Approaching Zero Breakdowns by Advancing Breakdown Analysis-1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

Approaching Zero Breakdowns by Advancing

Breakdown Analysis-1

April 9, 2018In : 5 Why Analysis Autonomous Maintenance Blog Planned Maintenance Root Cause Analysis
0 2,157 23 min read Website: https://leanmanufacturing.online/

What is Maintenance?
Maintenance: It is a set of developed, organized and administered activities with the aim to economically viable ensure the
operational status of a specific system.

The 7 steps concept of Autonomous Maintenance (operators)


are similar to 7 steps of Planned (Effective) Maintenance
(trades): “the left and right hand working together”

Breakdown/Failure definition
Breakdown/Failure means: Loss of the equipment defined function. Unscheduled stop of the equipment, performing loss of function,
for over 10 minutes, with or without parts replacement.
Breakdown=With parts replacement,
Failure=Without parts replacement.

Why and What advantages in Recording the Breakdown/Failure?

 Ensures the team knowledge in relation to the breakdown and failure: When the breakdown occurred, What happened, where it
happened and what was done to solve the problem. The breakdown record is also used as input into the Breakdown
Analysis (BDA).
 This information can also be used to identify topics for training during the fourth stage of AM when the systems are prioritized by
the type of breakdown/failures which happen more often;
 Allows the team to get to the root cause(s) to reduce to zero breakdowns/Failures;

Page 1 of 15
 Allows to figure out if the cause(s) of the problem has a relation with the Man Method, Machine or materials so all contributing
factors can be identified and appropriate countermeasures applied;
 Allows over time to evaluate the effectiveness of our maintenance activities and help determine if we need to modify our current
preventive plan;
 Allows to set the training priorities in the fourth AM stage, when the systems are prioritized by the quantity of breakdowns/failures
which happen more often.

How the Breakdown Happens…


“ The equipment does not break by itself, it is broken by the man”

ZERO BREAKDOWNS
Why Do breakdowns happen?

Page 2 of 15
Breakdowns Iceberg/Failure
Notify Potential Failure is to prevent occurrence of Breakdowns/Failures

Causes Structure of Chronic Loss

Page 3 of 15
Typical Categories of Root Caused for Breakdowns/Failures
During the BDA, the team will be required to recommend corrective action based upon root cause(s) identified using facts in the Why-
Why analysis. To help prepare the team for this task, it is be helpful to understand the primary categories of root causes for most
Breakdowns / Failures. This information will assist in the identification of effective countermeasures.

6 Root Causes & Measures to eliminate the Failures

6 Measures to eliminate the Failures

1. Structuring of the basic conditions


Cleaning

 elimination of the causes of the forced deterioration


Lubrication
 elimination of the problems related to lack of oil or dirt in it
 Improvement of the lubrication methods
 standardization of the oil types

Page 4 of 15
Adjustment
 inspection of the nuts and bolts
 measures to prevent loosening
Development of standards for cleaning, inspection and lubrication
Autonomous maintenance activity

2. Compliance with conditions of use


Establishment of operation conditions
 Establishment of conditions such as: pressure, vacuum, temperature, concentration, viscosity, water content, particle diameter,
etc.
Standardization of operation methods
 preparation of manuals
 implementation of training “on the job”
Standardization of work adjustments and adjustments
 survey of the adjustment points
 improvement of the adjustment methods – Visual Controls, set points, Poka Yoke
Standardization of the operation at the start and finish (Start-up and ramp-down).

3. Recovery of the deterioration, detection/prevention of deterioration


Inspection of the process through the five senses and detection of the deteriorated parts
Preparation of a criteria for routine inspection
Development of standards of inspection and periodic replacement
Establishment of standardized replacement time (hrs or cycles)
Establishment of methods for prediction of abnormalities in the process
Development of control standards
– establishment of reference measurement

– improvement of measuring devices

Establishment of priorities in maintenance work


 implementation of evaluation of equipment
 PM equipment selection
 Develop record of equipment maintenance (CMMS)
 history control
 optimization of maintenance intervals
Standardization of the periodic maintenance on-going on the equipment
 annual calendar
 introduction of electronic data processing (CMMS)
Standardization of the process of disassembly, assembly and replacement
Improvement of operation method of inspection,repairs and exchanges
Control of spare parts
 common use and centralization (CMMS)
 creation of norms for inventory control
Control of schematic drawing and documentation
common and centralized use improvement of the access method

4. Elimination of the elements in the environment which cause forced deterioration


Measures against the sources of dirt
 Detection of sources
 General inspection of scattering dust points
 General inspection of dust collection installation
 Improvement of the dust sources, liquid and gas leak
 Elimination of accumulated dust from buildings and structures
Measures against places of difficult access
 Survey of the areas of difficult access for inspection and measurement
 Survey of inconvenient places in the lay-out
 Specific Improvement for difficult access places
Support for the improvement of the sources of dirt and places of difficult access run by Autonomous Maintenance

5. Improvement of the equipment problem points


Improvement of the peculiar problem points of the equipment arising from project and assembly failure
 measure, degree of precision, material type, resistance, structure and function
 format (slope on the transport lane, etc)
 Corrosion resistance, wear resistance, (Dissimilar metal Corrosion)
Improvement of problem points related to the work environment
 Research of anti corrosive paints
 Research of new materials resistant to corrosion
 Research of coating material
Process improvement
 Nozzle design – anti clogging or self-cleaning
 Increase in the process capability
 Measure against overload

Page 5 of 15
Recurrence of serious accident
 Measures against similar accidents
6. Upskilling of operators through AM steps 0 to 4
Preparation of manuals about physical changes and operational conditions
 indication of the correct adjustment value
 strengthen the visual control
 indication of flow direction and the contents of the pipelines
 indication of the opening and closing process for the valves and registers
 indication of operation range,measurement instruments manuals
Prevention of erosion of the measures adopted during abnormalities
 standardization of the measures to be taken
 standardization of the method of prediction
Safe operation
 interlock (LOTO)
 indication of open or closed switch
 improvement of emergency stop method
 strengthening of the activity to prevent danger

7. Enhancement of operation and maintenance ability level
Prevention of maintenance errors
 analyses of recurrence of failures
 improvement of maintenance methods
 creation of norms and standardization for material selection
 use of commom spare parts and materials
 development of norms for execution order
Prevention of errors and error monitoring
 increase of the supervisory capacity
 creation of supervisory norms
 system structuring for operation and maintenance supervision
Errors prevention of the experimental operation
 standardization of the experimental operation
 elaboration of the checklist to verify the experimental operation

Breakdown Record & Analysis Flowchart

Page 6 of 15
BDA Process Steps

Page 7 of 15
Breakdown record

Page 8 of 15
Breakdown analysis

Page 9 of 15
Principles of Operation
 Follow the process flow for the area where problem was seen on the line – (Breakdown Record)
 Identify how each step functions and what purpose does it do.
 Identify what conditions must be in place for each step to function properly, e.g. Temperature, speed, pressure, adjustment,
etc.
 Agree as a team, when in doubt, go out to shop floor and confirm. Principles of operation (POO) should be factual….Not what
I think happens.
–Do not move to next step until this POO completed.

Phenomenon Analysis (5W – 2H)


 What – What specific thing (e.g. product/part) are you seeing the problem on?
 When – When have you seen the problem? ( Start-up, Ramp Down, normal production, after a changeover, shift, time, etc).
 Where – Where are you seeing the problem? (e.g. packing line, equipment, specific location, material or activity)
 Who – Is the problem related to the skill of anyone? (e.g. New operator, skill dependent or independent)
 Which – Which Trend (pattern) are you noticed the problem e.g. increasing frequency, look at historical data to determine if
pattern exists
 How – How does the problem differ from normal operation or ideal state
 How Much – How often does the problem occur and how much to correct? How much waste/loss is generated due to
the problem?

Link between Phenomenon Statement and Why Why Analysis


 After completing the 5W-2H form, this information is used to construct a phenomenon statement – The specific problem to be
solved.
 The phenomenon statement is then transferred onto the Why-Why analysis form.
 Now ask the first Why…..Why is the problem happening?
 All answers should relate directly to the specific problem identified in the 5W-2H. Any answers not relating are “out of scope’
and will not lead to a solution. They will only cause confusion and delay. Get rid of them.

But ……What Breakdowns do we start


analyzing first?
Page 10 of 15
If not much information is available to st
art with?…use these rules of thumb:
 Select the TPM pilot equipment first
 Select equipment critical to your operation – A Asset
 Select equipment linked to your loss tree – Largest BD loss
 Select equipment you will have resources to analyze (labor & material)
 Select equipment with unexpected failures first, then equipment with repetitive failures or showing upward trend of occurrences
 Select equipment with no redundancy in place
 Select Breakdowns with the longest downtime
 Select equipment affecting the business the most
Ok, …so what do we do once found a breakdown matching the criteria we selected?
 Verify the data you have is reliable.
 If a Breakdown record has been completed. Use it as input into the process. Hopefully, AM / PM working together are already
completing BD records for all Breakdowns over 1 hour. (Perhaps adjust the CMMS work orders to log the same information
as in the Breakdown Record form.)
 Bring the Operators into the process !
Teach and allow the operators to initiate the breakdown record with help from the crafts in the area.
Get Started!!!!

How to register and analyse the breakdowns?? Rules and Tips:


 It is the responsibility of the line operators or area mechanics to ensure the breakdown record is completed at the moment the
breakdown happens to capture the facts as best as possible.
 It is necessary for the operator and mechanic who acted in the breakdown to fill out the front of the breakdown record as
completely as possible. This will improve the quality of input into the BDA
 The maintenance supervisor has the role to verify the status and use of the breakdown record. Insure information is accurate.
 Rules to analyse a breakdown will be = or > than 60 minutes; (This can be changed by the site to meet their level of TPM
progression)
 Operators are in charge for tagging the breakdowns/failure in the DT System (Informance) with the correct reason codes. This
information can be used as input into BDA
 The target for complete BDA review should be up to 8 days, from the date of the occurrence (This can be adjusted by the plant
to meet their needs)
 Fill out all the BDA form trying to get information from specialist; or operators who witnessed the breakdown
 The supervisors responsible for the lines should constantly monitor the line breakdown records to insure they are completed
properly;
 The maintenance team will visit daily the areas and line checking the BD records;
 The operators should insure adequate quantity of new BD records sheets for the notebooks before supplies run out. Include
this into line 5S standards.

Before you start to solve the problem!


The key to success is to have a Crystal Clear Understanding of Equipment to be Analyzed before Problem Solving Starts.

 Make sure everyone (mechanics and operators) understand and agree upon the sequence and principles of operation before
problem solving
 Use video camera to help with this or go to shop floor to insure everyone fully understands the principles of operation
 All settings and adjustments required for this mechanisim to work properly should be quantified
o Air pressure, Temperature, Vacuum, Adjustment locations, Speed, etc.
 After this is completed, proceed to 5W2H
USING THE 5 WHY´S
Practical Rules for a good 5 WHY´S Analysis:
 DON’T JUMP TO CONCLUSIONS! Remember what Happens when we ASSUME!
 BEFORE ANALYSING THE WHY Why Anslysis go to the shopfloor and do the following:
Go to the working place,
Observe the real things,
Observe the real conditions,
Identify the phenomenon,
Take a realistic attitude.
Suggestions for the SUCCESS of the Workshop
 Participate in at least one BDA
 Engage operators and mechnics with knowledge of asset on which breakdown occurs
Use Breakdown record and broken part as input into BDA and Engage Supervisors; Operators, Mechanics in BDA.

Validation
 Double check that counter measures were implemented as agreed upon by the team.
 Talk to operators and mechanics to get feedback on performance since counter measures implemented
 Check Informance system to determine if breakdown has been reduced (frequency) or eliminated (Zero Breakdown Case if
breakdown has not recurred in 3 month)
 Use breakdown re-occurrence matrix to visually show progress against BD loss

Page 11 of 15
Approaching Zero Breakdowns by Advancing
Breakdown Analysis-2: Application of FMEA for Root
Cause Analysis

December 12, 2020In : Blog FMEA Root Cause Analysis


0 2,702 3 min read
Failure Mode(s) and Effects Analysis (FMEA) is one of the most effective analytic tools (methodology) to
identify Potential Factors in a system, which is:

Product or Design – to achieve the desired Quality

Work System – Process Safety and Operational Efficiency

Machine – Equipment Reliability and Maintainability, as well as Life Cycle Costs

FMEA was born as a tool to identify Potential Failure and help to improve the system – such as Process,
Equipment, and Products in Design Phase, we will call 1st Look FMEA.
On the other hand, the application of FMEA for Root Cause Analysis (RCA) is a tool to analyze Possible Causes
and also helps to improve the existing (current) system – 2nd Look FMEA.

Page 12 of 15
Two types of Failures

Analytical Approach

Page 13 of 15
2nd Look Process FMEA Worksheet
 Step 0 Team Organization (3-5 Cross-Functional Team Members)
 Step 1 List of All Components of the system – Reliability Functional Block Diagram
o Visualize Process Functional Flow & Structure (by Component Level)
 Step 2 Analyze Potential Failure Mode – Deviation from Required Conditions & Verify Failure Mode
(Deviation)
 Step 3 Analyze the effects of system Relationship Between Quality Defect and Failure Mode
 Step 4 Evaluate “Severity Rating” (1 – 10 pts)
 Step 5 Analyze (Potential) Causes of Failure Mode (Deviation)
 Step 6 Evaluate “Occurrence Rating” (1 – 10 pts) by Loss Tree (Daily Production Record)
 Step 7 Review Current Control System Investigate Current Maintenance Level
 Step 8 Evaluate “Detection Rating” (1 – 10 pts)
 Step 9 Calculate Risk Priority Number (RPN)
o RPN=Verification Criteria x Severity Rating x Occurrence Rating x Detection Rating
 Step 10 Create Actions for High-Risk Failure Mode
 Step 11 Assign Who & by When taking Actions & Record Countermeasures by M-P Record
 Step 12 Evaluate Actions for Reducing Risk of Failure Mode Summarize the Results

Reliability Functional Block Diagram

Page 14 of 15
How to Use 2nd Look Process FMEA Worksheet

Page 15 of 15