Avida Atria Tower 3 Fit-Out Project Atria, Mandurriao, Iloilo City Progress Report AS OF JUNE 18, 2021

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

AVIDA ATRIA TOWER 3 FIT-OUT PROJECT

Atria, Mandurriao, Iloilo City

PROGRESS REPORT
AS OF JUNE 18, 2021
1. Large mirror frame backing support
2. Large mirror frame plywood backing installation
3. On-going lamination works in reception cabinets (80% completed)
4. Elevator Car (Right Side) Plywood backing (100% completed)
5. Elevator Car (Right Side) Lamination works (100% completed)
6. Baseboard installation in the lobby (70% completed)
7. Installation of ACU doors (100% completed)
8. Accent wall (100% completed)
9. Powder room ceiling works (90% completed)
10. Picture.

1
2
3
Prepared by Noted by:
Engr. Jeremiah V. Gilbolinga Engr. Paul Lorenz Carmelo