NDT Inlet Guide Vanes
NDT Inlet Guide Vanes
NDT Inlet Guide Vanes
Scope of Work
The Scope of Work is intended as a guide for the Contractor. Contractor is responsible for developing the
proper work, using Prudent Industry Practices for sequences, procedures and processes to perform the
expected scope of work during a Frame 7B Major Inspection. Contractor is responsible for providing critical
path schedule for disassembly and assembly.
All parts removed are to be tagged and bagged, or otherwise location and/or part number identified.
Disassembly:
External components
1. Visually inspect all compartments
2. Check unit alignment
3. Remove all roof interference
4. Remove turbine roof & side panels as required
5. Remove cooling & sealing air piping as required
6. Remove all fuel gas /oil/water/atomizing air/fuel oil pigtail pipes
7. Remove all upper-half gas manifolds
Combustion Components
1. Remove all combustion covers
2. Remove all combustion liners, cross-fire tubes & retainers
3. Remove all upper half transition pieces
4. Remove necessary Combustion Wrapper Bolting
5. Remove Upper-Half Combustion Wrapper
6. Remove Transition Pieces
Case Removal, Turbine, Compressor, Inner Barrel, First Stage Support Ring and Nozzle:
1. Install mechanical casing support jacks
2. Remove all turbine shell bolting
3. Remove all fwd & aft compressor casing bolting
4. Remove all compressor discharge casing bolts
5. Remove all inlet bellmouth casing bolts
6. Remove all exhaust frame/diffuser bolts
7. Remove upper halves fwd & aft compressor casings
8. Remove upper-half turbine shell
9. Remove upper-half compressor discharge casing
10. Remove upper-half inlet bellmouth
11. Remove upper-half inner barrel bolts
12. Remove upper-half inner barrel
13. Remove upper-half 1st stage nozzle (nozzle is being replaced)
14. Remove upper-half 1st stage nozzle support ring
15. Remove upper-half exhaust frame / diffuser
16. Remove exhaust plenum top hat (cap)
17. Remove exhaust plenum side panel (wing)
18. Remove exhaust frame/exhaust plenum flex seals
19. Remove exhaust diffuser/exhaust plenum flex seals
20. Remove exhaust plenum fwd wall
21. Remove exhaust plenum chamber insulation panels
22. Remove aft exhaust diffuser insulation panels (for bolt removal)
10
Attachment 1
Scope of Work
Rotor Removal
1. Remove all rotor coupling bolts
2. Check accessory shaft alignment
3. Break accessory and load coupling
4. Inspect accessory shaft
5. Install compressor rotor support & split marriage coupling
6. Remove all upper-halves of bearing housings
7. Record all bearing/seal clearances
8. Remove turbine rotor
9. Remove as required 1st, 2nd and 3rd stage turbine buckets
10. Remove compressor rotor and prep for shipping
11. Set compressor/turbine rotors on truck
12. Prep rotor for shipping
Disassembly Inspection:
Contractor and Owner to mutually determine as parts are removed, which parts will be required to be sent
to Repair Facility(ies) for refurbishment
1. Take & record a full set of turbine clearances
2. Take & record a full set of compressor clearances
3. Inspect all turbine/compressor components
4. Record all damage to compressor/turbine components
5. Measure/inspect turbine bearings
6. Measure and record all rabbit fits
7. Record all bearing and seal clearances and rotor diameters
8. As found rotor thrust
Cleaning/NDT/Inspection
1. Clean and NDT IGV’s
2. Clean all compressor stator blades
3. NDT all compressor stator blades
4. Clean all inlet guide vanes
5. NDT all inlet guide vanes
6. Clean all bolting
11
Attachment 1
Scope of Work
7. Clean all bolt hole area's on fwd & aft rotor stub shafts
8. NDT all bolt hole area's on fwd & aft rotor stub shafts
9. NDT all turbine bearings
10. NDT coupling bolts
11. NDT on all couplings
Unit Pre-Assembly:
1. Clean out lower-half turbine/compressor casings
2. Assemble 1st stage shroud blocks
3. Assemble 2nd stage shroud blocks
4. Assemble 3rd stage shroud blocks
5. Assemble lower-half 1st stage nozzle
6. Assemble lower-half 2nd stage nozzle segments
7. Assemble lower-half 3rd stage nozzle segments
8. Carry out final inspection of lower-half turbine/compressor casings
Unit Assembly:
Note: Buckets can be installed either at the shop or on site at Contractor’s discretion
12
Attachment 1
Scope of Work
13
Attachment 1
Scope of Work
1. Provide FE/TFA, supervision and craft as required. Start up to occur immediately following
outage without Contractor incurring stand by time or delay in providing support. If start up is
delayed, Contractor will minimize Owner cost to the degree Contractor can apply personnel to
demobilizing work site.
14