Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Mechanical Completion L.V. Power, Control and Telecomm / Instrument Cables

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

NAXIS ROO E01A ELECTRICAL

Mechanical Completion
L.V. Power, Control and Telecomm /
Instrument Cables
DMC1 No Description
MC1 No Description
Term Drawing No From
To
No. Items to be Checked OK N/A P/L
1 Confirm the cable type is as per cable schedule and drawings.   
2 Confirm the cable identification markers are correct at each end, and at ALL transits (if applicable).   
Bending radius and stretch prevention IS according to specification and the gland is not stressed
3
by the cable.   
Cable glands are the correct type for the application. Thread type and size of gland is confirmed
correct. Serrated washers or earthing requirement is adequate. IP washers are fitted where
4
required and IP rating of equipment is maintained. Ensure the assembly of gland is correct to   
manufacturer’s instructions.
5 Confirm earth bonding is correct to design specification   
6 Ensure gland plates for single core cables are non-magnetic.   
7 Check terminations and earth connections are tight and correct.   
8 Ensure the correct size of crimp connector has been used.   
9 Confirm the cable is mechanically protected, and supported as per installation specification.   
10 Cable suitably fastened using cable ties according to specification.   
Confirm the spare cores and screens are made off correctly and earthed in accordance with the
11
drawings and specification.   
12 Confirm cable routing and segregation is in accordance with the specification   
13 For fieldbus cables record cable installed length. ______________ M
14 Installation drawings have been “Red Lined” as per the Project Completions Procedure.   
Comments / Remarks:

REFER TO SHEET 2 FOR LIST OF CABLES TESTED

Test Equipment Used


Make Model Serial No. Cal. Expiry Date

Make Model Serial No. Cal. Expiry Date

Make Model Serial No. Cal. Expiry Date


ROO E01A ELECTRICAL
Mechanical Completion
L.V. Power, Control and Telecomm /
Instrument Cables
DMC1 No : MC1 No :
Carry out IR and continuity tests in all cores, screen, earth and armour and note results below
(record lowest IR value).   
NOTE: Only one type of cable to be listed per E01A, i.e. Do not mix Power & Instrument cables
IR Test Continuity (Max Value)
Cable No. Type Cores Size Core- Core- Screen to SCR /
Core
Core Earth Armour Armour to
Ω
MΩ MΩ Ω Earth Ω

R504-10-C-PT/PS-0001

15


16 Punchlist raised - Yes  No  Punchlist No:
Punchlist Recorded in CMS Database
(GOC Certification Engineer)

Completed By Accepted By W I  R
Signature:
Print Name:
Date:
Company: ROO
W=Witnessed I=Inspected R=Reviewed (Tick as applicable)
5IWDR ROO E02A ELECTRICAL

Mechanical Completion
High Voltage Cable
Cable Tag No. Description
DMC1 No Description Electrical
MC1 No Description
Voltage
Term Drawing No From
Term Drawing No To
No. Items to be Checked OK N/A P/L
1 Correct cable type as per electrical cable schedule and drawings.   
2 Confirm cable markers are correct at each end, and at transits (if applicable).   
3 Ensure clamping / cleating cable support correct, as per project specification   
4 Bending radius and stretch prevention according to specification and no stress on gland.   
5
Cable glands are the correct type and size as per cable schedule. Serrated washers / IP washers
are fitted and gland threads have a light smear of approved grease according to specification.   
6 Confirm earth bonding is correct to design specification   
7 Ensure gland plates for single core cables are non-magnetic.   
8 Ensure single core power cables installed in fault rated trefoil cleats.   
9 Ensure mechanical cable protection correct.   
10 Ensure the correct size of crimped connector has been used.   
11 Check terminations and earth connections are tight and correct.   
12 Check that phase identification is correct.   
13 Ensure torquing of Split, Bolted connections correct. Check after IR and pressure test.   
14 HV cable kits correctly installed, stress relieved and earthed.   
15a Confirm continuity on all cores and screens.   
Carry out IR and High Voltage Pressure Test on all cores and record results below:

L1 to L2, L3 L2 to L1, L3 L3 to L1, L2


Screen, Armour & Earth Screen, Armour & Earth Screen, Armour & Earth

IR Test before HP Test MΩ MΩ MΩ

High Voltage Pressure Test kV kV kV


15b
Test Duration Min Min Min

Leakage Current mA mA mA

IR Test after HP Test MΩ MΩ MΩ

Note: Ensure all cores are discharged to earth for a minimum of 15 minutes after completing HP Test.

16 Reconnect cable cores and confirm correct terminations and phase rotation.
End “A” Yes  No 
End “B” Yes  No 
End “A” Nm mm
17 Record torque settings and bolt size
End “B” Nm mm
ROO E02A ELECTRICAL

Mechanical Completion
High Voltage Cable
Item / Tag No. Description
No. Items to be Checked OK N/A P/L
18 Gland body to earth path resistance (Max 0.1Ω). ____________ Ω.   
19 Confirm protective measures (i.e. kick plates) are fitted correctly.   
20 Replace covers and check all bolts are correct and none missing.   
21 Installation drawings have been “Red Lined” as per the Project Completions Procedure.   
22 Punchlist raised - Yes  No  Punchlist No:
Punchlist Recorded in CMS Database
(GOC Certification Engineer)

Test Equipment Used
Make Model Serial No. Cal. Expiry Date
Make Model Serial No. Cal. Expiry Date
Make Model Serial No. Cal. Expiry Date

Comments / Remarks:

Completed By Accepted By W I  R
Signature:
Print Name:
Date:
Company: ROO
W=Witnessed I=Inspected R=Reviewed (Tick as applicable)