Avida Atria Tower 3 Fit-Out Project Atria, Mandurriao, Iloilo City Progress Report AS OF JUNE 18, 2021
Avida Atria Tower 3 Fit-Out Project Atria, Mandurriao, Iloilo City Progress Report AS OF JUNE 18, 2021
Avida Atria Tower 3 Fit-Out Project Atria, Mandurriao, Iloilo City Progress Report AS OF JUNE 18, 2021
PROGRESS REPORT
AS OF JUNE 18, 2021
1. Large mirror frame backing support
2. Large mirror frame plywood backing installation
3. On-going lamination works in reception cabinets (80% completed)
4. Elevator Car (Right Side) Plywood backing (100% completed)
5. Elevator Car (Right Side) Lamination works (100% completed)
6. Baseboard installation in the lobby (70% completed)
7. Installation of ACU doors (100% completed)
8. Accent wall (100% completed)
9. Powder room ceiling works (90% completed)
10. Picture.
1
2
3
Prepared by Noted by:
Engr. Jeremiah V. Gilbolinga Engr. Paul Lorenz Carmelo