Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Architectural Permit: Office of The Building Official

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

NBC FORM NO.

A - 01

Republic of the Philippines


City/Municipality of GUIGUINTO
Province of BULACAN
OFFICE OF THE BUILDING OFFICIAL

ARCHITECTURAL PERMIT
APPLICATION NO. AP NO BUILDING PERMIT NO.

BOX 1 (TO BE ACCOMPLISHED IN PRINT BY THE OWNER/APPLICANT)


OWNER/APPLICANT LAST NAME FIRST NAME M.I. TIN

FOR CONSTRUCTION OWNED FORM OF OWNERSHIP USE OR CHARACTER OF OCCUPANCY


BY AN ENTERPRISE
ADDRESS: NO., STREET, BARANGAY, CITY/MUNICIPALITY ZIP CODE TELEPHONE NO

LOCATION OF CONSTRUCTION: LOT NO. _______________ BLK NO. ________________ TCT NO. ______________________ TAX DEC. NO. _____________________
STREET___________________ BARANGAY ____________________________________________________ CITY/ MUNICIPALITY OF ________________________________

SCOPE OF WORK
NEW CONSTRUCTION RENOVATION ________________________ RAISING _______________________________________
ERECTION CONVERSION ________________________ ACCESSORY BUILDING/STRUCTURE________________
ADDITION REPAIR _____________________________ OTHERS (Specify) ________________________________
ALTERATION MOVING _____________________________ ________________________________________________

BOX 2 (TO BE ACCOMPLISHED BY THE DESIGN PROFESSIONAL)


1. ARCHITECTURAL FACILITIES AND OTHER FEATURES PURSUANT TO BATAS PAMBANSA BILANG 344, REQUIRING CERTAIN BUILDINGS, INSTITUTIONS,
ESTABLISHMENTS AND PUBLIC UTILITIES TO INSTALL FACILITIES AND OTHER DEVICES.
STAIRS WASH ROOMS AND TOILETS SWITCHES, CONTROLS, BUZZERS DRINKING FOUNTAINS
WALKWAYS LIFTS/ELEVATORS HANDRAILS PUBLIC TELEPHONES
CORRIDORS RAMPS THRESHOLDS SEATING ACCOMMODATIONS
DOORS, ENTRANCES & THRESHOLDS PARKING AREAS FLOOR FINISHES OTHERS (Specify) __________

2. PERCENTAGE OF SITE OCCUPANCY 3. CONFORMANCE TO FIRE CODE OF THE PHILIPPINES (P.D. 1185)

PERCENTAGE OF BUILDING FOOTPRINT ______________% NUMBER AND WIDTH OF EXIT DOORS FIRE WALLS OTHERS (Specify)

___________
PERCENTAGE OF IMPERVIOUS SURFACE AREA _______% WIDTH OF CORRIDORS FIRE FIGHTING AND SAFETY FACILITIES
PERCENTAGE OF UNPAVED SURFACE AREA __________% DISTANCE TO FIRE EXITS SMOKE DETECTORS
BOXOTHERS
3 (Specify) __________________________________ BOX
ACCESS TO PUBLIC 4
STREET EMERGENCY LIGHTS

DESIGN PROFESSIONAL, PLANS AND SPECIFICATIONS SUPERVISOR / IN-CHARGEOF ARCHITECTURAL WORKS

Date____________ Date____________
ARCHITECT ARCHITECT
(Signed and Sealed Over Printed Name) (Signed and Sealed Over Printed Name )
Address Address
IAPOA No. Validity IAPOA No. Validity
PRC No. Validity PRC No. Validity
PTR. No Date Issued PTR. No Date Issued
Issued at TIN Issued at TIN

BOX 5 BOX 6
BUILDING OWNER WITH MY CONSENT: LOT OWNER

(Signature Over Printed Name) (Signature Over Printed Name)


Date__________________ Date___________________

Address Address

C.T.C. No. Date Issued Place Issued C.T.C. No. Date Issued Place Issued
TO BE ACCOMPLISHED BY THE PROCESSING AND EVALUATION DIVISION
BOX 7

RECEIVED BY DATE

FIVE (5) SETS OF ARCHITECTURAL DOCUMENTS


1. VICINITY MAP/LOCATION PLAN WITHIN A TWO- 8. DETAILS OF RAMPS, PARKING FOR THE DISABLED, STAIRS,
KILOMETER RADIUS FIRE ESCAPES, CABINETS AND PARTITIONS
2. SITE DEVELOPMENT PLAN 9. SCHEDULE OF DOORS AND WINDOWS
3. PERSPECTIVE 10. SCHEDULE OF FINISHES FOR FLOORS, CEILINGS AND WALLS
4. FLOOR PLANS 11. ARCHITECTURAL INTERIOR
5. ELEVATIONS, AT LEAST FOUR (4) 12. SPECIFICATIONS
6. SECTIONS, AT LEAST TWO (2) 13. COST ESTIMATE
7. CEILING PLANS SHOWING LIGHTING FIXTURES AND 14. OTHERS (Specify)
DIFFUSERS _______________________________________________________
_______________________________________________________

BOX 8

PROGRESS FLOW
IN OUT
PROCESSED BY:
DATE TIME DATE TIME

ARCHITECTURAL DRAWINGS
SPECIFICATIONS

OTHERS (Specify)

BOX 9

ACTION TAKEN:

PERMIT IS HEREBY ISSUED SUBJECT TO THE FOLLOWING:

1. That under Article 1723 of the Civil Code of the Philippines, the architect (and engineer) who drew up the plans and
specifications for the building/structure is responsible for damages if within fifteen (15) years from the completion of the
building/structure, the same should collapse due to defect in the plans or specifications or defects in the ground. The
engineer or architect who supervises the construction shall be solidarily liable with the contractor should the edifice collapse
due to defect in the construction or the use of inferior materials.
2. That the proposed architectural works shall be in accordance with the architectural plans filed with this Office and in
conformity with the latest Architectural Code of the Philippines, the National Building Code and its IRR.
3. That prior to any construction activity, a duly accomplished prescribed “Notice of Construction” shall be submitted to the
Office of the Building Official.
4. That upon completion of the construction, the licensed full-time inspector and supervisor/in-charge of construction works
shall submit the entry to the logbook duly signed and sealed to the building official including as-built plans and other
documents, and shall also accomplish the Certificate of Completion stating that the architectural works conform to the
provision of the Architectural Code, the National Building Code and its IRR.
5. That this permit is null and void unless accompanied by the building permit.

PERMIT ISSUED BY:

Engr. ARCADIO LEOVER P. SULIT


BUILDING OFFICIAL
(Signature Over Printed Name)
Date ___________________