Oil Tank 750 m3
Oil Tank 750 m3
Oil Tank 750 m3
:
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 1 of 15 0
- SDCC : Original
- CNEEC : Copy
- Originator: Copy
Mech. Engineer Area Manager SMR Site Manager -WBS/Sect : Copy
00
TABLE of CONTENT
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 2 of 15 0
No Description Page
COVER 1 OF 15
TABLE of CONTENT 2 OF 15
1.0 TITLE 3 OF 15
3.0 OBJECTIVE 3 OF 15
4.0 REFERENCE 3 OF 15
8.0 SCOPE 5 OF 15
1. TITLE
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 3 of 15 0
Precedure for fabrication of Oil tank for 3 x 330 MW Coal fired steam power
generation.
2. SCOPE OF APLICATION
This procedure describes the fabrication of Oil Tank set PLTU 1 West Java
( Indramayu ) – Indonesia.
In this connection, if any modification to this instruction it shall be carried out after
reviewed by the concern person.
3. OBJECTIVE
This procedure is to ensure that the fabrication of the oil tank set following the client
requirement, code and specification and to obtain good quality workmanship during the
installation works. And this is also as systematic guidance for concerned Supervisor or
Engineer to oil tank .
4. REFERENCE
4.1. SDCC-001, Guidelines for Establishing Project Procedure.
4.2. E03033-PR-3001, Construction Execution Plan.
4.3. MC-001, Material Receiving.
4.4. MC-003, Moving Storage Procedure.
4.5. Arrangement Drawing from Vendor.
5. DESCRIPTION OF PROCEDURES
5.1. Material
5.1.1. General
All materials required for completion of fabrication and ensure that
material to be procured in the field are as follows:
5.1.1.1 Old materials having any loss of effective thickness due to rust
shall not be used.
5.1.1.2. All distortion caused during transportation or handling shall be
corrected by approved method.
5.1.2. Delivery
5.1.2.1. Take delivery of equipment to be fabricated and inspect for
damage.
5.1.2.2. Complete a list of all materials delivered to site and provide
a copy to Client.
5.1.2.3. If following the delivery, equipment members are found to have
defect, bends from the required shape they shall be corrected
and repaired prior to erection.
5..1.2.4. Damage equipment members shall be reported, in writing to the
Client.
5.1.3. Handling
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 4 of 15 0
5.1.5. Protection
5.1.5.1. Use all means to protect steel members and packaged materials
from corrosion and deterioration.
5.1.5.2. Protect the work and materials from damage by all other trades.
6. RELATED DOCUMENT
Applicable Law codes and Regulation
1) The welders who weld pressure parts and non pressure parts joints such as all
permanent and temporary clips and lugs ,to pressure parts shall be qualified
in
accordance with ASME Section IX.
2) The list of qualified welder and previous welder’s records shall be submitted to
the purchaser’s inspector for review prior to commencement of welding works.
3) If new test for welders was taken the welder performance qualification test
shall be performed in accordance with the welders qualification test
procedure.
8. SCOPE
The following materials shall be identified by the mill marking on actual materia And
heir material identification record shall be made.
2) .CM shall be done with LSD (low stress die stamp) or white color paint in
accordance with the requirements show in the following table and shall be
circled with paint to find out the location of them early.
3). CM is retraceable marking for mill marking, which consists of tank number,
part or shell course
number serial number ,material spec, and original heat no ,or plate no.
4).CM shall be so located as to be plainly visible when CM disappears in shop
paint it shall be, re-marked on the painted surface of materials.
5). The location of coded marking is as follows.
Approx. 200 mm
inside
Heat No &
Coded Marking
Shell Plate
1 The plate shall be cut by thermal means and the contamination such as oxide scale
slag which
would be adversely affected to the quality or strength of the weld shall be removed.
d
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 7 of 15 0
d
A A
A- A’
Note:
( *1 ) Repair weld shall be performed by a qualified welder and approved welding
Procedure specification ( WPS )
4 . If the tolerances of bevel are not specified in the drawing they shall be as follows.
a a a
b b
a
Single –V Square-groove Double – V
Type of Tolerance
Square-groove ±2.5~ -
Single-V
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 8 of 15 0
±2.5~ ±1.5
Double-V
1) The dimension inspection of shell plates shall be performed prior to bending. The
dimension tolerances of shell are as follows
A E B
Measurement items Tolerance mm
Width (AC,BD,EF ) ±2
Length (AB, CD) `± 2
Diagonal (AD,BC ) 3 Max
C F D
2) The curvature of shell plate shall be checked by a curvature gauge with the tank
radius as shown below. The deviation (C1, C2, E) of curvature on the inside surface
of shell plate shall be 3 mm and less.
C1
C2
E
Gauge 1.5 m
The dimensional tolerance of nozzle and manhole attached to shell plate are as follow.
Manhole Projection ( C ) ± 10
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 9 of 15 0
Inclination of ± 1.0~
Flange face to neck ( D)
O.D of manhole neck ( A ) ±3
O.D of flange ( B ) ±4
Thickness of plate flange -0 ,+3
Location ( H,L ) ± 20
D B
C
A
H
Measurement
Tolerance ( mm)
items
d 1 ,d2 ` 1.5
D1 ,D2 ` 3.0
d1 D1
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 10 of 15 0
d2
D2
The curvature of top angle and shell stiffener shall be checked by means of placing
them along the marked line of tank radius on platform.
Length ( L ) ` 3.0 / 6 m
Warp distortion( S ) 1.15% of length ( Max .9.0
mm)
Twist distortion( S ) Max .5.0 mm
Curvature ( E) ` 3.0 / 6 m
S
S
Warp Twist
Girth Butt
Longitudinal butt All + 1.5
Branch connection
2.3) Plate
± 1.5 ±1.5
± 2.0 ±2.0
13. VISUAL INSPECTION
13.1. Regardless of any others method of inspection used , all weld shall be subjected
to v Visual inspection and they shall meet the following requirements.
1).The welded parts shall be free from crack, overlap , convex , ripples, slag and
others deleterious defects and undercut shall not exceed 0.4 mm in depth
2).The reinforcement of the welds on all butt joints on each side of the plate shall not
exceed the following thickness
T ≤ 13.0 ¼t ¼t
13.0 < T ≤ 25.0 3.0 ¼t
25.0 < T 1/8 t 1/8 t
3). Complete fusion and required penetration exists at the joint between the weld
metal and the Base metal.
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 13 of 15 0
13.2. Welded that fail to meet the visual inspection criteria given item 9.1 shall be repair
before Hydrostatic testing in accordance with the following.
13.3. The gasket contact surface of the flange shall be visually checked to ensure
cleanliness and is free from any surface defect.
13.4. All the flange surface shall be protected from mechanical damage an the time.
14.1 The extent of NDE is as show in the following table and shall be carried out in
accordance with the NDE procedure.
14.2 Final NDE ( MT ) for butt weld joint shall be carried out after PWHT ( if any )
Abbreviation
CW : Completed Weld N/A : Not Applicable
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 14 of 15 0
15.1 When defect appears to be removed , repair weld shall be made accordance with
the approved welding procedure specification and welding repair procedure
Repaired area shall be re-examined by the same method originally taken
15.2 Defects in weld shall be repaired by chipping , grinding or gouging out the defects
from one side or both sides of the joint as required and welding
15.3 When the defect found is a major defect, a detailed defect map and the weld repair
procedure shall be issued for approval. It shall describe the work step of the repair,
applicable NDE and its extend before and after the weld repair, together with WPS &
PQR intended to use. The repair work of any major defect shall not be performed
without any approval.
16.2 Painting
1) Before any painting works the brand name and RAL Code no of paint material
shall be checked against the paint specification.
2). NO painting works shall be done in the following weather condition of the working
area.
(1). Rain, snow ,fog or mist
(2). When the relative humidity is greater than 85%
(3). Dust effects adversely due to high wind
PROCEDURE FOR FABRICATION DOCUMENT NO. :
OIL TANK 750 M3 P-T3109-CONS-044
PLTU 1 3X330 MW POWER PLANT ISSUED DATE :
INDRAMAYU – WEST JAVA July ’ 04 2009
UNIT ISSUING: APPROVED BY : Site Manager PAGE REVISION
Construction 15 of 15 0
3) At each thickness, step of painting work , number and dry film thickness of coats
shall be confirmed whether , meets the requirement specified in the painting
procedure.
4) Coating system is cured as specified by the paint manufacturer’s printed
instruction for recoat intervals.
5) The painted surface shall be visually inspected for defects such as inadequate
curing, runs and lack of adhesion, pin hole ,mechanical damage etc .all repairs
should be done for defects.
6) After completion of painting work, the final color shall be visually checked with the
standard of color, whether it meets the specified one.
7) The coating work indicating defects, improper application, runs ,sags, damages
excessive repairs, incomplete curing or excessive thickness is subject to
rejection.
The results of inspection and test shall be properly recorded just after the inspection
and test the following inspection and test record shall be submitted to the purchaser
after final inspection.
1).Mill certificates
2).Nondestructive examination report.
3).Dimensional inspection record.
4).Painting inspection record.