MS009 Water Treatment Plant
MS009 Water Treatment Plant
MS009 Water Treatment Plant
4.0 Responsibilities
4.1 All works associated with above mentioned project limited to construction of Water
treatment plant and all other associated works will be the responsible in accordance
with the contract.
4.2 Resources for Personnel is as follows:
4.2.1 Site Engineer
He is responsible to carry out the work as per the Project Specification,
approved drawing for construction, approved shop drawings, approved
method statements, co-ordinates with the Sub contractor and ensures all
works are provided, inspected & approved by the Engineer.
He/she is also responsible to ensure the specialized sub-contractor has
adequate equipment, tools, materials, manpower are in place before starting
the works.
4.2.2 QA/QC Engineer
He/she is responsible to ensure work has been done as per the specification
and drawings, inspections are done as per Quality Control Procedure and
offer works for Engineer inspection.
4.2.3 Supervisor/Foreman
Carrying out the work and the proper distribution of all the available
resources in coordination with the site engineer on a daily basis.
Daily reports of the works achieved and coordinate for the future planning
with the Site engineer.
Incorporate all the quality control and Safety requirements as requested by
the concerned Engineer.
Met with any type of unforeseen incidents or requirements and reporting
to the site engineer immediately
5.0 RESOURCES:
5.1 Materials.
a. Activated Carbon Filter
b. Pumps
c. Dosing System
d. Cartridge filter
e. UV System
f. UF System
g. RO System
h. Pipes
i. Cable Tray
j. Pipe and Cable Tray Supports
k. Electrical Cables
l. Tanks
m. Valves
n. Fittings
o. Control Panel
5.2 Equipment
a. Tool Box
b. Measuring Tape
c. Hacksaw
d. Spirit Level
e. Drill Machine / Grinder
f. Pressure Gauges
g. Hand Pump/Electric Pressure Pump
h. Ammeter/Voltmeter
i. Welding Machine
5.3 Personnel
a. Site Engineer
b. QA/QC Engineer
c. Supervisor/Foreman
d. Skilled workers
e. Labourers
6.0 DEFINITIONS & ABBREVIATIONS
a. QC - Quality Control engineer
b. HSE - Health and safety plan
c. MEP - Environmental management plan
d. MS - Method Statement
7.0 PROCEDURE
METHOD AND SEQUENCE OF CONSTRUCTION
7.1 Preparation of all approved construction drawings (all units of the water treatment
plant)
7.2 Setting out of the treatment plant, as per surveyed data(ALL UNITS)
7.3 Excavation will be done as per method statement of excavation
7.4 Dewatering where necessary will be done as per MS-####
7.5 All concrete structures will be done as per MS-####
7.6 Block work will be constructed as per MS - ####
All stages of construction will need Engineer approval before moving next stage. example,
setting out will be approved prior starting excavation, and after excavation done the
engineer approval of level will be required prior to pour blinding concrete, this procedure
will be followed in each stage
Upon structure completion of Water treatment plant units, which compiles flocculattion,
sediment tanks, Filters and filter washing, service water tank, Disinfection or chemical
dosing unit Clean water tank and ancillary units, will be followed by mechanical
installations.
7.8 Installation procedure of Pipe Work for Water Treatment Plant
7.8.1 General Requirements
All the materials received at site will be inspected, upon receipt.
Any discrepancies, damages, etc. should be notified and report to the supplier
for further action.
All construction/ inspection/ testing works shall be carried out in accordance
with specifications.
Work shall be carried out by the site foreman staff under the guidance of site
engineer and shall further be checked and approved by Engineer.
If any damage for the material has been happened on the site, the site persons
will be responsible for the damage.
7.8.2 Handling
7.8.3 Installation
Mark the routing of pipe work according to approved shop drawings.
6.2.5.1 Pipe Work (for uPVC Pipes)
Measure length of pipe required, making due allowance for
any pipe fittings to be used. Cut the pipe to the measured
length.
Ensure that the ends are cut square and clean all burs.
A chamfer to the depth of half wall thickness to be applied to
each spigot.
The spigot and socket to be jointed
should be carefully examined for any damage which could
impair the jointing procedure.
The spigot insertion depth should be measured as
the depth form the mouth to the shoulder of the socket.
The insertion depth should be marked on the spigot
using marker.
The jointing system for piping system is “Solvent weld.”
The mating areas of the spigot and the socket should
be thoroughly cleaned using the pipe cleaner and a clean rag.
Using a brush apply an even layer solvent cement to the
spigot and socket mating surfaces. The glue should be applied
in a lengthwise direction and not with a circular motion.
The glue should be applied simultaneously to the spigot and
socket by two people.
Immediately following gluing application ensure that the pipe is
suitably anchored, and push the spigot home in the socket
without turning the pipe.
The spigot should be inserted with a steady, continuous
motion and held in place for 20 seconds.
Remove the surplus glue from around the mouth of the socket.
Leave the joint undisturbed for five minutes, and then handle
with reasonable care.
6.2.5.2 Pipe Supports
For the pipes above ground supports will be given of ring type
pipeclamps with rubber packing and for pipes at more height
will be given standard galvanized channel support with pipe
clamps.
6.3 Installation for Pressure Testing
6.3.1 Procedures for Installation
Check first the approve drawing submitted for the location and marking of
the pipes.
Prepare the necessary materials for installation
Start layout of the pipe as per coordinated marking and levels.
After the layout make a support for all the pipes using thrust block, rubber
clamp and steel bar.
Prepare the materials for the pressure testing such as plugs, pressure
pump, pressure gauges and other equipment / tools required.
Clean the edge of the pipe and put plug on locations where valves are not
required.
After putting plug, install the pressure pump with threaded nipples, connect
to the valve for the purpose of bleeding to the part you can remove the air
inside the pipelines then connect a G.I Tee to interlink between the
calibrated pressure and the pipe to be tested.
Fill entire system with water through any faucet by meansof pail and put it
on the pressure hand pump.
Check for any leak in the connection /layout. If so, modify/ rectify first before
applying the pressure.
The working pressure of the pipe is 4 bars; however, for testing Pressure
the lines until it reaches the test pressure of 6 bars which is1.5 times of the
working load.
Check the points / connections again for leakage. If there is no leak close
the valve and remove the pressure hand pump.
Maintain pressure in the pipe line for at least 4 hours.
Prepare the necessary documents such as drawings, pressure test
certificate indicating the start and end, together with the pressure rated and
losses and get signature from Consultant
After checking the bar rating passed, remove the pressure of the pipes up to
1 bar by experience person.
After remove the end plugs and valves.
Remove the water and flushed the lines.
Close all the end points using masking tapes.
6.4 Pump Room Equipment Installation
6.4.1 Mark out the location of the plinths for the pumps and filters as per
approved shop drawings and cast the plinths in place up to the required
thickness.
6.4.2 Fix the interconnected pipe work between the pumps, filters and the
suction and delivery lines as per the approved drawings.
6.4.3 Route and level shall be as per the approved drawing and clearance to
be maintained as required.
6.4.4 After installation of equipment’s & piping’s in pump room are completed
and raise stage by stage WIR for getting approval from the Engineer.
6.4.5 Installation of cable tray and trunking shall be carried out as per
specification and approved shop drawing.
6.4.6 Cable tray and cable trunking and related accessories shall be by an
approved manufacturer and the material should be inspected prior to the
installation of work.
6.4.7 Route and level shall be as per the approved drawing and clearance to
be maintained as required.
6.4.8 Support spacing to be executed as per the approved drawing and site
condition.
6.4.9 Spacing between others services shall be coordinated on the site.
6.4.10 Remove burrs and sharp edges from cable trays/trunking.
6.4.11 Fasten cable tray/ cable trunking to building structure.
6.4.12 Any cutting or drilling support channel, threaded rod, tray/trunking
edges shall be cleaned up and painted with zinc paint.
6.4.13 6.4.14 Install cable tray/trunking with enough space to permit access for
installing cables. Install the cable tray/trunking with proper alignment
with other services.
6.4.14 After installation clean and cover it properly to avoid any mechanical
damages from other services.
6.4.15 Install cables only when cable tray/trunking installation has been
completed and raise stage by stage WIR for getting approvalfrom the
consultant as per approved ITP.
6.4.16 Install the control panel.
6.4.17 Terminate the cables at the control panel as well as the equipment and
pumps.
7.0 METHOD STATEMENT FOR TESTING AND COMMISSIONING
Scope:
To test and commission the water treatment plant system.
1. Check for fresh water supply line in the pump room for filling and make up.
2. Check for incoming power supply for the control panel
3. Verify the connection and termination of control panel
4. The water has to be filled to the required level in the raw water tank.
5. After that close and open all the necessary valves to start the system
6. First set to open the butterfly valve on the suction line and discharge line.
7. Run the filtration pump on HAND position to start the operation
8. Check the direction of rotation of pump is proper
9. The chemical system is filled with appropriate reagents and working properly.
10. Check for any leakage in the piping, if there is turn OFF the pump and close all the
valves to rectify the fault.
11. If there is no leakage or fault in the system, continue the operation.
8.0 Quality Control
8.1 Check all the materials delivered to site are inspected properly as perapproved
MAR (Material Approval request) and proper storage.
8.2 Work shall be carried out by the site personnel under strict supervisionand
guidance of the supervisors/foreman / engineers.
8.3 Work inspection Request (WIR) will be submitted for witness and holdpoints as
detailed in the attached Inspection and Test Plan for MEP.
8.4 Pressure gauges for testing will be calibrated and certificates will be provided
during testing.
9.0 Attachments
9.1 Inspection Test Plan
9.2 Risk assessment
9.3 Manufacturers Manual
9.4 Checklist for Mechanical Installation
9.5 WIR format
SE - Site Engineer
QC - Quality Engineer
FR – Foreman
WIR - Work Inspection Request
6.7 Flocculation,
4.1.3 Flocculation
a. Basin Design - Inlet and outlet design shall minimize short-circuiting and destruction of
floc.
b. Detention – The detention time for floc formation should be at least 30 minutes
with consideration to using tapered (i.e., diminishing velocity gradient)
flocculation. The flow-through velocity should be not less than 0.5 nor greater
than 1.5 feet per minute.
c. Equipment - Agitators shall be driven by variable speed drives with the peripheral
speed of paddles ranging from 0.5 to 3.0 feet per second. External, non-
submerged motors are preferred.
e. Other designs - Baffling may be used to provide for flocculation in small plants only
after consultation with the reviewing authority. The design should be such that the
velocities and flows noted above will be maintained.