Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Lubrication, Shaft-Sealing and Oil-Control Systems and Auxiliaries (Amendments/Supplements To Iso 10438)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 42

LUBRICATION, SHAFT-SEALING AND OIL-CONTROL

SYSTEMS AND AUXILIARIES


(AMENDMENTS/SUPPLEMENTS TO ISO 10438)

DEP 31.29.60.32-Gen.

January 2010

DESIGN AND ENGINEERING PRACTICE

This document is restricted. Neither the whole nor any part of this document may be disclosed to any third party without the prior written consent of Shell Global
Solutions International B.V., The Netherlands. The copyright of this document is vested in this company. All rights reserved. Neither the whole nor any part of this
document may be reproduced, stored in any retrieval system or transmitted in any form or by any means (electronic, mechanical, reprographic, recording or otherwise)
without the prior written consent of the copyright owner.
DEP 31.29.60.32-Gen.
January 2010
Page 2

PREFACE

DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of:
Shell Global Solutions International B.V. (Shell GSI)
and/or
Shell International Exploration and Production B.V. (SIEP)
and/or
other Shell Service Companies.
They are based on the experience acquired during their involvement with the design, construction, operation and
maintenance of processing units and facilities, and they are supplemented with the experience of Shell Operating Units.
Where appropriate they are based on, or reference is made to, international, regional, national and industry standards.
The objective is to set the recommended standard for good design and engineering practice applied by Shell companies
operating an oil refinery, gas handling installation, chemical plant, oil and gas production facility, or any other such
facility, and thereby to achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at
each locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs they shall be solely responsible for the quality of work and the
attainment of the required design and engineering standards. In particular, for those requirements not specifically
covered, the Principal will expect them to follow those design and engineering practices which will achieve the same
level of integrity as reflected in the DEPs. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting
from his own responsibility, consult the Principal or its technical advisor.
The right to use DEPs is granted by Shell GSI, in most cases under Service Agreements primarily with Shell companies
and other companies receiving technical advice and services from Shell GSI or another Shell Service Company.
Consequently, three categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or other Shell Service Company. The use of DEPs
by these Operating Units is subject in all respects to the terms and conditions of the relevant Service
Agreement.
2) Other parties who are authorized to use DEPs subject to appropriate contractual arrangements (whether as part
of a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI
disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or
person whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination
of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell
Service Company. The benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Service
Company, or companies affiliated to these companies, that may issue DEPs or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and
the DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be
returned after use, including any copies which shall only be made by users with the express prior written consent of
Shell GSI. The copyright of DEPs vests in Shell GSI. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this
requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
DEP 31.29.60.32-Gen.
January 2010
Page 3

TABLE OF CONTENTS
PART I INTRODUCTION ........................................................................................................4
1.1 SCOPE........................................................................................................................4
1.2 DISTRIBUTION, APPLICABILITY AND REGULATORY CONSIDERATIONS ..........4
1.3 DEFINITIONS .............................................................................................................4
1.4 CROSS-REFERENCES .............................................................................................5
1.5 SUMMARY OF CHANGES SINCE PREVIOUS REVISION.......................................5
1.7 COMMENTS ON THIS DEP .......................................................................................6
PART II AMENDMENTS/SUPPLEMENTS TO ISO 10438......................................................7
CHAPTER 1 GENERAL REQUIREMENTS ....................................................................................8
4. GENERAL ...................................................................................................................8
5. PIPING ........................................................................................................................8
6. INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS .........................11
7. INSPECTION, TESTING, AND PREPARATION FOR SHIPMENT .........................13
8. VENDOR'S DATA .....................................................................................................14
APPENDIX G DEFINITIONS AND EXAMPLES OF VITAL, ESSENTIAL AND NON-
ESSENTIAL SERVICES ...........................................................................................16
CHAPTER 2 SPECIAL PURPOSE OIL SYSTEMS ......................................................................17
4 GENERAL REQUIREMENTS...................................................................................17
5 PIPING ......................................................................................................................26
6 INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS .........................27
7 INSPECTION, TESTING, AND PREPARATION FOR SHIPMENT .........................31
ANNEX B PIPING AND INSTRUMENT DIAGRAMS ................................................................32
CHAPTER 3 GENERAL PURPOSE OIL SYSTEMS ....................................................................33
4 GENERAL .................................................................................................................33
5 PIPING ......................................................................................................................35
CHAPTER 4 SELF-ACTING GAS SEAL SUPPORT SYSTEM ....................................................36
4 GENERAL .................................................................................................................36
5 PIPING AND TUBING...............................................................................................36
6 INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS .........................38
7 INSPECTION, TESTING, AND PREPARATION FOR SHIPMENT .........................39
ANNEX B PIPING AND INSTRUMENTATION DIAGRAMS .....................................................40
PART III REFERENCES .........................................................................................................41
DEP 31.29.60.32-Gen.
January 2010
Page 4

PART I INTRODUCTION

1.1 SCOPE
This DEP specifies requirements and gives recommendations for lubricating oil, seal oil
and control oil supply systems and shaft sealing systems using self-acting gas seals and
auxiliaries. These systems may serve compressors, fans, centrifugal pumps, steam
turbines, gas turbines, expanders, gears and electric motors. This DEP does not apply to
shaft sealing for centrifugal pumps.
Notwithstanding the requirements of Chapter 1, Section 4.3.1 of ISO 10438, as
supplemented by this DEP, the Principal shall advise whether general-purpose
requirements or special-purpose requirements are to be applied to a particular piece of
equipment. This shall be indicated on the equipment data sheets.
This DEP is based on ISO 10438:2008. Part II of this DEP amends, supplements and
deletes various clauses/paragraphs of API 614. Clauses of ISO 10438 that are not
mentioned in this DEP shall remain applicable as written. This DEP shall be used in
conjunction with the data/requisition sheet relevant to the equipment it serves.
This DEP is a revision of the DEP of the same number dated November 2006; see (I-1.5)
regarding the changes.

1.2 DISTRIBUTION, APPLICABILITY AND REGULATORY CONSIDERATIONS


Unless otherwise authorised by Shell GSI, the distribution of this DEP is confined to Shell
companies and, where necessary, to Contractors and Manufacturers/Suppliers nominated
by them.
This DEP is intended for use in oil refineries, chemical plants, gas plants, exploration and
production facilities and, where applicable, suppy/distribution installations.
When DEPs are applied, a Management of Change (MOC) process should be
implemented; this is of particular importance when exisiting facilities are to be modified.
If national and/or local regulations exist in which some of the requirements may be more
stringent than in this DEP, the Contractor shall determine by careful scrutiny which of the
requirements are the more stringent and which combination of requirements will be
acceptable with regards to the safety, environmental, economic and legal aspects. In all
cases the Contractor shall inform the Principal of any deviation from the requirements of
this DEP which is considered to be necessary in order to comply with national and/or local
regulations. The Principal may then negotiate with the Authorities concerned, the objective
being to obtain agreement to follow this DEP as closely as possible.

1.3 DEFINITIONS
The Contractor is the party which carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier/Vendor is the party which manufactures or supplies
equipment and services to perform the duties specified by the Contractor.
The Principal is the party which initiates the project and ultimately pays for its design and
construction. The Principal will generally specify the technical requirements. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The lower-case word shall indicates a requirement.
The capitalised term SHALL [PS] indicates a process safety requirement.
The word should indicates a recommendation.
DEP 31.29.60.32-Gen.
January 2010
Page 5

1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets. Other documents referenced by this DEP are listed in
(Part III).

1.5 SUMMARY OF CHANGES SINCE PREVIOUS REVISION


The previous edition of this DEP was dated November 2006. The following are the main
changes.
Old New Section Change
Section
General Process safety requirements have been indicated by the use of the capitalised
term "SHALL [PS]"
Chapter 1
4.1 4.1 Deleted
4.2 4.2 Deleted
4.3.1 4.3.1 Deleted ref to DEP 31.29.40.30-Gen, generalized to API 617
5.1.2 5.1.2 Deleted Group II and III systems
Changed spec ref from DEP 31.28.01.11-Gen to DEP 31.28.01.12-Gen and DEP
31.28.01.15-Gen
Added “the Contractor shall extract the relevant Line Class specification(s) from the
DEP for inclusion in the RFQ or PO, rather than including the entire DEP”
Changed Tables ‘1A, 1B, 1C, 1D’ to ‘Tables 1, 2, 3, 4’
5.1.4 Added that all flanged connections terminate within the baseplate, to capture any
drips.
5.1.5 5.1.5 Deleted ref to DEP 31.29.00.10-Gen, generalized to API 686
5.1.12 5.1.12 Deleted
5.1.32 5.1.32 Added new para consistent with change to 5.1.2
5.2.7 Added requirement for 2 oil sample connections.
6.1.6 Deleted
6.2.1.2 Deleted ‘if specified’
6.3.2 Deleted clause re: switches in ISO
6.3.3.1 Deleted ‘if specified’
6.4.3 Re: thermowells – deleted reference to DEP 31.38.01.11-Gen
6.5.1 6.4.2 Added second sentence
7.2.1.1 7.2.1.1 Deleted requirement for Type 3.1B material certificates for Group II and III systems.

APP F Deleted
8.3.2 8.3.2 Added requirements for Dimensional Outline Drawing.
8.3.3 8.3.3 Only require welding procedures for auxiliary process systems for ANSI Class 900
and above
Chapter 2
1.1.14 4.1.13 Added points e – h; added ‘from the skid edge’ to point d
1.1.4 4.1.21 Re-located
1.1.16 Re: electrical reqmts
1.1.20 Deleted
1.1.22 4.1.19 Re: run-down tanks - deleted ref to DEP 31.29.40.10-Gen
1.1.25 4.1.22 Re-located
1.2.9 Deleted
1.3.4 Deleted
1.3.6.2.4 Deleted
4.3.5.2 Added ‘When extraction fans are required or specified, the number of fans, the
instrumentation, and the alarms and trips shall be mutually agreed between the
Buyer and Seller.
1.3.7.2 4.3.7.2 Added ‘3-phase (to facilitate the dis-abling of the heater on low oil level)’
1.4.1 4.4.1 Added ‘When centrifugal pumps are provided, experience has shown that system
stability is increased by running both pumps at all times.’
4.4.27.c Added requirement for non-sparking coupling guard.
1.4.24 Deleted
1.4.24.3 Deleted
1.4.25.5 7.3.3.1 Moved
1.5.3.4.2 4.5.2.2 Added ‘for pressures above ASME Class 300’
1.5.5 4.5.2.7 Added ‘for pressures above ASME Class 300’
4.5.4.4.b Deleted ‘If Specified’
1.5.8.3 4.5.1.17 Moved
1.6.3 4.6.5.b Moved
1.9.1.4.3 4.9.1.4.d Re: level gauges – deleted ref to DEP 31.38.01.11-Gen
1.10.3 Deleted
DEP 31.29.60.32-Gen.
January 2010
Page 6

1.11.4 Deleted
Table 1, Note Table 1, Deleted ref to DEP 32.80.10.10-Gen
5 Note 5
3.1.6 6.1.3 Moved
3.2 Moved to Ch 1
4.1.1 Moved to Ch 1
4.4 Deleted
Appendix A Annex B Fig 2A-17 / B.20 – added reqmt for TCV
Chapter 3
1.2.6 4.2.5 Re: noise reqmts - deleted ref to para in Ch 2, replaced with the text from Ch 2
1.2.13 Re: electrical reqmts
1.4.7.1.2 Deleted
4.5.4 Re: aux pump – delete ‘If Specified’
4.5.17 Added reqmt for non-sparking coupling guards.
4.6.1.2.f Re: cooling water parameters – delete ‘If Specified’
4.6.2.4 Require a TEMA datasheet
1.7 4.7 Re: filter requirements
5.1.3 Re: piping X-ray – delete ‘if specified’
Chapter 4
2.1.2 4.2.2 Deleted ref to DEP 31.29.40.10-Gen
2.1.13 4.2.7 Relocated
5.6 Re: seal welding of small bore threaded connections
2.3.1 Deleted
2.3.4 Deleted
4.3.3.1 Deleted
Table 1 Added S/D to lines 5-7 of Table 1
Appendix A Annex B Fig 4A-1/B.1 – added a flow element with transmitter for each seal. Changed
‘primary seal’ to ‘inboard seal’.
Fig 4A-3 / B.3 – changed ‘Should’ to ‘Shall’.
Fig 4A-6B / B.9 – added a flow element with transmitter for each seal
Fig 4A-7A /B.12 – added a PDIT between the secondary seal gas supply and the
secondary vent
References
Updated

1.7 COMMENTS ON THIS DEP


Comments on this DEP may be sent to the DEP Administrator at standards@shell.com.
Shell staff may also post comments on this DEP on the Surface Global Network (SGN)
under the Standards folder.
DEP 31.29.60.32-Gen.
January 2010
Page 7

PART II AMENDMENTS/SUPPLEMENTS TO ISO 10438

For ease of reference, the clause numbering of ISO 10438 has been used throughout
Part II of this DEP.
This part covers four chapters ofISO 10438:
- CHAPTER 1: General Requirements
- CHAPTER 2: Special Purpose Oil Systems
- CHAPTER 3: General Purpose Oil Systems
- CHAPTER 4: Self-Acting Gas Seal Support Systems
DEP 31.29.60.32-Gen.
January 2010
Page 8

CHAPTER 1 GENERAL REQUIREMENTS

4. GENERAL

4.3 SYSTEM SELECTION

4.3.1 Add to this clause:


The Vendor shall base his offer on the requirements and recommendations of the
appendices in Chapters 2, 3, and 4. The final selection of the system shall be subject to the
Principal's approval, irrespective of the schematics in the proposal.
Unless otherwise specified, lube and control oil systems are to be a single combined
system for driver and driven equipment, including intermediate transmissions, if applicable.
Gas turbine driven equipment shall be served by the gas turbine oil system, except for
aero-derivative gas turbine driven equipment, which may have separate oil systems for the
gas generator part and the driven equipment part.
Lube and control oil systems for aero-derivative gas turbine gas generators are designed
and constructed in accordance with Manufacturers' standards and, as such, may deviate
from this DEP. However, detailed exceptions and deviations shall be subject to the
approval of the Principal.

Special purpose oil systems in accordance with Chapter 2 are required for the following
equipment and services:
1. Lube and control oil systems for axial and centrifugal compressors in accordance with
ISO 10439 / API 617 irrespective of the driver type.
2. Compressor shaft seal oil systems.
3. Pressurized lube and control oil systems for all equipment in unspared essential
service.
4. All equipment driven by special purpose steam turbines or by gas turbines.

General-purpose oil systems in accordance with Chapter 3 are required for the following
equipment and services:
1. Pressurized lube and control oil systems for spared equipment in essential services,
driven by either an electric motor or a general-purpose steam turbine.
2. Lube and control oil systems for equipment in non-essential service.

For definitions of essential and non-essential service, refer to Appendix G.

Add new clause:


4.3.3 Seal oil systems SHALL [PS] be designed so that the release of process gas into
atmosphere is positively prevented.
If the process gas may not be contaminated by seal-oil, the design shall accommodate this
requirement by appropriate buffering and filtration.

5. PIPING
5.1 GENERAL

5.1.2 Add to this clause:


Auxiliary systems of Groups I shall be in accordance with the applicable piping class of
DEP 31.38.01.12-Gen or DEP 31.38.01.15-Gen as applicable (the Contractor shall extract
DEP 31.29.60.32-Gen.
January 2010
Page 9

the relevant Line Class specification(s) from the DEP for inclusion in an RFQ or PO, rather
than including the entire DEP).
Socket welded connections shall not be used in Group I and IV services. Threaded joints
may be used only for instrument connections and in tubing systems.
All oil and gas containing piping material of Groups I and IV shall be stainless steel; this
includes the supply and drain piping components connected to the main equipment casing
or bearing housing.

Tables 1, 2, 3, 4: replace gasket requirements by:


All flange gaskets shall be spiral wound, 316L, graphite-filled with an external centering
ring, 316L.
5.1.4 Add to this clause:
Flanged connections shall terminate within the baseplate so any liquid drips are captured
within the baseplate.

5.1.5 Add to sub-clauses b, d & e:


b) Piping shall be supported at least 1 inch above the console deck to facilitate wash down.
Piping shall be routed so that it does not create tripping hazards.
d) Piping Vent connections shall be DN20 (NPS 3/4 in) in size and shall have valves.
e) Piping Drain connections shall be DN20 (NPS 3/4 in) in size and shall have valves.
Add to this clause:
f) Pockets, traps, etc., which may collect debris and prevent thorough flushing and
drainage, shall be avoided.
g) Headers shall terminate with blind flanges to accommodate flushing and/or cleaning.
h) Strain-free piping shall be installed in accordance withAPI 686.
5.1.7 Replace this clause with:
Pipe bushings and unions shall not be used in piping systems. The use of couplings in
tubing systems shall be kept to a minimum.
Add to this clause
Swage fittings or reducer couplings shall be used. Reducer bushings shall not be used.
5.1.8 Add to this clause:
PTFE tape shall not be used as a thread sealant.
5.1.12 Add to this clause:

Tubing may be used only in Group II, III and IV systems in general purpose applications,
and only if approved by the Principal. The tubing shall be seamless stainless steel; it shall
have an outside diameter of 19 mm or 25 mm and a nominal wall thickness of 2.6 mm.
NOTE: The equivalent USC sizes are 3/4 in or 1 in outside diameter, respectively, with a nominal wall
thickness of 12 gauge (0.1046 in).

Unless otherwise specified on the data sheets, all compression fittings shall be of the
two-ferrule design. Tubing fittings shall be stainless steel.
Couplings in tubing systems shall not be located close to high-temperature equipment
components such as turbine casings or steam piping.

5.1.18 Add to this clause:


Stainless steel weld neck flanges, raised face, shall be used for all flanged connections in
pressurized oil lines. Stainless steel slip-on flanges are allowed in atmospheric oil drain
lines and reservoir connections.
DEP 31.29.60.32-Gen.
January 2010
Page 10

5.1.19 Replace this clause by:


All components shall be made of steel.
5.1.20 Replace this clause by:
Threaded or threaded seal welded pipe connections are not acceptable in any steam, oil or
gas application. Threaded (but not seal-welded) connections shall be permitted
downstream of instrument block valves.
5.1.21 Add to this clause:
All valves that are larger than DN 50 (NPS 2) shall be flanged, and all control valves shall
be flanged. Valves DN 100 (NPS 4) and smaller shall comply with ISO 15761. Valves larger
than DN 100 (NPS 4) shall comply with ISO 10434. Globe valves shall also comply with
applicable portions of ISO 15761 or ISO 10434.
NOTES: 1. API 600 is equivalent to ISO 10434.
2. API 602 is equivalent to ISO 15761.

5.1.30 In this clause, delete the words "If specified,"


5.1.32 Replace this clause by:
For Auxiliary Systems of Group I, valves shall be in accordance with purchaser specified
standards (refer to the relevant Piping Line Class) in addition to the mandatory
requirements of this part of ISO 10438.

5.1.33 In this clause, delete the words "If specified,"


Add new clauses:
5.1.35 Cadmium and Zinc plated studs, bolts, and nuts shall not be used.
5.2 OIL PIPING
5.2.1 Replace the last two sentences of this clause by:
Drain lines shall be connected individually to the return header at a 45 ° angle in the
direction of flow at a point above the header centreline. The minimum size for drain lines
shall be DN50 (NPS 2), unless otherwise approved by the Principal.
Add to this clause:
Drain lines shall not be reduced in size from the machine drain connection to the return
header. Branch connections (pressure and oil return) shall be flanged at the header and at
the machine. Branch pipe shall not be directly welded to run pipe. Tees shall be used.
NOTE: The hydraulic design of drain lines for gears with high pitch line velocities shall prevent the backing up of
drained oil into other components of the machine train.

Add new clauses:


5.2.5 Filter vent lines connected to the filter cover shall have flexible elements, such as stainless
steel hose, of adequate length so that the filter cover can be opened in order to replace the
cartridge. Pressure rating of flexible elements shall be a minimum of 1.5 times the pressure
rating of the filters.
5.2.6 Main oil supply header shall have DN 20 (NPS 3/4 in) flanged and blinded connections in
the top of the pipe just downstream of the lube oil filter and just downstream of each
pressure regulating valve. Connections shall be used to inject nitrogen to aid cleaning.
5.2.7 A minimum of two oil sample connections shall be provided on the oil console piping: one
on the supply piping between the supply pumps and the filters; and one on the return line
from the main equipment.
5.3 INSTRUMENT PIPING AND TUBING
5.3.2 Add to this clause:
DEP 31.29.60.32-Gen.
January 2010
Page 11

Instrument pressure connections to main headers shall be made with branch welding
fittings (weldolets).

Add new clauses:


5.3.4 A sampling connection with a needle valve shall be installed in the line downstream of the
filter. A block valve shall be installed to isolate this sampling connection.

5.4 Delete this clause

5.5 Delete this clause

6. INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS

6.1 GENERAL

6.1.2 Replace this clause by:


Unless otherwise specified by the Principal, the Vendor shall supply all on-skid
instrumentation, instrument piping, and cabling. Instrumentation of overhead and run-down
tanks shall be included.
The instruments shall include pressure and temperature indicators, pressure and level
transmitters, level switches, thermocouples and/or RTDs for indication, control, alarm
and/or shutdown functions as described in ISO 10438 as amended by this DEP.
Instruments and instrument signal lines shall be installed and lined up to a common junction
box on the edge of the base plate.
Instrument makes and types shall be subject to the approval of the Principal and/or shall be
chosen from a list of acceptable instruments which will be provided by the Principal. If the
supply of above instrumentation is deleted by the Principal on the data/requisition sheets,
only the instrumentation considered to be an integral part of the equipment shall be
supplied by the Vendor. Furthermore only the various instrument connections and level
indicators, as specified in this DEP, are required.
For procedures see DEP 32.31.09.31-Gen. and for connections see DEP 32.31.00.32-Gen.

6.1.4 Delete this clause

6.2 ALARM, SHUTDOWN AND CONTROL SYSTEMS

6.2.1.2 In this clause, delete the words "If specified,"

6.3 INSTRUMENTATION

6.3.2 Delete this clause

6.3.3 Transmitters

6.3.3.1 In this clause, delete the words "If specified,"

6.3.4 Temperature Indicators


6.3.4.2 Replace this clause by:
Temperature-sensing elements shall not be located in oil flow sight-glasses.
DEP 31.29.60.32-Gen.
January 2010
Page 12

6.3.7 Level instruments


Add to this clause:
Displacer operated type level switches shall not be used. Level switches shall comply with
DEP 32.31.00.32-Gen. Sensing elements shall be made of stainless steel.

6.3.8 Pressure Indicators

6.3.8.2 Replace this clause by:


Pressure gauges shall be in accordance with DEP 32.31.00.32-Gen.

6.3.9 Oil sight flow indicators

6.3.9.1 Replace this clause by:


Flow indicators shall be furnished in the atmospheric oil-drain return line from each bearing,
gear, seal, coupling guard and, if specified (refer to ISO 10438, Chapter 2, 4.4.17), from
each relief valve. Flow indicators shall not be installed in pressurized lines.

6.3.9.3 Replace this clause by:


Flow indicators shall have flanged connections, shall be of the bull’s eye type and shall
have a stainless steel body. Flow indicator sight glasses shall be made of non-flammable,
permanently transparent material.
Flow indicators with a threaded type sight glass in the drain line shall not be used.
Flow indicators shall be mounted outside noise enclosures, unless the enclosures are of
the “walk-in” type.
Flow indicators shall have a diameter not less that the inside diameter of the oil pipe.

6.3.10 Solenoid Valves

6.3.10.1 Add to this clause:


Solenoids shall have Class H high temperature coils.

6.3.12.5 Add to this clause:


e. Distributed Control System (DCS) shall not be used for controlling pressure-regulating
valves or the auto-start of a spare pump.

6.4 ELECTRICAL SYSTEMS


6.4.2 Add to this clause:
All electrical equipment shall comply with the relevant DEPs stated in the order. All
electrical components and installations SHALL [PS] be suitable for the area classification,
gas grouping and temperature class specified on the data/requisition sheet.
6.4.12 Add to this clause:
Vendor-supplied electrical devices that require external connections provided by the
Principal (except motor leads) shall be wired by the Vendor to terminal and junction boxes,
segregated by voltage level, and mounted at the edge of the console baseplate.
DEP 31.29.60.32-Gen.
January 2010
Page 13

7. INSPECTION, TESTING, AND PREPARATION FOR SHIPMENT

7.1 GENERAL

7.1.1 Add to this clause:


The Purchaser shall indicate whether, and to what extent, he will witness the
Manufacturer's quality control, inspection and testing. This may include, but need not be
limited to, the following:
- A check (against outline drawings which have been approved by the Purchaser) of all
main dimensions, base plate dimensions, location of foundation boltholes,
size/position/rating of flanges and coupling guard arrangement;
- An inspection of flange face finish;
- Verification that the Manufacturer has performed the specified inspections and tests with
satisfactory results;
- A verification of the required material certificates and (to the extent specified) their
traceability to the respective components;
- A visual check for good workmanship and clean finish of internals;
- Verification or witnessing of machinery alignment;
- Performance and functional testing of the complete unit.
- Ergonomically aspects verification.
The advance notice given by the Manufacturer to the purchaser shall be at least
five working days.

7.1.2 Delete from this clause the words “If specified,”

7.2 INSPECTION

7.2.1.1 Replace sub-clause a) by:


a) Material certificates
The Manufacturer shall furnish material certificates in accordance with ISO 10474, of the
type as specified in the table below.

CERTIFICATION OF MATERIALS BY COMPONENT


COMPONENT ISO 10474
CERTIFICATE TYPE
Pressure-containing parts (pump casings, 2.1 or 2.2
coolers, filter housings, valve bodies) and Group
II, III and IV oil piping, flanges and connections
up to a MAWP of 20 bar (ga).
Pressure-containing parts (pump casings, 3.1.B
coolers, filter housings, valve bodies) and Group
IV oil piping, flanges and connections with a
MAWP above 20 bar (ga).
Pump shafts and rotors 2.1 or 2.2
Mechanical seals 2.1 or 2.2
Bolting 2.1 or 2.2
All process and auxiliary piping, flanges and 3.1.B
connections of Groups I
DEP 31.29.60.32-Gen.
January 2010
Page 14

7.2.3.2 Add to this clause:


Multi-compartment reservoirs shall be witness inspected for cleanliness before the top plate
is finally installed and welded.

If specified on the datasheet, inspection of piping for cleanliness following flushing shall be
a HOLD point.

7.3 TESTING

7.3.1 General

Add new clauses:


7.3.1.3 The pressures of the lube, seal and control oil at delivery points shall be continuously
recorded during the test, including all transients (e.g., pump starts, filter switching, etc.)
introduced to the system and other observations.
7.3.1.4 If specified on the datasheet, a sound power level test shall be conducted during the
operational tests.

7.4 PREPARATION FOR SHIPMENT


7.4.3.a Add to this clause:
All carbon steel material shall be fully painted on all surfaces including plate surfaces
behind junction boxes supports and behind all other surface mounts.
7.4.3.b Add to this clause:
Material Safety Data Sheets shall be provided for all rust preventative materials used.
7.4.3.c Add to this clause:
The rust preventative shall be of the vapour space inhibitor type, e.g., Shell VSI Turbo 32 or
equivalent.

8. VENDOR'S DATA

8.1 GENERAL

8.1.3 Add to sub-clause g:


g. Schematics shall show line sizes and flange ratings.

8.2 PROPOSALS

8.2.3 Technical data


8.2.3.1 Add to this clause
The relevant data/requisition sheet(s) and API data sheets shall be completed to the fullest
possible extent.

8.3 CONTRACT DATA


8.3.2 Add to this clause:
Vendor shall supply ISA specification sheets for instruments and valves in his scope of
supply. Vendor shall complete datasheets.
DEP 31.29.60.32-Gen.
January 2010
Page 15

Dimensional outline drawing shall also include:


• Shell and tube heat exchanger bundle pull out dimension;
• Reservoir heater removal dimension;
• Cable tray and wiring routing, so that accessibility for maintenance can be
evaluated.
Schematic drawing shall also include:
• Line sizes and flange ratings;
• Relief valve settings;
• Control valve CVs; and
• The complete lube system for the equipment it serves.
8.3.3 Technical data
Add to this clause:
The information shall include the documents for controls and instrumentation as specified in
DEP 32.31.09.31-Gen.
The required number of copies of drawings and the time within which these have to be
submitted shall be specified in the order. Electronic drawings are acceptable in an agreed
format between the Vendor and the Purchaser and shall include, but not be limited to:
• Oil System Data Sheets;
• Pump Data Sheets (separate data sheets for each item);
• Steam Turbine Data Sheets (separate data sheets for each item);
• Motor Data Sheets (separate data sheets for each item);
• Heat Exchanger Data Sheets (separate data sheets for each item);
• Pressure Vessel Data Sheets (separate data sheets for each item);
• Instrument Data Sheets;
• Instrument Summary Sheets; and
• Alarm and Emergency System Tabulations.
As a minimum the following drawings (listed in ISO 10438, Chapter 1, Annex C) are
required for review and approval: a) to g), h) for auxiliary process systems of ANSI Class
900 and above, and n).

8.3.3.2 In this clause, delete the words "When specified,"

8.3.4 Progress reports


Add to this clause:
The required extent, frequency and details of reporting shall be specified in the order.
8.3.6 Installation, Operation, Maintenance and Technical Data Manuals

8.3.6.1 Add to this clause:


Separate manuals shall be provided for each oil system. An advance, generic version of
the manual shall be provided no later than ten weeks after receipt of order.
DEP 31.29.60.32-Gen.
January 2010
Page 16

Add new Appendix:

APPENDIX G DEFINITIONS AND EXAMPLES OF VITAL, ESSENTIAL AND NON-ESSENTIAL


SERVICES
SAFETY OTHER EQUIPMENT
EQUIPMENT
SERVICE CATEGORY
VITAL ESSENTIAL NON-ESSENTIAL
Non-spared Spared
equipment equipment
Definition A service in which A service in which A service in which All other services.
failure of equipment failure of equipment failure of
causes an unsafe renders a plant or equipment
condition of the plant process unit renders a plant or
or installation inoperable or process unit
resulting in jeopardy reduces inoperable or
to life and/or major performance to a reduces
damage (fire, level unacceptable performance to a
explosion etc.). to the Principal. level
unacceptable to
the Principal.
Selection Equipment shall be A decision not to Spare equipment Economic evaluation
Criteria adequately spared to install spare is normally required to justify spared
ensure 100% equipment is based installed where equipment.
availability of the upon economic potential losses
service under all considerations and due to equipment
circumstances proven equipment outage greatly
availability. Non- outweigh
spared equipment equipment Capex.
availability may be Sparing
upgraded by means philosophy shall
of additional Capex be economically
to match required evaluated and is
plant availability. typically
2 x 100 % or
3 x 50 %.
Driver Independent power Independent
Selection sources shall be power sources
Criteria selected to ensure may be selected,
100% service for start-up and
availability utility availability
reasons
Examples - Firewater pumps - Hydro-cracker - Boiler feed- - Drinking water pumps;
with diesel and feed pump; water pumps; - Sewage pumps.
motor drives; - Hydro-cracker - Fractionator
- Emergency shut- recycle bottom
down systems; compressor; pumps;
- Emergency - Cat-cracker - Hydro-cracker
instrument air main air fresh gas
compressor. compressor; compressors.
- Forced-draught
and induced-
draught fans.
DEP 31.29.60.32-Gen.
January 2010
Page 17

CHAPTER 2 SPECIAL PURPOSE OIL SYSTEMS

4 GENERAL REQUIREMENTS

4.1 GENERAL

4.1.1 In this clause, replace the words “5 years” by the words “6 years”

4.1.5 Replace this clause by:


4.1.5 Noise

4.1.5.1 Noise Control


The Contractor shall comply with DEP 31.10.00.31-Gen. and thereby communicate to the
Vendor the specified equipment noise limitations by using data sheet
DEP 31.10.00.94-Gen., which forms part of the requisition. The Vendor is responsible for
ensuring that these equipment noise limitations have been specified.

4.1.5.2 Information to be submitted with the tender


The Vendor shall submit guaranteed sound power levels and sound pressure levels of the
equipment, together with any other relevant information as requested in data sheet
DEP 31.10.00.94-Gen. The Vendor shall indicate what special silencing measures, if any,
are proposed in order to meet the specified levels.

4.1.6 Add to this clause:


Separate lube-oil and seal-oil systems are required if one or more of the following are
applicable:
a) Separate lube-oil and seal-oil systems SHALL [PS] be supplied if the equipment
served by the seal-oil system handles gases containing hydrogen sulphide and/or
other corrosive or hazardous gases (as indicated by the Principal on the
data/requisition sheet).
b) A steam turbine driver is specified as main equipment driver. In this case the control oil
for the turbine shall be taken from the lube-oil system. If applicable, control oil for
compressor control shall also be taken from the lube-oil system.
c) Separate lube-oil and seal-oil systems shall be supplied if all the following conditions
apply:
1) The main driver is an electric motor.
2) The main driver is lubricated from the compressor lube-oil system.
3) The process gas is flammable.
4) The system includes a degassing tank (in accordance with 1.11) which returns
the contaminated seal-oil direct into the main reservoir after degassing.
d) If specified by the Principal.
4.1.8 Add to this clause:
If specified by the Principal, the system shall also have sufficient turndown capabilities to
accommodate operation of part of the equipment served.

4.1.10 Add to this clause:


Start-up, parallel pump operation and "off-design" conditions (as indicated in the order)
shall be accommodated without affecting the mechanical integrity of the various
components in the system or exceeding its cooling capacity; this is particularly important in
high pressure systems.
DEP 31.29.60.32-Gen.
January 2010
Page 18

4.1.11 Replace the end of the last sentence by:


…with the compressor and the seal cavity at atmospheric pressure.

4.1.12 Add to this clause:


As a minimum the systems shall be suitable for unsheltered outdoor operation. The
anticipated weather and environmental conditions shall be indicated by the Principal on the
data/requisition sheets, and so shall the need for any special precautions (e.g.
"winterizing").
4.1.13 Replace this clause by:
Lubrication and shaft-sealing systems shall have sound mechanical design and orderly
arrangement. If possible, the Vendor's "standard" system shall be used. Design of systems
shall be subject to review by purchaser to ensure compliance with this DEP.
Oil systems shall conform to the data sheet and shall include the following features:
a. All instrustments shall be installed so that they can be read from an
operator-accessible location no more than 600 mm (2 ft) away.
b. Filters shall be located so there is free overhead space to replace the elements.
Personnel shall be able to switch and to replace filtering elements from an
operator-accessible location.
c. Piping, instrumentation, and other components shall not obstruct either side of the oil
pumps and drivers. Both sides of the pumps and drivers shall be clear for a minimum
distance of 750 mm (30 in). Piping shall not be run through this space above the
pumps and drivers.
d. Valves, control valves, and instrumentation shall be accessible from the skid edge for
operation and maintenance.
e. Junction boxes and Hand/Off/Auto switches shall be located so that they do not
obstruct access to equipment.
f. When heat tracing and insulation will be site-applied, ensure adequate spacing has
been allowed for the heat tracing and insulation.
g. When top-mounted pumps are supplied, piping layout should allow for vertical lifting of
the pump/motor assembly with minimal piping disassembly.
h. Consider arranging the immersion heater and shell-and-tube exchanger bundle pull out
zones in the same direction, to minimize maintenance space requirements.

4.1.16 Replace this clause by:


Oil systems with a pressure rating of ASME rating class 900 and higher shall have, as a
minimum, double block valves in the following services:
a) Pump discharge;
b) Cooler vents on the oil side
c) Filter vents;
d) Level gauges in pressurized services;
e) Isolation valves of control valves and instruments that are to be serviced during full
pressure operation of the system;
f) Isolation of seal oil traps.

4.1.19 Add to this clause:


Gravity fed rundown tanks shall be selected as a first option for emergency lube-oil supply.
If the appropriate sizing of a rundown tank becomes impractical or uneconomic, or if
extended cool down lubrication is required (i.e. for a gas turbine or steam turbine driver), an
emergency lube-oil pump, including a separate single filter, may be applied. Emergency
lube-oil pumps shall be driven from an uninterruptible emergency power supply. If the
available equipment space is limited (i.e. off-shore platforms), shaft driven lube-oil pumps
DEP 31.29.60.32-Gen.
January 2010
Page 19

for run-down purposes may be considered instead of run-down tanks. However these
alternative arrangements are subject to the approval of the Principal.
The design of seal oil systems SHALL [PS] be such that, upon seal oil supply failure, any
uncontrolled release of process gas from reference gas lines into the atmosphere (through
empty seal oil lines) is positively prevented.
Add new clauses:

4.1.21 This DEP requires various components to be provided in stainless steel. In this respect
stainless steel shall only be either AISI 316 L or AISI 316 Ti stainless steel or appropriate
equivalents according to internationally accepted standards.
The use of any other stainless steel of the AISI 300 series is subject to the approval of the
Principal.
Oil system components covered by this clause are:
- Strainers
- Reservoirs;
- Accumulators;
- Overhead tanks;
- Run-down tanks;
- Degassing drums and collecting drums;
- Piping;
- Flanges.
4.1.22 In oil systems with a pressure rating of ASME rating class 900 and higher, the welds in the
pressurized areas shall be subjected to 100 % radiography.
4.1.23 A high-fidelity dynamic simulation shall be conducted to verify the design performance for
special-purpose control oil, lube oil and seal oil systems. As a minimum, the high-fidelity
dynamic simulation shall incorporate detailed models for piping isometric arrangements
including pipe characteristics (connectors and capacity), heat exchangers, filters, detailed
control valve characteristics (including actuator dynamic characterization), oil pump
performance curves, electric motor/steam turbine driver inertia and other factors. The
Principal shall review and approve the methods used to conduct this high-fidelity dynamic
simulation. The dynamic simulation study shall demonstrate the following:
• Control oil, seal oil and lube oil pressures shall not drop below the midpoint between
the standby pump’s automatic-start setting and the equipment’s shut-down pressure
level during normal operations and during transient upset conditions. This includes
auto starting / manual shutdown of the spare oil pump(s), rapid control oil demand, and
switching of oil filters and coolers.
• Relief valves shall not lift or oscillate under normal and transient operations.
• The system should not cause a compressor trip or start the spare pump (if the main
pump is still running) during normal operations and during transient and upset
conditions if accumulators are NOT present.
4.1.24 Shop and/or field verification of the performance of the control oil, seal oil and lube oil
system shall be conducted. During these tests, various measurement points shall be
recorded with high-speed recorder(s). As a minimum, pressure measurements shall be
taken from the alarm and trip transmitters for each pressure level, the various pressure
level header transmitter locations, and at the autostart pump pressure transmitter(s).
Stroking of the control valves shall be measured to confirm the simulated stroke time and
valve performance. These tests shall be conducted with accumulators in operation and
again with them isolated from the system. The oil system performance shall be compared
with the dynamic simulation. The oil system shall be proven to be stable when switching oil
pumps, when tripping and auto-starting spare pump(s), when switching coolers and filters,
and when instantaneously full stroking the governor valves for steam turbine drivers. A
complete written report of the oil system test and comparison with the dynamic simulation
shall be provided following all of the tests and shall include copies of the high-speed
DEP 31.29.60.32-Gen.
January 2010
Page 20

recordings. The Principal shall be provided with this report for review and comment prior to
acceptance of the oil system.

4.2 BASEPLATES

4.2.1 Add to this clause:


The oil system shall be arranged in a single package, unless impractical on account of its
size. Subject to the approval of the Principal, oil systems of gas turbine driven units may be
integrated within the confines of the machinery base plate and include vertical tank
mounted oil pumps.
4.2.2 Replace this clause by:
Drain rim shall have a slope of 10 mm/m (1/8 in/ft) towards a single drain collection point.
The drain connection shall be at least DN50 (NPS 2) in size.
4.2.5 Add to this clause:
If approved by the Principal, the baseplate shall be supplied without a deck plate, i.e., open
deck design.
NOTE: Such a design makes field grouting easier: grout is simply poured into the open cavities and the grout
surface is finished by sealing with an epoxy sealant.

4.3 OIL RESERVOIRS

4.3.3 Oil connections and internal piping

4.3.3.3 Replace this clause by:


Each back-pressure control valve line and relief valve return line shall be separate and shall
discharge oil via internal piping below the pump suction-loss level as shown in Figure B.24.
Pressurised oil shall not be returned to stilling tubes or degassing trays. Internal piping shall
have bottom baffles. Internal piping of relief valve return lines shall be provided with a
internal vent hole above the highest oil level to facilitate emptying of the flow sight indicator
of the relief valve return line (see 4.4.17).

4.3.3.5 Replace this clause by:


All reservoir pipe connections shall be flanged.

4.3.5 Features and appendages

4.3.5.2 Replace this clause by:


Vents SHALL [PS] be provided to prevent over pressurizing of both lube-oil and seal-oil
reservoirs in the event of gross leakage of the compressor seals. These vents shall be
sized to handle the calculated gas flow or one standard pipe size larger than the respective
main oil return lines whichever is greater.
The reservoir vents SHALL [PS] be directed outside the immediate area of the oil systems,
and it shall be the responsibility of the Vendor with overall responsibility of the oil systems
to size the vents and to provide the flanged connections; however the vent lines themselves
and the required overpressure protection devices shall be supplied by the Contractor. The
design of the nitrogen purge on the reservoir shall take this device into account.
When extraction fans are required or specified, the number of fans, the instrumentation,
and the alarm and trips shall be mutually agreed between the Buyer and Seller.
DEP 31.29.60.32-Gen.
January 2010
Page 21

4.3.7 Heating
4.3.7.2 Replace this clause by:
Unless otherwise specified, reservoirs heaters shall be electric, 3-phase (to facilitate the
dis-abling of the heater on low oil level).

4.3.7.5 Add to this clause:


Electrical heaters shall be provided with a thermostatic temperature control and a separate
over-temperature protection shutdown function. These control and protection functions may
be integrated in the heater. In addition, heaters shall also have an external shutdown
function upon low-level alarm of the oil reservoir.
4.3.9 Replace this first sentence of this clause by:
Above the rundown oil level, each reservoir shall be provided with two flanged welded stub
connections at least DN25 (NPS 1) in size with blind flanges.
4.3.10.1 Replace this clause by:
When the oil system supplies a steam turbine, or when specified, the vendor shall provide
a 25mm (1 in) flanged, valved and blinded connection (see Figure B.24, Footnote I),
located below the pump suction level for use as an oil supply connection for an oil
conditioner.

4.3.12 Special features


Replace this clause by:
If the top of the reservoir is 1 m (3 ft) or more above grade, the reservoir shall be provided
with the required facilities of 4.13.12.1 a) – c).

4.4 PUMPS AND PUMP DRIVERS

4.4.1 Add to this clause:


Unless otherwise specified, rotary positive displacement pumps are required. Pumps that
are mounted externally from the reservoir shall be of the horizontal type, and shall operate
at 1500 r/min or 1800 r/min. If this is impractical for high-pressure seal oil pumps, higher
speeds may be applied if approved by the Principal.
If centrifugal pumps are specified, they shall comply with DEP 31.29.02.30-Gen. When centrifugal
pumps are provided, experience has shown that system stability is increased by running both
pumps at all times.

4.4.4 Add to this clause:


Mechanical seals shall have a balanced face design.

4.4.9 Replace this clause by:


Electric motors shall comply with DEP 33.66.05.31-Gen.

4.4.10 Replace this clause by:


Steam turbines shall comply with DEP 31.29.60.30-Gen. and shall be equipped with a
NEMA class “A” oil relay governor, as specified in API 611.

4.4.11.b Replace this clause by:


Each pump shall be capable of supplying the normally required oil flow at the design supply
temperature plus the following:
a) 20 % of the normal flow or 40 l/min (10.5 U.S. gal/min), whichever is greater;
b) All transient control oil, lube oil and/or seal oil requirements of the system.
DEP 31.29.60.32-Gen.
January 2010
Page 22

The above requirement shall include the equipment Manufacturer’s allowance for normal wear.
Accumulator capacity shall not be utilized to meet the transient oil capacity requirements, except
for when pumps are being switched over. The equipment Supplier shall provide all details of the
transient conditions. If the main oil pump is shaft driven, the pump capacity shall be sufficient to
meet the requirements of this clause at the minimum operating speed of the main equipment.
4.4.11.e Add to this clause:
Rotary pumps shall be able to operate continuously at 100 °C (210 °F) oil temperature and
corresponding viscosity without any contact between the pump rotor and the casing.
4.4.13 Add to this clause:
Motors shall meet the following additional requirements:
c) Motor horsepower and starting torque shall be adequate for pumping oil at a viscosity
corresponding to the minimum ambient temperature shown on the data sheets
regardless of the effect of the lube oil heater.
d) Standby pump motor shall have a space heater that is energized when the motor is not
running. The motor shall have a space heater disconnect switch.

4.4.17 Add to this clause:


Relief valves shall be installed in an upright vertical position. The valve body shall be steel
and shall have flanged connections.
Relief valve discharge lines shall be individually routed back to the main oil reservoir and
shall be provided with a flow indicator, which shall be installed above the highest oil level in
the main reservoir.
4.4.21 Add to this clause:
Temporary fine mesh screen shall not be installed on strainers.
4.4.25 Replace this clause by:
The standby (or auxiliary) pump shall be equipped with a "Manual-Off-Automatic" switch.
The switch shall be spring loaded so that it requires to be locked to stay in the "off" position.
The standby pump shall start automatically upon system pressure falling to a
predetermined "alarm" level. Once started, the standby pump shall remain running until
manually stopped. On gas turbine driven installations alternative methods are acceptable.

4.4.26 Add to this clause:


The use of booster pumps requires the explicit approval of the Principal.

4.4.27.c Add to this clause:


Non-sparking guards of agreed material shall be supplied.

4.4.28 Replace the first sentence of this clause by:


Unless otherwise specified by the Principal, couplings shall be flexible all-metal
non-lubricated disk or membrane type with spacer.

4.4.32.d Replace this clause by:


Pumps and drivers shall be mounted on a separate sub-base on the system console.

4.5 COOLERS.

4.5.1.3 Add to this clause:


When air-coolers are specified, they shall comply with DEP 31.21.70.31-Gen.
DEP 31.29.60.32-Gen.
January 2010
Page 23

4.5.1.13.b Replace this clause by:


Thermostat temperature control valves shall not be used in special-purpose oil systems.

4.5.1.15 In this clause, delete the words “If specified,” and replace the words 150 °C (300 °F) with
175 °C (350 °F)

4.5.1.17 In this clause, delete the words “If specified,”

4.5.1.19 Replace this clause by:


Each vent on the oil side shall be valved and provided with an orifice, a return line and a
flow indicator back to the reservoir.
Vents on the waterside and all drains shall be valved and provided with blinds.

4.5.2.2 Add to this clause:


Shell-and-tube coolers for pressures above ASME Class 300 shall comply with
DEP 31.21.01.30-Gen.

4.5.2.7 Add to this clause:


For pressures above ASME Class 300, cooler materials shall comply with
DEP 31.21.01.31-Gen.

4.5.4.4.b In this clause, delete the words "If specified,"

4.6 FILTERS

4.6.4 Replace this clause by:


Each filter vent shall be valved and provided with an orifice, a return line and a flow
indicator back to the reservoir.
A nitrogen connection with valve on the top of each filter housing shall be furnished.
If specified, filter housing clean drain and vent connections shall be routed back to the main
lube oil reservoir through sight flow indicators. Otherwise the drains shall be valved and
provided with blinds.
NOTE: Nitrogen shall be used to pressure oil from the filter housing through the drain line back to the
reservoir.

4.6.5.e Replace this clause by:


Single filter elements of the adequate length shall be supplied.

4.6.5.b In this clause, replace the words “with purchasers approval” with “with Principal’s approval”.
4.6.9 Add to this clause:
The access area for filter maintenance shall be a minimum of 600 mm x 600 mm
(2 ft x 2 ft).

4.7 TRANSFER VALVES

4.7.1 Add to this clause:


Only individual transfer valves (Figure B.20) shall be used.
For systems with a pressure rating of ASME rating class 900 and higher, transfer valves
shall be double executed.
DEP 31.29.60.32-Gen.
January 2010
Page 24

4.7.4 Replace this clause by:


In systems with a pressure rating of ASME rating class 900 and higher, spectacle blinds
shall be used for tight shut-off purposes to facilitate maintenance.

4.8 ACCUMULATORS.

4.8.2 Add to this clause:


The sizing of the accumulator shall take into account a minimum delay of a two second
response time of the logic control system before the stand-by pump motor is actually
started.

4.8.3 Replace this clause by:


Accumulators shall be of the bladder type. The vessels shall be made of stainless steel.
The bladders may only be pre-charged with dry nitrogen. The pre-charge pressure shall be
indicated on the vessel.
Unless otherwise specified by the Principal, bladder accumulators shall have pre-charge
facilities (see Figure B.18). The pre-charge facility shall be removable and in accordance
with the Manufacturer’s standard. If the nitrogen supply pressure exceeds the maximum
allowable working pressure of the accumulator vessel, the pre-charging facility shall be
equipped with a safety relief valve to prevent over pressurizing of the accumulator.
Accumulator nameplates shall state the normal operating oil pressure, the maximum
allowable working pressure and the required nitrogen pre-charge pressure.

4.8.5 Delete this clause

4.8.8 Replace this clause by:


If the specified minimum ambient temperature is lower than the minimum oil temperature
required by the Manufacturer for proper functioning of the oil system, the accumulator shall
be equipped with thermostatically controlled electrical tracing and insulation.

4.8.12 Add to this clause:


Accumulators shall be provided with a block valve and a drain valve to permit removal
during operation of the oil system.

4.9 OVERHEAD TANKS

1.9.1 Seal oil tanks


4.9.1.1
Add to this clause:
Overhead tanks, including the oil and reference gas lines, shall be insulated and heat
traced (either electrically or by steam).

4.9.1.2 In the first sentence of this clause, replace the words "3 minutes" by the words "8 minutes"
Add to this clause:
The vendor shall specify the overhead tank elevation and corresponding interconnecting
piping losses.

4.9.1.3 Replace this clause by:


Overhead seal-oil tanks shall be designed in accordance with the design code indicated by
the Principal on the data/requisition sheets. If ASME VIII is selected, they shall comply with
DEP 31.29.60.32-Gen.
January 2010
Page 25

DEP 31.22.20.31-Gen. If PD 5500 is selected, they shall comply with


DEP 31.22.10.32-Gen.

4.9.1.4.d Replace this clause by:


For oil systems with a pressure rating of ASME rating class 600 and lower, a full-length
level gauge arrangement shall be provided, covering the range from 25 mm (1 in) above
the high-level alarm (or trip) to 25 mm (1 in) below the rundown level. For systems with a
pressure rating of ASME rating class 900 and higher, the Manufacturer shall provide an
alternative level instrument arrangement suitable for the prevailing pressure rating.
Proposals are subject to the approval of the Principal.
Add to this clause:
Plate-type level gauges are not allowed. Magnetic type level gauges, with DN 20 flanged
vent and drain connections, shall be used.
4.9.1.4.h Add new clause:
For direct contact seal-oil overhead tanks, the piping and level control system shall be
arranged so that seal oil continuously flows through the tank.

4.9.1.5 Replace this clause by:


If the specified gas or gases contain abrasive or corrosive elements or elements that
negatively affect the oil properties (see NOTE below), the seal oil overhead tank shall be
separated from the seal oil supply line by one or more bladder-type accumulators in
accordance with Figure B.17.
The bladder material shall be fully compatible with the process gas.
NOTE: It is impossible to state precise allowable levels in this DEP. In all cases, the Principal shall be
consulted.

4.9.2 Lube-oil rundown tanks


4.9.2.1 Replace this clause by:
The design shall be based on providing adequate lube oil in the event of an oil system
failure so that the rotor can coast down to a complete stop without the shaft journals or
bearings being damaged. The tank shall provide full lube oil flow to all train components
until the speed slows down to approximately 10 % of the normal operating speed but for no
less than 3 min. The coast down time of the machinery train shall be reviewed with the
Purchaser before the method of protection and tank sizing are finalized.
Run-down tanks serving steam turbines shall be insulated and heat traced (either
electrically or by steam) to bearing oil supply temperature.
NOTE: Reference figures of ISO 10438 are B.15 and B.16.

4.9.2.2 Add to this clause:


The bottom outlet connection of emergency lube oil run-down tanks shall extend at least
25 mm (1 in) inside the vessel in order to retain foreign matter. In addition, a flush-mounted
DN 50 (NPS 2) flanged drain connection shall be provided.

4.9.2.4 Replace this clause by:


If pressurized tanks are specified, they shall comply with (4.9.1.3).
DEP 31.29.60.32-Gen.
January 2010
Page 26

4.10 SEAL-OIL DRAIN TRAPS

Add new clause:

4.10.8 Seal trap materials shall be subject to the same requirements as the compressor materials
in contact with the process gas.

4.11 DEGASSING DRUM

4.11.1 Replace this clause by:


Unless otherwise specified by the Principal, degassing facilities shall be provided if the
contaminated seal oil does not contain corrosive elements and can be restored to original
'clean' reservoir conditions by degassing only. Proven types are required. The Manufacturer
shall provide full technical details of the proposed system, including references, in his
proposal. The drum and internals shall be made of stainless steel.
If corrosive elements or any other constituents that may affect a proper degassing of the
contaminated oil are present, a collecting tank for the contaminated seal oil shall be
supplied instead of degassing facilities. The collecting tank shall be sized to hold at least
the quantity of four days' normal seal oil consumption of the compressor, with a minimum
of 400 litres (105 gallons). With the exception of the heater and the nitrogen degassing
arrangement (4.11.2), the collecting tank shall comply with all requirements for degassing
drums.
Unless otherwise specified by the Principal, degassing drums and sour seal oil collecting
tanks shall be designed for a minimum pressure of 3.5 bar(g) (55 psig).
If separate seal oil recovery facilities are specified, packaged seal oil recovery units shall be
supplied. These units, typically comprising a combined oil heating and vacuum stripping
system, are subject to the approval of the Principal.
The oil recovery unit shall utilize the same utilities as the oil system and its design shall
comply with the overall oil system requirements. As far as practical, the unit shall be
designed not to remove essential additives from the oil. The Manufacturer shall provide full
technical details of the proposed system, including references, in his proposal.

4.11.2 Add to this clause:


In order to enhance liquid-gas separation, the degassing drum shall be provided with an
inert gas (nitrogen) stripping arrangement, which consists of a perforated ring line on the
bottom of the tank.

4.11.5 In this clause, replace the words "4-hour" by the words “24-hour”

4.11.6 Delete from this clause the words "If specified,"

5 PIPING

5.1 General

Add to this clause:


In special purpose oil systems, all connections shall be welded and/or flanged. In these
systems, tubing and tube fittings shall not be used.
Connections to equipment shall be welded and flanged or machined, studded and flanged.
Welded fittings shall be butt-welded; socket welding shall not be used.
DEP 31.29.60.32-Gen.
January 2010
Page 27

5.3 Add to this clause:


Except for instrument connections, threaded connections shall not be used.
5.4 Add to this clause:
Process piping shall be in accordance with the applicable codes of the relevant process
system.

6 INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS

6.1 General
Add to this clause:
Any logical functions and/or respective actions that prevent the start of the spare oil pump
upon the loss of adequate bearing or seal oil pressure are not allowed. Systems shall be
designed so that upon loss of adequate lube/seal oil pressure auxiliary/emergency systems
will provide sufficient oil supply during run-down and cool-down of the relevant machinery
components under all circumstances. The decision to switch off the oil supply to the main
equipment shall be left entirely to the operating personnel.

6.1.1 Replace this clause by:


Unless otherwise specified by the Principal, the Vendor shall furnish as a minimum the
following for indication, alarm and/or shutdown purposes:
a) For pressure indication (valved and flanged connections required):
- Discharge of lube oil and seal oil pumps (upstream of discharge valves);
- Control oil, if applicable;
- Differential across lube oil and seal oil filters;
- Lube oil at the bearings;
- Seal oil at seals;
- Downstream of each pressure controller;
- Gas reference pressure;
- Seal oil to gas reference differential.
b) For temperature indication (thermowell connection required):
- Lube oil and seal oil at inlet and outlet of lube and seal oil coolers;
- Lube oil and seal oil reservoirs at pump suction location;
- Degassing drum;
- Lube and seal oil return lines from bearings and seals.
c) For level indication (including valved and flanged level indicator):
- Lube oil/seal oil reservoir;
- Contaminated seal oil separators;
- Seal oil overhead tank;
- Degassing drum or collecting tank;
d) For alarm and/or cut-in of stand-by pumps (connections required as under (a), (b), (c)):
- Low lube oil/control oil/seal oil pressures;
- High lube oil temperature downstream of cooler;
- Low level in seal oil overhead tank *;
- High level in seal oil overhead tank *;
- High seal oil temperature downstream of cooler;
- Low level in seal oil reservoir;
- Low level in lube oil reservoir;
- Low level lube oil emergency rundown tank;
- Seal liquid (in seal ring cavity) to gas reference differential pressure **;
- High level contaminated seal oil separators.
e) For shutdown (connections required as under (a), (b), (c)):
DEP 31.29.60.32-Gen.
January 2010
Page 28

- Low-low lube oil pressure;


- Low-low level in seal oil overhead tank *;
- High-high level in seal oil overhead tank if no accumulator is installed;
- Low-low seal liquid to gas reference differential pressure **.
* If liquid film seals are used.
** If mechanical contact seals are used.

Separate connections shall be provided for each of above functions.


For reference, Table 1 provides the minimum requirements for indicating, alarm and
shutdown functions.
DEP 31.29.60.32-Gen.
January 2010
Page 29

Table 1 Indicating, alarm and shutdown functions for special purpose oil systems
Local Remote Remote Main
Function (1) Display Display alarm equipment Other actions
(2)(3) (4) (4) shutdown (5)
1. Level (6)
1.1 Lube oil level
Reservoir(s) I I L L: Switch heater off
Emergency rundown tank(s) I L/H H: Start permissive
1.2 Seal oil level
Reservoir(s) I I L L: Switch heater off
Contaminated seal oil I I H
separator(s)
Seal oil Overhead tank(s) I I HH (7) HH (7)
H
L
LL LL L: Start stand-by pump
Degassing drum(s) or I I L L: Switch heater off
collecting tank(s)
2. Pressure (6)
2.1 Lube oil pressure
Pump(s) discharge I I H H: Running indication
Filter(s) differential I I H
Lube oil to equipment I I L L: Start stand-by pump
LL LL
Lube oil at the bearings I
2.2 Seal oil pressure
Pump(s) discharge I I H H: Running indication
Filter(s) differential I I H
Seal oil to equipment I L L: Start stand-by pump
Seal oil at seals I
2.3 Control oil pressure (8)
Control oil I I L L: Start stand-by pump
2.4 Gas reference pressure
Gas reference pressure I
Differential seal oil/gas I I L
reference LL(9) LL(9)
2.5 General
Downstream of each I
pressure controller
3. Temperature (10)
3.1 Lube oil temperature
Reservoir at pump suction I I
Cooler(s) inlet I
Cooler(s) outlet I I H
3.2 Seal oil temperature
Reservoir at pump suction I I
Cooler(s) inlet I
Cooler(s) outlet I I H
Degassing drum(s) I I H
Collecting tank(s) I
DEP 31.29.60.32-Gen.
January 2010
Page 30

NOTES: 1. The listed functions are to be considered as minimum requirements. IPF classification, if applied,
may set further requirements. The Vendor shall indicate in the proposal which permissives are
recommended for start-up.
2. Local display means that the information is available at a suitable and accessible location in the
vicinity of the equipment. It may be located on a free stand or a gauge board. Local panels should
not be used.
3. Separate connections shall be provided for local instruments and those for remote display.
4. Remote display/alarm at Principal’s control centre.
5. Separate process connections and transmitters for required for HH and LL functions and for
pre-alarm and shutdown functions.
6. Valved and flanged.
7. Only if no transfer barrier (bladder-type) is installed.
8. If applicable.
9. Only if mechanical contact seals are used.
10. Thermowell required.
Nomenclature for functions:
I = Indication of measured value
H = High alarm
HH = High-High alarm and shutdown of main equipment
L = Low
LL = Low-Low alarm and shutdown of main equipment

Add new clause:


6.1.3 The following are additional requirements:
a. Indicating transmitters may be used as an alternative to separate gauges and blind
transmitters for measuring pressure, temperature and levels.
b. Pump discharge pressure indicator shall be visible to the operator while starting
pumps.
c. For direct acting pressure control valves, the sensing point shall be as close as
possible to the valve itself. Sensing lines shall slope continuously from the sensing
point to the valve and shall have vents as required to permit complete filling of the lines
with liquid. If tubing is used for sensing lines, it shall be a minimum size of 12.7 mm
(1/2 in).

6.2 Replace this clause by:


Unless otherwise specified by the Principal, each alarm or shutdown function shall
comprise local or local panel-mounted electronic transmitters, which shall be connected to
the relevant alarm or shutdown system.
6.3.1 Replace this clause by:
Unless otherwise specified by the Principal, each alarm or shutdown function shall
comprise local or local panel-mounted electronic transmitters, which shall be connected to
the relevant alarm or shutdown system.
6.3.2 Delete this clause
6.3.3 Delete this clause

6.4 Add to this clause:


Arrangement 3 shall only be used if approved by the Principal.
DEP 31.29.60.32-Gen.
January 2010
Page 31

7 INSPECTION, TESTING, AND PREPARATION FOR SHIPMENT

7.1 General
Add to this clause:
Operational test shall be witnessed. Hydrostatic tests and preparation for shipment shall be
observed. Witnessing and observing parties shall be stated in the order.

7.3 Testing

7.3.3.11 In this clause, delete the words “If specified,”


DEP 31.29.60.32-Gen.
January 2010
Page 32

ANNEX B PIPING AND INSTRUMENT DIAGRAMS


Insert new clause:
SCHEMATICS
The following requirements apply to the selected figures:

Figure B.2 : The incorporation of booster pumps is only allowed if approved by


the Principal.
Figure B.3 : Note c: Option B is required.
Figure B.4 : Shall be used.
Figure B.5 : Shall not be used.
Figure B.10 : Note a: Unless otherwise specified, accumulators shall be bladder
type (B.18).
Fifure B.12 : Note f: Unless otherwise specified, accumulators shall be bladder
type (B.18).
Figure B.13 : Note a: Irrespective of the coupling type a coupling guard drain line,
including FG, shall be provided.
Figure B.14 : Note d: Option D is required.
Figure B.15 : Note a: Option A is required.
Note b: Sufficient vapour space above the permissive start level shall
be provided to prevent the tank from overflowing through the
atmospheric vent during the filling procedure.
Note c: Add to this note:
The filling valve and the drilled check valve shall be located on the
compressor deck adjacent to each other in an operator accessible
location.
Figure B.16 : This arrangement shall not be used, unless specifically approved by
the Principal.
Figure B.17 : Note a: Option A is required for separate seal oil systems.
Notes c & d: Options B and C SHALL [PS] be replaced by an LSHH
trip of main compressor driver if a direct contact type overhead tank
is used.
Note e: Option D: FC action required in the supply header.
Add: Note f: Refer to paragraph 4.9.1.4.h for configuration changes.
Figure B.19 : Note a: Option A: a constant pressure regulating system is required.
Figure B.20 : Note a: Option A, a TAH alarm function is required; depending on the
specified ambient conditions, a TAL alarm function may be required
as well.
Note c: Option C, a bypass line and a constant-temperature, two-way
control valve is required
Figure B.21 : Deleted.
Figure B.22 : Note b: Option A is required for oil systems with a pressure rating of
ASME class 900 and higher.
Note c: Option B: a transmitter is required.
Figure B.24 : Note k: Option F is required.
Figure B.26 : Shall not be used.
Figure B.27 : Shall be used.
Note a: Option B is required.
NOTE: Each instrument installed in the pressure measurement line shall have its own dedicated isolation and
bleed-valve.
DEP 31.29.60.32-Gen.
January 2010
Page 33

CHAPTER 3 GENERAL PURPOSE OIL SYSTEMS

4 GENERAL

4.1 BASIC DESIGN


Add to this clause:
Manufacturers may propose alternative options as upgrades to the basic system if required
or if offered as standard for the equipment served.

4.1.1 Add to this clause:


An external pressure lubrication system shall contain as a minimum the following
components:
a) Single pump, either shaft or electric motor driven. The pump casing shall be steel or
nodular cast iron. A suction strainer shall be provided.
b) A motor driven auxiliary oil pump shall be equipped with a "Manual-Off-Automatic"
switch to automatically start the pump on low oil pressure and manual shutdown only.
c) Valving in carbon steel with stainless steel trim.
d) Oil piping in stainless steel with carbon steel slip-on flanges in accordance with
ASME B31.3. Alternatively, stainless steel tubing and fittings may be offered.
Compression fittings shall be of the two-ferrule design.
e) Reservoir in stainless steel, either freestanding or integrated in the equipment base.
f) A single oil cooler. Internal oil coolers are not acceptable.
g) A duplex full-flow filter with replaceable elements.
h) Single regulator for the control of the delivered oil pressure.
i) Sight flow indicators in each bearing drain line.
j) As a minimum, the following instruments:
- A pressure gauge (valved for removal) for each pressure level, and a pressure
differential indicator to measure filter pressure drop
- Temperature gauges (with thermowells) in the reservoir, after the oil cooler, and in
each bearing drain line
- One local level indicator in the reservoir;
- One low pressure alarm and one low/low pressure shutdown function;
- One high temperature alarm function after the cooler;
- One low level alarm function in the reservoir.

4.2 GENERAL

4.2.5 Replace this clause by:


The Contractor shall comply with DEP 31.10.00.31-Gen. and thereby communicate to the
Vendor the specified equipment noise limitations by using data sheet
DEP 31.10.00.94-Gen., which forms part of the requisition. The Vendor is responsible for
ensuring that these equipment noise limitations have been specified.
The Vendor shall submit, with the tender, guaranteed sound power levels and sound
pressure levels of the equipment, together with any other relevant information as requested
in data sheet DEP 31.10.00.94-Gen. The Vendor shall indicate what special silencing
measures, if any, are proposed in order to meet the specified levels.
DEP 31.29.60.32-Gen.
January 2010
Page 34

4.2.9 Add to this clause:


As a minimum the systems shall be suitable for unsheltered outdoor operation. The
anticipated weather and environmental conditions shall be indicated by the Principal on the
data/requisition sheets, and so shall the need for any special precautions (e.g.
"winterizing").
4.2.11 Delete from this clause the words “If specified,”

4.4 OIL RESERVOIRS


4.4.2 Protection from dirt and water
Replace the second sentence of this clause with:
Top man way openings shall extend a minimum of 25 mm (1 in) above the top of the
reservoir to minimize the ingress of water and debris.

4.4.4 Manways and Drains


4.4.4.2 Delete the words in this clause: “If Specified,”
4.4.4.3 Delete the words in this clause: “If Specified,”

4.4.5 Features and Appendages


4.4.5.d Delete the words in this clause: “If Specified,”
4.4.5.f Delete the words in this clause: “If Specified,”
4.4.6 Capacity and Configurations
4.4.6.1 Delete the words in this clause: “If Specified,”
4.4.6.2.a Add to this clause:
The normal operating range between Maximum Operating Level and Minimum Operating
Level shall be a minimum of 2 min of normal oil flow.

4.4.7 Heating

Replace the first sentence of this clause by:


If the specified minimum ambient temperature is lower than the minimum oil temperature
required by the Manufacturer for start-up of the main equipment, an electric heater shall be
provided, in accordance with the following:

4.4.7.a Add to this clause:


Electric heaters shall be provided with a thermostatic temperature control and a separate
over-temperature trip. Heaters shall also be interlocked with the low level alarm of the
reservoir.
4.4.9 Plugged Connections
Add to this clause:
Plugs in reservoir connections shall be made from stainless steel.

4.4.11 Materials
4.4.11.3 Replace this clause by:
Reservoirs integral with the baseplate shall be fabricated from stainless steel. If this is not
possible a separate reservoir shall be provided.
DEP 31.29.60.32-Gen.
January 2010
Page 35

4.5 PUMPS AND PUMP DRIVERS

4.5.1 Add to this clause:


Rotary positive displacement pumps shall be used. The use of centrifugal pumps is subject
to the approval of the Principal.
4.5.4 Delete the words in this clause: “If Specified,”

4.5.5 Replace this clause by:


Electric motors shall comply with DEP 33.66.05.31-Gen.
4.5.8 Add to this clause:
Motors shall meet the following additional requirements:
a) Motor horsepower and starting torque shall be adequate for pumping oil at a viscosity
corresponding to the minimum ambient temperature shown on the data sheets
regardless of the effect of the lube oil heater.
b) Standby pump motor shall have a space heater that is energized when the motor is not
running. Motor shall have a space heater disconnect switch.

4.5.17 Replace this clause by:


Removable non-sparking coupling guards of an agreed material shall be supplied.

4.5.18 Replace this clause by:


The use of elastomeric couplings is subject to the approval of the Principal. When
elastomeric couplings are not acceptable to the Principal, couplings shall be flexible all-
metal non-lubricated disk or membrane type with spacer.

4.5.18.a Replace this clause by:


Couplings and coupling-to-shaft junctions shall be rated for at least the nominal driver
power with a minimum service factor of 1.5.

4.6 COOLERS
4.6.1.2.f Delete the words in this clause: “If Specified,”
4.6.1.3 Delete the words in this clause: “If Specified,”
Add new clause:
4.6.2.4 The Supplier shall provide a TEMA datasheet for the cooler when submitting the
Component Datasheets (10438-1 Annex C).

4.7 FILTERS
4.7.7.L Delete the words in this clause: “If Specified,”

5 PIPING

5.1 GENERAL
5.1.3 Delete the words in this clause: “If Specified,”
DEP 31.29.60.32-Gen.
January 2010
Page 36

CHAPTER 4 SELF-ACTING GAS SEAL SUPPORT SYSTEM

4 GENERAL

4.2 BASIC DESIGN

4.2.1 In this clause, replace the words “5 years” by the words “6 years”.

4.2.2 Replace this clause by:


The compressor Manufacturer shall hold unit responsibility for the total scope of supply of
the compressor system, including the Dry Gas Seal system.
All Vendors and sub-suppliers of the gas seal support system and its components shall be
approved by the Principal.

4.2.4 Add to this clause:


As far as possible, the layout should be such that the functions of control valves and
changeover valves for spared items are clearly evident and the valves themselves are
easily accessible.
The location and arrangement of the DGS module or modules shall not cause obstruction
to normal operation and maintenance of the compressor. Maintenance, particularly of the
compressor bearings and seals, shall be possible with a minimum of disconnections.

4.2.5 Add to this clause:


f. Pressure fluctuations in flare and vent systems.
The seal gas support system shall be capable of providing the required service for the dry
gas seals in a fully automatic mode for any combination of the conditions, mentioned under
“a.” through “f”.

4.2.7 In this clause, replace the words “20 K (35 R)” by the words “30 K (55 R)”.
4.2.11 Replace this clause by:
For systems with a pressure rating of ASME class 900 and higher, double block and bleed
valves shall be installed for isolation of a component. Arrangements shall be in accordance
with the applicable process piping specification.

4.2.14 Replace the first sentence of this clause by:


The Manufacturer SHALL [PS] advise the Purchaser of any special provisions that are
required to maintain shaft seal and seal system integrity in the event of a failure in the seal
gas or buffer gas supply system. Temporary supply pressure fluctuations shall be taken
into account. The dry gas seal Manufacturer shall review these provisions and guarantee
the proper function of the seal and its components with these provisions.
Add new clauses:
4.2.18 Panels shall be in accordance with DEP 32.31.09.31-Gen., Instrumention for Packaged
Units. Panels shall have a system schematic on the front. All devices in the panel shall
have a stainless steel tag attached bearing the Principal’s tag number.

5 PIPING AND TUBING

5.2 Replace this clause by:


Unless otherwise specified, all gas flow lines in gas seal support systems with a maximum
allowable working pressure below 62 bar (ga) shall be manufactured of austenitic stainless
steel piping.
DEP 31.29.60.32-Gen.
January 2010
Page 37

Tubing may be used if approved by the Principal.


If approved, tubing shall be seamless stainless steel with a nominal wall thickness of:
Tubing outside diameter Nominal wall thickness
12.7 mm (1/2 in) 1.6 mm (0.0673 in)
19 mm (3/4 in) 2.6 mm (0.1046 in)
25 mm (1 in) 2.9 mm (0.1196 in)
NOTE: The above units are not exact conversions, they are the nominal sizes and thicknesses in
metric (SI) tubing and US Customary (inch) tubing. For example, a nominal thickness of
0.1196 in is a standard thickness and is the same as 11 gauge.

Tubing smaller than 12.7 mm (1/2 in) shall not be used. During installation of all fittings a
ferrule setting tool shall be used. All fittings shall be stainless steel and of the two-ferrule
design.

5.4 Add to this clause:


The first block valve directly mounted on the process piping shall conform the applicable
piping class. All valves shall have stainless steel bodies and trims, unless incompatible with
the process gas.

5.5 Replace the words “steel bodies” by “stainless steel bodies”


Add new clause:

5.6 Replace the second sentence of the NOTE in this clause by:
Seal welding is not an acceptable alternative.
5.7 Vent and drain lines shall slope away from the seal to ensure liquid drainage even if the
gas is specified as bone dry. The vent and drain lines shall have the same rating as the
compressor casing.

4.3 GAS FILTERS

4.3.1.4 Replace this clause by:


Filter housing construction

4.3.1.4.1 Gas filters shall have bolted covers. All connections to gas filter housings shall be welded
and flanged or machined and studded for a flanged connection. Screwed connections shall
not be used.

Add new clause:


4.3.1.4.2 Filters shall be double with a full flow transfer valve and valved and flanged drain and vent
connections.

4.3.1.5 Add to this clause:


O-rings, if applied, shall be resistant to explosive decompression.

4.3.2.1 Replace in this clause the word “twice” by the words “three times”
DEP 31.29.60.32-Gen.
January 2010
Page 38

Add new clause:


4.3.2.3 Filters shall be sized to provide at least 4 000 hours of service before replacement and/or
cleaning of elements is required.

4.3.3 Coalescing Filter Sizing


Add to this clause:
In the seal, buffer, and separation gas systems (if condensation is possible), and in
compressors that need to be liquid washed or otherwise have liquid regularly injected, the
filters and all piping downstream of the filter shall be suitably heat traced. In addition,
suitable coalescer separators shall be applied.
4.3.1.1 Replace this clause by:
The coalescing filter shall have a minimum efficiency of 98.7 % on particles less than or
equal to 2 µm (β2 ≥ 75) and shall be in accordance with the dry gas seal manufacturers
requirements.

4.4 TRANSFER VALVES


4.4.1 Add to this clause:
Two filters in parallel shall have the necessary valving, so that one filter can be taken out of
service, depressurized, and its element replaced with the compressor on line.
Double-block-and-bleed valving is required.

4.4.2 Replace this clause by:


Transfer valves shall have stainless steel bodies and internals.
For systems with a pressure rating of ASME rating class 900 and higher, double transfer,
vent and drain valves shall be installed.

4.5 CONDENSATE TRAPS

4.5.2 Delete this clause

4.5.3 Replace this clause by:


Automatic condensate traps are required. Mechanical float type traps may be used for gas
pressures up to 50 bar(g) (725 psig). Unless otherwise specified, the float and trim of these
traps shall be of the single lever stainless steel design.

4.5.4 Replace this clause by:


For fouling services and/or for gas pressures above 50 bar(g) (725 psig), snap acting level
transmitters/controllers and separate control valves shall be used.

4.5.6 In this clause, delete the words “and 4.5.3”.

6 INSTRUMENTATION, CONTROL AND ELECTRICAL SYSTEMS

6.2 ALARMS AND SHUTDOWNS

6.2.1 Add to this clause:


Unless otherwise specified, alarm and shutdown functions shall comprise individual locally
mounted transmitters, which are connected to the plant alarm and shutdown systems.
Application of one of the Arrangements 1, 2, or 3, shall be subject to specific approval of
the Principal.
DEP 31.29.60.32-Gen.
January 2010
Page 39

Table 1 Replace the fifth, sixth and seventh lines with:

Condition Alarm Shutdown


High primary vent-gas pressure or flow on tandem seal or X X
tandem seal with intermediate labyrinth (note c)
High secondary vent-gas pressure or flow on tandem seal or X X
tandem seal with intermediate labyrinth (note c)
Secondary seal-gas pressure of flow (note d) X X

6.3 INSTRUMENTATION

6.3.1 Flow indicators


6.3.1.1 Replace this clause by:
Flow measurement instruments shall be as specified on the data/requisitions sheets. Their
make and type shall be subject to the approval of the Principal.
6.3.1.3 Replace this clause by:
Non-metallic flow meters shall not be used.

7 INSPECTION, TESTING, AND PREPARATION FOR SHIPMENT

7.3 TESTING

7.3.3 Operational Tests

7.3.3.2 Replace this clause by:

The test gas shall be helium

7.3.3.4 Delete from this clause the words “If specified”


Add new clause:
7.3.3.5 At least 6 weeks prior to testing the Vendor shall submit to the purchaser for approval a
complete, detailed procedure of the agreed test program.
DEP 31.29.60.32-Gen.
January 2010
Page 40

ANNEX B PIPING AND INSTRUMENTATION DIAGRAMS


Insert new clause:
SCHEMATICS
The following requirements are referred to the selected Figures:

Figure B.1 : The seal gas supply to the seals shall be controlled by differential
pressure over the inboard seal. A flow element with transmitter shall be
supplied for each seal.
Figure B.2 : Option shall be supplied by the system Vendor.
Figure B.3 : Shall not be used in flammable and/or hazardous services.
Figure B.4 : Application is subject to the approval of the Principal.
Figure B.5 : Option 1 is subject to the approval of the Principal.
Figure B.7 : Transfer valve to be used instead of individual block valves.
Figure B.8 : Differential pressure control shall be accomplished by a separate
electronic transmitter/control valve combination.
Figure B.9 Flow control shall be accomplished by a separate electronic transmitter /
control valve combination. A flow element with transmitter shall be
supplied for each seal.
Figure B.12 : Differential pressure control shall be accomplished by a separate
electronic transmitter/control valve combination. Add a PDIT between
the secondary seal gas supply and the secondary vent (loss of
differential will indicate failure of the secondary dry gas seal).
Figure B.13 : Shall not be used.
Figure B.14 : Shall not be used.
Figure B.15 : The use of a rupture disk is subject to the approval of the Principal.
Figure B.16 : Not to be used if flare/vent pressure can fluctuate. The use of a rupture
disk is subject to the approval of the Principal.
Figure B.17 : Shall not be used.
Figure B.19 : Preferred to B.18.
DEP 31.29.60.32-Gen.
January 2010
Page 41

PART III REFERENCES

In this DEP, reference is made to the following publications:


NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell
Wide Web) at http://sww.shell.com/standards/.

SHELL STANDARDS
Noise control (amendments/supplements to ISO 15664) DEP 31.10.00.31-Gen.
Data/requisition sheet for equipment noise limitation DEP 31.10.00.94-Gen.
Shell and tube heat exchangers (amendments/supplements to DEP 31.21.01.30-Gen.
ISO 16812)
Selected construction materials for shell-and-tube heat DEP 31.21.01.31-Gen.
exchangers
Air-cooled heat exchangers (amendments/supplements to DEP 31.21.70.31-Gen.
ISO 13706)
Pressure vessels (amendments/supplements to PD 5500) DEP 31.22.10.32-Gen.
Pressure vessels (based on ASME Section VIII) DEP 31.22.20.31-Gen.
Centrifugal pumps (amendments/supplements to ISO 13709) DEP 31.29.02.30-Gen.
General-purpose steam turbines (amendments/supplements to DEP 31.29.60.30-Gen.
API 611)
Piping Classes – Refining and Chemicals DEP 31.38.01.12-Gen
Piping Classes – Exploration and Production DEP 31.38.01.15-Gen
Instruments for measurement and control DEP 32.31.00.32-Gen.
Instrumentation for equipment packages DEP 32.31.09.31-Gen.
Electrical machines - Cage-induction types (amendments/supplements to DEP 33.66.05.31-Gen.
IEC 60034-1 and IEC 60034-14)
AMERICAN STANDARDS

Bolted bonnet steel gate valves for petroleum and natural gas API 600
industries

Steel gate, globe and check valves for sizes DN 100 and smaller API 602
for the petroleum and natural gas industries
General-purpose steam turbines for petroleum, chemical and gas API 611
industry services
Lubrication, shaft-sealing and Oil-control systems and auxiliaries API 614,
fifth edition, April 2008

Axial and Centrifugal Compressors and Expander-Compressors API 617


Issued by:
American Petroleum Institute
Publications and Distribution Section
1220 L Street Northwest
Washington DC 20005
USA

Pipe flanges and flanged fittings, NPS ½ through NPS 24 ASME B16.5
metric/inch standard
DEP 31.29.60.32-Gen.
January 2010
Page 42

Process piping ASME B31.3


ASME boiler and pressure vessel code, Section VIII - Rules for ASME VIII
construction of pressure vessels
Issued by:
American Society of Mechanical Engineers
ASME International
Three Park Avenue M/S 10E
New York NY 10016
USA

BRITISH STANDARDS
Specification for unfired fusion welded pressure vessels PD 5500
Issued by:
British Standards Institution
389 Chiswick High Road
London W4 4AL
UK

INTERNATIONAL STANDARDS

Bolted bonnet steel gate valves for the petroleum, petrochemical ISO 10434
and allied industries
Lubrication, Shaft-sealing and Oil-control Systems and Auxiliaries ISO 10438
Axial and Centrifugal Compressors and Expander-Compressors ISO 10439
Steel and steel products – inspection documents ISO 10474
Safety of machinery – Guards – General requirements for the design and ISO 14120
construction of fixed and movable guards.
Steel gate, globe and check valves for sizes DN 100 and smaller for the ISO 15761
petroleum and natural gas industries
Issued by:
International Organisation for Standardization
Case Postale 56
CH-1211 Geneva 20
Switzerland

Copies can also be obtained from national standards organizations.

Last page of this DEP

You might also like