Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Estimate For Pipe Laying

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Estimate for Pipe Laying

S.NO Description Quantity Unit Rate Productivity in m Total Diesel required Total cost
1 Excavator 1 Nos 200000 20 420 1200 290000
2 Fitter 2 Nos 800 48000
3 Labour 4 Nos 450 54000
392000
4 Staff 1 Nos 15000 15000
5 Project manager 1 Nos 40000 40000
447000
cost per m 1064.286
20% profit 212.8571
1277.143
For Hard Rock

S.NO Description Quantity Unit Rate Productivity in m Total Diesel required Total cost
1 Excavator 1 Nos 200000 20 420 1200 290000
2 Fitter 2 Nos 800 48000
3 Labour 4 Nos 450 54000
392000
4 Staff 1 Nos 15000 15000
5 Project manager 1 Nos 40000 40000
Breaker 1 Nos 147500 1200 147500

594500
cost per m 1415.476
20% profit 283.0952
1698.571

You might also like