10-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Provision is made in the summary of these bills of quantities for the inclusion
of Value Added Tax (VAT) Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-11-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-12-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
12.1.13 OFFICES
[B6.4.3] Specific requirements: No specific requirements
12.1.16 WATER
[B7.2] Option Selected:
Option A (by contractor)
(yes/no) [ Y ]
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-13-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
12.1.17 ELECTRICITY
[B7.3] Option selected:
12.1.18 TELECOMMUNICATIONS
[B7.4] Telephone (yes/no) [Y]
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-14-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
12.1.23 DISTURBANCE
[B11.5] Specific requirements: All work is to be carried out in such a
manner as to cause no unacceptable and unreasonable dust, noise,
vibrations, nuisance, inconvenience, annoyance and the like to the public,
others, other properties and traffic. Any delays, stoppages and the like
arising from or in order to comply with the above will not constitute grounds for
adjustment to the contract period or contract sum whatsoever.
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-15-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Details: None
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-16-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
The contractor shall take delivery of, handle, store, use apply and/or fix all
proprietary branded products in strict accordance with the manufacturers'
instruction after consultation with the manufacturer's authorised
representative Item
The contractor shall not cede nor assign his rights or claims to any monies
due or to become due under this contract and no purported cession or
assignment will be recognised without the written consent of the employer Item
At the end of each week the contractor shall provide the principal agent with a
written record, in schedule form, reflecting the number and description of
tradesmen and labourers employed by him and all subcontractors on the
works each day. Item
At the end of each week the contractor shall provide the principal agent with
a written record, in schedule form, reflecting the number, type and capacity
of all plant, excluding hand tools, currently used on the works. Item
107 OVERTIME
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-17-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
108 CONTINGENCY
The Architect shall make such visits to the Works as he may from time to
deem necessary. In the event of any matter arising which the Contractor
considers of such importance that the Architect must be consulted, every
reasonable attempt shall be made by the Contractor to communicate with
him before proceeding with the point at issue.
The Architect is thus in no way responsible for any act or omission on the part
of the Contractor which may result in any patent or latent defects in materials
or workmanship, breach or neglect of any local regulations. The Contractor
therefor remains at all times responsible for any neglect, deviation or wrong
act, whether the same be discovered before or after the final certificate, or
any other certificate is issued.
Item
A registered Land Surveyor shall set out the building, gather all relevant
data such as datum levels, platform heights etc. and hand these information
to the Principal Agent in an electronic format Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-18-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Upon receipt of detail drawings for any works, the contractor shall, before
putting that work in hand, ascertain that the dimensions given on the detail
drawings correspond with the dimensions of any work already built
In the event of a discrepancy between the detail drawings and the work
already built, the discrepancy, shall be brought to the principal agent's
attention who shall decide the procedure
All drawings, whatever their origin, are to be issued to the site, or to any other
designated person or persons, only through the principal agent's office and
shall bear the principal agent's office stamp and signature. An up to date
register of all drawings issued to the contractor shall be kept on the works.
Any other drawings used on the site will be used at the contractor's risk and
should any work be incorrect due to the use of unauthorised drawings, the
cost of rectifying such work shall be for the contractor's account
All drawings used on the works shall be properly mounted on suitable sheet
material, or otherwise protected and kept in good condition. Any drawings
becoming bleached or otherwise obscured so that they cannot be properly
read shall be returned to the principal agent for replacement, as any errors
due to misreading of damaged or obscured drawings shall be made good by
the contractor at his own expense Item
The Contractor must allow under this clause for all requirements as specified
in the Compensation for Occupational Injures and Diseases Act, 1993 (Act
130, 1993) and must fully adhere to all requirements and should allow to
comply with all the relevant Legislation, as well as C.S.I.R Internal Services
Health and Safety Specification - Annexure A. A safety audit will be done on a
regular basis of all requirements. Item
Carried Forward R
Bill No. 1
Preliminaries
2010J027_P
-19-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
All right of publication of articles in the media, together with any advertising
relating to, or in any way connected with this project shall vest in the
employer.
The contractor, together with his sub-contractors shall not, without the written
consent of the employer, cause any statement or advertisement to be printed,
screened or aired by the media. Item
The site is contained is within and operating five star hotel and all care must
be taken by the subcontractor to ensure that all members of his staff are fully
conversant with the stipulated hours for activities and work with grinding,
percussion and hammer and breaking tools and equipment which cause
unacceptable and unreasonable dust, noise, vibrations, nieusance,
inconvenience annoyance and the like to public, others, other properties and
traffic.
Any delays, stoppages and the like arising from an order to comply with the
above will not constitute grounds for adjustment to the contract period or sum
whatsoever.
The subcontractor will explore alternative ways and methods to complete the
work in compliance with the programme as set out and agreed with the
contractor.
Item
Carried to Summary R
Bill No. 1
Preliminaries
2010J027_P
-20-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
PLUMBING (PROVISIONAL)
SUPPLEMENTARY PREAMBLES
Soil, waste and vent pipes and fittings shall be solvent weld
jointed.
Copper pipes:
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-21-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Reducing fittings
Fixing of pipes
Excavations
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-22-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Wire gratings
Flush pans
Flush pans shall have straight or side outlets and "P" or "S"
traps as necessary
Showers
Sealing of edges
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-23-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Waste unions
Rainwater disposal
As-built drawings
General
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-24-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
STAINLESS STEEL
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-25-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
"Vaal Potteries"
SANITARY PLUMBING
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-26-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
HDPE
44 56mm bend No 42
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-27-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
45 56mm junction No 18
48 110mm bends No 2
49 110mm junction No 4
"Cobra"
"Classic Trading"
TRAPS ETC
"Cobra"
"Flexi-trap"
"Watercomfort"
FLOOR DRAIN
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-28-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
"Kessel"
"Hansgrohe"
62 Croma 100 Vario (Eco Smart) 65mm shower rail set, including
chrome Fixit accessory wall outlet (HGHG27776000 and
HG27454000 No 2
"Classic Trading"
"Cobra"
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-29-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
valves
81 50mm strainer No 1
WATER SUPPLIES
"MEKAN"
83 22mm Pipes m 88
84 28mm Pipes m 96
86 42mm Pipes m 60
88 75mm Pipes m 12
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-30-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
91 15mm Fittings No 66
92 22mm Fittings No 13
93 28mm Fittings No 12
94 35mm Reducer No 14
95 42 x 35mm Reducer No 3
96 54mm Reducer No 12
97 54 x 35mm Reducer No 8
98 28mm Elbow No 6
99 35mm Elbow No 5
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-31-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
116 22x22mm CxFI copper to female iron wall plate elbow, code
D707-3-5M-22 No 16
Vacuum breaker
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-32-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Watermeter
CONNECTORS
WATER DISPENSERS
"Franke"
PIPE INSULATION
SUNDRIES
Carried Forward R
Bill No. 2
Plumbing
2010J027_P
-33-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
Brought Forward R
Sleeves
TESTING
Carried to Summary R
Bill No. 2
Plumbing
2010J027_P
-34-
2010/09/23
15 on Orange
N/S Subcontract: Plumbing and Drainage
FINAL SUMMARY
2 Plumbing -34-
-35-
TENDER FORM
FORM OF TENDER
THIS DOCUMENT IS FOR USE WITH
JBCC PRINCIPAL, NOMINATED / SELECTED AND MINOR WORKS AGREEMENTS
TENDERER:
VENUE: DMS QS
Wapadrand Office Park, Block D, SuiteS2, 90 King Bolt Crescent, Wapadrand
PRETORIA, 0041 : Tel : (012) 807-2501
Or sent via E-mail to: pete@dmsqs.co.za
Introduction
These specifications will apply for the duration of the project and should the principal contractor not abide I
comply, it will be deemed as a breach of contract.
The principal contractor will carry full responsibility regarding the adherence to any health and safety specifications when
sub-contractors are used to carry out construction work on the project.
The principal contractor is responsible for any insurance cover (liability) as well as registration with the Workman's
Compensation Commissioner I Federated Employers Mutual Assurance Company as far as employee injury insurance is
concerned.
Section 1
The principal contractor must provide a health and safety specifications file with all the necessary legal documentation and
inspection registers for use to comply with the provisions of the regulations. The principal contractor must ensure that all
persons employed to carry out work on this project are competent and properly inducted, instructed and trained. The
principal contractor must ensure that a personal file of each employee, reflecting name, ID, job description and medical
certificate, where applicable, is available on site. The principal contractor must report each reportable incident as per Section
24 of the Act, to the client as soon as possible, provided that in the case of a very serious incident or fatality, the report will
be done immediately. The principal contractor must ensure that a list of emergency telephone numbers is placed in a
conspicuous place in the site office. The principal contractor is responsible to notify the Dep. of Labor of intent to carry out
Construction Work as required by Construction Regulations 3(1).
SECTION 3: HEALTH AND SAFETY SPECIFICATIONS AND FORM
Section 2
The principal contractor to appoint competent persons to manage and supervise construction work on this project. The principal
contractor to ensure that any construction work on the project is always carried out under the supervision of
competent persons. All appointments are to be done in writing and kept in the health and safety file on site.
Section 3
The principal contractor must complete an "Agreement with Mandatory” with each sub-contractor before the commencement
of work by the sub-contractor. The principal contractor must appoint each sub-contractor for the specific construction work the
sub-contractor has to carry out on the site. NOTE: This appointment is part of the "Agreement with Mandatory" format. The
principal contractor must ensure that potential sub-contractors submitting tenders, have made provision for the cost of health
and safety during the construction process. The principal contractor must ensure that each sub-contractor has his own health
and safety file which shall include all the legal documentation as required by the OHS Act and Regulations.
The principal contractor must ensure that each sub-contractor where necessary, submits method statements, risk
assessments and safe work procedures pertaining to the construction work the sub-contractor is to carry out on the project.
The principal contractor must compile a comprehensive list of all the sub-contractors on site accountable to him.
Section 4
4. Risk Assessments
The principal contractor must appoint a competent person to carry out risk assessments before the commencement of any
construction work on the project. These assessments must include:
- The identification of all risks and hazards to which persons might be exposed to on the project
NOTE: Public liability risks must form part of these assessments.
- All risks and hazards must be properly analyzed and evaluated.
- A documented plan of safe work procedures must be drawn up indication how these risks are to be mitigated, reduced,
controlled and managed.
The principal contractor must have a copy of these risk assessments readily available on site. The principal contractor must
ensure that safe work procedure, established through risk assessments are properly communicated to those employees
concerned.
NOTE: sub-contractors must form part of the risk assessment of any activity that involves them.
Section 5
5. Fall Protection
The principal contractor must designate a competent person, responsible for the preparation of a fall protection plan. The
principal contractor must ensure that the fall protection plan identifies all the possible situations on the project where persons
are exposed to the possibility of falling whilst carrying out their work.
The principal contractor must ensure that all identified unsafe conditions are adequately guarded, fenced or barricaded and
that proper means are implemented to prevent falling.
SECTION 3: HEALTH AND SAFETY SPECIFICATIONS AND FORM
Section 6
6. Scaffolding and suspended platforms
The principal contractor must ensure that all scaffolding operations are carried out under the supervision of a
competent person and that all erectors, team leaders and inspectors are competent to carry out their work. The principal
contractor must ensure that scaffolding when used, complied with the safety standards as per SABS 085.
Section 7
The principal contractor to ensure that all formwork and support work operations is carried out under the supervision of a
competent person who has been appointed in writing. The principal contractor to ensure that all form I support work drawings
pertaining to their design is kept on site and are available if I when requested.
The principal contractor to ensure that all form I support work structures are inspected by a competent person (appointed in
writing), immediately before, during and after the placement of concrete and the result of such inspection recorded in a
register.
The principal contractor to ensure that form I support work is erected in such a way that on completion of the deck, a solid
handrail is also in place for the safety of person who has to carry out work on the deck. i.e. steel fixers etc.
Section 8
8. Excavations
The principal contractor shall ensure that all excavation work is carried out under the supervision of a competent person who
has been appointed in writing.
- Suitable steps are taken in order to prevent any person from being buried or trapped by a fall or dislodgement.
- Excavations are adequately shored or braced and safe access is provided by ladder.
The competent person contemplated in 8.1 above, shall do daily inspections of all excavations and record his finding in a
register.
Section 9
9. Mobile cranes
- The principal contractor to ensure that the crane is erected per the requirements of the Driven Machinery Regulations promulgated
by Government Notice No R 295 of February 1998.
- The principal contractor to ensure that tower crane operators are competent and certified to carry out their work safely.
- The principal contractor to ensure that the tower crane operator is in possession of a recent medical certificate of fitness.
- The principal contractor to have a banks man appointed who has been trained to give correct signals & guide the crane
operator safely.
Section 10
The principal contractor must ensure that any person who has to use an explosive powered tool is trained in:
- The operation, maintenance and use of such a tool.
- The use of protective equipment with the tool.
- The principal contractor must appoint a competent person as an Explosive Powered Tool Controller.
SECTION 3: HEALTH AND SAFETY SPECIFICATIONS AND FORM
Section 11
Section 12
12. Storage of flammable liquids
- The principal contractor must ensure where flammables are to be used, applied or stored on the site that it is done in a
manner which would cause no fire or explosion and that the storage area is effectively ventilated.
- The principal contractor must ensure than an adequate amount of fire fighting equipment is installed at suitable locations
where flammable liquids are stored.
- The principal contractor must ensure that all containers holding flammable liquids are kept tightly closed when not in use
and after contents have been used, to be removed from the construction site.
- The principal contractor must ensure that material such as cotton, waste, paper, plastics, cleaning rags or similar material
is stored together with flammable liquids.
Section 13
Section 14
14. Stacking and storage
Section 15
15. Facilities
The principal contractor must ensure that depending on the number of workers, provision is made for the following clean
facilities:
- At least one sanitary facility for every 25 workers
- At least one washing facility for every 15 workers
- Changing facilities for each sex
- Sheltered, clean eating areas
SECTION 3: HEALTH AND SAFETY SPECIFICATIONS AND FORM
Section 16
- Taking into account the nature of the hazard to which a worker by the exposed, the principal contractor must issue and
ensure that employees receive such personal protective equipment free of charge.
- The principal contractor must instruct his employees in the proper use, maintenance and limitations of the safety equipment
and facilities provided, taking into account the nature of the construction activities that will take place on this project, the
personal protective equipment that should be available on site is:
- Hard hats, eye protection, gloves, body safety belts, safety harnesses, welding helmets, dust masks, ear muffs and
ear plugs.
Section 17
17. Signage
The principal contractor must ensure that the following signs are placed correctly in conspicuous areas:
- No Unauthorized Entry
- Danger Construction Work
- Danger Workman Above
- Visitors to Report to Site Office
- Site Office Directional
- Hard Hat Area
- First Aid
- No Smoking
- Public Inconvenience
- Scaffolding Safe or Unsafe For Use
Section 18
18. Construction Vehicles and Mobile Plant
The principal contractor shall ensure that all Construction Vehicles are:
- On a daily basis inspected prior to use by a competent person, appointed in writing, and the findings of such inspections
are recorded in a register.
- Maintained in good working order.
- Operated by persons who received appropriate training and are certified competent and are authorized in writing to
operate such machine(s).
- Operated by persons medically certified fit to operate such machinery.
Section 19
19. Safety Reports
Written agreement on the arrangement and procedures between Employer and The Contractor
to ensure compliance by The Contractor with the provision of the Occupational Health & Safety
Act, The Compensation for Occupational Injuries and Diseases Act and Insurance Coverage
and
WHEREAS:
A. EMPLOYER shall from time to time require the services of the CONTRACTOR to effect maintenance /
1. The CONTRACTOR warrants that his subcontractors’ and employees are covered in terms of the Compensation
for Occupational Diseases Act, which cover shall remain in force whilst any such employee is present
on EMPLOYER premises.
2. The CONTRACTOR warrants that he is aware of the provisions of the Occupational Health and Safety Act
had made his employees aware of such provisions, and at all times ensures due compliance herewith.
3. The CONTRACTOR is to provide proof of his COID (Compliance Occupation Injuries Diseases Act, Act
130 of 1993) status and issue a certificate of good standing to EMPLOYER.
4. The CONTRACTOR further warrants that he is in possession of the following insurance cover which
shall remain in force and effect while he and/or his subcontractor and any employees are present on
EMPLOYER premises, alternatively for the duration of the contractual relationship between himself
and EMPLOYER.
4.2 Any other insurance cover, making adequate provision for any possible losses and/or claims arising from
his and/or his subcontractors, alternatively any employee’s acts or omissions on EMPLOYER premises.
SECTION 3: HEALTH AND SAFETY SPECIFICATIONS AND FORM
5. The CONTRACTOR warrants that he and/or his subcontractors, and/or their respective employees are familiar with
the requirements of the Occupational Health and Safety Act, and shall comply therewith. In this regard, they agree
that:
5.1. All work performed on EMPLOYER premises must be performed under close supervision.
5.2. The CONTRACTOR shall assume the responsibility in terms of Section 16(1) of the Occupational Health and
Safely Act.
5.3. The CONTRACTOR warrants that competent employees are employees by him, who shall be trained on any
aspects of the Occupational Health and Safety Act that is pertinent to such employees, alternatively such
work performed by the employees.
5.4. Discipline regarding Occupational Health and Safety shall be strictly enforced.
5.5. Personal protective equipment shall be issued as required and worn at all material times.
5.7. All incidents referred to in Section 24 of the Occupational Health and Safely Act shall be reported by the
CONTRACTOR to the Department of Manpower, as well as EMPLOYER, which shall be entitled to receipt of
any written documentation relating to such incidents.
5.8. No use shall be made of any of EMPLOYER or tenant's machinery/articles, substance or items without prior
written approval.
5.9. The CONTRACTOR acknowledges that EMPLOYER is an interested party of any incident, in terms of
Section 32 of the Occupational Health and Safely Act.
5.10. Any work requiring the issue of a permit, shall not be performed prior to the obtaining of such completed and
approved permit. The contractor will obtain all the relevant permits to the identified risk detailed in section 8 of
the OHS Act, before the work commences as may be applicable and required by either the tenant or
EMPLOYER.
5.11. No alcohol or other intoxicating substance or drug shall be allowed on EMPLOYER premises. Anyone
suspected to be under the influence of alcohol or any other intoxicating substance or drug shall not be
allowed on the premises.
5.12. Full participation shall be given if any when EMPLOYER employees inquire into Occupational Health and
Safety issues.
5.13. The contractor must identify the relevant risks in the premises and notify EMPLOYER before
commencement of any works.
6. The CONTRACTOR confirms that he has been informed that he must report to EMPLOYER management (in
writing) anything he deems to be unhealthy and/or unsafe.
7. The CONTRACTOR warrants that he shall not endanger the health and safety of EMPLOYER employees /
tenants, buildings or the public in any way whilst performing any work on EMPLOYER premises.
8. The CONTRACTOR hereby fully and completely indemnifies EMPLOYER in the event of any and all claims
arising from the CONTRACTOR, and/or his Subcontractor, and/or employees thereof, due to any act or omission
on the part of such CONTRACTOR, subcontractor and/or employee.
1 ………………………………………
2 …………………………………
Duly authorized
Name: ……………………………………….
Company: …………………………………..
Service: ……………………………………..
E-mail: ……………………………………....
1 …………………………………….
2 …………………………………….
Duly authorized
Name: ……………………………………….
Company: …………………………………..
Service: ……………………………………..
THIS PAGE MUST BE REPRODUCED AND SUBMITTED ON THE TENDER COMPANY’S ORIGINAL LETTERHEAD
By resolution of the Board of Directors / Power of Attorney / Written Delegation of Authority passed on
___________________________________________________________________________
has been duly authorized to sign all documents in connection with the Tender for contract ___
___________________________________________________________________________
Number ____________________________________________________________________
and any contract which may arise there from on behalf of _____________________________
___________________________________________________________________________
DATE _____________________________________________________
AS WITNESS 1. ___________________________________________________
2. ___________________________________________________
ANNEXURE D
FORM OF INDEMNITY
FORM OF INDEMNITY
TO EMPLOYER : _______________________________________________
PROJECT : _______________________________________________
We (CONTRACTOR) : _______________________________________________
From responsibility for any claim proceeding whatsoever due to fault in the design, calculations,
manufacturing and erection of the work to the extent that such design is undertaken by us.
Contractor _______________________________________________________________________
DRAWINGS