Bidding Document: Tribhuvan International Airport Civil Aviation Office Civil Engineering Division
Bidding Document: Tribhuvan International Airport Civil Aviation Office Civil Engineering Division
Bidding Document: Tribhuvan International Airport Civil Aviation Office Civil Engineering Division
BIDDING DOCUMENT
FOR
Issued by:
CIVIL AVIATION AUTHORITY OF NEPAL
TRIBHUVAN INTERNATIONAL AIRPORT CIVIL AVIATION OFFICE
CIVIL ENGINEERING DIVISION
GAUCHER, KATHMANDU, NEPAL
January 2016
0
Section I. Invitation to Bids
1
Instructions to Bidders
A. General
1. Scope of The Employer invites bids for the contraction of works as detailed in
Works attached specifications, drawings and the bill of quantities provided
herein. The successful Bidder is expected to complete the works as
mentioned in the Bidding Data.
2. Eligible Bidder This Invitation for Bids is open to all registered Bidders with
qualifications as described in the Bidding Data.
3.One Bid per Each Bidder shall submit only one bid, either individually or as a
Bidder partner in a joint venture. A Bidder who submits or participates in
more than one bid shall cause all the proposals with the Bidder’s
participation to be disqualified. A firm may participate in more than
one bid only as a subcontractor.
4. Cost of The Bidder shall bear all costs associated with the preparation and
Bidding submission of his bid and the Employer shall in no case be liable for
those costs.
5. Site Visit The Bidder at his own cost, responsibility and risk may visit the site
of the works and acquire all necessary information for preparing the
bid and entering into a contract for construction of the works.
B. Bidding Documents
6. Content of The Bidding Documents comprise the documents listed below:
Bidding Section
Documents I. Invitation for Bids
II. Instructions to Bidders
III. Sample Forms of Bid, Letter of Acceptance and Agreement
IV. General Conditions of Contract (GCC)
V. Special Conditions of Contract (SCC)
VI. Technical Specifications
VII. Drawings
VIII. Bill of Quantities
IX. Sample Forms of Securities
C. Preparation of Bids
8. Language of All documents relating to the bid shall be in English or in Nepali.
Bid
2
d. Rate Analysis (optional at request of Employer)
10. Bid Prices The contract shall be for the whole works described in scope of
works based on the priced Bill of Quantities submitted by the Bidder.
The Bidder shall fill in rates and prices for all items of the works in
Nepali Rupees. Items for which no rate or price is entered shall be
deemed covered by the other rates and prices in the Bill of
Quantities and shall not be paid by the Employer.
All duties, taxes and other levies payable by the contractor under the
contract shall be included in the rates, prices and total Bid Price
submitted by the Bidder.
11. Bid Validity The bid shall remain valid for the period specified in the Bidding
Data.
12. Bid Security The Bidder shall furnish a Bid Security in Nepali Rupees in the
amount specified in the Bidding Data. The Bid Security shall remain
valid for a period of 30 days beyond the original validity period for
bid and any period of extension subsequently requested by the
employer.
13. Format and One original and one duplicate copy of the bid shall be typed or
Signing of written in indelible ink and shall be signed by a person or persons
Bids duly authorised to sign on behalf of the Bidder. This authorization
shall consist of a written confirmation as specified in the Bidding
Data and shall be attached to the bid. The name and position held
by each person signing the authorization must be typed or printed
below the signature. Any entries or amendments including
alternations, additions or corrections made shall be initialled by the
same authorized person.
D. Submission of Bids
14. Sealing and The Bidder shall submit one original and a duplicate copy of the bid.
Marking of These bids shall be placed in sealed envelopes. Both the sealed
Bids envelopes shall be placed in an outer envelope which shall also be
sealed. The inner envelopes shall duly be marked as ‘Original’ and
‘Copy’. The envelopes shall be addressed to the Employer at the
address provided in the Bidding Data and bear the name and
identification number of the contract.
15. Pre-Bid A Pre-Bid meeting if provided for in the Bidding Data shall be held at
Meeting least 10 days before the bid submission date at the place, date and
time as mentioned in the Bidding Data. Any amendment to be made
in the Bid subsequent to the Pre-bid meeting shall be issued within 5
days of the meeting and the Addendum shall be circulated to all the
purchasers of the Bidding Document, The Addendum thus issued
shall be a part of the Bidding document.
16. Deadline for Bids shall be delivered to the Employer at the address no later than
Submission of the time and date specified in the Bidding Data.
Bids
3
17. Late Bids Any bid received by the Employer after the deadline shall not be
accepted and shall be returned unopened to the Bidder.
18. Modification 18.1 Bidders may modify or withdraw their Bids after it has been
and submitted by giving a written notice, duly signed by an
Withdrawal of authorized representative and shall include a copy of the
Bids authorization in accordance with Clause 13 before the deadline
prescribed in Clause 16. The corresponding modification of the
bid must accompany the respective written notice.
The Bidders' names, the Bid Prices, the total amount of each bid,
any discounts, bid modifications and withdrawals, the presence or
absence of Bid Security, difference of rate in words and figures,
quoted price for alternate technical specification if proposed,
whether the Bid Form has signature of the bidder or authorized
representative, corrections/effacement or obliteration in bidding
document, any remarks made by the bidder in the Bid Form, details
of rates if requested and such other details as the Employer may
consider appropriate shall be announced by the Employer at the
opening.
The Employer shall prepare and provide minutes of the bid opening
including the information disclosed to those present.
4
wishes to bring additional information to the notice of the
Employer, he should do so in writing.
22. Examination of 22.1 Prior to the detailed evaluation of Bids, the Employer shall
Bids and determine whether each bid (a) meets the eligibility criteria
Determination of defined in Clause 2; (b) has been properly signed; (c) is
Responsiveness accompanied by the required securities; and (d) is substantially
responsive to the requirements of the Bidding documents.
23.2 The amount stated in the bid shall be adjusted by the Employer
in accordance with the above procedure for the correction of
errors and, with the concurrence of the Bidder, shall be
considered as binding upon the Bidder. If the Bidder does not
accept the corrected amount, the bid shall be rejected and the
Bid Security may be forfeited.
24. Evaluation and 24.1 The Employer shall evaluate and compare only the Bids
Comparison of determined to be substantially responsive in accordance with
Bids Clause 23.
24.2 Further the employer shall evaluate :
Whether the construction work plan, work performance schedule and
5
mobilization period is consistent with the requirement of the
bidding document or not,
Whether the quoted item unit rates in the Bill of quantities are reliable
or not,
Whether or not the quoted price is unbalanced due to unnaturally
high rates quoted by the bidder for work items to be completed
in the initial stages of the contract or for work items whose
quantities are assumed by the bidder to be underestimated.
24.3 In evaluating the Bids, the Employer shall determine for each
bid the evaluated Bid Price by adjusting any corrections for
errors pursuant to Clause 23;
24.5 If the bid, which results in the lowest Evaluated Bid price, is
unbalanced or frontloaded in relation to the Employer’s
estimate of the items of Work to be performed under the
contract pursuant to Sub - Clause 24.2 ,the Employer shall ask
the bidder to give clarification with detailed rate analysis for
any or all items of the Bill of Quantities. If the clarification is
found satisfactory then the Employer shall increase at the
expense of the bidder the performance security set forth in
clause 28 by additional 8% of the quoted amount to protect the
Employer against financial loss in the event of default of the
successful bidder under the contract and if the clarification is
found unsatisfactory then the Employer may reject such bid.
.
F. Award of Contract
25. Award of The Employer shall award the contract to the Bidder who has
Contract offered the lowest evaluated Bid Price, provided that such Bidder
has been determined to be eligible in accordance with the provisions
of Clause2.
26. Employer's The Employer reserves the right to accept or reject any bid and to
Right to Accept cancel the bidding process and reject all bids, at any time prior to
any Bid and to the award of the contract, without assigning any reasons whatsoever
Reject any or and without thereby incurring any liability to the affected Bidder or
all Bids Bidders.
6
27. Notification of 27.1 The Employer shall notify it’s intention to award the Contract
Award and to the successful bidder in accordance with Clause 25 prior
Signing of to the expiration of the bid validity period and within 7 days of
Agreement acceptance of his bid. This notification (called the “Letter of
Acceptance”) shall state the sum that the Employer shall pay
the Bidder in consideration of the execution, completion, and
maintenance of the works as described by the contract. The
employer shall also provide information regarding the name,
address and the contract amount of the successful bidder to
all bidders who participated in the bid.
27.2 Any Bidder who is not satisfied with the procurement process
or Employer’s decision as per Sub - Clause 27.1 and believes
that the Employer has committed an error or breach of duty
which has or will result in loss to the bidder then the bidder
may give an application for review of the decision to the
Employer with reference to the error or breach of duty
committed by the Employer. The review application should be
given within 7 days of receipt of information regarding issue of
Letter of Acceptance by the Employer to the successful
bidder.
28. Performance Within 15 days after receipt of the Letter of Acceptance, the
Security successful Bidder shall deliver to the Employer a Performance
Security in acceptable format to the Employer as specified in
Section IX and equal to five percent (5%) of the contract Agreement
Amount.
29. Advance Payment The Employer may provide an Advance Payment on the Initial
Contract Price as stipulated in the Letter of Acceptance, subject to a
maximum amount as stated in the Bidding Data.
31. Adjudicator The Employer proposes the person named in the Bidding Data to be
appointed as Adjudicator under the Contract, at the hourly fee
specified in the Bidding Data, plus reimbursable expenses. If the
Bidder disagrees with this proposal, the Bidder should so state in his
Bid. If, in the Letter of Acceptance, the Employer does not agree on
the appointment of the Adjudicator, the Employer will request the
Appointing Authority designated in the Contract Data at the request
of either party.
32. Conduct of
32.1 The Bidder shall be responsible to fulfil his obligations as per
7
Bidders the requirement of the Contract Agreement, Bidding
documents, GoN’s Procurement Act and Regulations.
32.2 The Bidder shall not carry out or cause to carry out the
following acts with an intention to influence the implementation
of the procurement process or the procurement agreement :
a) give or propose improper inducement directly or indirectly,
b) distortion or misrepresentation of facts
c) engaging or being involved in corrupt or fraudulent practice
d) Interference in participation of other prospective bidders.
e) coercion or threatening directly or indirectly to cause harm to
the person or the property of any person to be involved in the
procurement proceedings,
f) collusive practice among bidders before or after submission
of bids for distribution of works among bidders or fixing
artificial/uncompetitive bid price with an intention to deprive
the Employer the benefit of open competitive bid price..
g) Contacting the Employer with an intention to influence the
Employer with regards to the bid or interference of any kind
in examination and evaluation of the bids during the period
after opening of bids up to the notification of award of
contract
33. Blacklisting 33.1 Without prejudice to any other right of the Employer under this
Bidder Contract, GoN, Public Procurement Monitoring Office may
blacklist a bidder for his conduct up to three years on the
following grounds and seriousness of the act committed by
the bidder:
a) if it is proved that the bidder committed acts pursuant to the
Sub - Clause 32.2,
b) if the bidder fails to sign an agreement pursuant to Sub -
Clause 27.4,
c) if it is proved later that the bidder/contractor had committed
substantial defect in implementation of the contract or had
not substantially fulfilled his obligations under the contract
or the completed work is not of the specified quality as per
the contract ,
d) if convicted by a court of law in a criminal offence which
disqualifies the bidder from participating in the contract.
e) if it is proved that the contract agreement signed by the
bidder was based on false or misrepresentation of bidder’s
qualification information,
f) other acts mentioned in the Bidding Data
8
G. Bidding Data
Instruction to Bidders Clause References
A. General
ITB 1 The Employer is: Tribhuvan International Airport Civil Aviation Office,
Gauchar, Kathmandu.
The Scope of Work: Renovation of Domestic Terminal Building at TIA.
B. Bidding Documents
ITB 7
Employer’s address for clarification purposes is: Tribhuvan
International Airport Civil Aviation Office, Civil Engineering
Division, Gauchar, Kathmandu.
Requests for clarification should be received by the Employer no later
than: 20 days.
C. Preparation of Bids
ITB 8 The language of the bid is: Nepali or English
ITB 11 The bid validity period shall be: 120 days from the date of opening Bid.
9
ITB 13 The written confirmation of authorization to sign on behalf of the Bidder shall indicate: [insert “
(a) The name and description of the documentation required to demonstrate the authority
of the signatory to sign the Bid such as a Power of Attorney; and
(b) In the case of Bids submitted by an existing or intended JV an undertaking signed by all
parties (i) stating that all parties shall be jointly and severally liable, and (ii) nominating a
Representative who shall have the authority to conduct all business for and on behalf of
any and all the parties of the JV during the bidding process and, in the event the JV is
awarded the Contract, during contract execution.”]
D. Submission of Bids
ITB 15 A Pre-Bid meeting shall not place.
ITB 16 The Employer’s address for bid submission purposes is: Tribhuvan
International Airport Civil Aviation Office, Civil Engineering Division,
Gauchar, Kathmandu.
The deadline for bid submission is:
Date: 2072/11/10
Time: 12.00 hrs
F. Award of Contract
ITB 29 The Advance Payment amount shall be: 20 % of Contract Price
ITB 31 The Adjudicator proposed by the Employer is: Will be decided later.
The hourly fee for this proposed Adjudicator shall be: Will be decided
later.
Brief biographical data of the proposed Adjudicator is as follows: NA
10
Section III. Sample Forms of Bid, Qualification
Information, Letter of Acceptance and
Agreement
11
Bid
We have examined the documents and offer to execute the Works in conformity with the
Contract for the sum of ……………………. ………………………….. (in words)
……………………………(in figures) or such other sum as may be ascertained under the
contract.
This bid is submitted in one original and one duplicate copy. We accept the appointment of
[______________name proposed in Bidding Data] as the Adjudicator
[or]
We do not accept the appointment of [name proposed in Bidding Data] as the Adjudicator,
and propose instead that [name] be appointed as Adjudicator, whose daily fees and
biographical data are attached.
This bid shall remain binding until ____________________ [date]. This bid and your written
acceptance of it shall constitute a binding contract between us.
We understand that the Employer is not bound to accept the lowest or any offer received for the
Works.
Name : _______________________________
Designation: ______________________
12
Eligibility Information
Notes to Bidders
The information to be filled in by Bidders in the following pages shall be used for purposes of
eligibility as provided for in Clause 2 of the Instructions to Bidders. This information shall not
be incorporated in the Contract. Attach additional pages as necessary.
1. Eligibility Requirements:
All Bidders shall submit following documents as pre- requisites for eligibility:
2.1 Attach the power of attorney of the signatory (ies) of the bid authorising signature of the
bid on behalf of the joint venture.
2.2 Attach the Agreement among all partners of the joint venture (and which is legally binding
on all partners), which shows that
(a) all partners shall be jointly and severally liable for the execution of the Contract in
accordance with the Contract terms;
(b) one of the partners will be nominated as being in charge, authorized to incur
liabilities, and receive instructions for and on behalf of any and all partners of the
joint venture; and
(c) execution of the entire Contract, including payment, shall be done exclusively with
the partner in charge.
(d) each joint venture partners shall provide details as per information listed in 1 above.
13
Letter of Intention to Award
[This letter should be in the letterhead paper of the Employer]
The issue of Letter of Intention to Award will be the basis acceptance of bid by the Employer
for issue of letter of Acceptance to the lowest evaluated Bidder and for providing information
to other unsuccessful bidders who participated in the bid as regards to the outcome of the
procurement process. This standard form of Letter of Intention to Award should be filled in
and sent to the successful Bidder only after evaluation of Bids has been completed but before
final acceptance of the Bid.
Date:
This is to notify you in accordance with the Instruction to Bidders that it is our intention to award
the contract [name of the Contract and identification number, as given in the Contract Data
1
and/or SCC] to you as your Bid price of the equivalent, of [amount in numbers and words in
2
Nepalese Rupees], as corrected and modified in accordance with the Instructions to Bidders, is
determined to be substantially responsive and lowest evaluated Bid price.
Authorized Signature:__________________________________________________
Name of Agency:______________________________________________________
14
Letter of Acceptance
[Letterhead of the Employer]
Date: ________________________
This is to notify you that your bid dated [date] for execution of the [name of the Contract and
identification number, as given in the Invitation to Bid] for the Contract Price of [insert the
3
amount in Nepalese Rupees in numbers and words] as corrected and modified in accordance
with the Instructions to Bidders is hereby accepted by our Agency.
You are hereby instructed to contact our office [Office address] to sign the formal agreement on
[date] at [time]. As per the Instructions to Bidders you are also required to submit Performance
Security, as specified in the SCC, consisting of a Bank Guarantee in an approved format or
cash deposit voucher in favour of the Employer in the Employer's Bank account as specified in
the SCC.
The Employer shall forfeit the bid security, in case you fail to furnish the Performance Security
and to sign the contract.
Please convey your unconditional acceptance by signing on the original of this letter and submit
the required Performance Security, at the time of formal agreement.
Authorised Signature:
Name:
Designation: :______________________________________________________
15
Agreement
This Agreement, made the [day] day of [month], [year] between [name and address of
Employer] (hereinafter called “the Employer”) and [name and address of contractor] (hereinafter
called “the contractor”) of the other part.
Whereas the Employer is desirous that the contractor execute [name and identification number
of contract] (hereinafter called “the Works”) and the Employer has accepted the bid for
________________ [insert the amount in Nepalese Rupees in numbers and words] by the
contractor for the execution and completion of such Works and the remedying of any defects
therein.
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to, and
they shall be deemed to form and be read and construed as part of this Agreement.
3. The Employer hereby covenants to pay the contractor in consideration of the execution
and completion of the Works and the remedying of defects wherein, the Contract Price or
such other sum as may become payable under the provisions of the Contract at the times
and in the manner prescribed by the Contract.
In Witness whereof the parties thereto have caused this Agreement to be executed the day and
year first before written.
[Addendum showing the corrections if any made during the bid evaluation should be attached
with this agreement]
16
Section IV. General Conditions of Contract (GCC)
1. General Provisions
1.1 Definitions In the Contract as defined below, the words and expressions
defined shall have the following meanings assigned to them,
except where the context requires otherwise:
The Contract 1.1.1 “Contract” means the Agreement signed between the
Employer and the contractor and the other documents
listed in the Special Conditions of Contract (SCC).
Date, Times 1.1.10 "Commencement Date" means the date 14 days after
and Periods the date the Agreement comes into effect or any other
date agreed between the Parties.
Money and 1.1.13 "Cost" means all expenditure properly incurred (or to be
Payments incurred) by the contractor, whether on or off the Site,
including overheads and similar charges, but does not
include profit.
17
1.1.14 “Contract Price”is the price stated in the letter of
Acceptance and thereafter as adjusted in accordance with
the provisions of the Contract.
1.2 Interpretation Words importing persons or parties shall include firms and
organisations. Words importing singular or one gender shall
include plural or the other gender where the context requires.
1.3 Priority of The documents forming the Contract shall to be taken as mutually
18
Documents explanatory of one another. If an ambiguity or discrepancy is
found in the documents, the Employer shall issue any necessary
instructions to the contractor, and the priority of the documents
shall be in accordance with the order as listed in the SCC.
1.5 Communications Where provision is made for the giving or issue of any notice,
instruction, or other communication by any person, unless
otherwise specified such communication shall be written in the
language stated in the SCC as shall not be unreasonably withheld
or delayed.
If a notice given pursuant to Sub-Clause 1.5 fails to be delivered
due to failure to trace the address of the party then the notice
shall be published as public notice in a National daily newspaper
and when the notice is so published then the notice shall be
considered to be delivered to the concerned party.
1.6 Statutory The contractor shall comply with the laws of the countries where
Obligations activities are performed. The contractor shall give all notices and
pay all fees and other charges in respect of the Works.
2. The Employer
2.1 Provision of The Employer shall provide the Site and right of access thereto at
Site the times stated in the SCC.
2.2 Permits and The Employer shall, if requested by the contractor, assist him in
Licenses applying for permits, licences or approvals which are required for
the Works.
2.3 Employer's The contractor shall comply with all instructions given by the
Instructions Employer in respect of the Works including the suspension of all
or part of the Works.
3. Employer's Representatives
3.1 Authorised One of the Employer's personnel shall have authority to act for
Person him. This authorised person shall be as stated in the SCC, or as
otherwise notified by the Employer to the contractor.
3.2 Employer's The Employer may also appoint a firm or individual to carry out
Representative certain duties. The appointee may be named in the SCC, or
notified by the Employer to the contractor from time to time. The
Employer shall notify the contractor of the delegated duties and
authority of this Employer's representative.
4. The Contractor
4.1 General The contractor shall carry out the Works properly and in
Obligations accordance with the Contract. The contractor shall provide all
supervision, labour, Materials, Plant and contractor's Equipment
which may be required. All Materials and Plant on Site shall be
deemed to be the property of the Employer.
19
During continuance of the of the contract, the contractor and his
sub-contractors shall abide at all times by all labour laws,
including child labour related enactments, and rules made there
under.
A child who has not attained the age of fourteen (14) years shall
not be employed in any work as a labourer.
4.2 Contractor's The contractor shall submit to the Employer for consent the name
Representative and particulars of the person authorised to receive instructions on
behalf of the contractor.
4.3 Subcontracting The contractor shall not subcontract the whole of the Works. The
contractor shall not subcontract any part of the Works without the
consent of the Employer.
4.4 Performance As stated in the SCC, the Contractor shall deliver to the Employer
Security no later than the date specified in the Letter of Acceptance.
5. Design by Contractor
5.1 Contractor's The contractor shall carry out design to the extent specified, as
Design referred to in the SCC. The contractor shall promptly submit to the
Employer all designs prepared by him. Within 15 days of receipt,
the Employer shall notify any comments or, if the design
submitted is not in accordance with the Contract, shall reject it
stating the reasons. The contractor shall not construct any
element of the permanent work designed by him within 15 days
after the design has been submitted to the Employer or where the
design for that element has been rejected. Design that has been
rejected shall be promptly amended and resubmitted. The
contractor shall resubmit all designs commented on taking these
comments into account as necessary.
5.2 Responsibility The contractor shall remain responsible for his tendered design
for Design and the design under this Clause, both of which shall be fit for the
intended purposes defined in the Contract and he shall also
remain responsible for any infringement of any patent or copyright
in respect of the same. The Employer shall be responsible for the
Specification and Drawings.
6. Employer's Liabilities
6.1 Employer’s In this Contract, Employer's Liabilities mean:
Liabilities
a. war, hostilities (whether war be declared or not), invasion, act
of foreign enemies, within the Country,
b. rebellion, terrorism, revolution, insurrection, military or
usurped power, or civil war, within the Country,
c. riot, commotion or disorder by persons other than the
contractor's personnel and other employees, affecting the
Site and/or the Works,
d. ionising radiations, or contamination by radio-activity from
any nuclear fuel, or from any nuclear waste from the
combustion of nuclear fuel, radio-active toxic explosive, or
other hazardous properties of any explosive nuclear
20
assembly or nuclear component of such an assembly, except
to the extent to which the contractor may be responsible for
the use of any radio-active material,
e. pressure waves caused by aircraft or other aerial devices
travelling at sonic or supersonic speeds,
f. use or occupation by the Employer of any part of the Works,
except as may be specified in the Contract,
g. design of any part of the Works by the Employer's personnel
or by others for whom the Employer is responsible,
h. any operation of the forces of nature affecting the Site and/or
the Works, which was unforeseeable or against which an
experienced contractor could not reasonably have been
expected to take precautions,
i. Force Majeure,
j. a suspension under Sub-Clause 2.3 unless it is attributable to
the contractor's failure,
k. any failure of the Employer,
l. physical obstructions or physical conditions, other than
climatic conditions, encountered on the Site during the
performance of the Works, which obstructions or conditions
were not reasonably foreseeable by an experienced
contractor and which the contractor immediately notified to
the Employer,
m. any delay or disruption caused by any Variation,
n. any change to the law of the Contract after the date of the
contractor's offer as stated in the Agreement,
o. losses arising out of the Employer's right to have the
permanent work executed on, over, under, in or through any
land, and to occupy this land for the permanent work, and
p. damage which is an unavoidable result of the contractor's
obligations to execute the Works and to remedy any defects.
7.2 Programme The contractor shall submit to the Employer a programme for the
Works within the time stated in the SCC
21
7.4 Liquidated If the contractor fails to complete the Works within the Time for
Damages for Completion, the contractor's only liability to the Employer for such
Delay failure shall be to pay the amount stated in the SCC for each day
for which he fails to complete the Works. The total amount of
Liquidated damages shall not exceed the amount stated in the
SCC.
7.5 Bonus The Contractor shall be paid a Bonus calculated at the rate per
calendar day stated in the SCC for each day that the Completion
is earlier than the date for Time of Completion. The Employer
shall certify that the Works are complete, although they may not
be due to be complete. The total amount of Bonus shall not
exceed the amount stated in the SCC.
8. Taking-Over
8.1 Completion The contractor may notify the Employer when he considers that
the Works are complete.
8.2 Taking-Over The Employer shall notify the contractor when he considers that
Notice the contractor has completed the Works stating the date
accordingly. Alternatively, the Employer may notify the contractor
that the Works, although not fully complete, are ready for taking
over, stating the date accordingly.
The Employer shall take over the Works upon the issue of this
notice. The contractor shall promptly complete any outstanding
work and, subject to Clause 9, clear the Site.
9. Remedying Defects
9.1 Remedying The Employer may at any time prior to the expiry of the period
Defects stated in the SCC, notify the contractor of any defects or
outstanding work. The contractor shall remedy at no cost to the
Employer any defects due to the contractor's design, materials,
plant or workmanship not being in accordance with the Contract.
9.2 Uncovering The Employer may give instruction as to the uncovering and/or
and Testing testing of any work. Unless as a result of any uncovering and/or
testing it is established that the contractor's design, materials,
plant or workmanship are not in accordance with the Contract, the
Contractor shall be paid for such uncovering and/or testing as a
Variation in accordance with Sub-Clause 10.2.
22
10.2 Valuation of Variations shall be valued as follows:
Variations
a. where appropriate, at rates in the Contract, or
b. in the absence of appropriate rates, the rates in the Contract
shall be used as the basis for valuation,
c. at appropriate new rates, as may be agreed or which the
Employer considers appropriate, or
d. if the Employer so instructs, at daywork rates set out in the
SCC for which the contractor shall keep records of hours of
labour and contractor's Equipment, and of Materials used.
10.3 Early Warning A Party shall notify the other as soon as he is aware of any
circumstance which may delay or disrupt the Works, or which may
give rise to a claim for additional payment. The contractor shall
take all reasonable steps to minimise these effects.
10.4 Right to Claim If the contractor incurs cost as a result of any of the Employer's
Liabilities, the contractor shall be entitled to the amount of such
cost. If as a result of any of the Employer's Liabilities, it is
necessary to change the Works, this shall be dealt with as a
Variation.
10.5 Variation and The contractor shall submit the Employer an itemised make-up of
Claim the value of Variations and claims within 30 days of the instruction
Procedure or of the event giving rise to the claim. The Employer shall check
and if possible agree the value. In the absence of agreement, the
Employer shall determine the value.
23
11.4 Payment of One half of the retention and any such other retention shall be
First Half of paid by the Employer to the contractor within 15 days upon expiry
Retention of Defects Liability Period.
11.5 Payment of The remainder of the retention shall be paid by the Employer to
Second Half of the contractor within 15 days after submission of evidence
Retention document from the concerned Internal Revenue Office that the
contractor has submitted his Income Returns.
11.6 Final Payment Within 45 days of the latest of the expiry of the defects liability
period, the contractor shall submit a final account to the Employer
together with any documentation reasonably required to enable
the Employer to ascertain the final contract value.
11.8 Delayed The contractor shall be entitled to interest at the rate stated in the
Payment SCC for each day the Employer fails to pay beyond the prescribed
payment period.
11.9 Advance a The Employer may make advance payment to the contractor
Payment of the amounts stated in the SCC within 15 days, against
provision by the contractor of an Unconditional Bank
Guarantee in a form and by a bank acceptable to the
Employer in amounts and currencies equal to the advance
payment. The Guarantee shall remain effective until the
advance payment has been repaid, but the amount of the
Guarantee shall be progressively reduced by the amounts
repaid by the contractor. Interest shall not be charged on
the advance payment.
24
Contract Agreement is concluded following the Invitation for
National Level Bidding and after the signing of the Contract
Agreement if the price of the construction materials stated in
the SCC increase or decrease in an unexpected manner in
excess of ten (10%) percent in comparison to the base price
stated in the SCC, then the price adjustment for the increase
or decrease of price of the construction material beyond 10%
shall be made by applying the following formulas:
Where:
“ P” is price adjustment amount
“ R1” is the present price of the construction material
”
“ R0 is the base price of the construction material
“ Q “ is quantity of the construction material consumed in
construction during the period of price adjustment
consideration
(b) The Price Adjustment amount pursuant to the clause will be
limited to a maximum of 25% of the initial Contract Amount
unless otherwise is specified in the SCC
11.11 Local a. The prices tendered by the Contractor shall include all
Taxation & taxes that may be levied in accordance to the laws and
Value Added regulations in being in Nepal on the date 30 days prior to
Tax the closing date for submissions of Bids on the
Contractor’s equipment, plant and materials acquired for
the purpose of the Contract and on the services performed
under the Contract. Nothing in the Contract shall relieve
the Contractor from his responsibility to pay any tax that
may be levied in Nepal on profits made by him in respect
of the Contract.
If the contractor has not taken all practicable steps to remedy the
default within 15 days after the contractor's receipt of the
Employer's notice, the Employer may, by a second notice given
within a further 22 days, terminate the Contract. The Contractor
25
shall then demobilize from the Site leaving behind Materials and
Plant and any contractor's Equipment which the Employer
instructs in the second notice to be used until the completion of
the Works.
12.2 Default by If the Employer fails to pay in accordance with the Contract, or is,
Employer despite a written complaint, in breach of the Contract, the
contractor may give notice referring to this Sub-Clause and stating
the default. If the default is not remedied within 7 days after the
Employer's receipt of this notice, the contractor may suspend the
execution of all or parts of the Works.
12.3 Insolvency If a Party is declared insolvent under any applicable law, the other
Party may by notice terminate the Contract immediately. The
contractor shall then demobilise from the Site leaving behind, in
the case of the contractor's insolvency, any contractor's
Equipment which the Employer instructs in the notice is to be
used until the completion of the Works.
12.5 Payment upon After termination, the contractor shall be entitled to payment of the
Termination unpaid balance of the value of the Works executed and of the
Materials and Plant reasonably delivered to the Site, adjusted by
the following:
a. any sums to which the contractor is entitled under Sub-
Clause 10.4,
b. any sums to which the Employer is entitled,
c. if the Employer has terminated under Sub-Clause 12.1 or
12.3, the Employer shall be entitled to a sum equivalent to
20% of the value of those parts of the Works not executed at
the date of the termination,
d. if the contractor has terminated under Sub-Clause 12.2 or
12.3, the contractor shall be entitled to the Cost of his
suspension and demobilisation together with a sum
equivalent to 10% of the value of those parts of the Works not
executed at the date of termination
The net balance due shall be paid or repaid within 30 days of the
notice of termination.
26
loss or damage so that the Works conform to the Contract.
13.2 Force Majeure If a Party is or shall be prevented from performing any of its
obligations by Force Majeure, the Party affected shall notify the
other Party immediately. If necessary, the contractor shall
suspend the execution of the Works and, to the extent agreed
with the Employer, demobilise the contractor's Equipment.
The net balance due shall be paid or repaid within 30 days of the
notice of termination.
14. Insurance
14.1 Extent of The contractor shall, prior to commencing the Works, effect and
Cover thereafter maintain insurances in the joint names of the Parties:
a. for loss and damage to the Works, Materials, Plant and the
contractor's Equipment,
b. for liability of both Parties for loss, damage, death or injury to
third parties or their property arising out of the contractor's
performance of the Contract, including the contractor's liability
for damage to the Employer's property other than the Works,
and
c. for liability of both Parties and of any Employer's
representative for death or injury to the contractor's personnel
except to the extent that liability arises from the negligence of
the Employer, any Employer's representative or their
employees.
14.2 Arrangements All insurances shall conform with any requirements detailed in the
SCC. The policies shall be issued by insurers and in terms
approved by the Employer. The contractor shall provide the
Employer with evidence that any required policy is in force and
that the premiums have been paid.
27
All payments received from insurers relating to loss or damage to
the Works shall be held jointly by the Parties and used for the
repair of the loss or damage or as compensation for loss or
damage that is not to be repaired.
14.3 Failure to If the contractor fails to effect or keep in force any of the
Insure insurances referred to in the previous Sub-Clauses, or fails to
provide satisfactory evidence, policies or receipts, the Employer
may, without prejudice to any other right or remedy, effect
insurance for the cover relevant to such default and pay the
premiums due and recover the same as a deduction from any
other monies due to the contractor.
16.Conduct of
16.1 The Bidder shall be responsible to fulfil his obligations as
Bidders
per the requirement of the Contract Agreement, Bidding
documents, GoN’s Procurement Act and Regulations.
16.2 The Bidder shall not carry out or cause to carryout the
following acts with an intention to influence the
implementation of the procurement process or the
procurement agreement :
a) give or propose improper inducement directly or
indirectly,
b) distortion or misrepresentation of facts
c) engaging or being involved in corrupt or fraudulent
practice
28
d) interference in participation of other prospective bidders.
e) coercion or threatening directly or indirectly to cause
harm to the person or the property of any person to be
involved in the procurement proceedings,
f) collusive practice among bidders before or after
submission of bids for distribution of works among
bidders or fixing artificial/uncompetitive bid price with an
intention to deprive the Employer the benefit of open
competitive bid price..
g) contacting the Employer wit an intention to influence the
Employer with regards to the bid or interference of any
kind in examination and evaluation of the bids during the
period after opening of bids up to the notification of
award of contract
17. Blacklisting 17.1 Without prejudice to any other right of the Employer under this
Bidder Contract, GoN, Public Procurement Monitoring Office may
blacklist a bidder for his conduct up to three years on the
following grounds and seriousness of the act committed by
the bidder:
a) if it is proved that the bidder committed acts pursuant to the
Sub - Clause 16.2,
b) if the bidder fails to sign an agreement pursuant to ITB Sub
– Clause 27.4,
c) if it is proved later that the bidder/contractor had committed
substantial defect in implementation of the contract or had
not substantially fulfilled his obligations under the contract
or the completed work is not of the specified quality as per
the contract ,
d) if convicted by a court of law in a criminal offence which
disqualifies the bidder from participating in the contract.
e) if it is proved that the contract agreement signed by the
bidder was based on false or misrepresentation of bidder’s
qualification information,
f) other acts mentioned in the Bidding Data
29
Section V Special Conditions of Contract (SCC)
This SCC forms part of the Agreement
[Note: with the exception of the items for which the Employer's requirements have been
inserted, the Bidder shall complete the following information before submitting his bid.]
30
Valuation of the Works* 11.1 [insert “Ad measurement with bid bill of quantities” or
“Lump Sum price in case of Lump sum contract”]
31
Section VI. Technical Specification
32
SECTION 100
GENERAL REQUIREMENTS
101. BID DOCUMENTS
The Specifications and Bills of Quantities shall be read in conjunction with the other Bid
Documents. All the documents and drawings are to be regarded as mutually explanatory. In the
event of any discrepancy or assumed discrepancy being found between them, the Contractor
shall immediately inform the Chief Officer, Civil Engineering Division about the matter in
writing and the Chief Officer of CED will issue his instructions in the matter in accordance with
the Conditions of Contract.
Notes: Engineer means Civil Engineering Division, Tribhuvan International Airport Civil
Aviation Office,
Engineer's Representative means Representative from Civil Engineering Division,
Tribhuvan International Airport Civil Aviation Office,
102. STANDARDS
All standards referred to in the Bid Documents or on any Contract Documents or Contract
Drawings or instructions forming part of the Contract or issued under the provisions of the
Contract shall refer to the editions in effect on the date of issue of the Tender Documents, or any
superseding Standard, including all amendments published thereto unless some other edition is
specially referred to herein or referred to in instructions issued subsequent to the signing of the
Contract.
Where it is unclear which specific provisions of a Standard are intended to apply, or where
Standards may conflict in their requirements, the matter shall be referred to the Engineer who
shall make a determination, which shall not constitute a variation to the contract.
The Contractor shall maintain a complete set of Standards referred to in the specification, and
those deemed equivalent, on site for review by the Engineer upon request.
103. APPROVAL
The terms “approved”, “directed”, “instructed”, “satisfactory”, and “required’ shall mean to
the approval, direction, instruction, satisfaction or requirement of the Engineer or the it’s
Representative.
104. LOCATION
The site is located at Tribhuvan International Airport Gauchar, Kathmandu. The airport is
located at 4390 ft or 1338 m above mean sea level. The airport is located at latitude of 850 21’
33
28” and longitude of 270 41’ 50”N. The average temperature is 27.8 Celsius Degree.
The Contractor shall take account of the restrictions, method of work, sequence of work and
other conditions detailed in the following sub-clauses of this clause.
106.1 Definitions
The definitions of the terms used in this clause of the Specification are as follows:
a. “Passenger Area” means any area of the terminal, and associated apron areas used for
the processing of embarking and disembarking passengers.
b. “Public Areas” means those areas in and adjacent the terminals where there is no
restriction on public access.
c. “Restricted Public Area” means any area of the terminal where public access is
permitted by payment of fee.
d. “Staff Area” means any area accessible to airport, airline and other airport workers with
suitable passes, but which is restricted to public or passenger access.
e. “Civil Aviation Authority of Nepal (CAAN)” means, for the purposes of this
Specification the official or officials within Department of Civil aviation who has/have
been so designated in writing to the Contractor and to the Engineer to issue instructions
and to give directions as to the manner in which the works are to be carried out within
the Movement Area.
he Contractor shall be solely responsible for all the equipment and personnel employed directly
or indirectly and shall be responsible for ensuring that the requirements and restrictions imposed
by this specification are understood and adhered to by all personnel engaged under this contract
in the execution of the works.
During the continuance of the Works the airport as well as domestic apron area will be in
operational use and the Contractor must be all times ensure his work does not cause a hazard to
flying operations and to aircraft on the ground. He must also ensure the safety of all persons
including the public, passengers, airport and airline staff and his own labor force at all times.
34
Special consideration for minimum disruptions and safety of air traffic, travelers, and public and
operation staff shall be paramount during construction.
A detailed safety management plan for airport and site safety during construction shall be
established by the Contractor and adhered to for all aspects of the work with special emphasis
on airport operations and public interfaces. The minimum standard of site safety will be as per
standard code for occupational health and safety act and regulations for construction projects.
The Contractor shall submit construction safety code for Engineer's approval.
106.4 Liaison
For the purpose of complying with the requirements of this section of the specification and for
exchanging information on flying operations, terminal operations and day-to-day restrictions
which may be imposed on the Works the Contractor shall designate a member of his staff to be
called the Contractor’s Liaison Officer who shall be solely responsible for the receipt of
instructions from the Civil Engineering Division, Tribhuvan International Airport Civil Aviation
Office.
The Contractor’s Liaison Officer shall be a senior member of the Contractor’s supervisory staff
and he shall have a good understanding of civil aviation and operational aspects of the airport.
He shall be fluent both in Nepalese and English languages. The Contractor’s Liaison Officer
shall also be responsible for maintaining and posting an up to date list of telephone numbers of
key personnel of the Civil Engineering Division TIACAO and the Contractor, who should be
contacted in the event of difficulties or emergencies while the Works are in progress.
106.5 Airport Passes
All employees of the Contractor and Sub-contractors (if any) must visibly display an airport
Identity pass on their person while working in the Movement Area or airfield area. Passes may
be obtained on application to the General Manager, TIACAO stating the name, address and
position or occupation of the member of staff together with two recent visa size photographs.
The Contractor shall be responsible for ensuring that all staff is in possession of valid passes.
The validity period for each card will be determined by the General Manager and expired cards
shall be returned to the General Manager with applications for renewed cards. On termination of
employment of any member of staff the Contractor shall be held responsible for returning such
person’s pass to the Airport Manager.
The Civil Engineering Division of the Airport reserves the right to permanently remove from
the site any member of the Contractor’s staff who is found not to be in possession of a valid
Airport Identity Pass. Mobile equipment not displaying a valid airport permit shall under no
circumstances be permitted to enter the airside and/or the Movement Area.
106.6 Security Barriers
Security barriers, such as fences, walls, gates, doors, locks and door hardware, between security
zones of the Airport which are required to be opened, removed or otherwise breached for
purposes of completing the work, shall be reinstated as soon as possible and at the end of each
working day. If it is necessary to remove barriers for extended periods, equivalent temporary
barriers shall be provided and located so as to maintain security. If it is impractical to reinstate
barriers at the end of the working day, alternative arrangement shall be made by the Contractor
in consultation with the Airport Security Police and Airport CED Manager.
The position and construction of temporary security barriers shall be subject to approval of the
Engineer. Should the Contractor fail to reinstate such barriers as required, other forced
arrangement may be made to do so with any resulting costs being recovered from the
Contractor?
35
When it is necessary to remove or breach security barriers to gain access for construction, the
Contractor shall supply an uniformed security guard to control access to authorized personnel
bearing suitable passes. Access control procedures will be established and monitored by the
Airport Security Police. If required the Contractor shall be responsible for the cost of any
security personnel required in excess of normal airport requirements.
The Contractor shall, as may be required, familiarize himself with the schedule of aircraft
movements at the airport, and take account of consequent operating requirements, and peak
times of activity when planning daily, weekly, and seasonal plans of work.
The Contractor shall generally be allowed to work on airfield, subject to the security and safety
conditions of clause 105 of this specification and only if the workforce are fully supervised and
do not enter any aircraft maneuvering areas. If the Contractor cannot demonstrate that the works
will be carried out in manner that is satisfactory to the CED, TIACAO further restrictions will
be imposed to ensure the safety of airport operation and the Contractor shall not have any
recourse to additional compensation.
Contractor may obtain access to the works at various points subject to the security, safety and
coordination. Access to site will be provided by CED, TIACAO through existing entry points or
gates subjected to security checking.
36
107 COORDINATION WITH OTHER CONTRACTORS
The contractor will work in conjunction with other contractors working in the same location so
as to avoid conflicts in movements and progress of works. The contractor shall pay
compensation to other contractors if his activities are found to cause negative impact or delay on
progress of works by other contractors.
108 SUBMITALS
108.1 General Requirements
The Contractor will maintain an approved system of recording and tracking submissions
indicating dates, status (i.e. approved, not approved, approved subject to conditions), quantities,
and other details as required. Copies of all approved submissions will be retained securely and
properly filed on site, available for reference by the Employer at any time.
108.2 Program of Work
As soon as possible after the Letter of Acceptance and before signing of the Contract
Agreement, the Contractor shall submit in triplicate the program and particulars required under
clause 27 of the Conditions of Contract. In the program and particulars the Contractor shall
provide details of how he proposes to carry out the Works including:
1. A Critical Path analysis showing all major activities, trades and phases of works. Detail
shall be sufficient and to the satisfaction of the Engineer to demonstrate the relationships
and interdependencies between all aspects of the work. The Critical Path Analysis shall
identify off-site as well as on-site activities including delivery lead times, shop drawing
production and approval, materials testing, samples submission and preparation of mock-
ups. The Critical path Analysis shall be prepared by a competent and experienced
construction programmer using a computer program approved by the Engineer. It shall be
prepared so as to permit revisions, inclusion of additional detail and regular updates as the
work progress. The Critical Path analysis shall include sufficient time for contingencies.
108.3 Samples
The Engineer may at his discretion request or take samples of any material or product intended
for use in the Works. Where samples are requested in the specification they shall be submitted
in the number requested or if not specified then as directed by the Engineer.
Samples will be of the type and size specified and be fully representative of the materials
proposed to be used. Samples will be indelibly and clearly marked with the date of submission,
material reference and any other data required to determine the source and kind of sample.
One or more samples of each kind submitted will either be returned marked “ACCEPTED” and
signed by a representative of the Engineer or the Contractor will be requested to provide new
samples and be notified of deficiencies present in the submitted samples.
One or more “accepted” samples will be retained by the Engineer for comparison with materials
and workmanship supplied and will form the standard of acceptance.
37
One or more “accepted” samples shall be retained at the Contractor’s site office and be available
for reference on request.
The Engineer may reject any materials and goods which in his opinion are inferior to the
samples thereof previously approved and the Contractor shall promptly remove such materials
and goods from the Site.
The Contractor shall provide the Engineer with one copy of all orders for the supply of materials
and goods required in connection with the Works as the Engineer may require.
108.5 Photographic Record of Existing Condition
The Contractor shall provide a photographic record of the execution of the works by having
photographs taken at weekly intervals from such points as the Engineer may specify. The
Contractor shall supply three copies of 100 x 150 mm colour prints together with the negative of
each photograph to the Engineer within five days of the end of the month. Two sets of the
aforementioned prints shall be captioned, and a type-written label indicating the caption, date
and signature of the Contractor and the Engineer’s Representative shall be affixed to the back of
each photograph. One copy of such prints will be returned to the Contractor.
The construction drawings shall show at a suitable scale all the particulars of the work including
dimension, materials, finishes, lines, levels, tolerances and other details to show compliance
with the specification, the suitability of item for its compliance.
The Engineer and its representatives will review the drawings only for their general compliance
with the intent of the drawings and specifications. Responsibility for accuracy of dimensions,
technical design, performance and suitability for intended purpose of the items shall remain with
the Contractor.
Three (3) copies of each construction drawing are to be submitted in sufficient time to allow for
review, possible revisions and resubmission for approval prior to ordering materials, fabricating,
installing and coordinating all affected and contingent work without delay to the schedule of
construction.
Two copies of all construction drawings will be retained by the Engineer. The remainder copies
will be returned to the Contractor signed by a representative of the Engineer and marked
“REVIEWED” with either:
38
b. a note indicating the drawing has been reviewed but is subject to conditions noted or
listed, and does not require resubmission; or
c. a note indicating the drawing has been reviewed and is considered to meet the intent of
the design and does not require resubmission.
The drawings shall be submitted at least two weeks before the commencement of construction
of work for which these drawings are intended.
The construction should not commence until construction drawings have been reviewed and
are returned under the Conditions of Contract except where instructed by the Engineer.
39
GENERAL SPECIFICATION FOR CIVIL WORKS
The Work shall be carried out according to these Specifications whether specifically mentioned
elsewhere or not. No extra in any form will be paid unless it is definitely stated as an item in the
Bill of Quantities.
Whenever the Specifications are not given or when the Specifications are ambiguous, the
relevant Nepal Standard or Indian Standards or British Standards and further amendments will
be considered as final and binding.
All Works shall be carried out simultaneously with electrical, plumbing, sanitary and other
services and in co-operation with the Contractors the above services. The Work shall be carried
on till it is completed satisfactorily along with the completion of other essential services. The
building Contractor shall keep the other Contractors informed of the proposed programme of
Work, well in advance, so that the building Work is not hindered. The Contractor shall further
cooperate with other Contractors in respect of any facility required by them e.g. making holes in
shuttering for sanitary, pipes, electric conduits, fan hook etc. However, no extra payment shall
be admissible to him for such reasonable assistance and facilities afforded to other Contractors
and the building Contractors shall be deemed to have taken these factors into consideration
while quoting his rates.
The Work shall be related to the drawings, which the Contractor is presumed to have studied.
Nothing extra will be paid for any item because of its shape, location or other difficult
circumstances, even if the schedule makes no distinction, as long as the item is shown in the
drawings.
The source of materials stated in the Specifications is those from which materials are generally
available. However, materials not conforming to Specifications shall be rejected even if they
come from the stated sources. The Contractor should satisfy himself that sufficient quantity of
materials of acceptable Specification is available form the stated or other sources.
GENERAL:
1. Office accommodation and WC :
The Contractor shall provide at his own expense adequate temporary accommodation and toilet
facilities for his Workmen and keep the same in good conditions. This may be done to suit Site
conditions with the approval of Project Engineer. The above mentioned temporary structures
shall be removed on the completion of Works at Contractor's own cost. All materials shall
belong to the Contractor.
40
5. Measuring Materials:
Materials requiring measuring shall be measured separately in boxes of appropriate sizes
before being mixed as directed by Project Engineer.
6. Temporary Protections:
All trenches, walls newly laid concrete or other Work requiring protection from weather or
accidental injury shall be protected by means of tarpaulin or in any other way so as to keep the
Work safe from damage. Nothing extra shall be paid for on this matter.
7. Quality of Work:
Materials, tools and plants, and Workmanship shall be the best of several kinds obtainable in
the market and as approved by the Project Engineer.
8. Leave clean:
On completion, all Work must be cleaned down, rubbish removed and the Works and land
cleared of rubbish, surplus materials, debris and other accumulations and everything left in a
clean and orderly conditions.
9. Samples:
Samples of each class of Work required and materials shall be submitted by the Contractor for
the approval of the Project Engineer and after such approval, these samples shall be deposited
at a place chosen by the Project Engineer. The Contractor will be required to perform all Work
under the Agreement in accordance with these approved samples.
11. Storage:
Safe, dry and proper storage shall be provided for all materials, particularly cement. For
installed at the Site of Work the Project Engineer may reduce the capacity of storage.
12. Water:
Water shall be clean and free from oil, waste, acid or other organic matter in solution or
suspension. Water shall be from municipal main or tank or well water. Storage for the water
shall be of sufficient size and as directed by the Project Engineer. The Contractor shall make his
own arrangements for water supply.
13. Earth:
Earth for filling and terracing shall be free from all rubbish, organic or vegetable growth including
roots, weeds etc. All clods shall be first broken-down.
14. Sand:
Sand shall be clean from river and of approved quality and free from salt, earth, dust or other
impurities. If required by the Project Engineer, it shall be washed with clean water and not more
than 5% of fine materials (clay, dust and silt) will be allowed, as tested by the settlement in
water. The sand may contain particle size up to 5mm and should be well graded. Coarse sand
for concrete Work shall be from local rivers or from any other place as approved by the Project
Engineer and shall conform to cement concrete specification.
41
should also be stacked in not more than 6 layers high to prevent bursting of bottom bags. The
Project Engineer may order testing of cement if required. In no case cement of grade less than
43 shall be used.
16. Stone:
Stone for rubble masonry shall be of the best of its kind. It shall be strong, angular, and free
from flakes and must be of quality approved by the Project Engineer. No earthy or discoloured,
weather or water worn stone shall be used.
18. Aggregate:
Aggregate shall be from hard stone of size as specified under item of Work. In general 30mm
(1.25") maximum gauge aggregate shall be used for mass concrete in foundation and 19mm
(3/4") and down gauge i.e. 13mm (1/2”) in average, graded aggregate broken from stone
crusher or pebbles for RCC Work. The Project Engineer shall approve the quality of the
aggregate and if not shall be deported from the Site. The aggregate shall be brought to the Site
from same approved quarry and crusher, in any condition if Contractor wants to change the
quarry, the further approval shall require. In general, the other specification relating to
aggregate shall follow standard practice of Department of Urban Development and Building
Construction.
19. Bricks:
All bricks shall be of first class quality, approved by the Project Engineer. The bricks shall be
free from grit and other impurities such as lime, iron and other deleterious salts, well burnt,
copper coloured, sound, hard, square with sharp edges and shall give ringing sound when
struck with a mallet. Machine made bricks shall be of best quality. Chimney made local bricks
shall be of first class quality available, satisfying above-mentioned properties. Every lot the
quality of the bricks shall be checked by the Project Engineer to ensure the quality of it.
20. Steel:
The reinforcement shall be cold twisted deformed steel or TMT as per schedule, as approved by
the Project Engineer. The reinforcement shall be free from fillings, loose rust, mill scale, paint,
oil, grease, adhering earth or any other material that, in the opinion of the Project Engineer may
impair the bond between the concrete and the reinforcement or that causes corrosion of the
reinforcement or disintegration of the concrete.
Test certificates may be required from the suppliers, and in addition, the Contractor must
undertake tensile and bending tests on random samples of the reinforcement delivered to the
Site. All steel, which is represented by a sample, which fails to reach the minimum requirements
as per standard code of practice is to be removed from the Site immediately.
21. Tiles:
Tiles shall be of smooth surface, durable and of sizes and colours as per schedule. The sample
should be approved by the Project Engineer before commencement of flooring work.
22. Scaffolding:
Scaffolding shall consist of well seasoned Sal wood planks or water proof plywood or steel plate
with necessary battens, planks and metal props with accessories. All the scaffolding members
shall be checked before installation for their strength and stiffness and tied up properly. It shall
42
be fixed and tied together. In case of finished Work such as plastering, painting and
distempering, no part of the scaffolding should touch the structure. Where ladders are used,
gunny bags shall be tied up at the ends to prevent any damage to Work by sliding or tipping.
23. Timber:
Sal wood shall be used in general if otherwise specified and shall be of the best quality
available, perfectly dry, free from knots, cracks, shakes other defects and any appearance of
rot.
24. Glass:
Glass shall be of approved make of thickness as stated in the schedule of quantities and
visually clear when viewed from any direction. It shall be free from bubbles, waves and all other
defects.
43
Section VII. Drawings
44
Section VIII. Bill of Quantities
45
Section IX. Forms of Securities
46
Bid Security (Bank Guarantee)
Whereas, [name of Bidder] (hereinafter called “the Bidder”) has submitted his bid dated [date] for the
improvement of east side surface drain at TIA (hereinafter called “the bid”).
Know all people by these presents that We [name of Bank] of [name of country] having our registered
office at [address] (hereinafter called “the Bank”) are bound unto Tribhuvan International Airport Civil
Aviation Office(TIACAO),Civil Maintenance Division, Gauchar, Kathmandu (hereinafter called “the
Employer”) in the sum of ................... for which payment well and truly to be made to the said Employer,
the Bank binds itself, its successors, and assigns by these presents.
Sealed with the Common Seal of the said Bank this [day] day of [month], [year].
(1) If, after bid opening, the Bidder withdraws his bid during the period of bid validity specified in the
Form of Bid; or
(2) If the Bidder having been notified of the acceptance of his bid by the Employer during the period of
bid validity:
(a) fails or refuses to execute the Form of Agreement in accordance with the Instructions to
Bidders, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the Instruction to
Bidders; or
we undertake to pay to the Employer up to the above amount upon receipt of his first written demand,
without the Employer’s having to substantiate his demand, provided that in his demand the Employer will
note that the amount claimed by him is due to him owing to the occurrence of one or any of the three
conditions, specifying the occurred condition or conditions.
2
This Guarantee will remain in force up to and including the date [number] days after the deadline for
submission of bids as such deadline is stated in the Instructions to Bidders or as it may be extended by the
Employer, notice of which extension(s) to the Bank is hereby waived. Any demand in respect of this
Guarantee should reach the Bank not later than the above date.
________________________________________________________________________
[signature, name, and address]
47
Performance Bank Guarantee
To:
Whereas [name and address of contractor] (hereinafter called “the contractor”) has undertaken, in
pursuance of Contract No.............. dated .......................[date] to execute [name of Contract and brief
description of Works] (hereinafter called “the Contract”);
And whereas it has been stipulated by you in the said Contract that the contractor shall furnish you with a
Bank Guarantee by a recognized bank for the sum specified therein as security for compliance with his
obligations in accordance with the Contract;
And whereas we have agreed to give the contractor such a Bank Guarantee;
Now therefore we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
contractor, up to a total of....................................................................... [amount of Guarantee] [amount in
words] such sum being payable in the types and proportions of currencies in which the Contract Price is
payable, and we undertake to pay you, upon your first written demand and without cavil or argument, any
sum or sums within the limits of [amount of Guarantee] as aforesaid without your needing to prove or to
show grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the contractor before presenting us
with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract or of the
Works to be performed there under or of any of the Contract documents which may be made between you
and the contractor shall in any way release us from any liability under this Guarantee, and we hereby
waive notice of any such change, addition, or modification.
This Guarantee shall be valid for at least 30 days beyond the date of issue of Defects Liability Certificate.
Name of Bank
Address
Date
48
Bank Guarantee for Advance Payment
To:
[Name of Contract :]
Gentlemen:
In accordance with the provisions of the Conditions of Contract, Sub clause 11.9(“Advance Payment”) of
the above-mentioned Contract, [name and address of contractor] (hereinafter called “the contractor”) shall
deposit with Tribhuvan International Airport Civil Aviation Office(TIACAO), Civil Maintenance Division,
Gauchar, Kathmandu, a Bank Guarantee to guarantee his proper and faithful performance under the said
Clause of the Contract in an amount of [amount of Guarantee] [amount in words]
We, the [Bank or Financial Institution], as instructed by the contractor, agree unconditionally and
irrevocably to guarantee as primary obligator and not as Surety merely, the payment to Tribhuvan
International Airport Civil Aviation Office(TIACAO), Civil Maintenance Division, Gauchar, Kathmandu, on
his first demand without whatsoever right of objection on our part and without his first claim to the
contractor, in the amount not exceeding [amount of Guarantee] [amount in words]
We further agree that no change or addition to or other modification of the terms of the Contract or of
Works to be performed there under or of any of the Contract documents which may be made between
Tribhuvan International Airport Civil Aviation Office(TIACAO), Civil Maintenance Division, Gauchar,
Kathmandu, and the contractor, shall in any way release us from any liability under this Guarantee, and we
hereby waive notice of any such change, addition, or modification.
The validity period of the guarantee shall be 30 days beyond the period scheduled for repayment of the
advance payment and the guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until the [name of Employer] receives full repayment of the same amount from
the Contractor.
Yours truly,
Address:
Date:
49
Section X. Rules for Adjudication
Referred to in GCC Sub-Clause 15.1
9. The Adjudicator shall treat the details of the Contract and all
activities and hearings of the Adjudicator as confidential and
shall not disclose the same without the prior written consent
of the Parties. The Adjudicator shall not, without the
consent of the Parties, assign or delegate any of his work
under these Rules or engage legal or technical assistance.
50
11. The Adjudicator shall in no circumstances be liable for any
claims for anything done or omitted in the discharge of the
Adjudicator's duties unless the act or omission is shown to
have been in bad faith.
Payment 13. The Adjudicator shall be paid the fees and expenses set out
in the Adjudicator's Agreement.
16. The retainer and daily fees shall remain fixed for the period
of tenure of the Adjudicator.
Procedure for 19. A dispute between the Parties may be referred in writing by
Obtaining either Party to the Adjudicator for his decision, with a copy to
Adjudicator's the other Party. If the Adjudicator has not been agreed or
Decision appointed, the dispute shall be referred in writing to the
other Party, together with a proposal for the appointment of
an Adjudicator. A reference shall identify the dispute and
51
refer to these Rules.
23. No later than the sixty days after the day on which the
Adjudicator received a reference or, if later, the day on
which the Adjudicator's Agreement came into effect, the
Adjudicator shall give written notice of his decision to the
Parties. Such decision shall include reasons and state that
it is given under these Rules.
52
Adjudicator's Agreement
Identification of Project:
(the "Project")
(the "Employer")
(the "contractor")
(the "Adjudicator")
Whereas the Employer and the contractor have entered into a contract ("the Contract")
for the execution of the Project and wish to appoint the Adjudicator to act as adjudicator
in accordance with the Rules for Adjudication ["the Rules"].
1. The Rules and the dispute provisions of the Contract shall form part of this
Agreement.
Expenses (including the cost of telephone calls, courier charges, faxes and telexes
incurred in connection with his duties; all reasonable and necessary travel
expenses, hotel accommodation and subsistence and other direct travel
expenses).
53
3. The Adjudicator agrees to act as adjudicator in accordance with the Rules and has
disclosed to the Parties any previous or existing relationship with the Parties or
others concerned with the Project.
5. The language of this Agreement shall be English [or in Nepali if both parties
agrees].
SIGNED BY _________________________________________
Witness _____________________________________
Name ___________________________________________
Address ___________________________________________
Date ___________________________________________
SIGNED BY ____________________________________
Witness ___________________________________________
Name ___________________________________________
Address ___________________________________________
Date ___________________________________________
SIGNED BY ________________________________________
Witness ___________________________________________
Name ___________________________________________
Address ___________________________________________
Date _________________________________________
54
Table of Contents
Bidding Data 9
55