General Civil Works Risk Assessment

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Risk Assessment

1. Subject : General Civil Works (Earth works, Lifting


works, Concrete works, Waterproofing and Coating 5. Date : 31 Oct.2020
works)
2. Project : Umm Al Hayman Wastewater Project 6. Document No. :

3.Contract No.: SE/171 7. Revision No. : Rev.0


4. Location : Umm Al Hayman W 300/132/11 kV
8. Sub contractor: SHBC
Substation

Prepared by Reviewed by Approved by


Name Mudassir.K

Job title HSE Manager

Company MELCO

Date 31-Oct-20
Risk Rating Final assessment
Potential Persons
before controls General Control Measures of Risk
Hazard at Risk
L S RR L S RR
General Requirements
• Prior to work commence, valid work permit shall be obtained. All works which is
conducted at site shall be comply with Permit to work.
• Before starting activity, TBT shall be conducted to identify and understand hazards
and control measures.
Unauthorized • Only competent and trained person should be allowed to perform the job.
Working Staff 3 B M 1 A L
work • Prior to work commence all involved personnel shall undergo required training
courses in accordance with Training plan and training matrix.
• MSDS sheet should be displayed conspicuously at the work station and a copy to be
forwarded to the first aid station. Training in MSDS shall be provided.

• Provide approved personal protective equipment safety helmet, high visiblity vest,
Non availability of
Working Staff 3 B M safety shoes for all employees working in the project sites. • Ensure task specific 1 A L
PPEs
personal protective equipment e.g. goggles, ear defenders, mask etc.

Non availability of
Working Staff 3 B M • Ensure the availability of first aid kit as per the ministry & or clients requirements. 1 A L
first aid kit

Lack of fire
• Fire extinguisher ABC type should be available to ensure that in case of fire it would
fighting Working Staff 3 B M 1 A L
be easy to control it.
equipment

• Ensure continual full supervision of Executor and HSE Supervisor until the work has
No supervision Working 3 B M been ended safely. 1 A L
Staff • There must be no unauthorized person within the range of work activities.

Earth works

• Locate the area first prior to digging and assess if there are some live energized facility
Underground
Working 3 E H or pipping system which can affect or harm any personnel working in the area. If 3 C L
utilities
Staff possible only hand digging shall be made up to 1 meter.

• Ensure that there is no running water on the area,materials should not be surrounded
Soil collapse due
Working 3 E H or stocked that can increase tension on the soil and there is no shock and vibration from 2 B L
to Cave-in
Staff any heavy vehicles or equipment which can loosen soil's ground stability.
Risk Rating Final assessment
Potential Persons
before controls General Control Measures of Risk
Hazard at Risk
L S RR L S RR
General Requirements
• If the excavation is more than 1 meter deep, suitable ladder must be positioned
projecting a minimum of 1 metre above the edge of the excavations.
Insufficient
Working 3 D M • Platforms,walkways and pedestrian crossover must be designed by competent person 1 B L
Access/Egress
Staff and it should be sufficient enough with handrails in case of emergency it is accessible to
use and it should be free from any obstruction.

• During the hours of work or even at night any excavations,openings,or obstructions


Inadequate signs Working 2 B L near or on roadways and walkways must be indicated by a sufficient number of 1 A L
Staff warning lamps,signboards,barrication and other protection.

• Place excavated material a sufficient distance at least 1 meter from the edge of the
Spoils/grade soil Working 3 E H 2 B L
excavation to prevent from falling into the excavation or causing cave-ins.
Staff

Falling of debris or • Materials must not be stocked close to the edge of excavations minimum 1 meters
Working 3 D M 2 B L
other materials away from the edge.
Staff

• The area of excavation should be barricaded and protected with signboards.Always


Falls of mobile
Working 3 E H ensure the mobile equipment should be in the safe ground stability in excavating the 2 B L
equipment
Staff soil. All heavy equipmnet shall be parked at least 3 meters away to prevent cave-ins.

• Always check the area if it is congested for the workers to use and ensure that the
The area Adjacent structure's stability is strong enough from any soil collapse if not, install protective
Working 3 B M 1 B L
to the structure system like shoring,trenching or supporting system if excavation is greater than 1.5
Staff
meters.

Non-critical Lifting works

• Prior to start of work crane operator should always check the ground area for crane
Crane failure/
Working Staff 3 E H stability and conduct inspection of crane before start lifting works to install the drainage 1 C L
collapse
manhole.Ensure daily checklist for crane will be done.

• Before lifting of any Construction Materials, rigger must ensure that the lifting gears
Lifted load fall
Working Staff 3 D M like sling belt, shackles should be tight properly and no cracks,damage or cut. All lifting 2 C L
from height
gears must have valid 3rd Party certficates.

• The ground shall be properly graded and compacted with gatch materials.
Unstable ground
Working Staff 3 D H • The load bearing capacity of the soil shall be greater than the weigth of the crane. 1 B L
preparation
• All the four outriggers shall rest on the outriggers pads.
Risk Rating Final assessment
Potential Persons
before controls General Control Measures of Risk
Hazard at Risk
L S RR L S RR
General Requirements
Effect of wind on • No critical lifting shall be carried out during such adverse weather conditions.
Working Staff 3 D H 1 A L
load and crane • Lifting shall be stopped when wind speed exceeds 10 m/s

• Lifting area shall be barricaded with adequate signs and no unauthorized personnel
enter inside barricade area.
• Communication equipment (radio)shall be used when the rigger cannot be give clear
Unsafe Slinging or signals to operators due to obstructions, height , or distance and when the operators
Deslinging Working Staff 3 D H can’t see the load. 1 A L
Methodalogy • Tagline length shall match with tagline length mentioned in the lifting plan.
• Only the designated rigger shall guide provide signal to the crane operator when
crane is being positioned or maneuvered.
• Crane operator or rigger shall not leave the area without substitute.

• Never exceed the working load limit and ensure that the sling belt selected has SWL
Overloaded Working Staff 2 B M 1 B L
greater than the mass lifted.

Concrete Works & Water Proofing/Coating works

• Shuttering or form works construction integrity passed QC inspection to avoid


collapse for concrete spillage.
Chemical
• Box shall be available for pump hose after pouring or paving to contain excess
exposure (contact Working 4 C H 2 B L
concrete mixture.
with concrete) Staff
• All concrete pouring boom shall be controlled by Tagline from outside in congested
area.

• Adequate warning and safety signs shall be posted in the site regarding the specific
hazards.
• Ensure all necessary PPE are worn by all Personnel such as full coated gloves, and
Collision hazard Working 3 D M 2 B L
disposable coverall for concrete (especially the PPE for handling concrete).
Staff
• Concreting team will be provided with Gum boot along with clear glasses during night
concrete pouring.

• The area should be free from any obstruction and no materials scattered everywhere.
Slip and Trip • Electrical cables should be above the ground and maintain good cable management.
Working 3 D M 2 B L
hazard • Spilled concrete to be collected and disposed in accordance with regulation.
Staff
• Safe access to the work area should be provided.
Risk Rating Final assessment
Potential Persons
before controls General Control Measures of Risk
Hazard at Risk
L S RR L S RR
General that
• It is recommended Requirements
workers should not touch directly concrete hose. They need
to use tag line to hold concrete hose.
Unsafe condition • Workers engaged in the job shall stay away when pump car and ready mixed truck,
of concrete Working 3 D M docking hose is on operation. 2 B L
pouring Staff • Concrete placement plan and sequence should be established and explained to all
workers during the pre-job meeting.
• Protective clothing to be provide and worn in accordance with SDS.

• Vibrator shall be inspected before use.


• Tools shall be inspected prior to the start of work and defective tools should be be
Noise Working 3 D M replaced. 2 B L
Staff • Site supervisor must ensure correct use of ear protection in area's marked up as a
noisy area(exceeding 85 decibles).

• Segregate or remove flammable liquids or material from source of ignition, shall be


cleared within area of activity.
• Provide fire extinguisher located near diesel driven welding machine/genset and
Fire Working 3 D H 3 C L
where hot works are conducted.
Staff
• Periodically inspected and approved fire extinguisher should be available near to the
area of activity.

• Elevate extension cables in height or provide protective guarding if to be laid on the


ground, keep away from sharp edges.
Electrocution Working 3 E H • Electric tools should not be used in damp or wet locations. 2 B L
Staff • Cords (double rubber insulated type) and hose should be laid safely to avoid damage
and tripping hazard, avoid laying cards or hose over sharp edges.

• The RPM of cutting or grinding wheel shall be higher than the RPM of the machine.
• Remove portable electric tools from the workplace if they are damaged, and attach a
Use of defective
Working 3 E M “Do Not Use” tag. 1 B L
tools & equipment
Staff • All electrical tools must comply with necessary safety requirements.

• User shall always disconnected tools from power sources before maintenance &
Cut & Abrasion Working 3 C M attaching accessories, put guard back in place before reuse, isolate power when not in 1 B L
Staff use.

Flying particles • Use the right tool for the job and ensure it the right size and has sufficient power to
during chipping do the job safely.
Working 3 D M 1 A L
and slag removal • Grinding wheel should have the same maximum permissible working speed as the
Staff
or damaged tools grinder or a higher safe speed.
Risk Rating Final assessment
Potential Persons
before controls General Control Measures of Risk
Hazard at Risk
L S RR L S RR
Spillage of General Requirements
• Small metal container should be provided to be used on the site, and storage area for
chemical Working 4 E H 2 B L
these container should be provided.
substance Staff
• Housekeeping shall be carried out in proper way and the Waste shall be disposed in
the designated place allocated by Contractor.
Chemical Hazards. Working 3 D M 2 B L
• Proper chemical shelter should be provided such as cage with bonding, SDS, limited
Staff
access & Fire Extinguisher

• Cords should be laid safely to avoid damage and tripping hazards. Avoid laying cords
Tripping Hazards. Working 3 D H 2 B L
over sharp edges.
Staff

• All workers shall wear proper PPE ( mask, disposable coverall and etc.)
Chemical contact Working 2 B M 1 B L
• Helmets, Safety glasses, safety shoess and gloves to be worn according to SDS.
Staff

Breathing • The workplace must be screened off to protect other people getting exposed to fumes
Working 3 D H 2 B L
Problems from Torch.
Staff

Health & Environmental Requirements

• Wear all the special required PPE (safety helmet, shoes, coverall, goggles, respiratory
High Noise &
Working Staff 3 D H & face protection, ear protection, electrically insulated (rightly rated) rubber gloves, 1 B L
Personal Injury
etc.) from approved company prior to work.

Poor Illumination
• For early start of works / night shift working hours ensure sufficient lightings
during early Working Staff 3 B M 1 A L
arrangements / lighting towers are in place at the work areas as applicable.
morning/night

• Take precaution when walking on site and in the dessert area.If encounter such
Attacked by
poisonous insect or animals immediately keep a distance,if bitten you need to specify
venomous insect Working 3 E H 1 B L
what kind,color and size and seek immediate attention to a nearest first aid station or
or animal Staff
hospital.

• On site need to manage break time especially during Hot season.Availabilty of the
Dehydration Working 3 B M water should be constant in the area.Drink water whenever you feel thirsty to avoid 1 A L
Staff getting dehydrated.Water drinking tank and rest shelters to be provided on the site.
Risk Rating Final assessment
Potential Persons
before controls General Control Measures of Risk
Hazard at Risk
L S RR L S RR
General Requirements
• Monitoring of temperature will be done prior to start of work to avoid heat stress and
Heat stress Working 3 E M heat stroke.Manage break time and Rest shelters per area will be installed for the 1 B L
Staff workers welfare.

• In the event of bad weather condition like sand storm and heavy rain, stop the work
Bad weather Working 3 B M which is hazardous to work area and make sure before leaving the site area all electrical 1 B L
Staff equipments will be shut off during rainy season and protected from the rain water.

• Prior to start of work housekeeping to be done before, during and after the work to
Poor
ensure that all unnecessary materials be removed to minimize hazards associated in the
Housekeeping and
Working 3 B M area. 1 B L
Waste
Staff • All waste shall be stored at designated bins/area and transportation/disposal of
management
wastes shall be as per KEPA regulations.
Risk Rating Table Likelihood (Frequency)
1 = Very Unlikely
5 L M H H H 2 = Unlikely
3 = Possible
4 = Likely
4 L M M H H 5 = Very Likely
Likelihood

3 L M M M H Severity (Consequence)
A = Minor first aid required only.
B = Medical Treatment (Need to see a doctor)
2 L L M M M
C = Lost time injury case
D = Major injury (Permanent Disability)
1 L L L L L E = Fatality

A B C D E Result of Risk
H = High Risk
Sevirity M = Medium Risk L = Low Risk

When calculating the risk the number of persons exposed and the frequency of exposure to the risk must be taken into account.
Risks that calculate as High MUST have further control measures put into place that reduce the risk BEFORE the activity is carried out.
Medium risk factors should have more control measures introduced where possible to reduce the risk to the lowest possible risk.

Subcontractor shall follow this Risk Assessment within high responsibilities