Mechanical Completion L.V. Power, Control and Telecomm / Instrument Cables
Mechanical Completion L.V. Power, Control and Telecomm / Instrument Cables
Mechanical Completion L.V. Power, Control and Telecomm / Instrument Cables
Mechanical Completion
L.V. Power, Control and Telecomm /
Instrument Cables
DMC1 No Description
MC1 No Description
Term Drawing No From
To
No. Items to be Checked OK N/A P/L
1 Confirm the cable type is as per cable schedule and drawings.
2 Confirm the cable identification markers are correct at each end, and at ALL transits (if applicable).
Bending radius and stretch prevention IS according to specification and the gland is not stressed
3
by the cable.
Cable glands are the correct type for the application. Thread type and size of gland is confirmed
correct. Serrated washers or earthing requirement is adequate. IP washers are fitted where
4
required and IP rating of equipment is maintained. Ensure the assembly of gland is correct to
manufacturer’s instructions.
5 Confirm earth bonding is correct to design specification
6 Ensure gland plates for single core cables are non-magnetic.
7 Check terminations and earth connections are tight and correct.
8 Ensure the correct size of crimp connector has been used.
9 Confirm the cable is mechanically protected, and supported as per installation specification.
10 Cable suitably fastened using cable ties according to specification.
Confirm the spare cores and screens are made off correctly and earthed in accordance with the
11
drawings and specification.
12 Confirm cable routing and segregation is in accordance with the specification
13 For fieldbus cables record cable installed length. ______________ M
14 Installation drawings have been “Red Lined” as per the Project Completions Procedure.
Comments / Remarks:
R504-10-C-PT/PS-0001
15
16 Punchlist raised - Yes No Punchlist No:
Punchlist Recorded in CMS Database
(GOC Certification Engineer)
Completed By Accepted By W I R
Signature:
Print Name:
Date:
Company: ROO
W=Witnessed I=Inspected R=Reviewed (Tick as applicable)
5IWDR ROO E02A ELECTRICAL
Mechanical Completion
High Voltage Cable
Cable Tag No. Description
DMC1 No Description Electrical
MC1 No Description
Voltage
Term Drawing No From
Term Drawing No To
No. Items to be Checked OK N/A P/L
1 Correct cable type as per electrical cable schedule and drawings.
2 Confirm cable markers are correct at each end, and at transits (if applicable).
3 Ensure clamping / cleating cable support correct, as per project specification
4 Bending radius and stretch prevention according to specification and no stress on gland.
5
Cable glands are the correct type and size as per cable schedule. Serrated washers / IP washers
are fitted and gland threads have a light smear of approved grease according to specification.
6 Confirm earth bonding is correct to design specification
7 Ensure gland plates for single core cables are non-magnetic.
8 Ensure single core power cables installed in fault rated trefoil cleats.
9 Ensure mechanical cable protection correct.
10 Ensure the correct size of crimped connector has been used.
11 Check terminations and earth connections are tight and correct.
12 Check that phase identification is correct.
13 Ensure torquing of Split, Bolted connections correct. Check after IR and pressure test.
14 HV cable kits correctly installed, stress relieved and earthed.
15a Confirm continuity on all cores and screens.
Carry out IR and High Voltage Pressure Test on all cores and record results below:
Leakage Current mA mA mA
Note: Ensure all cores are discharged to earth for a minimum of 15 minutes after completing HP Test.
16 Reconnect cable cores and confirm correct terminations and phase rotation.
End “A” Yes No
End “B” Yes No
End “A” Nm mm
17 Record torque settings and bolt size
End “B” Nm mm
ROO E02A ELECTRICAL
Mechanical Completion
High Voltage Cable
Item / Tag No. Description
No. Items to be Checked OK N/A P/L
18 Gland body to earth path resistance (Max 0.1Ω). ____________ Ω.
19 Confirm protective measures (i.e. kick plates) are fitted correctly.
20 Replace covers and check all bolts are correct and none missing.
21 Installation drawings have been “Red Lined” as per the Project Completions Procedure.
22 Punchlist raised - Yes No Punchlist No:
Punchlist Recorded in CMS Database
(GOC Certification Engineer)
Test Equipment Used
Make Model Serial No. Cal. Expiry Date
Make Model Serial No. Cal. Expiry Date
Make Model Serial No. Cal. Expiry Date
Comments / Remarks:
Completed By Accepted By W I R
Signature:
Print Name:
Date:
Company: ROO
W=Witnessed I=Inspected R=Reviewed (Tick as applicable)