CONSTRUCTION JOB PACK

Project Name: OSBL Stage 1


Project CJP WBS No: K-007 DESALINATED WATER SYSTEM
Date December 5, 2018
Project No. Area Sys. # Discipline Doc. Type Seq. No. Revision
18061 - G08 - 00 - PEN - CJP - 001 0

Originator: DC Checker PL Approver RS


Contact Details & Name:
1.0 GENERAL
1.1 Permit to work
Work Permit Required Y/N YES
Special PPE requirements Y/N YES
Specific Time & Date of Hydrotesting: Date: Time:
Notes (specifics e.g. road crossings, confined spaces, tool box talks ect.):
Construction Team (CT) and QA/QC representative to coordinate on the manifold hydrotesting schedule
and timeline.

1.2 Brief description of work:


1. Hydrostatic pressure testing of manifold as shown on the provided marked up Plan Drawing and Isometric.

1.3 Tie-in point numbers:


The tie-in number included in this job pack is IP-104.

2.0 SCOPE OF WORK


2.1. Summary of Work Activities
1. Prepare a marked up P&ID indicating the test limits and highlight line(s) to be tested.
2. Prepare then mobilize work force, tools, equipment and consumables at the job site.
3. Prepare bolts with extra lengths and gasket materials.
4. Coordinate lifting equipment as and when necessary.
5. Notify the QA/QC representative in advance of the hydrotesting activity schedule and timeline.
6. Prepare the test manifold for hydrotesting.
a) Use temporary bolts with extra lengths to specific flange joints providing enough space to insert test
spades and gaskets.
b) Install temporary blind flanges and test spades together with the compressed non-asbestos fiber
(CNAF) gaskets to all flange joints.
Note: Blind flanges shall be of correct flange ratings and test blinds are designed to withstand the
test pressure without distortion.
c. Complete bolting on all flange joints and tighten bolts properly on sequential order leaving one flange
untightened at the hightest point for overflow/bleeding purposes.
d. Install two (2) calibrated gauges, one located at an accessible low point of the test and one gauge
installed at the highest point on the test manifold.
e) Fill up test manifold or spoolpiece with water until overflow to ensure that the entire system is fully filled
up then tighten the flange bolts at the highest point.
f) Connect HP pneumatic hose from the air supply source to the test manifold.
g) With continuous water supply, apply slight pressure to the test manifold then loosen some flange bolts
at the highest point to bleed possible air trapped at the system then tighten the bolts properly.
h) Close the water supply isolating valve and perform hydrotesting to the designed test pressure at
5.4 barg.
i) Maintain/hold the pressure at least one hour duration.
6. Notify the QA/QC representative to witness the hydrostatic pressure testing activity for acceptance and
approval together with issuance of Acceptance Certificate.
7. Depressurize, drain water and dismantle all temporary blind flanges and test spades then cover the
open flanges when necessary.
8. Housekeep the area.
2.2. Method Statement Attached Y/N YES
Remarks: CT to prepare.
3.0 REFERENCE DOCUMENTS
Document Number Description Revision
ASME B31.3 PROCESS PIPING
ASME SECTION.IX WELDING AND BRACING QUALIFICATIONS
A7MI-4-0706-01-SOC-00020 LINE LIST 3
A7MI-4-0706-01-SOC-00025 PIPING AND INSTRUMENTATION DIAGRAM 6
A7MI-4-0706-01-SOC-00033 PIPING ARRANGEMENT DRAWING 3
A7MI-4-0706-01-SOC-00034 PIPING ISOMETRIC DRAWING 5
A7MI-4-0706-01-SOC-00035 PIPING SUPPORT PLAN AND DETAIL DRAWING 4
18061-XXX-00-GEN-XXX-001 HYDROTESTIC PRESSURE TESTING OF PIPING A
Notes: (e.g. 3D Snap shots attached): Refer to attached marked up Plan drawing and Isometric.

4.0 QA/QC
4.1 Weld Procedures Attached Y/N YES

4.2 Test Plans (RT, PWT, MPT, DP) Attached Y/N YES

4.3 Hydrostatic Test Attached Y/N YES

4.4 Flushing/Acidizing Quality Acceptance Attached Y/N NO


Notes: Please refer to Vendor Welding Procedure A7MI-4-0705-01-SOC-00071 and Hydrostartic Pressure Testing
for Piping 18061-XXX-00-GEN-XXX-001.

5.0 PREPARATION OF REQUIREMENTS FROM CLIENT


5.1 Blind List Attached Y/N YES
5.2 Line Flushing Diagram Attached Y/N NO

5.3 Type of Flushing (e.g. steam, water)


6.0 MANPOWER
6.1 Estimated Duration
No. Days Working on Sundays No. People Required
Y N
required
Level 5 procedure is under review.

7.0 MATERIALS
7.1 Material Take Off (MTO) Please refer to isometric drawing for materials Attached Y/N NO

7.2 List of free issued Materials Attached Y/N

7.3 Line list & Isometrics Attached Y/N YES

7.4 Support Numbers Attached Y/N


Notes:
Notes:
8.0 CRITICAL LIFTS/CRANE SCHEDULE
8.1 Lift Plans/Studies Attached Y/N YES

8.2 Lift Schedule Attached Y/N

9.0 SUB CONTRACTS


9.1 Contractor Activities Attached Y/N NO

9.2 Contractor List of Services Attached Y/N NO


Notes:

10.0 SCAFFOLDING
10.1 Scaffolding Plan Attached Y/N YES
Note: Flange joints on elevated areas and without access will require scaffold erection.
NO SHUTDOWN JOB PACK
SCHEDULE
NO. TIE-IN NO. DURATION (HOURS) DAY 1 DAY 2 DAY 3 DAY 4 DAY 5 DAY 6
1 IP-101 7
2 IP-106 4
3 IP-111
28
4 ITP-235
5 IP-112
22
6 ITP-112
7 IP-118
8 IP-120 20
9 ITP-152
DAY 7 DAY 8 DAY 9 DAY 10