LPGTK-PVP-INT-MRQ-7001 - C - MR For CV Code-4
LPGTK-PVP-INT-MRQ-7001 - C - MR For CV Code-4
LPGTK-PVP-INT-MRQ-7001 - C - MR For CV Code-4
SRN
Reviewer Date
30-04-21
Re issued for
C 29.04.21
Approval SRS SRS BPP
B Issued for Approval 25-03-21 SRS SRS BPP
15 Nos of 3-
Way Control
Valves
All the above shall be in accordance with the Specifications & documents issued within REQ DOC.NO.:
LPGTK-PVP-INT-MRQ-7001
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
ORDER
ORDER NO. PURCHASED FROM DEL PROM’D F.O.B. TERMS TAX
DATE
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDICES
DOCUMENT /
DOCUMENT / ATTACHMENT TITLE REV ATTACHED
ATTACHMENT
APPENDIX-A Scope of work 0
APPENDIX-B Vendor drawing & data requirement form 0
APPENDIX-C Spare parts 0
APPENDIX-D Source inspection plan 0
APPENDIX-E Inspection levels 0
APPENDIX-F Table of compliance 0
APPENDIX-G Technical Documents / Drawings 0
LPGTK-PVP-INT-
Datasheet for Control Valves C
DST-7012
LPGTK-PVP-INT-
Datasheet for 3-Way Control Valve C
DST-7015
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX – A
SCOPE OF WORK
(8 PAGES)
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
TABLE OF CONTENTS
1.0 GENERAL
Indian Oil Corporation Ltd. (IOCL), the largest commercial undertaking in India and a
Fortune 'Global 500' company, is engaged in the business of refining, transportation and
marketing of petroleum products. As a group, IOCL owns and operates ten refineries in
India with a total Capacity of over 1.3 million BPD (Barrels Per Day). It also owns and
operates a wide network of crude & products pipelines. It has its own Research &
Development Centre situated at Faridabad, Haryana, near New Delhi.
IOCL intends to set up an LPG Terminal at Kochi in the State of Kerala to import
refrigerated Propane and Butane for supplementing indigenous availability of LPG and
meeting demand in the southern states of India.
The LPG Terminal will be constructed on 15.5 Hectares of land taken from Cochin Port
Trust (CPT) at Pudu Vypeen adjacent to the Crude Oil Terminal of Kochi Refineries Ltd.
which is in the close vicinity of the Petronet LNG Terminal. This LPG terminal will have a
Design Capacity of 600,000 MTPA (Metric Tons per Annum).
1.1 Project Objective
The objective of this project is to carry out the detailed engineering of LPG import terminal
at Pudu Vypeen, Kochi for IOCL. The proposed LPG Terminal at Pudu Vypeen, Kochi shall
receive refrigerated Propane and Butane for supplying LPG in the Southern states of India.
Refrigerated butane and propane from ships will be unloaded at Jetty and transferred and
heated in Butane and Propane Heater using Butane and Propane Booster Pumps. The
heated butane and propane shall be routed to the LPG terminal through the cross-country
pipeline and subsequently stored in Butane / Propane mounted bullets of capacity 4200m3
under pressurized condition. The Butane and Propane Transfer Pumps will transfer the
stored butane and propane to the Blending skid and blended by batch controller to produce
LPG. The produced LPG will be dispatched via tank trucks.
1.2 Definitions
Company/Owner : Indian Oil Corporation Limited (IOCL)
PMC : TATA Consulting Engineers Limited (TCE)
Engineering : Jayathe Petrotech Engineers & Consultants (JPEC)
Sub-contractor
VENDOR : Equipment Supplier or Manufacturer
SHOULD : The word “should” is understood to be strongly
recommended to comply with the requirements.
SHALL : The word “shall” is understood to be mandatory to
Comply with the requirements
1.3 Abbreviations
GA : General Arrangement
MR : Material Requisition
PO : Purchase Order
This document outlines the technical requirements to be followed for the design, selection,
and scope of work for the Control Valves to be supplied for the IOCL LPG Import, Terminal
project.
CONTRACTOR shall be responsible for the delivery, off-loading and installation at site;
however, any special tools required for installation will be provided by the VENDOR.
VENDOR shall provide the services of experienced personnel to assist the CONTRACTOR to
carry out the Control Valve tests before and after installation.
SAT shall be performed to check the good working and the required performance of the
Control valves under the actual operating conditions and in compliance with the requirements
of the drawings and documents attached to the Material Requisition .
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
6.0 TRAINING
Special tools required for installation, testing, operation and maintenance of the Control
Valve and related accessories shall be supplied by the VENDOR and shall be included in
the quotation as a separate list with associated price.
Spare parts for Commissioning and Start-up shall be supplied by the VENDOR and shall
be included in the quotation as a separate list with price. VENDOR shall note that during
commissioning if any of the spare is consumed over and above the quoted
commissioning spares, the same should be replaced / supplied free of cost by the
VENDOR.
Spare Parts for normal operation shall adequately cover the requirements of the day-to-
day maintenance for a period of two (2) years operation. The spares for two (2) years
operation shall be separately quoted by the VENDOR and will be ordered later (only list
with price and Validity shall be provided
Bill of Quantity;
10.2 Each document submitted for review must be clear, legible, complete and properly
identified. Tags shall conform to Buyer standards. Failure to provide adequate documents
may result in them being returned without review at Vendor’s expense. In that event,
Vendor will be considered not to have formerly submitted the documents so returned.
10.3 All documents must show tag numbers, material requisition numbers, and Vendor's own
title, drawing and revision numbers, in the lower right hand corner. Documents must have
an open space 85 mm x 85 mm near bottom right hand corner to allow for supplier
document review stamp. Reproducible of reduced size certified drawings to be A3 (or by
varied length).
10.4 Vendor shall submit accurate, properly checked and approved by the responsible
Engineer(s). The documents shall be in English language.
10.5 Dimensions, weights, and measures for drawings, etc. to be in SI units, Nominal sizes to be
in inches.
10.6 Vendor must submit data and drawings “Certified Correct” within two (2) weeks after return
of approved documents.
10.7 Drawings and data approval does not relieve Vendor of his responsibility to meet Purchase
Order or Contract conditions relating to specifications, material design or construction, and
delivery requirements, nor relieve Vendor of responsibility for compliance with laws, codes
and regulations.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
• VENDOR’s name;
• Tag number, model number, purchase order number and serial number;
• Span and Range;
• Operating Voltage;
• IP Rating and Area Certification;
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX – B
TECHNICAL DOCUMENTS
DOCUMENT/
DOCUMENT/ATTACHMENT TITLE REV REMARKS
ATTACHMENT NO.
DOCUMENTS
LPGTK-PVP-INT-DST-
Datasheet for Control Valves C
7012
LPGTK-PVP-INT-DST-
Datasheet for 3-Way Control Valves C
7015
LPGTK-PVP-INT-SPC-
Specification for General Instrumentation 0
7001
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX – C
Notes:
1. Vendor Shall submit all deliverables within the period as indicated.
2. All Documents / Drawings shall be in English Language.
3. Final certified drawings and documents shall be submitted within two weeks of fabrication
and testing completion;
4. Certified correct data and drawings are required within two (2) weeks after return of “For
Approval” data and drawings;
5. All data and drawings are required by final invoice, if not a “ VENDOR Data Retention” will
be held back until receipt of data and drawings;
6. Reduced size reproducible A3 (or by varied length). Reproducible copies required if larger
than 11” X 17” (A3);
7. Cost of prints must be included in the quotation;
8. All drawings must show OWNER / CONTRACTOR name, PROJECT Title, Drawing
number, Revision number. Final drawings must be certified;
9. All deliverables shall be submitted by official Transmittals;
10. Submit all documents via courier service;
11. The submitted documents shall be accurate, checked and signed by responsible
Engineer(s);
12. Any additional drawing and documentation required by the Local Authorities shall be
provided the VENDOR
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX – D
TABLE I
The BIDDER shall indicate below Start-up and Commissioning Spares for equipment, plant or system offered by him.
MANUFACTURER
PERIOD (WEEKS)
RECOMMENDED
DESCRIPTION OF
FROM DATE OF
CONSTRUCTION
EQUIPMENT TAG
QUANTITY/SET
TOTAL PRICE
MATERIAL OF
EQUIPMENT
UNIT PRICE
AND PART
DELIVERY
PER UNIT
REMARKS
NUMBER
NUMBER
SL. NO.
SPARE
LOI
Rs.
Rs.
1.
2.
3.
4.
5.
COMPANY SEAL SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
Commissioning Spares are the Spare Parts which are used, and provided by, the Vendor during the Construction Phase and Commissioning
Stages, including Start-Up and Testing up to the issue of the Provisional Acceptance Certificate (PAC).
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
TABLE II
RECOMMENDED ACCESSORIES (Spares): Two Years Operation
The BIDDER shall indicate below Essential and Recommended Spares for two (2) years of trouble free operation of the
equipment, plant or system offered by him.
MANUFACTURER
DESCRIPTION OF
PERIOD (WEEKS)
RECOMMENDED
CONSTRUCTION
EQUIPMENT TAG
FROM DATE OF
QUANTITY/SET
MATERIAL OF
TOTAL PRICE
EQUIPMENT
UNIT PRICE
AND PART
REMARKS
DELIVERY
PER UNIT
NUMBER
NUMBER
SL. NO.
SPARE
LOI
Rs.
Rs.
A. ESSENTIAL SPARES AS INDICATED BY THE PURCHASER/CONSULTANT
1.
2.
B. RECOMMENDED SPARES AS INDICATED BY THE BIDDER IN ADDITION TO ESSENTIAL SPARES AS INDICATED
BY THE PURCHASER/CONSULTANT
1.
2.
COMPANY SEAL SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
Insurance Spares are parts of equipment, assemblies or complete items that are required for replacement of items that are not subject to
deterioration by normal use, but failure of which is critical for continuous and safe operation of the Equipment or Plant. It is understood that
such spares may have Long Lead Items.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX – E
MAN-HOUR RATES
Rates (US/h)
Service Personnel
Description No. Category Working Time Remarks
Normal Overtime
To specify proposed
Training
training period.
Note: Man-hour rates for site service specified in the Table shall be only applicable for site
service beyond free site-service period due to Company’s reasons.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX - F
Inspection Levels
Level 0
No Quality Surveillance required.
Level 1
Release for Shipment Surveillance. This level requires final surveillance inspection only
to ensure that the complete equipment / material is:
in compliance with the purchase order;
properly identified;
adequately prepared for shipment;
documentation requirements have been fulfilled.
Level 2
Limited Scope Surveillance. This level requires, in addition to surveillance activities
outlined under level 1, a prefabrication visit to review the quality requirements
established by purchase order plus witnessing of all verification and hold points outlined
in the Quality Surveillance Plan.
Level 3
Full Scope Surveillance. This level requires, in addition to surveillance activities outlined
under level 2, random visits during the fabrication cycle with the purpose of monitoring
and verifying the VENDOR’s compliance with his own Quality Control Program and
purchase order specifications, on a spot check basis. The frequency of visits shall be
based on the complexity of the equipment and the VENDOR’s performance.
Level 4
Extreme Surveillance and Residency Surveillance. This level requires, in addition to
surveillance activities outlined under level 3, daily visits or full residency as directed by
the PROJECT. The VENDOR’s Quality Program execution shall be monitored on an
ongoing basis and all specified tests shall be witnessed.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
DOCUMENTATION: IN ADDITION TO THE COPIES REQUIRED IN SECTION III, ONE COPY OF THE
DOCUMENTSCHECKED BELOW MUST BE PROVIDED BY THE VENDOR TO
INSPECTOR WHEN REQUESTED.
ASME Code data reports
Other Code Data Reports - Specify: seat pneumatic Certificate of Compliance(hydrotests)
P.O Documentation(Specifications/ Datasheet/ Drawing) Vendor’s Test & Quality Control Data Report
Material test reports (Mech. & Chem. Test Reports) Sub vendors P.O
Charpy impact tests (if required) Sub Vendor’s Inspection Report
Stress relief/Heat treat/Hardness chart (if required) NDT Reports
Packing list Certificate for parts
Nameplate rubbings or facsimile Manufacturers Data Book
Certificate of Compliance(test runs) Material Certificates / Mill & Test report
Design calculations Calibration and Test Reports
PROCEDURES: REPRESENTATIVE WILL AT HIS DISCRETION, CHECK (C), REVIEW (R) OR
APPROVE (A) THE PROCEDURES AND QUALIFICATIONS WHICH ARE
MARKED BELOW
High Pot Test Procedures Factory acceptance Procedures
Test Procedures for Electric Heaters (A) Tube Rolling Procedures
Machine Procedures Tube Cleaning and Installation Procedure
Welding Procedures (R/A) Quality Control Plan / Procedures (R)
Weloding Repair procedures(R/A) Surface Preparation, Painting & Coating Procedure
(A)
Welder qualification records ( R) Material Hardness Test Procedure (if required)
Noise Test Procedures (A) Post weld heat treatment procedure (PWHT) (if
required)
NDT Procedures (A) Pre manufacturing meeting
Performance Test Procedure (A)
INSPECTION CHECK LIST: THE INSPECTOR WILL CHECK (C), REVIEW (R), APPROVE (A) AND / OR
WITNESS (W) THE FOLLOWING:
R/C A W R/C A W
Level of Inspection – Specify Level 2 Sun blast, Coating and painting x x
Quantity & type as per P.O x Functional test of Inst. & Controls x
Drawings and Procedures x Name plates marking and Tagging x x
Materials and Components verification x Rust prevention applied to opening x
Hydro test x Compliance with Specifications x
Performance Test x x x Cleanliness prior to shipping x
Dimensional Checks & visual x x Spare parts included and list provided x
workmanship
Testing Equipment Calibrated and valid x Shipped loose parts identified properly x
Certificate for parts x x Temporary shipping supports provided x
Testing equipment validity certificates Transportation/ Security / packaging x
x
Electrical Test/ Mechanical/ Pneumatic x Weights/ dimensions as per specs x
Run Test
Inspection-Actuator, Positioner, Solenoid x Final release documentation and x
valve, Airset,Manual operation packing and shipping
Leakage Test x Take photograph (R ) x x
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
VENDOR SHALL PROVIDE / SHOW APPROVED DOCUMENTS TO INSPECTION REPRESENTATIVE FOR INSPECTION OF ANY
EQUIPMENT / MAIN ITEM AND SUB ITEMS ETC. INSPECTION SHALL NOT BE CARRIED OUT BASED ON COMMENTED
DOCUMENT.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
APPENDIX – G
TABLE OF COMPLIANCE
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT SUBCONTRACTOR
DETAILED ENGINEERING FOR
LPG IMPORT TERMINAL PROJECT
PUDU VYPEEN, KOCHI
PROJECT CODE:4280
MR FOR CONTROL VALVES
TABLE OF COMPLIANCE
The Vendor shall confirm below the Sections of the Requisition /Specification that he has
complied with/ accepted or further clarifications are desired, or Vendor has taken a deviation
with reasons there to. Columns 2,3,4 and 5 must be answered and initialed.
1 2 3 4 5
Document No. *Conforms *Deviations Noted Yes @Clarification or
Yes / No Yes / No / No Reasons for
Deviations
MR No.
LPGTK-PVP-INT-MRQ-7001
SRN 09-04-2021
,2&//3*,032577(50,1$/352-(&7
38'89<3((1.2&+,
352-(&7&2'(
'$7$6+((7)25&21752/9$/9(6
'2&12/3*7.393,17'67 5(9& 5(9'$7( 3DJHRI
0$18)$&785(5 97$
*(1(5$/ 0RGHO1R 97$
7DJ1XPEHU 5HIHU6KHHW
%RG\6W\OH $QJOH *OREH 6SOLW <W\SH %DOO
(QG&RQQHFWLRQV 5)
3XVK'RZQWR $VSHU)DLO6DIHSRVLWLRQ
)DLO6DIHDFWLRQ )DLO&ORVH
9$/9($&7,21
)ORZ'LUHFWLRQ )ORZWR2SHQ )ORZWR&ORVH
3QHXPDWLF&RQQHFWLRQ 137)
6HUYLFH 2Q2II 0RGXODWLQJ
0D[LPXPSUHVVXUHIRU$FWXDWRUWRZLWKVWDQG NJFPJ
5DQJHRI6LJQDOWR$FWXDWRU 97$
7UDYHO,QGLFDWRU 5HTXLUHG
'LDSKUDJP0DWHULDO 97$
%RG\0DWHULDO &DVW$OXPLQLXPZLWKHSR[\FRDWLQJ
6L]H 97$
2WKHU(33RVLWLRQHU'LUHFW5HYHUVHDFWLQJWREHDGMXVWDEOH
6SULQJ7\SH 'LDSKUDJP
2XWSXW6LJQDO aNJFPJ
(QFORVXUH:HDWKHUSURWHFWLRQ ,3([SURRI
(QFORVXUH02& $OXPLQLXPDOOR\
2YHUDOODFFXUDF\ 97$
$UHD&ODVVLILFDWLRQ6XSSO\9ROWDJH =RQH&ODVV,,$,,%79'&
,2&//3*,032577(50,1$/352-(&7
38'89<3((1.2&+,
352-(&7&2'(
'$7$6+((7)25&21752/9$/9(6
'2&12/3*7.393,17'67 5(9& 5(9'$7( 3DJHRI
0DNH 0RGHO 97$
6HUYLFH ,QVWUXPHQW$LU
,QOHW3UHVVXUH5DQJH aNJFPJ
2XWOHWSUHVVXUHUDQJH 97$
2XWSXWSUHVVXUHJDXJH 5HTXLUHGZLWKGLDO
$,5),/7(5
5(*8/$725 цϭйŽĨ^ĞƚƉŽŝŶƚĨŽƌƉƌĞĐŝƐŝŽŶ
$FFXUDF\
цϱйŽĨ^ĞƚƉŽŝŶƚĨŽƌŽŶǀĞŶƚŝŽŶĂů
%RG\02& 'LH&DVW$OXPLQLXP 66
6SULQJ &DUERQ6WHHO 66
/HDNDJH 97$
0RXQWLQJEUDFNHW 5HTXLUHG
&2'(6$1'67$1'$5'6
*HQHUDO5HTXLUHPHQWV6L]LQJ(TXDWLRQV,QVSHFWLRQ 5RXWLQH7HVWLQJ1RLVH&RQVLGHUDWLRQV%6(1
*HQHUDO5HTXLUHPHQWV6L]LQJ(TXDWLRQV,6
)ORZ(TXDWLRQIRU6L]LQJRI9DOYH$16,,6$
9DOYH/HDNDJH&ODVVDVSHU$16,)&,
'5$:,1*6
'DWDVKHHW&DOFXODWLRQIRU9DOYH6L]LQJ2XWOHW9HORFLW\)ODVKLQJ1RLVHDQG$FWXDWRUVL]LQJ
'LPHQVLRQDO'UDZLQJVKRZLQJPRXQWLQJGHWDLOV:HOGHQGGHWDLOV$FWXDWRU6WHPUHPRYDOVSDFLQJKDQGZKHHORULHQWDWLRQZHLJKWDQGSDUW/LVW
'DWDVKHHWIRU9DOYH$FWXDWRU$OODSSOLFDEOHDFFHVVRULHV
6HSDUDWH&KDUDFWHULVWLFFXUYHVIRUVSHFLILHGYDOYHVVKDOOEHVXEPLWWHG
9HQGRURVXEPLWDOO7HVW&HUWLILFDWHVIRU3XUFKDVHU&RQVXOWDQW
VUHYLHZ 5HFRUGV
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
C C
Sl. Vapour Packing Flow Rate
Tag Number Fluid Name / phase State Critical Pressure Body / Bonnet Material Trim Material Bonnet nuts/ bolts Gasket Material Rating
No. pressure(kg/cm2) Material TPH
ASTMA 182 Gr. F304/ ASTM A ASTM A193 Gr S8/ASTM A194BgR Spiral wound,
1 FV-210 Mercaptan Liquid 56 1.144 SS304 Graphoil 300# 0.0209
351 Gr CF8 8 SS316
ASTMA 182 Gr. F304/ ASTM A ASTM A193 Gr S8/ASTM A194BgR Spiral wound,
2 FV-310 Mercaptan Liquid 56 1.144 SS304 Graphoil 300# 0.0209
351 Gr CF8 8 SS316
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
1 Positioner, Actuator and accessories requiring tubing shall be mounted with Valves and Tubes.All Tubing and fittings shall be of SS316.
2 Control Valves shall be sized to have an Opening of 15% at minimum Flow conditions and 80% at maximum Flow conditiosn.
3 All applicable Codes and Standards to be followed.
4 Noise Level at 1.5 Meters shall be limited to 85dBA.
5 Vendor shall size the Actuator as per the requirement.
6 The positioner shall be side mounted on the Control Valve and shall have corrosion resistance Linkages and rugged brackets.
7 All the Pressure Gauges in the E/P Positioner shall be in SS Casing and movement.
Trim Characteristic shall be Equal Percentage in general.Control valve plug shall be top and bottom guided for double seated valve and heavy
8
top guided for single seated valve.
16 Radiography procedure, Areas of casting to be radiographed shall be as per ASME B16.34 and acceptance criteria shall be as per ASME
B16.34 annexure B.However for areas of Casting to be radiographed for type of valves not covered in ASME 16.34, Vendor shall enclose details
of areas to be radiographed in line with ASME B 16.34.
For random radiography wherever specified, the sampling shall be per size of the quantity ordered for each foundry.Radiography shall be done
by X-ray/ gamma ray to get the required sensitivity.
Radiography specified as Random 10% or 20% etc. in the respective valve datasheet implies 10% or 20% etc of number of valves ordered
against each item number with a minimum of one valve against each item.
17 All Cable entries shall be using double compression type Cable gland.Cable glands & plugs shall be as per Design basis report and Suitable for
the area classification.
18 C All unused Cable entries shall be plugged with plugs suitable for Hazardous area classification.
OWNER ENGINEERING CONSTRUCTION CONSULTANT CONTRACTOR ENGINEERING
CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
SRN 09-04-2021
21 Spring Type / Spring MOC Closed type / Corrosion Resistant (Cadmium or Nickel plated)
34 Size VTA
44 Cable Entry size / Nos. / Cable Gland 1/2" NPT(F) / 2 Nos. / M20
58 Tubing and Fittings(Refer note-1) SS316 Seamless tubing of 1/4" Size.Fittings shall be SS316 Double Compression type
74 Leakage VTA
79 Type & port Direct, 3/2 Way port 5/2 Way port
82 Insulation Class as per IEC 60085 /IS 1271 Class B Class E Class F Class H For high temperature
96 Weather protection IP 65 C
102 Seat leakage Test as per ANSI B16-104 Required Not Required
1 General Requirements, Sizing Equations, Inspection & Routine Testing, Noise Considerations-BS EN 60534.
2 Dimensional Drawing showing mounting details, Weld end details, Actuator / Stem removal spacing, handwheel orientation, weight and part List.
5 Vendor o submit all Test Certificates for Purchaser / Consultant's review & Records.
OWNER ENGINEERING CONSTRUCTION ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR CONTRACTOR SUBCONTRACTOR
3 TVV-332 P-104A Booster Pump Discharge 10"-PBL-302-B4A-CI LPGTK-PVP-PRO-PID-1102 -42/55 21.25 21.25 582 0.202 Yes (1 No.) 250
4 TVV-333 P-104B Booster Pump Discharge 10"-PBL-301-B4A-CI LPGTK-PVP-PRO-PID-1102 -42/55 21.25 21.25 582 0.202 Yes (1 No.) 250
5 TVV-334 P-104C Booster Pump Discharge 10"-PBL-300-B4A-CI LPGTK-PVP-PRO-PID-1102 -42/55 21.25 21.25 582 0.202 Yes (1 No.) 250
6 TVV-335 P-104D Booster Pump Discharge 10"-PBL-1180-B4A-CI LPGTK-PVP-PRO-PID-1102 -42/55 21.25 21.25 582 0.202 Yes (1 No.) 250
7 TVV-323 Propane transfer Pump P-101A 6"-PL-141-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 23.125 23.125 465 0.114 Yes (1 No.) 75
8 TVV-324 Propane transfer Pump P-101B 6"-PL-143-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 23.125 23.125 465 0.114 Yes (1 No.) 75
9 TVV-325 Propane transfer Pump P-101C 6"-PL-1086-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 23.125 23.125 465 0.114 Yes (1 No.) 75
10 TVV-326 Propane transfer Pump P-101D 6"-PL-1215-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 23.125 23.125 465 0.114 Yes (1 No.) 75
11 TVV-327 Butane transfer Pump P-102A 6"-BL-175-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 18.125 18.125 545 0.182 Yes (1 No.) 90
12 TVV-328 Butane transfer Pump P-102B 6"-BL-177-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 18.125 18.125 545 0.182 Yes (1 No.) 90
13 TVV-329 Butane transfer Pump P-102C 6"-BL-179-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 18.125 18.125 545 0.182 Yes (1 No.) 90
14 TVV-330 Butane transfer Pump P-102D 6"-BL-1201-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 18.125 18.125 545 0.182 Yes (1 No.) 90
15 TVV-331 Butane transfer Pump P-102E 6"-BL-1203-B1A-NI LPGTK-PVP-PRO-PID-2103 15/55 18.125 18.125 545 0.182 Yes (1 No.) 90
Sl. Vapour
Tag Number Fluid Name / phase State Critical Pressure Body / Bonnet Material Trim Material Packing Material Bonnet nuts/ bolts Gasket Material Rating
No. pressure(kg/cm2)
C
Spiral wound,
1 TVV-337 Propane Liquid 43.56 13.5 ASTM A352 Gr LCB 13% Cr Graphoil ASTM A320 Gr L7 / ASTM A194-7 300#
SS304
Spiral wound,
2 TVV-338 Butane Liquid 38.37 4.153 ASTM A352 Gr LCB 13% Cr Graphoil ASTM A320 Gr L7 / ASTM A194-7 300#
SS304
Spiral wound,
7 TVV-323 Propane Liquid 43.56 13.5 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
8 TVV-324 Propane Liquid 43.56 13.5 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
9 TVV-325 Propane Liquid 43.56 13.5 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
10 TVV-326 Propane Liquid 43.56 13.5 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
11 TVV-327 Butane Liquid 38.37 4.153 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
12 TVV-328 Butane Liquid 38.37 4.153 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
13 TVV-329 Butane Liquid 38.37 4.153 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
14 TVV-330 Butane Liquid 38.37 4.153 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
Spiral wound,
15 TVV-331 Butane Liquid 38.37 4.153 ASTM A216 WCB AISI 410 / A276-T410 Graphoil ASTM A193-B7/ASTMA194-2H 300#
SS316
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
16 Radiography procedure, Areas of casting to be radiographed shall be as per ASME B16.34 and acceptance criteria shall be as per ASME
B16.34 annexure B.However for areas of Casting to be radiographed for type of valves not covered in ASME 16.34, Vendor shall enclose details
of areas to be radiographed in line with ASME B 16.34.
For random radiography wherever specified, the sampling shall be per size of the quantity ordered for each foundry.Radiography shall be done
by X-ray/ gamma ray to get the required sensitivity.
Radiography specified as Random 10% or 20% etc. in the respective valve datasheet implies 10% or 20% etc of number of valves ordered
against each item number with a minimum of one valve against each item.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
TABLE OF CONTENTS
1.0 INTRODUCTION:
M/s Indian Oil Corporation Ltd. (IOCL), the largest commercial undertaking in India and a Fortune
'Global 500' company, is engaged in the business of refining, transportation and marketing of
petroleum products. As a group, IOCL owns and operates ten refineries in India with a total
Capacity of over 1.3 million BPD (Barrels Per Day). It also owns and operates a wide network of
crude & products pipelines. It has its own Research & Development Centre situated at Faridabad,
Haryana, near New Delhi.
IOCL intends to set up an LPG Terminal at Kochi in the State of Kerala to import refrigerated
Propane and Butane for supplementing indigenous availability of LPG and meeting demand in the
southern states of India.
Refrigerated Butane and Propane will be heated from (-) 4 °C and (-) 42 °C respectively to 15 °C
and subsequently stored in pressurised condition. Propane and Butane will be blended in the
static mixer to produce LPG. The LPG Terminal will be constructed on 15.5 Hectares of land taken
from Cochin Port Trust (CPT) at “Pudu Vypeen” adjacent to the Crude Oil Terminal of Kochi
Refineries Ltd. which is in the close vicinity of the “Petronet LNG Terminal”. This LPG terminal will
have a Design Capacity of 600,000 MTPA (Metric Tons per Annum).
The objective of this project is to carry out the detailed engineering of LPG import terminal at Pudu
Vypeen, Kochi for IOCL. The proposed LPG Terminal at Pudu Vypeen, Kochi shall receive
refrigerated Propane and Butane for supplying LPG in the Southern states of India as follows:
Refrigerated Butane and propane will be unloaded at Jetty and transferred to the Butane and
Propane Heater using Butane and Propane Booster Pumps for heating the same from (-)4oC and
(-)42oC respectively to 15oC. The heated Butane and Propane shall be routed to the LPG
terminal through the cross country pipeline which is approx. 3.5km in length and subsequently
stored in Butane / Propane mounted bullets of capacity 4200m3 under pressurized condition. The
Butane and Propane transfer pumps will transfer the stored Butane and Propane to the Blending
unit to produce LPG. The produced LPG will be dispatched via tank trucks.
The purpose of this document is to define the General Instrumentation requirements as reference
to be used for Instrumentation & Control System. This document provides general information,
process and engineering data and guidance for the Field Instruments & the System.
The Design intent is for the Instrumentation to be selected from the Latest Technologies with
proven track record and confirming to latest standards.
DEFINITIONS
NOMENCLATURE DESCRIPTION
Company Indian Oil Corporation Limited
Engineering
Tata Consulting Engineers Limited
Consultant
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
The latest editions of Codes, Standards including all addendum, supplements or revisions current
at time of order placement, as issued by the following authorities shall apply:
API RP 607: 2005 : Fire test for soft seated quarter turn valve
IEC 534-2: 1998 : Sizing equations for incompressible fluid flow under
installed conditions
Other Standards
OMIL R117: 2007 : Dynamic Measuring Systems for Liquids other than
water
The system of measurement units for the project is SI (System International) and they are listed
below. Units in brackets may be used when the property is quoted in dual units:
Temperature : C
0
Length, Level : mm / m
Level (Relative) : %
Electrical Power : Kw
Density : kg/m3
Viscosity : cP
Illumination : LUX
All field mounted instruments, equipment and junction boxes, etc. including entries and blanking
plugs in field shall have an environmental protection rating of IP-65 to BS EN 60529.
Control panels and control room instruments in air conditioned environment shall comply with
IP-20 as minimum.
6.2.2 In case intrinsically safe equipment is not available, flameproof/ex-proof enclosures (EEx'd') for
Zone-1, Gr. IIA/IIB, T3 shall be provided.
6.2.3 Following concepts shall be applied for protection if intrinsically safe or flameproof concept cannot
be applied.
6.3.4 Particle Size: The particle size in the air/ gas stream at the instrument shall be less than 5
microns.
6.3.5 Oil Content: The total oil or hydrocarbon content exclusive of noncondensable shall be as close to
zero weight / weight or volume / volume as possible. Under no circumstances, it shall exceed 1
PPM weight / weight or volume / volume under normal operating conditions.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
6.3.6 Contaminants: The instrument air shall be free of all flammable, corrosive, oil and toxic
contaminants.
6.3.7 Pneumatic Valve Actuator shall be designed for min. 4kg/cm²(g) pressure .
6.3.8 Air requirement for Solenoid operated Valve shall be max. 5 SCFM and for panel purging shall be
max. 1 SCFM.
6.4.1 Spare shall include spare parts, special tools and tackles, including tool box, as required for
pre-commissioning & commissioning, start-up and interim operation, day-to-day maintenance,
any premature failures for the facilities and first two years operation.
(a) Local gauges, instruments, switches, lamps etc – 10% of each type model or 1 no.
minimum whichever is higher.
(b) All electronic items / transmitters – 10% of each type / model or 1 no. minimum whichever
is higher.
7.1 General
7.1.1 All field instruments being offered/ supplied should have been operating satisfactorily in an oil &
gas industry under similar process conditions for at least 4000 hrs. Proven Track Record (PTR)
for all field instruments shall be furnished for minimum of 4000 hours and for system oriented
items such as Analysers, PLC, controllers etc., the same shall be minimum 1 year.
7.1.2 All line or equipment mounted instruments like control valves, pressure relief valves, Thermowell,
orifice flanges, level instruments, pressure gauges etc., installed on pipes and vessels under IBR
shall be certified by IBR or their authorized representative. They shall comply to the special Piping
Material Specification requirements.
Installation items on the IBR lines like Syphon, Condensate chambers, Pipe and Pipe fittings,
Steam tracing fittings shall have IBR Certification.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
7.1.3 Generally transmitters shall be of latest microprocessor based electronic "SMART" type with 2
wire 24VDC loop powered. This allows efficient preventive maintenance with the use of a HART
communicator. The maintenance shall be able to investigate parameters such as range,
calibration, temperature, pressure etc.
7.1.4 Wherever it is not possible to have a loop powered two wire instruments, 4 wire transmitters may
be considered with power supply 230 VAC.
7.1.7 Switch function shall be snap acting hermetically sealed gold plated SPDT with potential free
contacts, unless otherwise specified. Minimum contact rating for switch contacts shall be 5A, 24
VDC.
7.1.8 All electronic transmitters shall be fitted with an integral local indicator with a read out digital
engineering units in general. All instrument ranges shall be selected such that the normal
operating range shall be between 30% and 70% of the instruments total range.
7.1.9 For Critical instruments which shall be used for Emergency shutdown application shall be SIL 3
rated.
7.1.10 All pressure instruments shall have integral manifold as applicable. Manifold shall be of 2 valve, 3
valve or 5 valve type.
7.1.11 The transmitter enclosure shall be of copper free cast aluminium with epoxy coating suitable for
coastal atmosphere.
7.1.12 All instruments with process connection as flanged shall be as per ASTM B16.5 except orifice
plate flange assembly which shall be as per ASTM B 16.36.
7.1.13 The interlock and shutdown system shall be designed fail safe and shall meet following
requirements:
a) All initiating contacts shall be closed in normal condition and shall open under abnormal
condition.
b) All relays and solenoid valves shall be energised under normal condition and shall
de-energise under abnormal conditions.
7.1.14 All field mounted transmitter shall be supplied with 2” pipe mounting arrangement (2” Pipe
mounting „U‟ bolt with nut & bolt) unless otherwise specified.
7.1.15 The philosophy for considering instruments in hazardous area shall be as follows:
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
7.2.1 Flow meter shall be selected to suit process requirement for accurate and reliable measurement.
7.2.2 Flow meter for LPG Services shall be of Coriolis type with minimum pressure drop and accuracy
below +/- 0.15% in general.
7.2.3 Coriolis Mass Flow Meter / Oval Gear Meter of high accuracy shall be used for the flow
measurement and totalisation at product receipt line. Flow transmitter output shall be pulse type
and shall interface with batch controller.Coriolis Meter shall measure mass flow rate, density and
temperature.
7.2.4 Differential pressure flow meter shall be used wherever it is not required to have flow instruments
of high accuracy.
7.2.5 Concentric, square edged orifice plate shall be provided for liquid and gas services. Orifice plate
calculation shall be done as per ISO 5167.Beta ratio(d/D) shall be between 0.3 and 0.7.
7.2.6 Where line size is 2” and below, prefabricated metering runs shall be used with integral manifold
to mount differential pressure transmitter directly on the meter.
7.2.7 In case of water service, electro-magnetic flow meter shall be used. Accuracy of electro-magnetic
flow transmitter shall be 0.25% for 10:1 turn down or better.
7.3.1 Pressure gauge shall be bourdon / diaphragm / capsule type as per application. Pressure gauges
shall have 6” white dial and black scale marking.
7.3.2 All pressure gauges shall have blow out disc on the back side of the gauge.
7.3.3 All the pressure gauges on the discharge line of pumps or pulsating service shall have snubber in
order to avoid any pulsation on the pointer at the start.
7.3.4 Pressure gauge shall have micrometer pointer for zero adjustment.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
7.3.5 Pressure switch shall be non-indicating type in general. Pressure switch sensing element shall be
diaphragm or bellow. Set point of the pressure switch shall be field adjustable. An indicating scale
shall be provided on the pressure switch.
7.3.6 Micro switch shall be SPDT type and shall be hermetically sealed with gold plated switch.
7.3.7 Pressure transmitter process connection and wetted parts shall be selected depending upon the
service and the process conditions. Integral 2 valve manifold shall be provided.
7.3.8 Process connection of all pressure transmitters shall be ½” NPTM unless specified otherwise.
7.3.9 For differential pressure transmitter process connection shall be ½” NPTF with integral 5 valve
manifold compatible with isolation valve and if required erection software needs to be considered.
7.3.10 All wetted parts including sensing element as well as accessories like syphon, snubber, valve
manifolds shall be of SS-316 as a minimum.
7.3.11 All pressure instruments shall be provided with 2” galvanized CS pipe mounting arrangement with
FRP canopy. Mounting bracket and nuts and bolts shall be of SS.
7.4.1 Duplex RTD (Resistance Temperature Detector) shall be platinum element 3 wire type with 100 Ω
resistances at 0˚C as per IEC 751. Duplex element shall have two separate cable entries. The
response time of the RTD shall be less than 10sec when installed with thermowell.
7.4.2 Thermowell shall be machined SS 316 drilled from solid bar stock of 34mm.Thermowell process
connection shall be 1½” flanged with ½” NPT instrument connection in general. Thermowell shall
be checked for the possibility of wake frequency induced damage, as per ASME PTC 19.3 wake
frequency analysis shall be carried out for all thermowell.
7.4.3 Field mount temperature transmitter with integral display shall be used in general. All temperature
transmitter shall have inbuilt lineariser function to produce output linear to temperature range.
7.4.4 Temperature Gauge shall be bi-metallic type, all angle type weatherproof hermetically sealed,
adjustable construction, with 150 mm (6") diameter dial Temperature gauge. Temperature gauge
shall have accuracy of +/- 1% of FSD (full scale division) as minimum. Temperature gauge casing
shall be of SS304.
7.4.5 Thermowells
a) All temperature elements shall be protected by thermowells, except surface (skin)
temperature measurements and motor winding temperature measurements.
Thermowell material shall be SS 316 unless material of special quality is called for according
to process condition.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
b) They shall be fabricated out of barstock up to a length of 500 mm.Beyond 500 mm; fabricated
construction shall be used considering the thickness of pipe.
c) Flange mounted thermowells are preferred. Minimum flange rating shall be 300#. Higher
rating shall be provided as per the piping material specification for the application.
e) Insertion length shall be measured from the outer surface of the pipe flange to the tip of
the thermowell. The process flange nozzle shall be 150mm + (60% to 80%) of pipe
diameter irrespective of pipe size.Other sizes and immersion lengths may be
considered based on special condition / actual requirements.
7.5.1 Control valves wherever used shall be globe type unless specified otherwise.
7.5.2 Top guided single seated type globe valve shall be used in general.
7.5.3 Control valve end connection shall be flanged as per ASTM B 16.5 for valve up to 600mm. And
sizing of control valve shall be as per ISA-S75-0110.5.4. Valve body & bonnet material, flange
type and finish shall conform to the Valve material specification. However, the body and flange
rating shall be minimum 300# as per ANSI. Trim material shall be SS 316 or better. Trim shall be
stellited in case of high pressure drops across valve.
7.5.4 Wetted parts or trim martial wherever specified shall consist of seat ring, valve plug, plug guide,
plug stem, guide bushing and cage etc.
7.5.5 Control valve actuator shall be pneumatically operated spring return type. Actuator shall be
diaphragm type in general. However, in case the shut off pressure is too high across the valve,
piston type actuator may be used. Standard air control signals to positioner shall be 3 to 15 psig.
Control valve actuator shall be painted green for air fail-to-open (FO) valves and red for air
fail-to-close (FC) valves.
7.5.6 Electro-pneumatic (E/P) valve positioner shall be provided for all control valves. E/P positioner
shall be operating on input signal 4 - 20 mA, 24 VDC. Proper canopy shall be provided for E/P
positioner & other accessories as required.
7.5.7 The completer valve E/P positioner assembly shall be mounted on the valve body.
7.5.8 Mechanical Valve position indicator shall be provided to see the valve opening at field.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
7.5.9 The valve shall be supplied complete with tubing, fittings and E/P Positioner mounted on the
valve.
7.5.10 Solenoid valves, booster relay, air lock relay etc shall be supplied wherever required.
7.5.11 Air Filter shall have 5 μm sintered bronze / ceramic filter element as minimum with manual drain
and 2” dial pressure gauge unless otherwise specified.
7.5.12 The body/ housing material of filter regulator, solenoid valve, booster relay and air lock relay shall
be preferably stainless steel.
7.6.1 Radar level transmitter shall be used for Tank level measurement.
7.6.2 Radar level transmitter shall be selected for better accuracy with minimum beam angle. Accuracy
shall be +/- 3mm or better.
7.6.3 Radar level transmitter shall be 2 wire (loop powered), 24VDC, 4-20mA output, HART type. The
transmitter impedance shall be 600Ω or better.
7.6.4 The radar level transmitter shall be flanged end and if required stilling shall be provided. Suitable
canopy shall be provided to protect from direct sunrays.
7.6.5 Reflex type level gauge shall be used for clean & colourless liquids. Reflex type level gauge with
illuminator shall be used wherever required. The illuminator power supply shall be 230 VAC.
7.6.6 Level switch wherever specified shall be of displacer type or vibration type.
7.6.7 Displacer shall be designed for single phase liquid. Displacer switch selected shall be of high
integrity and suitable for LPG service
7.6.8 External cage type or Vibration fork level switch shall be used wherever it is not possible to keep
displacer internal to the vessel or for high turbulence service. Cage material shall be same as pipe
material. Refer Piping Material Specification for the selection of material of pipe.
7.7.1 On-Off Valve shall be used for isolation and on-off control application.
7.7.2 For on-off application, ball valve shall be used in general. Other type of valve may be used to fulfil
process requirement.
7.7.3 Floating ball design shall be used for 3" and smaller valves and in low pressure applications.
Trunnion style valves shall be used for 4" and larger valves. All shutdown and blow down valves in
hydrocarbon service shall be "fire safe" design. Floating ball valves shall meet the requirements of
API STD 607/BS 6755 part 2 and trunnion ball valves shall meet the requirements of API-RP 6F
or API-STD 607. Alternative valve types shall be considered in accordance with the project piping
material specification.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
7.7.4 For emergency shutdown application, solenoid pneumatically actuated on-off valves shall be
used. Solenoid valves (Direct acting type) shall be used as the pilot valve for operation of On/Off
valves. Solenoid valves, wherever used for on-off valves, shall be universal type three-way unless
otherwise specified. The solenoid valves shall be continuous rated type with class H coil
insulation as per IEC 85/IS 1271.
7.7.5 Solenoid valve shall be explosion proof low wattage type. Freewheeling diode shall be provided
across the solenoid.
7.7.6 Solenoid valves shall be in energized condition during normal operation. It shall have integral
junction box with 1/2" NPT (F) cable entry. Flying leads are not acceptable.
7.7.8 All shutdown valves shall be supplied with 2 nos. limit switches for valve position indications. Two
separate limit switches shall be used, one for "closed" position and one for "open" position. Limit
switches shall be SPDT type and gold plated hermetically sealed micro switch with explosion
proof certification.
7.7.9 All valves shall be fire safe design and shall meet the requirements of API-RP 6F or API-STD 607.
7.7.10 All Shutdown valve actuator shall be fire safe and stainless steel fire box shall be provided for the
safe operation.
7.7.11 Valve body & bonnet material, flange type, rating and finish shall conform to the piping
specification, however, the body & flange rating shall be minimum 300# as per ANSI. In general
all On-Off valves shall be flanged type as per ASTM A 16.5 and valve flange to flange distance
shall be as per ASTM A 16.10. Body material, rating of control valve and flange shall be in
accordance with the pipe specification.
7.7.12 The valve opening and closing times shall be reviewed and for critical applications where quick
closing is required, quick exhaust valves shall be provided. All accessories shall be neatly tube
and mounted in a control box adjacent to valve actuator.
7.7.13 All fire safe design of valve and fire box shall be suitable for jet fire for minimum 30 mins at
1100ºC.
7.7.14 Air Filter shall have 5 μm sintered bronze / ceramic filter element as minimum with manual drain
and 2” dial pressure gauge unless otherwise specified.
7.7.15 Location and orientation of valve actuators shall be such as to permit accessibility for manual
operation of the valve and maintenance of the actuator. Easy access to hand wheel, engaging
levers, valve position indication, and integral pushbuttons is also required. If these conditions
cannot be satisfied, permanent facilities shall be provided for operation/maintenance access.
7.7.16 The preferred mounting arrangement of the actuator is with the actuator horizontal and the limit
switch compartment horizontal or vertically up. If it is necessary to mount in any other position, the
mounting position shall be stipulated at the time of the order. Additional grease/oil may be
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
required. Mounting positions which would cause vulnerable areas of the actuator (motor and limit
switch compartment) to be saturated with lubricant if a failure occurs, should be avoided.
7.7.17 The dimension of the working space in the direction of access to electrical parts likely to require
examination, adjustment, servicing, or maintenance while energized shall be a minimum clear
distance of at least 3 feet (900mm). This dimension shall be measured from the enclosure front or
other opening. In addition, the work space shall not be less than two and one half feet (0.75 m)
wide in front of the electrical equipment.
7.8.1 Relief valves shall be of the conventional type or balanced bellows type, depending on the
process conditions. Sizing shall be in accordance with API RP 520 Part-I & API RP 521.
7.8.2 All flanged relief/ safety valves shall be as per API 526 for valve inlet & outlet size, orifice design,
etc.
7.8.3 Pressure relief valves shall be full nozzle full lift type except for thermal relief valves.
7.8.4 The pressure relief valves shall be type tested for capacity with 5% blow down as per ASME sec
VIII UG-131 and the actual blow down of individual valves shall meet the process requirement.
7.8.5 Conventional valves shall be specified for constant back pressure while bellows seal type valves
shall be specified for variable back pressure more than 10% of set pressure. Pilot operated
pressure relief valves shall be used for special services and where set pressure is closer than
10% of the operating pressure, in general.
7.8.6 For all valves in gas, vapour or steam service with design code ASME Sec VII or Sec I, discharge
co-efficient of 0.975 as per API 520 shall be considered.
7.8.7 The body & flange material and rating shall be as per piping material specification. Nozzle, orifice
guide and spindle material shall be SS 316 as a minimum.
7.8.8 Body drain and plug shall be provided for all pressure safety/ relief valves.
7.8.9 All gaskets shall be PTFE. Gaskets with asbestos filler or with asbestos bearing material shall not
be used.
7.8.10 Valve Spring shall be selected suitably to permit +/- 5% adjustment of the set pressure.
7.8.12 Bonnet shall closed type for all pressure relief/ safety valve in hazardous area service.
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
7.8.13 Test gag shall be provided with pressure relief/ safety valves.
7.8.14 Spring material shall be zinc or nickel plated carbon steel for temperature up to 250ºC and
tungsten allow steel shall be used for temperature above 250ºC.
7.8.15 For thermal relief, ¾” x 1” threaded modified nozzle type valve shall be used.
Following power supply voltage level shall be used, unless specified otherwise.
All field instruments shall be furnished with a Stainless steel corrosion resistant nameplate
permanently fastened with screws and stamped as follows:
Manufacturer’s name
Model number
Serial number
PO Number
Supply voltage
Operating range
Calibrated range
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
Output
Pressure rating
10.1 4 / 8 tap prefabricated air manifold fitted with SS 316 1/2 NPT (F), 3000# ball valve shall be
provided.
10.2 All valve & manifolds shall be forged type. Air manifold made out of 2" SS 304 pipe.
10.3 At air inlet 1" SS 304 flange (150#, RF) ball valve & at drain 1/2" NPT (F) ball valve shall be
provided.
10.4 Necessary clamp, nuts, bolts, SS tag plate (for air manifold and individual distribution line.
i.e. 4 / 8 air distribution tapings) and all other required fittings(if any) shall be in the scope of air
header fabricator/ vendor.
10.5 Packing material shall be PTFE. Blind Plug shall be provided for unused spare tapings
Please refer to the Reference Drawing Doc No. TCE.M2-IC-IN-ICE-01 in the attachments. This
shows the complete earthing scheme of the plant.
A separate bus bar insulated from panel framework but otherwise similar to above shall be
provided for terminating shields of all signal cables and safety barrier earth.
A minimum of 15 tapings with screws shall be provided on the bus bar.The signal earth shall be
electrically insulated from panel, structure,equipment, incoming cable tray, armor of cable, etc.
and shall be used for shields and grounding wires of signal cables, barrier earth etc.
All metallic cases/frames of relays, instruments, other panel mounted equipment shall be
connected to the safety ground bus and shields & drain wires of signal/control cables shall be
OWNER ENGINEERING CONSTRUCTION CONTRACTOR ENGINEERING
CONSULTANT CONSULTANT DETAILED ENGINEERING FOR SUBCONTRACTOR
connected to the system ground bus by independent copper wires of not less than 2.5 sq. mm.
The system ground bus shall be electrically isolated from AC mains earthing bus. The insulation
colour code for earthing wires shall be green with yellow bands.
11.4.1 For impulse tubing, tube shall be 1/2" OD x 0.065" thick ASTM A 269 SS-316 fully annealed, cold
drawn and seamless tubes as a minimum and instrument air tubing shall be ¼” OD X 0.049” thick
SS.
11.4.2 No pipe & pipe fittings shall be used. Galvanised forged screwed carbon steel screwed fittings of
2000 # rating fittings shall be used.
11.4.3 Hardness of tube and tube fittings shall be in range of HRB 70 to 79 and hardness of ferrules shall
be in the range of HRB 85-90 to ensure a hardness difference of the order of 5 to 10 between tube
and tube fitting for better sealing.
11.4.4 Fittings shall be double ferrule compression type consisting of two ferrules, nut and body with one
selected compression fitting manufacturer shall be used.
11.4.5 Nomenclature of all tube fittings shall be as per ISA RP 42.00.01 and threaded ends of fittings
shall be NPT as per ANSI B 1.20.1. Unless specified otherwise all fittings are of Swagelok / Parker
make or of equivalent make.
For hydrocarbon service, impulse line shall be made of 1/2" piping up to near to transmitter.
Transmitter shall be joined by a small portion of 1/2" SS 316 tubing.