Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

CMMI For Acquisition (CMMI-ACQ) Primer, Version 1.3

Download as pdf or txt
Download as pdf or txt
You are on page 1of 57

CMMI® for Acquisition (CMMI-ACQ)

Primer, Version 1.3


Mike Phillips

March 2011

TECHNICAL REPORT
CMU/SEI-2011-TR-010
ESC-TR-2011-010

Software Engineering Process Management


Unlimited distribution subject to the copyright.

http://www.sei.cmu.edu
This report was prepared for the

SEI Administrative Agent


ESC/XPK
5 Eglin Street
Hanscom AFB, MA 01731-2100

The ideas and findings in this report should not be construed as an official DoD position. It is published in the
interest of scientific and technical information exchange.

This work is sponsored by the U.S. Department of Defense. The Software Engineering Institute is a federally
funded research and development center sponsored by the U.S. Department of Defense.

Copyright 2011 Carnegie Mellon University.

NO WARRANTY

THIS CARNEGIE MELLON UNIVERSITY AND SOFTWARE ENGINEERING INSTITUTE MATERIAL IS


FURNISHED ON AN “AS-IS” BASIS. CARNEGIE MELLON UNIVERSITY MAKES NO WARRANTIES OF
ANY KIND, EITHER EXPRESSED OR IMPLIED, AS TO ANY MATTER INCLUDING, BUT NOT LIMITED
TO, WARRANTY OF FITNESS FOR PURPOSE OR MERCHANTABILITY, EXCLUSIVITY, OR RESULTS
OBTAINED FROM USE OF THE MATERIAL. CARNEGIE MELLON UNIVERSITY DOES NOT MAKE
ANY WARRANTY OF ANY KIND WITH RESPECT TO FREEDOM FROM PATENT, TRADEMARK, OR
COPYRIGHT INFRINGEMENT.

Use of any trademarks in this report is not intended in any way to infringe on the rights of the trademark holder.

Internal use. Permission to reproduce this document and to prepare derivative works from this document for
internal use is granted, provided the copyright and “No Warranty” statements are included with all reproductions
and derivative works.

External use. This document may be reproduced in its entirety, without modification, and freely distributed in
written or electronic form without requesting formal permission. Permission is required for any other external
and/or commercial use. Requests for permission should be directed to the Software Engineering Institute at
permission@sei.cmu.edu.

This work was created in the performance of Federal Government Contract Number FA8721-05-C-0003 with
Carnegie Mellon University for the operation of the Software Engineering Institute, a federally funded research
and development center. The Government of the United States has a royalty-free government-purpose license to
use, duplicate, or disclose the work, in whole or in part and in any manner, and to have or permit others to do so,
for government purposes pursuant to the copyright license under the clause at 252.227-7013.

For information about SEI publications, please visit the library on the SEI website (www.sei.cmu.edu/library).
Table of Contents

Acknowledgments iii

Abstract v

1 Introduction 1

1.1 Purpose and Objectives 1

1.2 CMMI Terminology 2

1.3 Improving Processes for Acquisition 3

1.3.1 Project-Level Process Improvement 3

1.3.2 Organizational Process Improvement 4

2 Process Areas 5

2.1 Project Management Process Areas 5

Project Planning (PP) 6

Project Monitoring and Control (PMC) 10

Integrated Project Management (IPM) 12

Risk Management (RSKM) 14

Solicitation and Supplier Agreement Development (SSAD) 15

Agreement Management (AM) 18

Requirements Management (REQM) 20

2.2 Acquisition Engineering Process Areas 22

Acquisition Requirements Development (ARD) 23

Acquisition Technical Management (ATM) 25

Acquisition Verification (AVER) 27

Acquisition Validation (AVAL) 29

2.3 Support Process Areas 31

Configuration Management (CM) 32

Decision Analysis and Resolution (DAR) 34

Measurement and Analysis (MA) 35

Process and Product Quality Assurance (PPQA) 37

3 Generic Practices 38

Appendix Implementation Questions 42

References/Bibliography 47

CMU/SEI-2011-TR-010 | i
CMU/SEI-2011-TR-010 | ii
Acknowledgments

Thanks to the author of the CMMI-ACQ, V1.2 Primer, Dr. Karen J. Richter. Her work on the Ver-
sion 1.2 report was the basis for this report. Thanks also to Sandy Shrum for her thoughtful and
careful editing of the final version.

CMU/SEI-2011-TR-010 | iii
CMU/SEI-2011-TR-010 | iv
Abstract

This primer identifies practices that are most effective and efficient for projects acquiring
products and services. Focusing on project-level improvement, the primer selects a subset of
practices from the CMMI for Acquisition (CMMI-ACQ) model. These practices include
monitoring and controlling suppliers and contractors as well as ensuring repeatedly effective
execution of product and service development and service delivery. After using this primer,
readers will be able to expand their use of the best practices on their acquisition projects, and their
organizations will be positioned to explore the use of the CMMI-ACQ model.

CMU/SEI-2011-TR-010 | v
CMU/SEI-2011-TR-010 | vi
1 Introduction

The CMMI®for Acquisition (CMMI-ACQ) Primer is a stand-alone guide that describes practices
to use when acquiring products and services. This guide also prepares you for implementing the
CMMI for Acquisition (CMMI®-ACQ) model1 for process improvement.

This primer focuses on efficient and effective acquisition processes and practices that are
implemented by first-level acquisition projects, such as those conducted by a system program
office or program manager in the Department of Defense (DoD) or a purchasing department or
supply chain manager in a corporation.

This primer can also be used by organizations that manage multiple programs (e.g., product
centers, acquisition commands, procurement engineering, supply chain management) to
implement process improvement activities. However, at that organizational level, the CMMI-
ACQ model is more beneficial and complete. (See Section 1.3.)

1.1 Purpose and Objectives

Acquisition projects are complex because they are directed outward and inward. They are directed
outward, toward acquiring products, systems, services, and capabilities to meet a set of
operational expectations. They are directed inward toward ensuring that the acquisition process is
conducted with discipline. The CMMI-ACQ model incorporates this duality by recognizing that
some activities are under the direct control of the acquisition project, while others involve
monitoring or facilitating the success of external partners and suppliers.

Development projects face the challenge of meeting aggressive performance, cost, and schedule
objectives. At the same time, acquisition leaders create a flexible environment for acquisition
projects while drastically decreasing acquisition cycle times and improving credibility. Rising
levels of product and service complexity; increasing software contribution to overall system
functionality; demands for agile, adaptable products; and shortened delivery timeframes place
stress on existing acquisition practices. Congressional and DoD-level guidance emphasizes
software acquisition process improvement, including the measurement of process performance.

The CMMI-ACQ model is designed to influence the outcome of the acquisition process so that it
delivers the right capabilities to users on schedule and at predictable costs through the disciplined
application of efficient and effective acquisition processes. Applying this approach requires a
dedication to defining, implementing, measuring, and maintaining the acquisition processes that
are fundamental to a technically sound project.

Acquisition projects perform a number of processes to achieve success. The primer’s goals and
practices that correspond to these processes are described in general terms to support the
variations in application that occur in different acquisition environments. Because variations in
execution are at the discretion of the acquisition project, the CMMI-ACQ model and primer focus

1
The CMMI-ACQ, V1.3 model is a collection of best practices that is generated from the CMMI V1.3 Framework.
This collection includes acquisition best practices from government and industry for acquiring products and ser-
vices.

CMU/SEI-2011-TR-010 | 1
on “what” should be done not “how” it is done; neither CMMI document prescribes specific
implementation approaches.

1.2 CMMI Terminology

This primer uses terminology from CMMI-ACQ, which groups the process areas into the
following process area categories:

• Process Management (i.e., Organizational Management)


• Project Management
• Support
• Acquisition Engineering

Most Process Management, Project Management, and Support process areas are common to all
CMMI models. This fact makes it convenient to align processes between the acquirer and the
supplier if the supplier is using the CMMI for Development (CMMI-DEV) or CMMI for Services
(CMMI-SVC) model. The Acquisition Engineering process areas are specific to the CMMI-ACQ
model as well as two of the Project Management process areas. This primer includes selected
Project Management and Support process areas that define the requirements for managing and
defining processes within acquisition and all of the acquisition specific process areas.

The Process Management process areas in the CMMI-ACQ model provide details on how to
define and improve processes within the context of the organization in which the acquisition
project resides. The CMMI-ACQ model also contains those Project Management and Support
process areas considered to contain practices at a higher level of maturity than those contained in
this primer. For more information about Process Management and high maturity process areas,
see the CMMI-ACQ model at http://www.sei.cmu.edu/library/abstracts/reports/10tr032.cfm.

Project Planning (PP)


Project Monitoring and Control (PMC)
Project
Integrated Project Management (IPM)
Management Risk Management (RSKM)
Solicitation and Supplier Agreement Management (SSAD)
Agreement Management (AM)
Requirements Management (REQM)
M (RSKM)
Acquisition Requirements Development (ARD)
Acquisition Acquisition Technical Management (ATM)
Engineering Acquisition Verification (AVER)
Acquisition Validation (AVAL)

Configuration Management (CM)


Support Decision Analysis and Resolution (DAR)
Measurement and Analysis (MA)
Process and Product Quality Assurance (PPQA)

Figure 1: Process Areas Covered in this Primer

CMU/SEI-2011-TR-010 | 2
It is important to understand CMMI terminology in both the acquisition and process improvement
contexts before using this primer. For example, in the CMMI Product Suite, the following terms
are important to understand:

• The term project denotes a managed set of interrelated resources that delivers one or more
products to a customer or end user. A project (or program, depending on local interpretation)
refers to the entire acquisition project or, perhaps, to major subsets of the acquisition project.
The scope of the term is tailored to the specific acquisition. (The term project is not used in
this way in the CMMI-SVC model. Instead, the terms work and work group are used.)
• The term organization is typically used to denote an administrative structure in which people
collectively manage one or more projects. Projects share a senior manager and operate under
the same policies. Examples of acquisition organizations include larger or “super” program
offices, product centers, procurement engineering or supply chain management departments,
acquisition commands, program executive officers, and service/component acquisition ex-
ecutives.
• The term work product is any artifact produced by a process.
• The term product denotes a tangible output or a service that is a result of a process and that is
intended for delivery to a customer or end user. A product is a work product that is delivered
to the customer. The term system is not used; the term product is used instead. And the term
product includes services.
• The term supplier is used instead of the term contractor since agreements can take forms
other than contracts, such as a memorandum of agreement.
• The term supplier agreement is used instead of the term contract. A supplier agreement is a
documented agreement between the acquirer and supplier (e.g., contract, license, or memo-
randum of agreement).

Decide how these terms apply in your environment.

1.3 Improving Processes for Acquisition

Process improvement can be viewed from two perspectives: at the project level and at the
organization level. Both are important for sustained process improvement in an acquisition
organization.

1.3.1 Project-Level Process Improvement

Acquisition projects ensure the practices they perform effectively reduce risks associated with
common management, technical, and support issues that arise during the project. The specific
practices in Section 2 and the generic practices in Section 3 represent the project level practices
that can be used to identify gaps in the project’s implementation or process related risks. Careful
use of selected measures can help gain insight into the effectiveness of project level process
implementations.

In addition, higher level acquisition organizations with multiple projects or with oversight
responsibility can use these practices to identify areas that may require a process improvement

CMU/SEI-2011-TR-010 | 3
focus. A project that has well-defined processes has a greater ability to deal with risk and
complexity.

1.3.2 Organizational Process Improvement

Process improvement at the organizational level creates an effective environment and


infrastructure that allows acquisition projects in the organization’s span of control a greater
probability to succeed. When a project has clear guidance, starter templates, historical data, and a
strong process culture at the organizational level, it is more likely to sustain effective practices
and ultimately achieve its objectives.

Acquisition organizations that manage multiple programs (e.g., product centers, acquisition
commands, program executive offices, procurement engineering or supply chain management
departments) can improve by

• working with successful projects to capture success stories;


• measuring the effectiveness of processes across the projects they manage; and
• beginning to build a standard set of acquisition practices, proven by their success in real
projects, for use in subsequent projects.

Senior leaders can establish an infrastructure and strong process culture that rewards projects
building realistic plans and executing according to those plans.

Acquisition organizations can improve the capability of their organizational processes and the
capability of selected project level processes across the organization by using the CMMI-ACQ
model. Process areas to use when improving organizational capability include Organizational
Process Focus, Organizational Process Definition, and Organizational Training. The CMMI-ACQ
model is available at http://www.sei.cmu.edu/library/abstracts/reports/10tr032.cfm.

CMU/SEI-2011-TR-010 | 4
2 Process Areas

The process areas in this section are selected from the CMMI-ACQ model. They represent a
minimal set of processes that cover the best practices needed to successfully address the entire
acquisition lifecycle at the project level. Each acquisition project operates within a unique
environment that influences the definition of its lifecycle.

The acquisition lifecycle, especially as it applies to upgrades and modifications, may restart after
a cycle is initiated and partially completed. For example, the acquisition of a major upgrade may
be initiated for a product or service that has already been developed, fielded, and placed into
operation. In these cases, the deployment of CMMI-ACQ could result in the upgrade acquisition
being considered a new acquisition lifecycle, with complex implementation requirements of its
own that may impact another acquisition lifecycle already underway. Or, in other cases, the
acquisition lifecycle may continue throughout the product’s lifecycle, including disposal.

The process areas in this section list goals in bold text. Below each goal are numbered statements
that reflect the recommended practices. For more extensive treatment of these goals and practices,
see the CMMI-ACQ model, which also includes subpractices, example work products, example
supplier deliverables, and references to other related process areas.

2.1 Project Management Process Areas

Project Management process areas cover project management activities related to planning,
monitoring, and controlling projects, including ensuring the alignment of plans and work products
with requirements. In addition, they include activities that ensure the products or services acquired
can make the transition into operational use and be maintained during the operational life of the
product or service. Two acquisition specific process areas are included. The first describes the
activities leading to the signing of an agreement with chosen suppliers. The second describes the
activities associated with managing the resultant agreement with the chosen suppliers.

CMU/SEI-2011-TR-010 | 5
Project Planning (PP)

The purpose of Project Planning is to establish and maintain plans that define project activities.

Project planning starts by setting the acquisition strategy and follows with planning the
acquisition process in ever-increasing levels of detail. The resulting plans should be reviewed for
consistency with the overall acquisition plans. The acquirer’s and supplier’s project planning
processes are continuously conducted, as the plans evolve to meet the project’s needs.
If an existing product is to be replaced as part of the acquisition, the acquirer may be required to
consider transition from operation and the disposal of the existing product as part of the planning
for executing the new product. Any such transition activities should be included in the project
plan as well as provisions for accommodating such specialized requirements.
1. Estimates of project planning parameters are established and maintained.
1.1 Establish and maintain the acquisition strategy.
The acquisition strategy relates the acquisition objectives , constraints, availability of
assets and technologies, consideration of acquisition methods, potential supplier
agreement types and terms, accommodation of end user considerations, consideration of
risk, and support for the project over its lifecycle.
1.2 Establish a top-level work breakdown structure (WBS) to estimate the scope of the
project.
The WBS should list the tasks for the entire project, including activities performed by the
acquisition project as well as suppliers and other stakeholders (e.g., test community,
operational users). Include all these parties to ensure the planning effort includes the
scope for the entire acquisition.
1.3 Establish and maintain estimates of work product and task attributes.
Estimates of the attributes of the work products and tasks are used to bound the budget
and schedule.
1.4 Define project lifecycle phases on which to scope the planning effort.
Typical lifecycle choices include single-step or evolutionary incremental. Include in
planning the entire known lifecycle from user needs through initial and subsequent
upgrades. The acquisition organization should consider the full collection of supplier
agreements within a project context to ensure an integrated approach rather than an
approach that deals with activities individually. An integrated approach supports project
planning activities on occasions when some elements of the acquisition or lifecycle may
be out of the control of the acquisition organization.
1.5 Estimate the project’s effort and cost for work products and tasks based on estimation
rationale.
In addition to creating an estimate of project work products, the acquisition organization
should have its estimate independently reviewed by those external to the project to
validate the project estimate. Be sure to include the effort and cost supporting execution
of the acquisition processes as well as the effort and cost supporting development of the
product or service. Estimates of the effort and cost of work products and tasks are used to
establish the overall project budget and schedule.

CMU/SEI-2011-TR-010 | 6
2. A project plan is established and maintained as the basis for managing the project.
2.1 Establish and maintain the project’s budget and schedule.
The acquisition project’s budget and schedule should be created and maintained for the
duration of the project. The budget and schedule should include lifecycle-related
activities of the acquisition organization itself, the supplier, supporting organizations,
suppliers that support the acquisition organization, and other stakeholders.
2.2 Identify and analyze project risks.
Identify risks from multiple perspectives (e.g., acquisition, technical, management,
operational, supplier, support, and user) to ensure all project risks are considered in
planning activities.
2.3 Plan for the management of project data.
Consider how data will be shared across all relevant stakeholders, including informal data
as well as formal project data and plans. Create plans for managing data within integrated
teams and the infrastructure required to manage data among the supplier, operational
users, and other relevant stakeholders. Decide which project data and plans require
version control or more stringent configuration control and establish mechanisms to
ensure project data is controlled. Consider the implications of controlling access to
classified information and sensitive but unclassified information (e.g., proprietary, export
controlled, and source selection sensitive information) and other access-controlled data.
2.4 Plan for resources to perform the project.
Plan the resources required for the acquisition project as well as tools and infrastructure
required during the life of the project. Include resource planning for integration and test
facilities.
2.5 Plan for knowledge and skills needed to perform the project.
Plan for knowledge and skills required by the project team to perform their tasks.
Knowledge and skill requirements can be derived from project risks. For example, if the
project team is acquiring a software-intensive product, ensure expertise in systems and
software engineering exists on the project team or provide training for the project team in
these areas. Include orientation and training for the project team and stakeholders in
acquisition practices and the domain knowledge required to execute the project.
2.6 Plan the involvement of identified stakeholders.
Stakeholders can include operational users and project participants from test or other
support communities as well as potential suppliers. When acquiring products or services
that must interoperate with other products or services, plan for the involvement of
stakeholders from other projects or communities to ensure the delivered product or
service can perform as required in its intended environment.
2.7 Plan transition to operations and support.

CMU/SEI-2011-TR-010 | 7
The acquisition project is responsible for ensuring the acquired products not only meet
specified requirements (see the Acquisition Technical Management process area) and can
be used in the intended environment (see the Acquisition Validation process area) but
also that they can be transitioned into operational use to achieve the users’ desired
mission capabilities and can be maintained and sustained over their intended lifecycles.
The acquisition project is responsible for ensuring reasonable planning for transition into
operations is conducted, clear transition criteria exist and are agreed to by relevant
stakeholders, and planning is completed for product maintenance and support of products
after they become operational. These plans include reasonable accommodation for known
and potential evolution of products and their eventual removal from operational use.
Planning for transition includes establishing the strategy for support (e.g., source of
repair) through organic support infrastructures, supplier logistics support, or other
sources. It can also include defining the levels of support to be established (e.g.,
organization, intermediate, and depot). The strategy is important because it drives most of
the other transition planning activities as well as product design considerations.
Planning includes identifying and providing for initial spares, operational and support
training capabilities, facilities, etc. Eventual disposal of the product should also be
considered as well as disposal of existing products to be replaced.
The roles and responsibilities of the acquirer, supplier, and user should be defined for
lifecycle support of the product. Explicitly identifying organizational responsibility for
support (i.e., level 1 maintenance) and for enhancements (i.e., level 2 maintenance)
ensures that relevant stakeholders are involved early in the acquisition project’s planning
processes.
Responsibility for capability enhancements during the support phase should be assigned.
Criteria used to support the assignment of responsibilities should include the magnitude
and complexity of the envisioned change, the domain knowledge and experience
required, and the acquisition expertise required.
2.8 Establish and maintain the overall project plan.
The overall project plan can take on many forms and may even be found in multiple
plans, such as the acquisition strategy, single acquisition management plan, program
management plan, lifecycle management plan, and systems engineering plan.
Regardless of its form, the plan or plans should address the acquisition strategy as well as
the cradle-to-grave considerations for the project and product to be acquired.
3. Commitments to the project plan are established and maintained.
3.1 Review all plans that affect the project to understand project commitments.
The project may have a hierarchy of plans (e.g., risk management plan, systems
engineering plan, and requirements management plan). In addition, stakeholder plans
(e.g., operational, test, support, and supplier plans) should be reviewed to ensure
consistency among all project participants.
3.2 Adjust the project plan to reconcile available and estimated resources.
When available resources (e.g., personnel, facilities, stakeholders, schedule, and funding)
are inadequate to accomplish the project, consider de-scoping the effort to match
available resources. When de-scoping is not feasible, identify and mitigate these risks.

CMU/SEI-2011-TR-010 | 8
3.3 Obtain commitment from relevant stakeholders responsible for performing and
supporting plan execution.
Major project planning should be coordinated with stakeholders and the resulting plans
should be approved by them.

CMU/SEI-2011-TR-010 | 9
Project Monitoring and Control (PMC)

The purpose of Project Monitoring and Control is to provide an understanding of the project’s
progress so that appropriate corrective actions can be taken when the project’s performance
deviates significantly from the plan.

Project monitoring and control functions are directed within the acquisition project early in the
process as acquisition planning is performed and the strategy is defined. As the acquisition project
unfolds, monitoring and controlling are essential to ensuring that appropriate resources are being
applied and that acquisition activities are progressing according to plan. The Project Monitoring
and Control process area involves establishing the planned internal activities and schedule for
completion and then monitoring the status of these activities and work product completions
through measurement and analysis (i.e., metrics). It is important that the acquisition project has
internal processes, plans, and work products that are monitored for satisfactory completion and
progress.
Included in those internal items monitored should be work product completion (e.g.,
specifications, plans, and request for proposal components), staffing levels and qualifications
applied, project performance objectives and thresholds, infrastructure readiness (e.g., tools and
networks) and other activities and products included in project planning. Project risk identification
and mitigation should also be monitored for status.
After one or more suppliers are selected and agreements are established, the role of monitoring
and control becomes twofold: (1) the acquirer continues to monitor and control its activities and
work products, (2) at the same time, the acquirer monitors and controls the progress and
performance of supplier activities that affect the overall project plan.
1. Actual project progress and performance are monitored against the project plan.
1.1 Monitor actual values of project planning parameters against the project plan.
Monitoring schedule, budget, and acquisition activity progress should begin as soon as a
project plan is established.
1.2 Monitor commitments against those identified in the project plan.
Commitments for resources that result in expenditures (e.g., issued purchase orders and
completed deliverables that have been accepted) should be tracked when incurred, even
prior to formal payment, to ensure that future financial and legal obligations are
accounted for as soon as they are incurred.
1.3 Monitor risks against those identified in the project plan.
The acquisition project should manage risks independent of the supplier’s risk
management procedures. Many risks are the responsibility of the acquisition project and
may include sensitive information that should not be shared with the supplier (e.g., source
selection sensitive, re-competition, and internal staffing information).
1.4 Monitor the management of project data against the project plan.
1.5 Monitor stakeholder involvement against the project plan.
1.6 Periodically review the project's progress, performance, and issues.
1.7 Review the project’s accomplishments and results at selected project milestones.

CMU/SEI-2011-TR-010 | 10
1.8 Monitor transition to operations and support.
The acquirer monitors and controls the transition of the accepted product or service
against the plan for transition to operations and support. Readiness is evaluated
throughout the acquisition lifecycle based on transition criteria. Using the previously
defined transition criteria, objectively evaluate the products’ readiness for transition.
As a result of analysis, transition activities and actions may be required of the acquisition
project, supplier, user, or support organization. The analysis may also identify areas for
improvement in future transition activities.
2. Corrective actions are managed to closure when the project’s performance or results
deviate significantly from the plan.
2.1 Collect and analyze issues and determine corrective actions to address them.
Corrective action is taken for both acquirer deviations and when supplier execution does
not align with project planning (e.g., milestones and work product date slippages).
Many issues and corrective actions are the sole responsibility of the acquirer and may
include information that should not be shared with the supplier (e.g., source selection
sensitive, re-competition, and internal staffing information).
2.2 Take corrective action on identified issues.
Corrective action should be applied when execution does not match project planning
(e.g., internal staffing, project plan completion dates, draft and final solicitation, and
supplier agreement award milestone dates).
2.3 Manage corrective actions to closure.
If a corrective action is required to resolve variances from project plans, these actions
should be defined and tracked to closure.

CMU/SEI-2011-TR-010 | 11
Integrated Project Management (IPM)

The purpose of Integrated Project Management is to establish and manage the project and the
involvement of relevant stakeholders according to an integrated and defined process that is
tailored from the organization’s set of standard processes.

Integrated Project Management involves establishing project management processes consistent


with and tailored from the organization’s standard processes. It includes higher level acquisition
guidance, regulations, instructions, and local practices established to be used across various
projects in the local organization. Establishing an integrated project management process that
incorporates and involves relevant stakeholders (e.g., executive level acquisition offices, users,
test organizations, developers, and associated government support organizations) is critical to the
success of the project. This defined project management process is typically defined in an overall
project management plan or equivalent document.
The integrated project management process needs to involve and integrate all relevant acquisition,
development, support, and operational activities. Depending on the size of the project, the size of
the coordination efforts can be significant.
Formal interfaces among project stakeholders take the form of memorandums of understanding
(MOUs), memorandums of agreements (MOAs), contractual commitments, associate supplier
agreements, and similar documents, depending on the nature of the interfaces and involved
stakeholders.
1. The project is conducted using a defined process tailored from the organization’s set
of standard processes.
It is possible that the organization has not established a standard set of processes. If so, the
project should define its own processes appropriate to its needs.
1.1 Establish and maintain the project’s defined process from project startup through the
life of the project.
Often, the defined process for a project is developed by tailoring and integrating higher
level organizational guidance. For example, guidance in the Defense Acquisition
Guidebook (http://akss.dau.mil/dag/) in conjunction with lower level guidance at the
service, component, or other level, would be used by a project to establish the process to
be used to acquire the project’s unique product or service. Where no organizational
process exists, the project develops the defined processes itself.
The project’s defined process is driven by the acquisition strategy. The acquirer’s defined
process is affected, for example, by whether the acquisition strategy includes introducing
a new technology to the organization or consolidating acquired products or services
currently in use by the acquirer.
1.2 Use organizational process assets and the measurement repository for estimating and
planning project activities.
When available, use the results of previous planning and execution activities as predictors
of the relative scope and size of the effort being estimated for the acquisition.
1.3 Establish and maintain the project’s work environment based on the organization’s
work environment standards.

CMU/SEI-2011-TR-010 | 12
The supplier’s work environment should be compatible with the acquirer’s work
environment to enable efficient and effective transfer of work products.
1.4 Integrate the project plan and other plans that affect the project to describe the
project’s defined process.
Tiered plans are often effective for large projects.
1.5 Manage the project using the project plan, other plans that affect the project, and the
project’s defined process.
1.6 Establish and maintain teams.
One of the best ways to ensure coordination and collaboration with relevant stakeholders
(specific goal 2 of this process area) is to include them on a team. For projects within a
system of systems framework, the most important team may include stakeholders
representing other systems as members.
1.7 Contribute process related experiences to organizational process assets.
If a repository of information from previous similar projects exists at the start of the
project, consider retaining the project’s estimates and actual results for use in estimating
future projects.
2. Coordination and collaboration between the project and relevant stakeholders are
conducted.
2.1 Manage the involvement of relevant stakeholders in the project.
The supplier agreement provides the basis for managing supplier involvement in the
project. Supplier agreements (e.g., interagency and intercompany agreements,
memorandums of understanding, and memorandums of agreement) that the acquirer
makes with stakeholder organizations, which may be product or service providers or
recipients, provide the basis for their involvement. These agreements are particularly
important when the acquirer’s project produces a system that must be integrated into a
larger system of systems.
2.2 Participate with relevant stakeholders to identify, negotiate, and track critical
dependencies.
Stakeholder activities that include dependencies critical to the project should be
negotiated with the stakeholders to obtain commitment to perform. The critical
dependencies should be identified in the project plan so those activities can be monitored
and controlled relative to their dependent activities.
2.3 Resolve issues with relevant stakeholders.

CMU/SEI-2011-TR-010 | 13
Risk Management (RSKM)

The purpose of Risk Management is to identify potential problems before they occur, so that risk
handling activities can be planned and invoked as needed across the life of the product or project
to mitigate adverse impacts on achieving objectives.

Risk identification and estimation of probability of occurrence and impact, particularly for those
risks involved in meeting performance requirements, schedules, and cost targets, largely
determine the acquisition strategy. The acquirer has a dual role: (1) Assess and manage overall
project risks for the duration of the project, and (2) Assess and manage risks associated with the
performance of the supplier. As the acquisition progresses to the selection of a supplier, the risk
specific to the supplier’s technical and management approach then becomes important to the
success of the acquisition.
The particular risks associated with integrated teams should be considered, such as risks
associated with loss of inter- or intra-team coordination.
1. Preparation for risk management is conducted.
1.1 Determine risk sources and categories.
Acquisition organizations should initially identify and categorize risks and risk sources
for the project and refine those risks and categories over time (e.g., schedule, cost,
supplier execution, technology readiness, and issues outside control of acquisition
organization).
1.2 Define parameters used to analyze and categorize risks and to control the risk
management effort.
Acquisition organizations should document the parameters used to analyze and categorize
risks so that they are available throughout the project for reference when circumstances
change over time. In this way, risks can easily be re-categorized and analyzed relative to
the original information when changes occur.
1.3 Establish and maintain the strategy to be used for risk management.
2. Risks are identified and analyzed to determine their relative importance.
2.1 Identify and document risks.
2.2 Evaluate and categorize each identified risk using defined risk categories and
parameters, and determine its relative priority.
3. Risks are handled and mitigated, as appropriate to reduce adverse impacts on
achieving objectives.
3.1 Develop a risk mitigation plan in accordance with the risk management strategy.
3.2 Monitor the status of each risk periodically and implement the risk mitigation plan as
appropriate.
Risks should be continually monitored and, when warranted, the mitigation plan should
be adjusted to adapt for change. When the situation requires action, mitigation actions
should be executed promptly based on the mitigation plan.

CMU/SEI-2011-TR-010 | 14
Solicitation and Supplier Agreement Development (SSAD)

The purpose of Solicitation and Supplier Agreement Development (SSAD) is to prepare a


solicitation package, select one or more suppliers to deliver the product or service, and establish
and maintain the supplier agreement.

The solicitation must comply with applicable federal, departmental, and service acquisition
regulations and policies. The solicitation should address activities appropriate to the product
domain or acquisition environment (e.g., supplier process evaluations; operational safety,
suitability, and effectiveness; certifications; architecture evaluations; and interoperability). The
representatives responsible for these activities within the project or stakeholder organizations
should be consulted for proper inclusion of those activities into the solicitation and supplier
agreement development process. The solicitation practices apply equally to initial supplier
agreement actions and subsequent change orders, task orders, etc.
The Solicitation and Supplier Agreement Development process area creates a proactive
environment that enables the acquirer to initialize the relationship with the supplier for the
successful execution of the project. It encourages creation of a supplier agreement that allows the
acquirer to execute its management of supplier activities using other process areas, such as
Agreement Management and Acquisition Technical Management. This encouragement may
include levying a requirement on the supplier to create a project plan that will successfully
execute the supplier agreement, to define and execute the processes needed to achieve success,
and to commit to executing the plan as it evolves during supplier agreement execution.
The Solicitation and Supplier Agreement Development process area involves planning for and
performing the practices necessary to develop and issue a solicitation package, preparing for the
evaluation of responses, conducting an evaluation, conducting supporting negotiations, and
establishing and maintaining the supplier agreement.
1. Preparation for solicitation and supplier agreement development is performed.
1.1 Identify and qualify potential suppliers.
1.2 Establish and maintain a solicitation package that includes the requirements and
proposal evaluation criteria.
For task orders or changes against an existing supplier agreement, ensure the acquisition
project has documented evaluation criteria against which to evaluate the proposed
changes from the supplier.
Define the proposal content that the suppliers must submit with their response.
Examples include:
Evidence of existing organizational processes upon which the project’s processes will
be based and the commitment to execute those processes from project inception
Descriptions in the proposed documents such as the statement of work (SOW),
integrated master plan (IMP), integrated master schedule (IMS), and software
development plan (SDP) of the processes, tasks, and activities characteristic of the
proposed development approach

CMU/SEI-2011-TR-010 | 15
Description of how the proposed approach (e.g., SOW, IMP, IMS, SDP or other
documents) demonstrates a commitment to execute the project using the processes and
methods proposed from project inception. Require suppliers to provide evidence of a
mechanism to encourage and monitor execution of organizational processes at project
start up. Require suppliers to describe measurements that provide project team
visibility into the supplier’s process adherence
Description of how the proposed approach demonstrates high confidence that the size
and complexity of the development and integration effort is understood, the effort and
schedule necessary to develop the required products are estimated with high
confidence, and that the proposed development effort is compatible with and can be
completed within the proposed funding and schedule
Plans appropriate to the scope and content of the project (e.g., integrated management
plan, systems engineering plan, software development plan, and risk management
plan)
Identification of the measurements, including development progress measures, to be
used in the project and made available to the project office
A description of the supplier’s planned use of COTS or re-use of previously
developed hardware or software components, including non-deliverable components
(This description should identify any limitations of data rights and rationale for the
supplier’s confidence that the levels of COTS and re-use can be achieved.)
An approach that provides visibility of development task progress and costs at a level
appropriate for the type of supplier agreement and commensurate with the degree of
risk related to the acquisition
Identification of the work to be performed by lower-level suppliers
Proposed tasks and activities to support product verification, validation, and transition
to operations and support
Technical, non-technical, and product verification requirements to be satisfied by the
supplier
Deliverables that provide the acquisition project sufficient data to evaluate and
analyze the acquired products
Requirements to ensure that the supplier supports each of the acquisition project’s
technical review and validation activities
Requirements for the supplier to establish a corrective action system that includes a
change control process for rework and reevaluation
The acquisition organization should request evidence of adherence to the supplier
organization’s mechanism for project start up in accordance with their defined processes.
1.3 Review the solicitation package with relevant stakeholders to obtain commitment to
the approach.
To ensure objectivity and realism, cost and schedule estimates should be reviewed by
individuals independent of the acquisition project team and supplier’s team.
Representatives from the functional or “home office” organizations within the acquisition
organization, such as finance and engineering, can support these efforts.
1.4 Distribute the solicitation package to potential suppliers for their response and
maintain the package throughout the solicitation.

CMU/SEI-2011-TR-010 | 16
In a competitive environment, ensure all potential suppliers have equal access and
opportunity to provide feedback on the solicitation package. Provide the opportunity for
the selected suppliers and end users to clarify points of ambiguity in the set of required
capabilities as well as any disconnects or concerns with the proposed solution. In a sole
source or change order environment, make sure relevant stakeholders understand the
intent of the new effort or the changes before placing additional work on the supplier
agreement.
2. Suppliers are selected using a formal evaluation.
2.1 Evaluate proposed solutions according to documented proposal evaluation criteria.
The criteria are used to evaluate the suppliers’ technical approach as well as their
management practices, sufficiency of plans, process capability in key project risk areas,
relevant domain experience, cost, schedule, and past performance.
2.2 Establish and maintain negotiation plans to use in completing a supplier agreement.
2.3 Select suppliers based on an evaluation of their ability to meet specified requirements
and established criteria.
3. Supplier agreements are established and maintained.
3.1 Establish and maintain a mutual understanding of the agreement with selected
suppliers and end users based on acquisition needs and the suppliers’ proposed
approaches.
As points of clarification and ambiguities continue to arise after supplier agreement
award, ensure the mutual understanding is revised and maintained through the life of the
project. Ensure that the supplier makes a commitment in the supplier agreement to
execute its proposed processes.
3.2 Establish and maintain the supplier agreement.
The acquisition project is responsible for establishing and maintaining the ground rules
for supplier communication, documenting decisions, and conflict resolution through the
life of the project. The acquisition project facilitates these activities with relevant project
stakeholders. Specific roles and responsibilities of relevant project stakeholders for
interaction with or direction of the suppliers need to be defined, coordinated, and adhered
to.
After the supplier agreement is awarded, the acquisition project should verify that the
supplier is effectively executing its organization’s processes.
After establishing the supplier agreement, the acquirer may find requirements that are no
longer optimal or applicable based on the supplier’s progress or environment changes.
Examples include the availability of new technology, overly burdensome documentation,
and reporting requirements. Changes to supplier agreements may also occur when the
supplier’s processes or products fail to meet agreed-to criteria.

CMU/SEI-2011-TR-010 | 17
Agreement Management (AM)

The purpose of Agreement Management (AM) is to ensure that the supplier and the acquirer
perform according to the terms of the supplier agreement.

The supplier agreement is the basis for managing the relationship with the supplier, including
resolving issues. It defines the mechanisms that allow the acquirer to oversee the supplier’s
activities and evolving products and to verify compliance with supplier agreement requirements.
It is also the vehicle for a mutual understanding between the acquirer and supplier. When the
supplier’s performance, processes, or products fail to satisfy established criteria as outlined in the
supplier agreement, the acquirer may take corrective action.
1. The terms of the supplier agreement are met by both the acquirer and the supplier.
1.1 Perform activities with the supplier as specified in the supplier agreement.
The acquirer and supplier establish and maintain a mutual understanding through
effective, timely, and appropriate communication. The acquirer should clearly identify
and prioritize its needs and expectations, as well as its suppliers’ capabilities. The
acquirer works closely with suppliers to achieve a mutual understanding of product
requirements, responsibilities, and processes that are applied to achieve project
objectives.
1.2 Select, monitor, and analyze supplier processes.
The supplier’s plans and processes are used as the basis for monitoring its activities. The
acquisition project is responsible for ensuring the supplier’s “as implemented” processes
address the needs of the project. The acquisition project should verify that the supplier’s
processes are executed from project inception.
If not performed with adequate care, monitoring can at one extreme be invasive and
burdensome, or at the other extreme be uninformative and ineffective. The acquirer
decides on the necessary level of monitoring depending on the level of risk if the
supplier’s process is not performed correctly. Monitoring activities can range from
reviewing supplier-supplied process data to on-site appraisals of the supplier’s
processes.2
1.2 Ensure that the supplier agreement is satisfied before accepting the acquired product.
This practice involves ensuring that the acquired product meets all requirements and that
customers concur before the product is accepted. The acquirer ensures that all acceptance
criteria have been satisfied and that all discrepancies have been corrected. Requirements
for formal deliverable acceptance and how to address non-conforming deliverables are
usually defined in the supplier agreement. The acquirer should be prepared to exercise all
remedies if the supplier fails to perform.
1.3 Manage invoices submitted by the supplier.

2
For more information on monitoring supplier’s processes, see Understanding and Leveraging a Supplier’s
CMMI Efforts: A Guidebook for Acquirers (CMU/SEI-2007-TR-004). Pittsburgh, PA: Software Engineering Insti-
tute, Carnegie Mellon University, March 2007.
http://www.sei.cmu.edu/publications/documents/07.reports/07tr004.html.

CMU/SEI-2011-TR-010 | 18
The intent of this practice is to ensure that payment terms defined in the supplier
agreement are met and that supplier compensation is linked to supplier progress, as
defined in the supplier agreement. This practice covers invoices for any type of charge
(e.g., one-time, monthly, deliverable-based, pass-through). It covers invoice errors or
issues, changes to invoices, billing errors, and withholding disputed charges consistent
with the terms and conditions of the supplier agreement. The acquirer must also ensure
that appropriate financial and invoice management controls are in place.

CMU/SEI-2011-TR-010 | 19
Requirements Management (REQM)

The purpose of Requirements Management is to manage requirements of the project's products


and product components and to ensure alignment between those requirements and the project's
plans and work products.

Requirements management processes manage all requirements received or generated by the


project, including both technical and nontechnical requirements as well as requirements levied on
the project by the organization. Requirements management is applied to the requirements that are
received from the acquisition requirements development process. Requirements management
includes the direct management of acquirer-controlled customer and contractual requirements (see
the Acquisition Requirements Development process area) and oversight of supplier requirements
management. Requirements are managed and maintained with discipline so that changes are not
executed without recognizing the impact to the project.
Requirements management does not end with the selection of a supplier and an award. The
acquisition project continues to manage high-level requirements, including changes, while the
selected supplier manages the lower level product and product component requirements.
1. Requirements are managed and inconsistencies with project plans and work prod-
ucts are identified.
1.1 Develop an understanding with the requirements providers on the meaning of the
requirements.
The acquirer should identify “authorized” requirements providers and an approved path
by which requirements are provided to the supplier. This identification prevents suppliers
from receiving requirements changes from unauthorized sources that are outside the flow
of the acquirer’s established requirements management process.
1.2 Obtain commitment to requirements from project participants.
Commitment to the requirements by project participants includes having coordinated and
approved documents that define requirements. Changes to requirements may lead to
changes in supplier agreements. These changes must be agreed on by the acquirer and
supplier after appropriate negotiations.
1.3 Manage changes to requirements as they evolve during the project.
Each change to a controlled requirement should be assessed for impact to the project’s
performance, cost, and schedule baselines and to project risk. The existing cost, schedule,
and performance baselines should be changed, as required, to accommodate the
requirements change. If contractual requirements defined in the supplier agreement are
affected by the changes, the supplier agreement also must be aligned with these changes.
1.4 Maintain bidirectional traceability among requirements and work products.
When requirements are managed well, traceability can be established from a source
requirement to its lower level requirements and from those lower level requirements back
to their source requirements. Such bidirectional traceability helps determine whether all
source requirements have been completely addressed and whether all lower level
requirements can be traced to a valid source.

CMU/SEI-2011-TR-010 | 20
Requirements traceability can also cover relationships to other entities, such as
intermediate and final work products, changes in design documentation, and test plans.
Traceability can cover horizontal relationships (such as across interfaces) as well as
vertical relationships. Traceability is particularly needed in conducting the impact
assessment of requirements changes on project activities and work products.
The supplier maintains comprehensive bidirectional traceability to requirements defined
in the supplier agreement by the acquirer, and the acquirer verifies that traceability. The
acquirer maintains bidirectional traceability between customer requirements and
contractual requirements.
1.5 Ensure that project plans and work products remain aligned with requirements.

CMU/SEI-2011-TR-010 | 21
2.2 Acquisition Engineering Process Areas

The Acquisition Engineering process areas establish a consistent set of requirements and
agreements that are derived from stakeholder needs and operational capability statements so that
work products developed internally by the acquirer and work products, delivered products, and
services from suppliers are proven to successfully satisfy end user needs and provide operational
capabilities. These process areas complement the two acquisition specific process areas
considered part of the Project Management category—Solicitation and Supplier Agreement
Development (SSAD) and Agreement Management (AM).

CMU/SEI-2011-TR-010 | 22
Acquisition Requirements Development (ARD)

The purpose of Acquisition Requirements Development (ARD) is to elicit, develop, and analyze
customer and contractual requirements.

Acquisition Requirements Development has two contexts. The first context is the amalgamation
and coordination of stakeholder requirements into a set of customer requirements that defines the
scope and direction of the acquisition. The second context is the refining and elaboration of the
customer requirements into contractual requirements that become the basis of the product and
product component requirements derived and developed by the supplier.
The requirements included in the solicitation package form the basis for evaluating proposals by
suppliers and for further negotiations with suppliers and communication with the customer. The
contractual requirements for the supplier are baselined in the supplier agreement.
When acquiring services instead of products, the same requirements process is used to define
high-level operational needs and to allocate those needs to lower level components of the service
to ensure the resulting service meets the original intent.
1. Stakeholder needs, expectations, constraints, and interfaces are collected and trans-
lated into customer requirements.
1.1 Elicit stakeholder needs, expectations, constraints, and interfaces for all phases of the
product lifecycle.
This practice includes review, coordination, and formalization of top-level operational
needs and requirements with the user.
1.2 Transform stakeholder needs, expectations, constraints, and interfaces into prioritized
customer requirements.
This practice includes the transformation of top level user requirements into engineering-
oriented requirements that are typically included in a solicitation. Requirements also
include non-functional requirements and other attributes such as evolvability,
maintainability, and re-usability, which can drive the definition of the product
requirements and architecture.
This practice also includes defining high-level interface requirements in a system of
systems.
2. Customer requirements are refined and elaborated into contractual requirements.
2.1 Establish and maintain contractual requirements that are based on the customer
requirements.
Requirements include not only the classical functional and performance requirements, but
also interface requirements, whether they are contained in separate interface
specifications or within the requirements specifications.
The acquirer’s level of involvement in allocating system-level requirements to lower
level subsystems and components varies depending on the acquisition environment.
2.2 Allocate contractual requirements to supplier deliverables.

CMU/SEI-2011-TR-010 | 23
As each level of requirements is defined, there is an iterative process of allocation, high-
level design, and requirements definition (for the next-lower level). Beyond the level of
the architecture at which this responsibility has been assigned to the supplier, it is the
acquirer’s role to oversee the adequacy of the supplier’s process and the resultant flow-
down and definition of lower level requirements.
3. Requirements are analyzed and validated.
3.1 Establish and maintain operational concepts and associated scenarios.
Concepts of operations documents or similar documents that define the intended usage
concepts and environments are useful in developing requirements and designs that
ultimately satisfy the user’s operational needs.
3.2 Analyze requirements to ensure they are necessary and sufficient.
3.3 Analyze requirements to balance stakeholder needs and constraints.
Balance stakeholder needs against constraints such as development cost and schedule or
operational and support considerations.
3.4 Validate requirements to ensure the resulting product performs as intended in the end
user’s environment.

CMU/SEI-2011-TR-010 | 24
Acquisition Technical Management (ATM)

The purpose of Acquisition Technical Management (ATM) is to evaluate the supplier’s technical
solution and to manage selected interfaces of that solution.

Acquisition technical management activities involve measuring technical progress and the
effectiveness of plans and requirements. Activities include those associated with technical
performance measurement and the conduct of technical reviews. A structured review process
should demonstrate and confirm completion of required accomplishments and exit criteria as
defined in project planning and technical plans (e.g., the systems engineering management plan).
Acquisition technical management activities discover deficiencies or anomalies that often result in
corrective action.
1. Supplier technical solutions are evaluated to confirm that contractual requirements
continue to be met.
1.1 Select supplier technical solutions to be analyzed and analysis methods to be used.
Depending on where in the acquisition lifecycle the highest risks occur, the acquirer
selects supplier technical solutions for analysis to reduce those risks. Analysis methods
are selected based on the type of technical solution being analyzed.
1.2 Analyze selected supplier technical solutions.
The acquirer should select a supplier’s design to analyze. The acquirer explores the
adequacy and completeness of a design by reviewing product representations (e.g.,
prototypes, simulations, models, scenarios, and storyboards) and obtaining feedback
about them from relevant stakeholders.
The acquirer may require delivery of verification results from the supplier of the
technical solution, as applicable. The suppliers may conduct verifications in an iterative
fashion, concurrently with the acquirer’s technical analyses, or the supplier may be
required to conduct follow-on verifications of technical solutions.
1.3 Conduct technical reviews with the supplier as defined in the supplier agreement.
Technical reviews (i.e., architectural evaluations) are performed throughout the project
lifecycle to gain confidence that the requirements, architecture, and supplier technical
solutions are capable of guiding a development that results in a product or service that
provides the required capability. This activity should be integrated with risk management
activities. Mature organizations typically perform technical reviews using different
proven techniques depending on the type of review. These organizations broaden the
basis of the review to include other stakeholder needs, expectations, and constraints.
2. Selected interfaces are managed.
2.1 Select interfaces to manage.
The interfaces considered for selection include all interfaces with other products and
services in the operations and support environments as well as environments for
verification and validation and services that support those environments. The acquirer
should review all supplier interface data for completeness to substantiate the complete
coverage of all interfaces when making the selection.

CMU/SEI-2011-TR-010 | 25
2.2 Manage selected interfaces.
Managing interfaces includes the maintenance of the consistency of the interfaces
throughout the life of the product and the resolution of conflict, noncompliance, and
change issues. In a system-of-systems environment, the management of interfaces
between products or services acquired from suppliers and other systems within the
system of systems is critical to the success of the project.

CMU/SEI-2011-TR-010 | 26
Acquisition Verification (AVER)

The purpose of Acquisition Verification is to ensure that selected work products meet their
specified requirements.

Acquisition verification involves ensuring that the evolving work products of the acquisition
project meet their specified requirements. The acquisition project should ensure that a proper
verification environment exists and that it selects work products to evaluate based on documented
criteria. Peer reviews are used to evaluate work products developed by the acquisition project.
The acquisition project is also responsible for ensuring that the supplier uses appropriate methods
to verify its work products. In this context, the test community is a major stakeholder, including
participation in up-front planning through final-product acceptance. The supplier and/or the test
community may perform many of these practices with the acquisition project facilitating the
correction of deficiencies or enhancements by the supplier or follow-on maintenance
organization. It is important that the acquirer define at the outset the degree to which verification
is required both early in the definition of the project and later when the products are received.
Verifications of the evolving products by the supplier are routinely conducted throughout the
entire supplier agreement performance period and results are analyzed to determine acceptability
of the products (see the Acquisition Technical management and Agreement Management process
areas). Acquisition project verification activities should be designed to reduce interference with
activities performed by the supplier and test communities and to reduce duplication of the
verification efforts.
1. Preparation for verification is conducted.
1.1 Select work products to be verified and verification methods to be used.
Acquirer work products are selected based on their contribution to meeting project
objectives and requirements, and to addressing project risks. Peer reviews are one of the
methods used to verify work products produced by the acquisition project. Other methods
should be selected when verifying work products from the supplier. Examples of these
other methods include demonstration, inspection, and actual testing.
1.2 Establish and maintain the environment needed to support verification.
The acquisition project should provide an adequate environment to carry out its
verification activities.
1.3 Establish and maintain verification procedures and criteria for the selected work
products.
2. Peer reviews are performed on selected work products.
A peer review is a method for conducting verification of work products that has had great
success in detecting defects, especially in documents for requirements and design. The
acquisition project uses peer reviews on selected products (e.g., solicitation documents,
system engineering plans, and test plans) they produce internally to find and remove defects
and to ensure compliance to acquisition standards. Many work products produced by the
acquisition project set the stage for the project success and are critical to the supplier’s
performance. The supplier typically uses peer reviews internally on selected interim work
products during development, but the acquirer should not rely solely on these results.

CMU/SEI-2011-TR-010 | 27
2.1 Prepare for peer reviews of selected work products.
2.2 Conduct peer reviews of selected work products and identify issues resulting from
these reviews.
2.3 Analyze data about the preparation, conduct, and results of the peer reviews.
3. Selected work products are verified against their specified requirements.
3.1 Perform verification on selected work products.
3.2 Analyze results of all verification activities.

CMU/SEI-2011-TR-010 | 28
Acquisition Validation (AVAL)

The purpose of Acquisition Validation is to demonstrate that an acquired product or service


fulfills its intended use when placed in its intended environment.

Acquisition Validation activities can be applied to all aspects of the product or service in any of
its intended environments such as operation, training, manufacturing, maintenance, and support
services. The methods employed to accomplish validation can be applied to work products as well
as to the product and product components. Work products (e.g., requirements, designs, and
prototypes) should be selected for validation based on which are the best predictors of how well
the delivered end product and product components will satisfy user needs.
Validation involves ensuring that the evolving acquisition work products (e.g., RFPs, SOWs, and
plans) meet the acquisition project’s needs. Validation activities are normally performed early and
continuously throughout the acquisition lifecycle. The acquirer also uses validation processes to
ensure that the product or service received from the supplier will fulfill its intended use. In this
context, the test community is a major stakeholder, participating in up-front planning through
final-product acceptance. The supplier and/or the test community may perform many of the
validation practices with the acquisition project facilitating the correction of deficiencies or
enhancements by the supplier or follow-on maintenance organization.
Validation involves the development of requirements for the validation approach, including
acceptance criteria, which are incorporated into both the solicitation package and the supplier
agreement. Validations of the evolving products by both the supplier and project are routinely
conducted throughout the entire supplier agreement performance period and results are analyzed
to determine acceptability of the products. Project validation activities should be designed to
reduce interference with supplier and test community-performed activities and to reduce the
duplication of validation efforts. Validation processes support establishing and validating
requirements. See the Acquisition Requirements Development process area for more information.
1. Preparation for validation is conducted.
1.1 Select products and product components to be validated and validation methods to be
used.
It is important that the acquirer define at the outset the degree to which validation is
required both early in the project (e.g., requirements validation activities) and later when
the end products are received.
1.2 Establish and maintain the environment needed to support validation.
Plans should identify adequate resources to execute validation activities.
1.3 Establish and maintain procedures and criteria for validation.
Validation procedures also address the validation of requirements and the acquired
product or service throughout the project lifecycle. Typically, formal acceptance testing
procedures and criteria are established to ensure the delivered product or service meets
stakeholder needs before it is deployed in the intended environment.
2. Selected products and product components are validated to ensure they are suitable
for use in their intended operating environment.
2.1 Perform validation on selected products and product components.

CMU/SEI-2011-TR-010 | 29
Validation activities are performed by the acquirer, the supplier, or both parties according
to the supplier agreement.
2.2 Analyze results of validation activities.

CMU/SEI-2011-TR-010 | 30
2.3 Support Process Areas

The Support process areas include the processes and tools required to allow projects to effectively
apply measurement, control, and decision techniques to manage the project.

CMU/SEI-2011-TR-010 | 31
Configuration Management (CM)

The purpose of Configuration Management is to establish and maintain the integrity of work
products using configuration identification, configuration control, configuration status accounting,
and configuration audits.

Acquired products may need to be placed under configuration management by both the supplier
and the acquirer. Provisions for conducting configuration management should be established in
supplier agreements. Methods to ensure that data are complete and consistent should be
established and maintained.
1. Baselines of identified work products are established.
1.1 Identify configuration items, components, and related work products to be placed
under configuration management.
Acquisition organizations should identify and categorize risks and risk sources for the
project initially and refine those risks and categories over time (e.g., schedule, cost,
supplier execution, technology readiness, and issues outside control of acquisition
organization).
1.2 Establish and maintain a configuration management and change management system
for controlling work products.
The acquirer considers how configuration items are shared between the acquirer and
supplier as well as among relevant stakeholders. If the use of an acquirer’s configuration
management system is extended to a supplier, the acquirer must exercise security and
access control procedures. In many cases, leaving acquired configuration items in the
physical possession of the supplier and having access to supplier deliverables is a viable
alternative. The supplier agreement specifies appropriate acquirer rights to supplier
deliverables in addition to requirements for delivery or access. Supplier work products,
whenever they are delivered to the acquirer, are presented in accordance with accepted
standards to ensure usability by the acquirer.
1.3 Create or release baselines for internal use and for delivery to the customer.
The acquirer reviews and approves the release of product baselines created by the
supplier. The acquirer creates baselines for acquirer work products that describe the
project, requirements, funding, schedule, and performance measures and makes a
commitment to manage the project to those baselines.
2. Changes to the work products under configuration management are tracked and
controlled.
2.1 Track change requests for configuration items.
Change requests can be initiated either by the acquirer or supplier. Changes that impact
acquirer work products and supplier deliverables as defined in the supplier agreement are
handled through the acquirer’s configuration management process.
2.2 Control changes to configuration items.

CMU/SEI-2011-TR-010 | 32
The acquirer decides which configuration items require version control or more stringent
levels of configuration control and establishes mechanisms to ensure configuration items
are controlled. Although the supplier may manage configuration items on the acquirer’s
behalf, the acquirer is responsible for approval and control of changes to these
configuration items.
3. Integrity of baselines is established and maintained.
3.1 Establish and maintain records describing configuration items.
3.2 Perform configuration audits to maintain the integrity of configuration baselines.

CMU/SEI-2011-TR-010 | 33
Decision Analysis and Resolution (DAR)

The purpose of Decision Analysis and Resolution is to analyze possible decisions using a formal
evaluation process that evaluates identified alternatives against established criteria.

A repeatable, criteria-based decision-making process is especially important both while making


the critical decisions that define and guide the acquisition process itself and later when critical
decisions are made with the selected supplier. The establishment of a formal process for decision
making provides the acquisition project with documentation of the decision rationale. Such
documentation allows the criteria for critical decisions to be revisited when changes impact
project requirements or other critical project parameters.
1. Decisions are based on an evaluation of alternatives using established criteria.
1.1 Establish and maintain guidelines to determine which issues are subject to a formal
evaluation process.
Not every decision is significant enough to require a formal evaluation process. The
choice between the trivial and the truly important may be unclear without explicit
guidance. The significance of a particular decision is dependent on the project and
circumstances and is determined by the established guidelines.
1.2 Establish and maintain criteria for evaluating alternatives and the relative ranking of
these criteria.
Regular use of decision-making criteria, even for less significant decisions, can be
extremely helpful in creating a practice for disciplined decision making. Practiced
evaluators have demonstrated that defined criteria and weighting can be a significant
contributor to the speed and consensus level of a decision.
1.3 Identify alternative solutions to address issues.
A wider range of alternatives can surface by soliciting as many stakeholders as is
practical for input. Input from stakeholders with diverse skills and backgrounds can help
teams identify and address assumptions, constraints, and biases. Brainstorming sessions
with support from the stakeholder may stimulate innovative alternatives through rapid
interaction and feedback.
1.4 Select evaluation methods.
Suppliers competing to develop a technical solution for the acquirer may be directly
evaluated in a final competition that involves a performance or functional demonstration
of proposed solutions.
1.5 Evaluate alternative solutions using established criteria and methods.
1.6 Select solutions from alternatives based on evaluation criteria.
Document the results of the evaluation for future reference.

CMU/SEI-2011-TR-010 | 34
Measurement and Analysis (MA)

The purpose of Measurement and Analysis is to develop and sustain a measurement capability
used to support management information needs.

The acquisition project has needs for information to help determine the status of its activities
throughout the acquisition lifecycle, the supplier’s activities per requirements in the supplier
agreement, and the status of the evolving products acquired. In acquisition projects in which
multiple products are acquired to deliver a capability to the end user, or in which there are
teaming relationships with other acquisition projects to acquire joint capabilities, additional
information needs may be identified to ensure programmatic, technical, and operational
interoperability objectives for the product are identified, measured, and achieved.
1. Measurement objectives and activities are aligned with identified information needs
and objectives.
Not all measurements are valuable. Those measurements that address the needs and
objectives of the acquisition project are the most valuable. It is best to identify the
measures that focus on the objectives, rather than measures that are easily obtained but
have questionable value.
1.1 Establish and maintain measurement objectives derived from identified information
needs and objectives.
Identify the information needed to keep the acquisition on track to a successful
conclusion. Establish measurement objectives and measurement criteria needed to
provide this information.
1.2 Specify measures to address measurement objectives.
In most cases, supplier measures are the primary source of data, especially with regard to
the development of the acquired product or service. For instance, measurement and
analysis of the product or product components provided by a supplier through technical
performance measures is essential for effective management. Technical performance
measures are precisely defined measures based on a product requirement, product
capability, or some combination of requirements and capabilities.
1.3 Specify how measurement data are obtained and stored.
The supplier agreement specifies the measurement data the supplier must provide to the
acquirer, the format in which data must be provided to the acquirer, how the data must be
collected and stored by the supplier (e.g., retention period of data), how and how often
data must be transferred to the acquirer, and who has access to data. Some supplier data
may be considered proprietary by the supplier and may need to be protected as such by
the acquirer. Some acquirer measurement data (e.g., total project cost data) may be
proprietary and should not be shared with suppliers. An acquirer must plan for the
collection, storage, and access control of sensitive data.
1.4 Specify how measurement data are analyzed and communicated.
The supplier agreement defines the data analysis and the definition and examples of
measures the supplier must provide to the acquirer.

CMU/SEI-2011-TR-010 | 35
2. Measurement results, which address identified information needs and objectives,
are provided.
2.1 Obtain specified measurement data.
2.2 Analyze and interpret measurement data.
2.3 Manage and store measurement data, measurement specifications, and analysis
results.
2.4 Communicate results of measurement and analysis activities to all relevant
stakeholders.

CMU/SEI-2011-TR-010 | 36
Process and Product Quality Assurance (PPQA)

The purpose of Process and Product Quality Assurance (PPQA) is to provide staff and
management with objective insight into processes and associated work products.

The acquirer evaluates critical acquirer work products, acquirer processes, results of supplier
process quality assurance, and supplier deliverables. For example, process and product quality
assurance process ensures that the solicitation package was developed using standard processes
agreed on by the acquirer and supplier and that the package conforms to all applicable policies.
The acquirer may review results of supplier quality assurance activities for selected supplier
processes to ensure that the supplier is following its own processes.
1. Adherence of the performed process and associated work products to applicable
process descriptions, standards, and procedures is objectively evaluated.
1.1 Objectively evaluate selected performed processes against applicable process
descriptions, standards, and procedures.
1.2 Objectively evaluate selected work products against applicable process descriptions,
standards, and procedures.
In addition to objectively evaluating critical acquirer work products, the acquirer uses
objective acceptance criteria to evaluate supplier deliverables throughout the project
lifecycle. The acquirer’s acceptance criteria for supplier deliverables are consistent with
project objectives and sufficient to allow the supplier to satisfactorily demonstrate that
the product conforms to requirements in the supplier agreement.
2. Noncompliance issues are objectively tracked and communicated, and resolution is
ensured.
2.1 Communicate quality issues and ensure the resolution of noncompliance issues with
the staff and managers.
2.2 Establish and maintain records of quality assurance activities.

CMU/SEI-2011-TR-010 | 37
3 Generic Practices

Generic practices are practices that should be included in every process area in addition to the
specific practices that appear in each process area. Generic practices improve the power of a
process by ensuring that the specific practices are executed. Generic practices also make sure that
the process is appropriately planned to ensure that it is feasible and well supported and that
stakeholders are appropriately involved.

In this section, generic practices are denoted in bold text and are followed by a brief explanation.
The last two generic practices in this section ensure that the performance of each process and the
lessons learned are saved and that this knowledge is used to establish new projects or to improve
the performance of an existing project. The 12 generic practices listed here correspond to the 10
generic practices under generic goal 2 and the two generic practices under generic goal 3 in the
CMMI-ACQ model.

1. Establish and maintain an organizational policy for planning and performing the
process.

The purpose of this generic practice is to define the organizational expectations for the process
and makes these expectations visible to the members of the organization who are affected. In
general, senior management is responsible for establishing and communicating guiding principles,
direction, and expectations for the organization.

Not all direction from senior management bears the label “policy.” The existence of appropriate
organizational direction is the expectation of this generic practice, regardless of what it is called
or how it is imparted.

This policy establishes organizational expectations for planning and performing the process,
including not only the elements of the process addressed directly by the acquirer, but also the
interactions of the acquirer with suppliers.

2. Establish and maintain the plan for performing the process.

The purpose of this generic practice is to determine what is needed to perform the process and to
achieve the established objectives, prepare a plan for performing the process, prepare a process
description, and get agreement on the plan from relevant stakeholders.

Planning a process applies to all process areas, including Project Planning. The process for
planning the project requires planning (e.g., resource, duration) just like any other activity.

The objectives for the process may be derived from other plans (e.g., project plans). Included are
objectives for the specific situation, including quality, cost, and schedule objectives. For example,
an objective might be to reduce the cost of performing a process for an implementation over its
previous implementation.

CMU/SEI-2011-TR-010 | 38
Establishing a plan includes documenting the plan and a process description. Maintaining the plan
includes updating it as necessary in response to either corrective actions or to changes in process
requirements and objectives.

The plan for performing the process typically includes the following elements:
• process description
• standards and requirements for the work products and services of the process
• objectives for performing the process (e.g., quality, time scale, cycle time, resource usage)
• dependencies among activities, work products, and services of the process
• resources (including funding, people, and tools) needed to perform the process
• assignment of responsibility and authority
• training needed for performing and supporting the process
• work products to be controlled and the level of control for each item
• measurement requirements to provide insight into the performance of the process, its work
products, and its services
• involvement of identified stakeholders
• activities for monitoring and controlling the process
• objective evaluation activities for the process
• management review activities for the process and work products

3. Provide adequate resources for performing the process, developing the work
products, and providing the services of the process.

The purpose of this generic practice is to ensure that the resources necessary to perform the
process as defined by the plan are available when they are needed. Resources include adequate
funding, appropriate physical facilities, skilled people, and appropriate tools.

The interpretation of the term adequate depends on many factors and can change over time.
Inadequate resources may be addressed by increasing resources or by removing requirements,
constraints, and commitments.

4. Assign responsibility and authority for performing the process, developing the
work products, and providing the services of the process.

The purpose of this generic practice is to ensure that there is accountability for performing the
process and achieving the specified results throughout the life of the process. The people assigned
must have the appropriate authority to perform the assigned responsibilities.

Responsibility can be assigned using detailed job descriptions or in living documents, such as the
plan for performing the process. Dynamic assignment of responsibility is another legitimate way
to perform this generic practice, as long as the assignment and acceptance of responsibility are
ensured throughout the life of the process.

CMU/SEI-2011-TR-010 | 39
5. Train the people performing or supporting the process as needed.

The purpose of this generic practice is to ensure that people have the necessary skills and
expertise to perform or support the process.

Training supports the successful performance of the process by establishing a common


understanding of the process and by imparting the skills and knowledge needed to perform the
process.

6. Place selected work products of the process under appropriate levels of control.

The purpose of this generic practice is to establish and maintain the integrity of selected work
products of the process (or their descriptions) throughout their useful life.

Designated work products are identified in the plan for performing the process, along with a
specification of the appropriate level of control.

7. Identify and involve the relevant stakeholders of the process as planned.

The purpose of this generic practice is to establish and maintain the expected involvement of
relevant stakeholders during the execution of the process.

To plan stakeholder involvement, ensure that sufficient stakeholder interaction that is necessary to
accomplish the process occurs, while avoiding excessive numbers of stakeholders that could
impede process execution.

8. Monitor and control the process against the plan for performing the process and
take appropriate corrective action.

The purpose of this generic practice is to perform the direct day-to-day monitoring and controlling
of the process. Appropriate visibility into the process is maintained so that appropriate corrective
action can be taken when necessary. Monitoring and controlling the process can involve
measuring appropriate attributes of the process or work products produced by the process.

9. Objectively evaluate adherence of the process and selected work products against
the process description, standards, and procedures, and address noncompliance.

The purpose of this generic practice is to provide credible assurance that the process and selected
work products are implemented as planned and adhere to their process descriptions, standards,
and procedures.

10. Review the activities, status, and results of the process with higher level
management and resolve issues.

The purpose of this generic practice is to provide higher level management with appropriate
visibility into the process.

Higher level management includes those levels of management in the organization above the
immediate level of management responsible for the process. In particular, higher level
management includes senior management. These reviews are for managers who provide the

CMU/SEI-2011-TR-010 | 40
policy and overall guidance for the process, and not for those who perform the direct day-to-day
monitoring and controlling of the process.

The following two generic practices form the basis for propagating good practice to future
acquisition projects. These practices facilitate process definition and identify process benefits that
encourage adoption of best practices on new projects.

A defined process is tailored from the organization’s set of standard processes according to the
organization’s tailoring guidelines and contributes work products, measures, and other process-
improvement information to the organizational process assets.

These two generic practices activate a process improvement cycle. The organization maintains a
process asset library and standard process that can be used by a project to create its processes. In
turn, the project provides information about the performance of its process to the organization’s
process asset library, which is used to improve and extend the standard processes.

The organization’s set of standard processes, which are the basis of the defined process, are
established and improved over time. Standard processes describe the fundamental process
elements that are expected in the defined processes. Standard processes also describe the
relationships (e.g., ordering, interfaces) between these process elements. The organization level
infrastructure to support current and future use of the organization’s set of standard processes is
established and improved over time.

11. Establish and maintain the description of a defined process.

The purpose of this generic practice is to establish and maintain a description of the process that is
tailored from the organization’s set of standard processes to address the needs of a specific
instantiation. The organization should have standard processes that cover the process area and
guidelines for tailoring these standard processes to meet the needs of a project or organizational
function. With a defined process, variability in how the processes are performed across the
organization is reduced and process assets, data, and learning can be effectively shared.

12. Collect process related experiences derived from planning and performing the
process to support the future use and improvement of the organization’s processes
and process assets.

The purpose of this generic practice is to collect process related experiences, including
information and artifacts derived from planning and performing the process. Examples of process
related experiences include work products, measures, measurement results, lessons learned, and
process improvement suggestions. The information and artifacts are collected so that they can be
included in the organizational process assets and made available to those who are (or will be)
planning and performing the same or similar processes. The information and artifacts are stored in
the organization’s measurement repository and the organization’s process asset library.

CMU/SEI-2011-TR-010 | 41
Appendix Implementation Questions

The questions in this appendix will help you, as an acquisition project manager, implement your
processes. The questions help you verify that best practices are being employed and provide a
means of gathering background information necessary to determine if the products or services
being acquired will meet the operational needs of your organization.

The questions in the following table were designed to facilitate review and improvement of the
processes in your acquisition organization. They address whether or not strategy development,
planning, and estimating activities occur. In large part, these early activities determine the success
of an acquisition process from the outset.

The questions also focus on risk identification, management practices, capabilities definition,
requirements generation, and the existence of repeatable processes that enable organizations to
institutionalize best practices. For each question in the left-hand column, the relevant process
areas, described in detail in Section 2, are listed in the right-hand column.

1. Processes in General

Questions CMMI-ACQ Process Areas

a. What are the content and source of your Project Planning, Integrated Project
acquisition processes? Management

Project Monitoring and Control,


b. What mechanisms do you use to monitor, control,
Measurement and Analysis, Process
and improve your acquisition processes?
and Product Quality Assurance

Project Monitoring and Control,


c. How do you know that your project is adhering to
Process and Product Quality
your acquisition processes?
Assurance

2. User Requirements

Questions CMMI-ACQ Process Areas

a. Is there a process in place to define, verify, and Acquisition Requirements


validate customer and contractual requirements? Development

Project Planning, Integrated Project


b. How do you manage users’ involvement in the Management, Requirements
requirements process? Management, Acquisition
Requirements Development

Requirements Management,
c. How do you ensure a clear understanding of user Acquisition Requirements
needs by relevant stakeholders? Development, Integrated Project
Management

CMU/SEI-2011-TR-010 | 42
Acquisition Requirements
d. What role does your organization play in
Development, Requirements
establishing the project requirements?
Management

e. What is your strategy for keeping up with the


evolving operational environment (e.g., threat, Integrated Project Management,
concept of operations, and technology Requirements Management
readiness)?

3. Acquisition Strategy

Questions CMMI-ACQ Process Areas

a. How did you determine the most appropriate Project Planning, Decision Analysis
acquisition strategy for this acquisition? and Resolution, Risk Management

b. How does your selected acquisition strategy


Project Planning, Risk Management
mitigate the risks you have identified?

c. Which stakeholders were involved in establishing Project Planning, Integrated Project


the acquisition strategy? Management

4. Acquisition Planning

Questions CMMI-ACQ Process Areas

Project Planning, Integrated Project


a. How do your acquisition plans reflect and
Management, Decision Analysis and
implement the acquisition strategy?
Resolution

b. How do you determine and document the scope


of the project, including acquisition project Project Planning, Solicitation and
activities, supplier activities, and other related Supplier Agreement Development
activities (operational testing, user activities, etc.)?

c. How do you determine the magnitude of the


Project Planning
development effort?

d. How do you determine resource needs for each


Project Planning
element of the project?

Project Planning, Integrated Project


e. How do you determine the critical path?
Management

f. How are plans coordinated with relevant


Project Planning, Integrated Project
stakeholders at both the management and
Management
working levels?

g. How do you ensure that you have adequate staff


with the necessary experience and training to Project Planning
execute your plans?

CMU/SEI-2011-TR-010 | 43
h. How do you ensure that the supplier has the Project Planning, Solicitation and
resources and tools needed to complete the Supplier Agreement Development,
project? Agreement Management

i. How do you ensure that the supplier has the Project Planning, Solicitation and
domain experience and process capability needed Supplier Agreement Development,
to complete the project? Agreement Management

5. Cost, Schedule, and Performance Baselines

Questions CMMI-ACQ Process Areas

a. How do you ensure that the cost, schedule, and


Project Planning, Integrated Project
performance baselines are integrated, realistic
Management
and executable?

Project Planning, Integrated Project


b. What provisions do you make for independent
Management, Acquisition
reviews of your cost, schedule, and performance
Requirements Development,
baselines?
Requirements Management

c. How do you ensure that all lifecycle costs are


Project Planning, Integrated Project
included in the baselines (e.g., testing, training,
Management,
sustainment, support)?

d. How do you plan to track cost, schedule, and


Project Monitoring and Control,
performance of the project throughout its
Measurement and Analysis
lifecycle?

e. How do you accommodate risks and engineering Project Planning, Risk Management,
changes in your baselines? Requirements Management

Configuration Management, Project


f. How do you manage changes to baselines? Monitoring and Control, Requirements
Management

Project Monitoring and Control,


g. How do you evaluate the impact of changes in
Solicitation and Supplier Agreement
cost and schedule on supplier’s development
Development, Requirements
efforts?
Management

6. Risk Identification and Management

Questions CMMI-ACQ Process Areas

a. How do you identify project risks? Project Planning, Risk Management

b. How do you identify risks related to your


Project Planning, Risk Management
acquisition strategy and plans?

c. How do you identify risks associated with cost Project Planning, Integrated Project
and schedule? Management, Risk Management

CMU/SEI-2011-TR-010 | 44
d. How do you ensure that you understand the cost Project Planning, Risk Management,
risk of obtaining the required capability? Requirements Development

Project Planning, Risk Management,


e. How do you identify risks related to supplier
Solicitation and Supplier Agreement
execution?
Development

f. How do you identify risks that are outside your Project Planning, Integrated Project
control? Management, Risk Management

g. How do you assess the likelihood and


Risk Management
consequence of project risks?

h. How do you monitor mitigation efforts for identified


Risk Management
risks?

i. Which risk management tools do you employ? Project Planning, Risk Management

j. Who is involved in project risk assessment (e.g.,


Integrated Project Management, Risk
users, the supplier, independent subject matter
Management
experts)?

k. How do you build in sufficient reserves for risk


mitigation and absorbing the impact of realized Project Planning, Risk Management
risks?

7. Supplier Monitoring

Questions CMMI-ACQ Process Areas

a. How do you assess the mechanisms the supplier


Agreement Management, Acquisition
uses to encourage execution of their
Technical Management, Risk
organization’s processes from the beginning of
Management
the project?

b. Is there a process in place to define, verify, and Acquisition Requirements


validate requirements and architectures for the Development, Acquisition Technical
product? Management

Project Monitoring and Control,


c. How will the status of development be monitored? Measurement and Analysis,
Agreement Management

d. How will the supplier demonstrate the


performance and stability of their development Agreement Management
environment and tools?

CMU/SEI-2011-TR-010 | 45
8. Nondevelopmental Items

Questions CMMI-ACQ Process Areas

a. What is your strategy for incorporating


nondevelopmental products (e.g., commercial off- Project Planning, Decision Analysis
the-shelf [COTS], government off-the-shelf and Resolution, Acquisition
[GOTS], reuse, and product lines) into the Requirements Development
project?

b. What percentage of the software is planned to be Project Planning, Measurement and


nondevelopmental? Analysis

Project Planning, Risk


c. How do you determine that you can achieve the
Management, Verification,
planned percentage of nondevelopmental
Validation, Decision Analysis and
software use on this project?
Resolution

Measurement and Analysis,


d. How do you determine that the planned
Requirements Development,
nondevelopmental products will provide the
Verification, Validation, Decision
required functionality and performance?
Analysis and Resolution

e. How do you determine that the interfaces for


nondevelopmental products are defined and Acquisition Technical Management
agreed to by relevant stakeholders?

Acquisition Requirements
f. How do you account for the effort required to test
Development, Acquisition Technical
and integrate nondevelopmental products?
Management, Validation

CMU/SEI-2011-TR-010 | 46
References/Bibliography

URLs are valid as of the publication date of this document.

[Dodson 2006]
Dodson, Kathryn M. et al. Adapting CMMI for Acquisition Organizations: A Preliminary Report
(CMU/SEI-2006-SR-005, ADA453524). Pittsburgh, PA: Software Engineering Institute, Carnegie
Mellon University, June 2006. http://www.sei.cmu.edu/library/abstracts/reports/06sr005.cfm.

[Gallagher 2011]
Gallagher, Brian; Phillips, Mike; Richter, Karen; & Shrum, Sandy. CMMI-ACQ: Guidelines for
Improving the Acquisition of Products and Services, 2nd Edition. Boston: Addison-Wesley, 2011.

[Lapham 2010]
Lapham, Mary Ann; Williams, Ray C.; Hammons, Charles; Burton, Daniel; and Schenker, Fred.
Considerations for Using Agile in DoD Acquisition (CMU/SEI-2010-TR-022). Pittsburgh, PA:
Software Engineering Institute, Carnegie Mellon® University, April 2010.
http://www.sei.cmu.edu/library/abstracts/reports/10tn002.cfm.

[Richter 2008]
Richter, Karen. CMMI for Acquisition (CMMI-ACQ) Primer, Version 1.2 (CMU/SEI-2008-TR-
010). Pittsburgh, PA: Software Engineering Institute, Carnegie Mellon University, May 2008.
http://www.sei.cmu.edu/library/abstracts/reports/08tr010.cfm.

[SEI 2007]
CMMI Guidebook for Acquirers Team. Understanding and Leveraging a Supplier’s CMMI
Efforts: A Guidebook for Acquirers (CMU/SEI-2007-TR-004). Pittsburgh, PA: Software
Engineering Institute, Carnegie Mellon University, March 2007.
http://www.sei.cmu.edu/library/abstracts/reports/07tr004.cfm.3

[SEI 2010]
CMMI Product Team. CMMI for Acquisition, Version 1.3 (CMU/SEI-2010-TR-032). Pittsburgh,
PA: Software Engineering Institute, Carnegie Mellon University, November 2010.
http://www.sei.cmu.edu/library/abstracts/reports/10tr032.cfm.

[DoD and DHS 2008]


Department of Defense and Department of Homeland Security. Software Assurance in
Acquisition: Mitigating Risks to the Enterprise, 2008. https://buildsecurityin.us-
cert.gov/swa/downloads/SwA_in_Acquisition_102208.pdf.

3
The Understanding and Leveraging a Supplier’s CMMI Efforts: A Guidebook for Acquirers report is currently
being updated and will be available in 2011.

CMU/SEI-2011-TR-010 | 47
CMU/SEI-2011-TR-010 | 48
Form Approved
REPORT DOCUMENTATION PAGE OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, search-
ing existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regard-
ing this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters
Services, Directorate for information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of
Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503.
1. AGENCY USE ONLY 2. REPORT DATE 3. REPORT TYPE AND DATES
COVERED
(Leave Blank) March 2011
Final
4. TITLE AND SUBTITLE 5. FUNDING NUMBERS
CMMI® for Acquisition (CMMI-ACQ) Primer, Version 1.3 FA8721-05-C-0003
6. AUTHOR(S)
Mike Phillips
7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) 8. PERFORMING ORGANIZATION
REPORT NUMBER
Software Engineering Institute
Carnegie Mellon University CMU/SEI-2011-TR-010
Pittsburgh, PA 15213
9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 10. SPONSORING/MONITORING
AGENCY REPORT NUMBER
HQ ESC/XPK
5 Eglin Street ESC-TR-2011-010
Hanscom AFB, MA 01731-2116
11. SUPPLEMENTARY NOTES

12A DISTRIBUTION/AVAILABILITY STATEMENT 12B DISTRIBUTION CODE


Unclassified/Unlimited, DTIC, NTIS
13. ABSTRACT (MAXIMUM 200 WORDS)
This primer identifies practices that are most effective and efficient for projects acquiring products and services. Focusing on project-
level improvement, the primer selects a subset of practices from the CMMI for Acquisition (CMMI-ACQ) model. These practices include
monitoring and controlling suppliers and contractors as well as ensuring repeatedly effective execution of product and service develop-
ment and service delivery. After using this primer, readers will be able to expand their use of the best practices on their acquisition
projects, and their organizations will be positioned to explore the use of the CMMI-ACQ model.

14. SUBJECT TERMS 15. NUMBER OF PAGES


acquisition, CMMI-ACQ, CMMI, primer, Version 1.3 57
16. PRICE CODE

17. SECURITY CLASSIFICATION OF 18. SECURITY CLASSIFICATION 19. SECURITY CLASSIFICATION 20. LIMITATION OF
REPORT OF THIS PAGE OF ABSTRACT ABSTRACT
Unclassified Unclassified Unclassified UL
NSN 7540-01-280-5500 Standard Form 298 (Rev. 2-89) Prescribed by ANSI Std. Z39-18
298-102

You might also like