Top Most Used 20 Industrial Engineering (IE) Formula
Powered By Textile and RMG Solution Visit:
CycleTime 75
Performance Rating 75%
Allowances 10
SAM (Standard Allowed Minute) 1.10
CycleTime 30
Performance Rating 85%
SMV (Standard Minute Value) 0.43
SMV 5.5
CPM 10.7
CM (Cost of Manufacturing) 58.85
Machine Utilization (%) = (Actual Machine Run Time X 100) / Total Time
Factory capacity = (Working Hour × Total Worker × Working Day × Factory Efficiency × 60)/Avg. SMV
Working Hour 10
Total Worker 2500
Working Day 27
Factory Efficiency 55%
Factory Average SMV 5.5
Factory Capacity 4050000
Top Most Used 20 Industrial Engineering (IE) Formula
Powered By Textile and RMG Solution Visit:
Cut to Ship Loss (%) = [(𝑇𝑜𝑡𝑎𝑙 C𝑢𝑡 Qty.- 𝑇𝑜𝑡𝑎𝑙 Ship Qty.)/ 𝑇𝑜𝑡𝑎𝑙 C𝑢𝑡 Qty.] × 100