G08 00 PEN CJP 001 - Rev0
G08 00 PEN CJP 001 - Rev0
G08 00 PEN CJP 001 - Rev0
4.0 QA/QC
4.1 Weld Procedures Attached Y/N YES
4.2 Test Plans (RT, PWT, MPT, DP) Attached Y/N YES
7.0 MATERIALS
7.1 Material Take Off (MTO) Please refer to isometric drawing for materials Attached Y/N NO
10.0 SCAFFOLDING
10.1 Scaffolding Plan Attached Y/N YES
Note: Flange joints on elevated areas and without access will require scaffold erection.
NO SHUTDOWN JOB PACK
SCHEDULE
NO. TIE-IN NO. DURATION (HOURS) DAY 1 DAY 2 DAY 3 DAY 4 DAY 5 DAY 6
1 IP-101 7
2 IP-106 4
3 IP-111
28
4 ITP-235
5 IP-112
22
6 ITP-112
7 IP-118
8 IP-120 20
9 ITP-152
DAY 7 DAY 8 DAY 9 DAY 10