Identifying and Recording Piping Locations: 6.1.10.6 Localized Repairs
Identifying and Recording Piping Locations: 6.1.10.6 Localized Repairs
Identifying and Recording Piping Locations: 6.1.10.6 Localized Repairs
94 • © BSI 2009
BS 6700:2006+A1:2009
6.1.12.1.3 Re-tests
Items failing any test shall be corrected immediately and re-tested
before further work proceeds.
© BSI 2009 • 95
BS 6700:2006+A1:2009
6.1.12.2 Inspection
The water supplier shall be given the opportunity to carry out visual
Licensed Copy: University of Glasgow, The University of Glasgow, 15/08/2013 11:59, Uncontrolled Copy, (c) The British Standards Institution 2013
inspections.
All internal pipework shall be inspected to ensure that it has been
securely fixed.
All cisterns, tanks, hot water cylinders and water heaters shall be
inspected to ensure that they are properly supported and secured, that
they are clean and free from debris and that cisterns are provided with
correctly fitting covers before testing takes place.
Unvented hot water storage installations shall be notified to the local
authority to verify that they conform to building regulations (see A.1).
Before accepting a pipeline, a check shall be made that valve and
hydrant boxes are aligned, that operating keys are provided for the
valves and, in the case of deep valves, that extension spindles are
installed.
COMMENTARY AND RECOMMENDATIONS ON 6.1.12.2
In the case of visual inspection of underground pipework, particular
attention should be paid to the pipe bed, the line and level of the pipe,
irregularities at joints, the correct fitting of air valves, washout valves,
sluice valves and other valves together with any other mains equipment
specified, including the correct installation of thrust blocks where
required, to ensure that protective coatings are undamaged.
Trenches should be inspected to ensure that excavation is to the correct
depth to guard against frost and mechanical damage due to traffic,
ploughing or agricultural activities.
No part of the pipe trench should be backfilled until these conditions have
been satisfied and the installation seen to conform to the drawings and
specifications and the WFRs [1].
A person registered with an water-industry approved Competent Persons
Scheme in accordance with the WFRs [1] can self-certify that the
installation conforms to the WFRs [1].
96 • © BSI 2009
BS 6700:2006+A1:2009
When water from the water supplier’s mains is used for filling the
pipeline under test, the main shall be disconnected from the pipeline
before the test is begun. To avoid the risk of contamination, water used
Licensed Copy: University of Glasgow, The University of Glasgow, 15/08/2013 11:59, Uncontrolled Copy, (c) The British Standards Institution 2013
© BSI 2009 • 97
BS 6700:2006+A1:2009
Test procedure A:
a) Fill the system slowly with drinking water to allow air to be
Licensed Copy: University of Glasgow, The University of Glasgow, 15/08/2013 11:59, Uncontrolled Copy, (c) The British Standards Institution 2013
expelled from the system. Raise (or lower) the pressure in the
system to 100 kPa (one bar: not shown in Figure 16). Inspect the
complete installation for leaks at this pressure prior to subsequent
hydraulic testing. Proceed if there is no visible leakage of water
after 45 min.
b) Test the installation hydraulically by subjecting the pipes, pipe
fittings and connected appliances to a test pressure of not less
than 1.5 times the maximum working pressure by pumping in
accordance with Figure 16. (The maximum working pressure is
defined as the maximum pressure that the system will operate at,
normally measured as the incoming mains pressure after any
pressure reducing valve.) Proceed if there is no visible leakage of
water after 15 min at this pressure.
c) Reduce the pressure in the pipework by bleeding water from the
system to one third of the previous test pressure. The test is
passed if there is no visible leakage of water and the pressure is
maintained for 45 minutes.
1
Y
0
0 10 20 30 40 50 60
X
Key
1 Pumping
2 Test pressure (1.5 times maximum working pressure)
3 0.5 times maximum working pressure
X Time (minutes)
Y Pressure
98 • © BSI 2009
BS 6700:2006+A1:2009
Test procedure B:
a) Fill the system slowly with drinking water to allow air to be
Licensed Copy: University of Glasgow, The University of Glasgow, 15/08/2013 11:59, Uncontrolled Copy, (c) The British Standards Institution 2013
1
Y
2
3
X
0
0 10 20 30 60 120 180
Key
X Time (minutes) 2 Pressure drop < 60 kPa (0.6 bar)
Y Pressure 3 Test pressure
1 Pumping 4 Pressure drop < 20 kPa (0.2 bar)
© BSI 2009 • 99
BS 6700:2006+A1:2009
the system accepted from the installer, the water supplier shall be
informed that the system is available for permanent connection to the
supply.
COMMENTARY AND RECOMMENDATIONS ON 6.1.12.4
Each draw-off tap, shower fitting and float-operated valve should be
checked for rate of flow against the specified requirements. Performance
tests should also be carried out on any connected specialist items to show
that they meet the requirements detailed in the specification.
7 Maintenance
7.1 Maintenance procedures
Maintenance procedures shall be adopted to maintain the performance
of the installation at the level specified in this standard for the original
design and installation.
Unvented hot water storage installations shall be maintained and
repaired only by a competent person (see the Building
Regulations [4] A.1).
COMMENTARY AND RECOMMENDATIONS ON 7.1
The degree of formalization of maintenance required depends upon the
size and utilization of the installation although the principles involved
apply to all installations.
Maintenance of ducts would not normally apply to single dwellings but
other requirements should be satisfied by the owner of the building. In
single dwellings the responsibility for maintenance normally rests on the
householders who should pay attention to apparent leakages and should
note any discharges from overflow pipes or regular discharges from any
valves.
The owner of the building should have been provided with maintenance
instructions and an accurate drawing of the installation, particularly
showing where pipe runs are concealed. Control valves should be clearly
labeled (see 6.1.11.4). Care should be taken to renew or protect labels
when redecorating. Any alterations should be recorded on inspection, and
a check made that these do not introduce undesirable features or
contravene statutory requirements.
The services of a competent person should be obtained to carry out
maintenance and repairs. Competence includes the appropriate skills and
a knowledge of the relevant statutory requirements relating to water
supply.
7.2 General
Inspection
Licensed Copy: University of Glasgow, The University of Glasgow, 15/08/2013 11:59, Uncontrolled Copy, (c) The British Standards Institution 2013
7.2.1
In other than single dwellings, the installation shall be inspected
periodically. Faults noticed on inspection shall be attended to
immediately.
COMMENTARY AND RECOMMEDATIONS ON 7.2.1
The need for formalized inspection and records depends upon the size,
type and complexity of the installation but in principle every installation
should be inspected at least once per year in addition to any statutory
inspections. Checks should be made that the appropriate backflow
prevention devices and relief valves are fitted where required.
7.3 Pipework
7.3.2 Joints
Leaking joints shall be rectified or where necessary the pipework shall
be renewed to stop all leakage.
7.3.3 Compatibility
When carrying out renewals, the existing pipework shall be identified
Licensed Copy: University of Glasgow, The University of Glasgow, 15/08/2013 11:59, Uncontrolled Copy, (c) The British Standards Institution 2013
7.3.4 Corrosion
If inspection of the system reveals leaks or leaks which have been
stifled, that component of the system shall be replaced and the
offending parts examined by an expert to determine the cause of the
leakage. Further action shall be dependent on the results of the
examination and recommendations of the examining expert.
COMMENTARY AND RECOMMENDATIONS ON 7.3.4
Pipes showing signs of serious external corrosion should be replaced. The
replacement pipe should have suitable protection (e.g. factory plastics
coated, spirally wrapped or sleeved with an impervious material) or
should be of a corrosion resistant material compatible with the remaining
pipework.