Kentucky Rock Asphalt Hot-Mix Surfaces
Kentucky Rock Asphalt Hot-Mix Surfaces
Kentucky Rock Asphalt Hot-Mix Surfaces
DEPARTMENT OF HIGHWAYS
WILLIAM B. HAZELRIGG
COMMISSIONER FRANKFORT,KENTUCKY 40601 ADDRESS REPLY TO
H-2-10
Kentucky Rock Asphalt has served prominently on our roads for many
years. At times its performance proved to be unreliable. About 1956, its use
was discontinued altogether--except for some de-slicking applications. The
Kentucky Rock Asphalt Company dissolved soon thereafter. H. G. Reynolds and
Associates acquired extensive holdings from the old company. Eventually, in-
terest reverted to redevelopment of the deposits as a source of bituminous
paving aggregateG T1;.;o avenues of choice were apparent: one was to pre-roast
the rich rock immediately prior to paving, and the other t,ras to produce and
ship lean or non-bituminous aggregate for conventional processing through hot-
mix plants. Beginning in 1962, serveral attempts were maoP to use lean rock
from the old quarries on traffic-bound roads in the area around Edmonson
County. These were not very successful: in some cases the lean pEoduct had
sufficient bitumen to cause it to bind together while in others it remained
loose--and reverted to sand. Thi.cker applications with bituminous seals on
top were also tried. Somewhat as a last resort, a compacted base course and,
optionally, a hot-processed su.rfac.e cou!'se o·r mu.lt:lple seal topping was speci-
fied experimentally on the Nolin Dam Road (KY 728) in Edmonson County. Forth-
with, the redevelopers made a. trial run of the crushed, lean rock through a
hot-mix plant and supplemented the indigenous asphalt with refinery asphalt;
whereupon, they determined to pave the. entire section of the project in this
manner. Unfortunately, the raw, lean, aggregate base did not perform well--
apparently it was too porous and unstable. Nevertheless, the project demon-
started the feasibility of processing and laying a high-type surfacing product.
Thereafter, the Department undertook a series of resurfacing projects employing
the processed product on an experimental basis. The report submitted herewith
is largely concerned with the eonstruct.ion and performance of those projects.
Rock Asphalt surfaces have always been admired for their high skid
resistance and quietness. Both of these qualities have persisted throughout
the redevelopment experiments"
DEPARTMENT OF HIGHWAYS
WILLIAM B. HAZELRIGG
COMMISSIONER FRANKFORT,KENTUCKY 40601 ADDRESS REPLY TO
H-2-10
Kentucky Rock Asphalt has served prominently on our roads for many
years. At times its performance proved to be unreliable. About 1956, its use
was discontinued altogether--except for some de-slicking applications. The
Kentucky Rock Asphalt Company dissolved soon thereafter. H. G. Reynolds and
Associates acquired extensive holdings from the old company. Eventually, in-
terest reverted to redevelopment of the de.posits as a source of bituminous
paving aggregate. Two avenues of choice were apparent: one was to pre-roast
the rich rock immediately prior to paving, and the other was to produce and
ship lean or non-bituminous aggregate for conventional processing through hot-
mix plants. Beginning in 1962, serveral attempts 1>1ere maciP to use lean rock
from the old quarries on traffic-bound roads in the area around Edmonson
County. These were not very successful: in same cases the lean product had
sufficient bitumen to cause it to bind together while in others it remained
loose--and reverted to sand. Thicker applications with bituminous seals on
top were also tried. Somewhat as a last resort, a compacte.d base course and,
optionally, a hot--processed surface course or multiple seal topping Has speci-
fied experimentally on the Nolin Dam Road (KY 728) in Edmonson County. Forth-
with, the redevelopers made s trial run of the c. rushed, lean rock through a
hot-mix plant and supplemented the indigenous asphalt with refinery asphalt;
whereupon, they determined t.o pave the entire section of the project in this
manner. Unfortunately, the rmv, lean, aggregate base did not perform well·--
apparently it was too porous and unstable. Nevertheless, the project demon-
started the feasibility of processing and laying a high-type surfacing product.
Thereafter, the Department undertook a series of resurfacing projects employing
the processed product on an experimental basis. The report submitted herewith
is largely concerned with the construction and performance of those projects.
Roc.k Asphalt surfaces have always been admired for their high skid
resistance and quietness. Both of these qualities have persisted throughout
the redevelopment experiments.
that hard binders assure sufficient stability--to prevent scaling but yet
permit some sacrificial wear.
Mr. Florence, who prepared the manuscript for this report and was
head of our Bituminous Section, resigned June 28, 1968, to accept a position
with the Bureau of Public Roads in North Carolina.
;;},.#,;y;AU~~~
Respectfull~~ub/ed,
H. Havens
JHH:em Director of Research
cc 1 s: Research Committee
FINAL REPORT
KYHPR-64-10; HPR-1 (1,), Part II
by
Robert L. Florence
Formerly Research Engineer
Division of Research
DEPARTMENT OF HIGHWAYS
Commonwealth of Kentucky
August 1968
INTRODUCTION
When this study was initiated in 1962, the objectives were disposed
toward the development of Kentucky Rock Asphalt for use as a traffic-bound
base and surface on rural roads near its source and toward redevelopment of
the material for use as hot-mixed, hot-laid, skid·-resistant surface course
for higher echelon roads. Between July 1962 and August 1965, eight experi-
mental, lean rock-asphalt bases were constructed and evaluated (1, 2, 3).
The success of the hot-mix surface on the Nolin Dam Road project re-
newed interest in rock asphalt for high-type surfacing and resurfacing. A
series of eight resurfacing projects, totaling 92.9 miles in length, was
let for the 1966 construction season. A Special Provision (dated March
1966, Appendix C) \vas prepared to govern this work. The developer, W. G.
Reynolds and Associates, expanded their rock asphalt production operations
during the spring of 1966. A company was formed under the name of Gripstop
Corporation and a large capacity crushing plant was set up in the Indian
Creek Rock Asphalt Quarry in Edmonson County. At the end of the 1966 con-
struction season, three of the resurfacing projects were completed and two
were partially completed. On the basis of the experience gained during the
1966 construction season, a revised Special Provision (dated March 1967,
Appendix C) was prepared, and seven additional resurfacing projects -- totaling
53.5 miles in length --were let to contract.
2
CONSTRUCTION INSPECTIONS, MATERIALS SAMPLING
AND LABORATORY TESTING
Construction Inspections
Materials Sampling
Laboratory Testing
Cold-feed material which was sampled in cloth bags was tested in the
laboratory for bitumen content by benzene extraction. The samples were dried
in the oven at 220°F prior to performing the extraction test. The extracted
aggregate was tested for gradation.
The finished mix, sampled from truck beds and placed in cloth bags, was
reheated to 280°F; and three or more Marshall specimens were prepared from each
sample. A Marshall mechanical compactor was used to prepare the specimens --
50-blow compaction at 260°F. A portion of the sample was tested for asphalt
content by Rotarex extraction with benzene. Gradation tests were performed on
the extracted aggregate. A summary of the Marshall test results is shown in
Table 1, Appendix B. The extraction test results on the cold-feed aggregate
and on the finished mix are summarized in Table 2 in Appendix B.
3
viscosity measurements were made at 77°F with a rotating coaxial cylinder
viscometer. A summary of the test results on the recovered asphalts is shown
in Table 3 in Appendix B.
4
CONSTRUCTION AND PERFORMANCE
The Indian Creek Quarry was operated by the Kentucky Roack Asphalt
Company in the period between 1928 and 1956. The Kentucky Rock Asphalt Company
hand picked material that would yield an average asphalt content of approxi-
mately seven percent, leaving the lower asphalt content material on the
quarry floor. This waste material was loose and exposed to weathering for a
period ranging from 10 to 38 years. The waste material ranged in size from
large boulders to sand grains. This loose, weathered material was processed
first and used in the first hot-mix surfacings. When this loose material
was exhausted, ledge rock from a portion of the quarry floor was processed.
In the spring of 1967, overburden was cleared from an area immediately
adjoining the existing quarry and the freshly exposed ledge rock was quarried
and processed.
During 1966 and a large part of 1967, the rock asphalt was processed
over a 1/2-inch screen. The aggregate used on the last four projects
constructed in 1967 was processed over a 3/8-inch screen. This change in
aggregate size was made by agreement between the Department and the producer
and did not require a modification of the existing gradation specification.
Approximately one mile of the 11.5 miles on the US 231, Butler County, project
was laid using the heat-treated rock asphalt. During an inspection on July 7,
1968, it was impossible to distinguish between this section and the remaining
5
Figure 1. Indian Creek Quarry and Crushing Plant in Edmonson County.
6
portion of this project resurfaced with rock asphalt which had not been heat
treated. No difficulties were reported by the contractor in laying the heat-
treated material.
Cost. Detailed cost data for each project are included in Appendix A.
These data were obtained from the final Contractor's Pay Estimate for ten
projects and for the remaining four projects from the most recent Contractor's
Pay Estimate available. Inasmuch as these four estimates were complete
except for minor adjustments, it is believed the average costs given here are
reasonably accurate. For those projects let to contract during 1966, asphalt
cement enrichment was a separate bid item. During 1967 the price of the
asphalt cement was concomitant with the bid price of the rock-asphalt mixture.
Following is a tabulation of average cost data for these projects:
7
From these data it is apparent that the finished rock-asphalt mixture (cost
of asphalt-cement enrichment included) cost an average of $4.13 per ton more
for those projects let to contract and completed during 1967. This is approxi-
mately a 30 percent increase in cost.
Percent Passing
Minus 1/2-inch Minus 3/8-inch
Sieve Size Maximum Size Maximum Size
1/2,-inch 100
3/8-inch 97.6 100
No. 4 88.:3 95.4
No. 8 82.7 91.3
No.• 16 . 79.9 88.8
No. 30 76.5 85.8
No. 50 39.5 41.9
No. 100 9.8 1().9
No. 200 4.2 3.8
During the 1966 construction season the usual procedure was to add
sufficient manufactured asphalt to maintain a total asphalt content of 8.5
percent. Based on the pay quantities, manufactured asphalt cement was added
at an average rate of 4.4 percent. For those projects let to contract during
1966, the total asphalt content was required to be in the range of 7 to 10
percent and the minimum allowable asphalt content of the cold-feed material
was 4.0 percent. During the 1967 construction season the total asphalt content
was generally maintained between 9 and 10 percent. For those projects,
8
the total asphalt content was required to be in the range of 8 to 11 percent,
and the required minimum asphalt content of the cold-feed material was 3.5 per-
cent.
Thin film oven tests (ASTM D 1754) were performed on four samples of
recovered asphalts and these test results are summarized below:
These data are very limited as a result of the quantity of material available
for the tests, but some interesting results were observed. It may be noted
that the percent loss was 4.6 percent for both smaples of natural asphalt even
though the samples varied in degree of weathering and penetration. Manufactured
asphalt cements used to enrich the rock-asphalt mixtures had losses of less
than 0.2 percent for the PAC-5 grade (85 to 100 penetration grade). Thus,
these natural asphalts have a relatively high proportion of constituents
that are volatile at the thin film oven test temperature (325°F). It may be
noted that the weight loss was reduced, but still substantial, for the
natural asphalt recovered from material sampled from the hot bin of an
asphalt plant. The weight loss of the blend of refinery and natural asphalt,
recovered from a sample of finished mix, was fairly predictable, inasmuch as
the weight loss (1.8 percent) was intermediate between that for the manufactured
9
asphalt (0.0 percent) and that for the heat-treated natural asphalt (3.2
percent).
10
was used in the leveling course. The material became stiff and um<orkable too
rapidly for proper manipulation with a grader. This problem was circumvented
by using conventional hot mix for leveling on the remaining projects. On
several projects the paver screed would tear or scrub the surface of the mat.
On one project, US 31E in Barren-Hart Counties, the paver left a small transverse
bump in the mat whenever the paver stopped. The addition of silicone fluid
appeared to reduce the tearing of the mat. It was found that these problems
were also reduced by operating the paver as continuously as possible. Revisions
were made in the Special Provision to promote continuous paver operation.
On most projects, entrances, crossovers and other areas inaccessible to the paver
and which required considerable handwork were paved with conventional hot-mix
surface course material. This v7ork was usually done after the main-line paving
was completed.
Much of the problem in laying the material must be attributed to the high
viscosity of the natural asphalt binder. The following are viscosities at
77"F for natural asphalt and blends of natural and manufactured asphalt re-
covered from the rock-asphalt aggregates and finished mixtures. For compara-
tive purposes, the viscosity of a 60 penetration asphalt cement is also shown.
Penetration Viscosity
at 77°F at 77°F
Asphalt Description (0.1 mm) (poises)
The hardest asphalt cement normally used for hot-mix paving is PAC-3
(60 to 70 penetration). From the tabulation of viscosities given above, it
is apparent that the blend of manufactured and weathered natural asphalts,
incorporated in the first surfacings, was about five times as viscous as
a 60 penetration material. The viscosity of the natural asphalt obtained
from freshly quarried ledge rock is much more comparable to the PAC-3, This
large variation in viscosity, of course, explains the greater difficulty
experienced in laying the material on the first projects as compared to the
last projects constructed.
ll
SUMHARY OF OBSERVATIONS AND CONCLUSIONS
The prime motivation in using rock asphalt for hot-mix surfacing is its
proven history of high skid resitance. Skid tests performed to date on the
hot-mix, rock-asphalt surfacings have yielded coefficients in the range of
0.57 to 0.72, which is excellent in comparison to results obtained on other
type surfaces.
The average cost of the rock-asphalt resurfacing was $13.45 per ton
(asphalt cement included) for those contracts awarded during calendar year 1966
and $17.58 per ton for those projects awarded and constructed during calendar
year 1967.
The lean, rock-asphalt aggregate was very uniform in gradation and re-
asonably uniform in natural asphalt content. The consistency of the natural
asphalt varied over a wide range. The natural asphalt contained in the loose
waste material processed first at the crushing plant was very hard, and mixtures
produced with this material had very high stabilities but were difficult to
place. The natural asphalt in material produced from freshly quarried ledge
rock was much softer and the mixtures produced from this material had much
lower stabilities and were much easier to place.
Host of the problems associated with plant mixing the material have been
minimized by thorough, daily cleaning of the plant. The soot and odor in
exhaust gases presents a potential problem for plants without adequate dust
collecting and washing systems.
12
RECm1MENDATIONS
3/8-inch 100
No. 16 80- 98
No. 100 0- 15
REFERENCES
13
US 31W, NEADE-HARDIN COUNTIES
SP 82-3, SP 47-39, SP 47-1039
Description: The Louisville-Elizabethtown Road (US 31W and US 60) from 550 feet
north of KY 868 in Nuldraugh (Neade County) to the south end of the Salt River
Bridge at the Jefferson County line in West Point
Unit Bids: Rock-Asphalt Hixture (Leveling and Surfacing) $ ll.OO per ton
Asphalt Cement (PAC 5) $ 0,14 per gallon
Diluted SS-lh $ 0.20 per gallon
Plant Location: Osborn Brothers Quarry on KY 434, 1.8 miles east of intersection
with US 31W
15
Figure 2. Middle West Roads Plant, August 18, 1966. Note that the
plant is exhausted through the wet collector.
Figure 3. Middle West Roads Plant, August 29, 1966. A view of the
plant after an explosion collapsed the duct between the
dry and wet dust collectors. An exhaust stack was. erected
immediately after the dry collector. Note the burned area
on the dry collector.
16
Plant Operations: The lean rock asphalt was first hauled to the plant site on
July 5, 1966. The first 200 tons of material was too coarse, a result of the
producer, Gripstop, Inc., changing from a 1/2-inch square opening screen to a
1/2-inc.h slotted screen. This material was returned to the source, Thereafter
material arriving at the plant site satisfactorily met all material requirements.
The following is the average indigenous asphalt content and average gradation
as indicated by District Materials reports:
The bitumen content of the rock asphalt was determined by centrifuge extraction
using first trichlorethylene as the slovent for two washes and then using a
final '"ash with gasoline. The trichlorethylene was necessary as the native
bitumen was found to b<" difficult to remove from the material using gasoline
alone. This test procedure was used for all projects, After the material was
dumped from trucks at the plant site, a clamshell was used to move the material
to a second stockpile. The material ~1as then loaded from the second stockpile
into two cold·-feed bins. In this manner thorough blending of the material was
insured and a uniform asphalt content was maintained in the final mixture.
Initially there was some concern that the indigenous bitumen content would be
variable and thereby cuase a variation in the bitumen content of the finished
mix.
The dried and heated rock asphalt was scalped over a 9/16-inch screen into
one hot bin. Petroleum asphalt cement (PAC 5) was added at a rate of 4 percent
of the final total batch l'leight. The material ,;as mixed in 3600-pound batches
with 5 seconds dry-mixing time (before adding petroleum asphalt) and 40 seconds
wet-mixing time (after adding petroleum asphalt). Average test values on the
final mixture at the plant (data taken from the plant inspector's field reports)
were as follows:
Paving Operations: The project proposal called for grader application of the
rock-asphalt leveling material. A uniform tack coat of diluted SS-lh was
applied before the mix was tailgated onto the road; but the mix became cool
17
and unworkable before it could be spread to the desired thickness (Figure 4).
A Barber-Greene paver was used for the remainder of the leveling operation
(Figure 5). As the outer lanes were rutted, a continuous leveling course was
placed. Approximately 50 pounds per square yard was used for this continuous
leveling. Spot leveling was used on the inside lanes. In some areas, a
considerable thickness of leveling resulted (Figure 6). However, the material
was very stable and appeared to stand up well under traffic. Approximately
2040 tons of mix and 10,300 gallons of tack (SS-lh) were used in the leveling
operation. About 0.1 gallon per square yard of tack was used between the
leveling and surfacing operation. In surfacing, a Cedar Rapids paver with
electronic screed control was used (Figure 7). The inside lanes were placed
first using a 20-foot ski which rode the outside lanes on which the full
leveling course had been placed. In laying the final surface on the outside
lanes, a foot rode on and matched the level of the inner lane. An application
rate of approximately 91 pounds per square yard was used in the final surface
course.
A tandem roller was used immediately behind the paver and a three-wheel
roller was used for back rolling. The material appeared to cool and become
stable very quickly. Only a minimum amount of rolling was used on the surface
course.
The surface was inspected one year later, March 7, 1968, and found to be
in good condition (Figure 9). At several locations cracking near the joints of
the underlying concrete has become rather severe (Figure 10), A few bituminous
patches have been placed at these locations,
18
Figure 4. US 31W, Hardin-Meade Counties. Leveling with a patrol
grader, as shown above, was unsuccessful as the material
cooled quickly and became stiff.
19
Figure 6. US 31W, Hardin-Meade Counties. The leveling was laid very
thick in some areas. The material has high stability and
appears to be performing well.
20
Figure 7. US 31W, Hardin-Meade Counties. A Cedar Rapids paver with
electronic screed control was used to lay the surface course.
21
Figure 9. US 31W, Hardin-Meade Counties, March 7, 1968. The surface
was in good condition overall.
22
US 31E, BARREN-HART COUNTIES
SP 5-12, SP 50-40
Description: The Glasgow-Hodgenville Road (US 31E) from the north city limits
of Glasgow to the Larue County line
Width: Variable width for 21.854 miles; 22 feet wide from north city limts of
Canmer to the Larue County line.
Plant Description: Barber-Greene 845L Continuous used in fall 1966 (Figure 11)
Hetherington-Berner Batch used in spring 1967 (Figure 12)
Plant Location: }!cLellan Stone Company on KY 218, 1.0 mile south of inter-
section with US 31W
23
Figure 11. Henry Farris Paving Plant, September 23, 1966. This plant,
a Barber-Greene continuous plant, was used to produce the
mixture in the fall of 1966.
Figure 12. Henry Farris Paving Plant, June 1967. A view of the dryer
of the Hetherington-Berner batch plant used to produce the
rock-asphalt mixture in the spring of 1967. Paint was
burned off much of the duct of the plant.
24
Plant Operations: This project started September 8, 1966, and paving was dis-
continued November 15 with approximately 1/3 of the project remaining to be
completed. Paving was resumed in the spring of 1967 and the project was com-
pleted July 3, 1967. A Barber-Greene continuous mix plant was used during the
fall of 1966 and a Hetherington-Berner batch plant was used in the spring of
1967.
All rock asphalt was hauled to the job site by truck and all of the
material passed the specifications requirements except for approximately ten
loads which were deficient in native asphalt. This material was returned to
the supplier. The following is the average native bitumen content and the average
extracted gradation for the stockpile materials as reported by the District
Materials Engineer for the fall of 1966:
At first, the rock asphalt would not feed through the cold-feed bins, equipped
with reciprocating type feeders. After some experimentation it was found tha~
the material would feed with a vibrator attached to the bin. A 10-foot smoke
stack was attached to the dust collector. The dust washer was not used for
this project. Operation of the dryer required constant attention from plant
personnel. It was reported that erratic cold feeding or fluctuating moisture
content of the cold-feed material would cause temperature fluctuations as
large as 100°F. It was necessary to clean the plant at several points every
time the plant shut dmm.
Plant production was set at 71 tons per hour with asphalt cement (PAC 5)
added at 4.0 percent. Data from the plant inspector's field reports, for the
fall of 1966, indicated the following average extraction test results:
These data, when compared to the data previously given on the stockpile material,
indicate that the gradation of the material is altered very slightly in the
plant processing.
Temperatures of the mix at the plant generally ranged between 250°F and
290°F. Some patching material was mixed at temperatures above 300°F in an
effort to increase workability. Mix temperatures between the first week of
October and when the work was discontinued were usually below 275°F. Some
material was laid satisfactorily at temperatures of 240°F.
25
erroneously low temperatures to be indicated and the automatic burner would
operate continuously causing fires in the plant.
Paving Operation: Tacking was done >lith diluted SS-lh and uniform coverage
was obtained. On cool days it was necessary to tack ahead for a considerable
distance in order for the tack to break properly prior to applying the hot mix.
When it was necessary to leave tack dotvn overnight, it t<as sanded with the lean
rock-asphalt aggregate.
Leveling was accomplished with a small grader (Figure 13), Many of the
leveled areas were rough as the material becomes um;orkable very quickly as it
cools.
The final surface course was started at the northern end of the project
in Hart County. Transverse bumps can be observed in the surface at regular
intervals. These were caused by the paver screed "riding over" cool material
after the paver was stopped for several minutes. Four different pavers were
used on the project during the fall. The first was an old clutch operated,
Barber-Greene; the second a Cedar Rapids: the third a small Blaw-Knox; and
the last a larger Blaw-Knox (Figure 14).
When work ceased in the fall of 1966, the surfacing was completed
from the Hart-Larue County line south to approximately 300 feet north of its
intersection with KY 218, an approximate distance of 19.8 miles. The road>1ay
>1as also completed on the southern end from the north city limts of Glasgow
to a point approximately 3.25 miles north.
The surfacing was last inspected March 7, 1968. Overall the surfacing
appeared to be in very good condition (Figure 17). The transverse bumps left
by the paver screed were still noticeable at the northern end of the project.
It wasabserved that the surface texture appeared to be somewhat improved since
the surfacing >1as first laid.
26
Figure 13. US 31E, Barren-Hart Counties, September 20, 1966. All of
the leveling on this project was grader-laid. The grader
could make about three passes over the material before it
became too stiff to work properly.
Figure 14. US 31E, Barren-Hart Counties, June 1967. A view of the Blaw-
Knox paver with electronic screed control which was used to
l-ay most of the surface.
27
Figure 15. US 31E, Barren-Hart Counties, April 12, 1967. An overall
view of the rock-asphalt surface near Glasgow.
Figure 16. US 31E, Barren-Hart Counties, April 12, 1967. A view of one
of the ravelled areas in the northbound lane of the southern
section paved in the fall of 1966.
28
Figure 17. US 31E, Barren-Hart Counties, March 7, 1968. An overall
view of the surface 4.0 miles north of Glasgow.
29
US 41, HENDERSON COUNTY
SP 51-299, SP 51-99
pescription: The Henderson-Sebree Road (US 41) from 0.311 miles south of KY
54 to KY 136 at Anthoston
Width: 22 feet
- -
Letting Date: May 6, 1966
Plant Operations: The rock asphalt was shipped to the plant site in railroad
cars and considerable difficulty was experineced in unloading the cars. After
some trials, the material was successfully unloaded by warming the material
with diesel fuel in five-gallon buckets prior to and during unloading. In
loading the cars, care was exercised to prevent the material from packing over
the discharge shutes. A vibrator 1vas also used in the unloading operation.
30
Average test results on the stockpile material as reported by the District
Materials Engineer were as follm;s:
Production of the hot-mix rock asphalt began October 25, 1966 and con-
tinued through October 29, 1966. The mixture was produced in 4000-pound batches
and asphalt cement was added at 4.2 percent. The mixing time was set for 3
seconds dry mixing and 42 seconds wet mixing. Dow-Corning silicone fluid was
added to the asphalt cement. During the first day of production, some oversize
material was found in the mix. The plant was equipped with a 9/16-inch scalper
screen which did not completely cover the three hot bins. The mixture was
produced at a temperature of 275°F + l5°F. The following is an average of the
field tests on the plant's production:
The surface was inspected a second time on March 6, 1968, and the
surface was still in good condition. The ravelled areas had been repaired
and these areas are no longer noticeable.
31
Figure 18. US 41, Henderson County, March 16, 1967. An overall view that is
typical of the generally good appearance of the surfacing.
Figure 19. US 41, Henderson County, March 16, 1967. A ravelled area at
the extreme northern end of the northbound laneo
32
Figure 20. US 41, Henderson County, March 16, 1967. There were a few
areas, such as shown above, in which the surfacing was
apparently pulled by the paver screed.
Figure 21. US 41, Henderson County, March 16, 1967. There were
several ravelled areas at the ends of bridge decks and
at the extreme ends of the project.
33
US 68, CHRISTIAN COUNTY
SP 24-65, SP 24-525
Description: The Hopkinsville-Elkton Road (US 68) from approximately 0.7 miles
east of junction of US 68 and US 41 to the Todd County line
Width: The contract involved base widening to a uniform 24-foot width. The
existing pavement was 20 and 22 feet in width.
Asphalt cement (PAC 5) was added to the mix at a rate of 4.2 percent.
A third inspection was made of the surfacing on March 6, 1968, and the
surface was found to be in good condition (Figure 25). The pulled areas in the
center of the surface were not as noticeable as on the previous inspections.
The condition of the surfacing in the cracked areas had deteriorated considerably
and these areas will soon require extensive maintenance.
35
Figure 22. US 68, Christian County, March 16, 1967. A ViQW of the
surfaee near the ea~tern end of the project at Fairview.
Figure 23. US 68, Christian County, March 16, 1967. There were three
cracked and deteriorated areas in the eastbound lane, in
close proximity, located about four miles from the western
end of the projecto Apparently these are batches of material
which were burned and/or deficient in added asphalt.
36
Figure 24. US 68, Christian County, March 6, 1968. A view of the
same area as shown in Figure 22. The deterioration of
the area is apparent.
37
US 31W, WARREN COUNTY
SP 114-68
Description: The Bowling Green-Cave City Road (US 31W) from the south end of
the Barren River Bridge at the old northeast city limits of Bowling Green
extending northeasterly
Width: Variable
Pay Quantities: (Based on estimate of July 13, 1967, not a final estimate)
Plant Location: Old Kyrock plant site on KY 259 near Sweeden, Kentucky
General Comments: Construction of the hot-mix surfacing began October 19, 1966,
and was discontinued November 14, 1966 - the usual cutoff date for hot-mix
construction. During this period the northernmost 4.9 miles, the section
with four lanes and depressed median,were paved. Considerable difficulty was
38
Figure 26. R. E. Gaddie's Batch Plant, October 18, 1966. Note the
long conveyor belts from the drier to the hot bins and
from the hot bins to the mixer.
39
experienced in both the plant and placement operations and distressed areas
were apparent in the newly placed surfacing. Construction was resumed in the
spring of 1967 and the surfacing was completed June 7, 1967. Repairs were made
on the surfacing placed in the fall. Class I surface was permitted by change
order for leveling the remaining section (curb and gutter section) to be
surfaced and for paving aprons. No difficulties were experienced during the
spring of 1967.
The mix was produced in 3750-pound batches. The asphalt cement enrich-
ment was set for 4.3 percent. Mixing time was 5 seconds dry mixing and 46
seconds wet mixing. The dry and <>~et dust collectors were disconnected and a
20-foot smoke stack was erected at the mouth of the dryer. The temperature
of the dryer aggregate fluctuated as much as 100°F, inasmuch as a blower was
not provided. Batch temperatures as low as 225°F and as high as 325°F were
observed. Some loads were rejected at 400"F. In order to properly lay the
material, construction personnel believed that. the mix had to arrive at the
paver at a temperature of 280°F. In order to do this, the rock asphalt had
to be heated to near 325"F, the upper specification limit, at the plant. The
plant had long conveyor belts between the dryer and hot bins and between the
hot bins and pugmill. Due to this arrangement of the plant, a decrease in
temperature up to 25°F occurred bett¥een the dryer and pugmill.
On October 31, 1966, the dust collectors were reinstalled in the plant.
Temperatures at the boot of the dryer were then generally maintained between
275°F and 300'F. The asphalt cement enrichment. vJas increased from 4.3 percent
to 4.5 percent on October 31. During the afternoon of October 26 the asphalt
cement enrichment was 4.8 percent. Beginning on October 29, silicone liquid
(Dow-Corning 200 fluid) was added to the asphalt cement at a rate of one
ounce per 1000 gallons of asphalt cement.
The following are average test data obtained from the plant inspector's
daily field reports:
When production was resumed in the spring of 1967, the asphalt cement
enrichment was initially set at 4.5 percent and then reduced to 4.2 percent.
No further special problems were reported in plant control or operation.
Paving Operation: Paving started at the northern end of the project on the
southbound lanes. No leveling was required on the section paved in the fall of
1966. The tack coat material was diluted SS-lh applied at a rate of 0.1 gallon
per square yard. A large. amount of tearing of the mat by the paver screed
40
was experienced. In an attempt to repair these areas, material was broadcast
over the mat by hand. This material did not blend into the mat when rolled
and presented a rough textured and ragged appearance. Hany of these areas wore
excessively after a short time under traffic.
When construction ~Mas resumed in the spring of 1967, repairs were made to
the areas showing distress which were paved in the fall of 1966. A thin course
of hot--mix rock asphalt was used to overlay 2000 feet of the sections showing
the most severe distress. A seal coat was used to cover areas showing slight
distress. Rock-asphalt aggregate, material processed through the dryer of the
plant but with no added asphalt c:ement, was used as the cover stone for the
seal coat.
Class I surf ace course rna terial I>as used to level the curb and gutter
section of the project, approximately 1. 6 miles, and to pave aprons. No
difficulties were reported in placing the material during the spring of 1967.
A second performance inspection was made on April 13, 1967. The surface
was, in general, the same condition as on the previous inspection except that
the wear had progressed further (Figures 30 and 31). A hot--mix patch was
placed in the most severely worn areas.
'•l
Figure 27, US 31H , Harren County, April 13, 1967. The area of pavement
is the same as shown in Figure 28. Note that a bituminous
concrete patch was placed in the area. In the inner wheel
path the course has been worn through to the underlying surface.
42
Figure 29. US 31W, Warren County, November 17, 1966. Holes were formed
from cold agglomerations of non-enriched rock asphalt.
Figure 30. US 31W, Warren County, April 13, 1967. A view of a typical
section of the surface.
43
Figure 31. US 31W, Warren County, April 13, 1967. A view of the
southern end of the resurfacing in the northbound lanes.
Note the open longitudinal construction joint.
44
A third performance inspection was made March 6, 1968 (Figure 32).
Many long cracks were noted in the surfacing. These cracks appeared to be
randomly located and oriented. Most of the cracks had been sealed by
Maintneance (Figure 33). The overlay placed on the distressed areas in the
southbound lanes appeared to be performing satisfactorily. Other than the
cracks previously mentioned, the surface appeared to be in good condition.
45
Figure 32. US 31W, Warren County, March 6, 1968. A typical view of
the pavement.
46
KY 80, ADAIR-METCALFE COUNTIES
SP 1-30, SP 85-24-5
Description: The Columbia-Edmonton Road (KY 80) from the new, west city limits
of Columbia to US 68 at the old, north city limts of Edmonton
Width: 18 feet
Plant Location: Montgomery and Company Quarry, Knob Lick, Metcalfe County
Plant Operation: Production of the surface mix began May 8, 1967. Asphalt
cement was added to the mixture at the rate of 4.5 percent, bringing the total
asphalt content to 9 percent. Silicone liquid was added to the asphalt cement.
Paving began on the eastern end of the project near Columbia.
47
Paving Operation: No undue difficulties were reported in the paving operation.
Performance: Inspections were made of the finished surface on October 10, 1967
and March 8, 1968. On both inspections, the surface appeared in good condition
(Figure 34). It was noted that the appearance of the surfacing generally
improved as one progressed over the surfacing from east to west.
48
US 127, RUSSELL COUNTY
SP 104-78-9
Description: The Jamestown-Albany Road (US 127) from KY 619 near the south
city limits of Jamestown to KY 55 south of Sewellton
Performance: An inspection was made of the surface on October 10, 1967, and
the surface was found to be in good condition. The surface was also inspected
on March 8, 1968. A few randomly located transverse cracks were noted, but
overall the surface was in good condition (Figure 35).
49
Figure 35. US 127, Russell County, March 8, 1968. A typical
view of the surface near Jamestown.
50
KY 101 and KY 259, EDMONSON-WARREN COUNTIES
SP 114-48-1, SP 31-138-2, SP 31-98--2
Description: The US 31W-Brownsville Road (KY 101 and KY 259) from its inter-
section with US 31W in Warren County extending northerly to its junction with
KY 70 east of Brownsville in Edmonson County
Pay Quantities: (Based on estimate of July 13, 1967, not a final estimate)
Plant Location: Old Kyrock plant site on KY 259 near Sweeden, Kentucky
Plant and Paving Operations: Asphalt cement was added to the mix at 4.2 per-
cent. No problems, such as were experienced in the fall of 1966, were en-
countered at the plant or at the paver. Reportedly, good temperature control
was maintained. Considerable time was spent each day in chipping rock asphalt
off the inside surfaces of the dryer, hot bins, etc.
51
Performance: A performance inspection was made of the surfacing on August 31,
1967, and the surface was found to be in good condition. Inspections were
repeated in October 1967 and in March 1968. In March 1968 the surface was
still in good condition (Figures 36 and 37).
52
US 79, TODD COUNTY
SP ll0-126-2
Description: The Russellville-Guthrie Road (US 79) from the Logan County line
extending southwesterly to the end of the cement concrete pavement
Width: 20 feet
- --
Letting Date: April 21, 1967
Plant and Paving Operations: Initially asphalt cement was added to the mix
at 4.5 percent. This was changed to 4.8 percent about midway through the
project in an effort to maintain the total bitumen content near 9.5 percent.
Some difficulty was experienced with temperature control of the mix. The
plant was operated without a dust collector.
A Cedar Rapids paver with automatic leveling controls was used to lay
the mixture. There was some scuffing of the mat by the paver screed (Figure 39).
Performance: Inspections were made of the surface in October 1967 and in March
1968. The· surface was found to be in good condition. Many areas which had been
scuffed by the paver screed were still visible but the damage appeared superficial
(Figure 40). A severely cracked area was noted in the southbound lane about
1/2 mile from the northern end of the project (Figure 41),
53
\
~
"
Figure 38. Kapco's Hot-Mix Plant, June 1967. The dust collectors. on
the plant were by-passed, as shown above.
,.
Figure 39. US 79, Todd County, June 1967. Some scuffing of the
mat by the paver screed occurred throughout the length
of the project.
54
Figure 40. US 79, Todd County, March 6, 1968. A view of the surfacing
near the southern end. of the project. Note that scuff marks
left by the paver screed are still apparent.
Figure 41. US 79, Todd County, March 6, 1968. An area of the southbound
lane, near the northern end of the project, in which the
mix wa_s deficient in asphalt and/or was overheated.
55
KY 70, BARREN COUNTY
SP 5-292-60
Description: The Brownsville-Cave City-Sulphur Well Road (KY 70) from US 31W
in Cave City extending easterly to the east city limits of Hiseville
Width: 20 feet from US 3111 to US 31E, 18 feet from US 31E to the east city
limits of Hiseville
Plant Location: HcLellan Stone Company on KY 218, 1.0 mile south of inter-
section with US 31W
56
{\$
Performance: The surface was inspected in October 1967 and in March 1968.
The surface was in good condition, having a uniform appearance and fine
texture (Figure 42).
57
US 31E, NELSON COUNTY
SP 90-5-7
Description: The Bardstown-Louisville Road (US 150 and US 31E) from Forest
Street in Bardstown to Cox's Creek
Hidth: 24 feet
Performance: An inspection was made of the surfacing on August 24, 1967. The
surface had a fine texture and very pleasing appearance. Inspections of the
surface were repeated in October 1967 and March 1968. In March 1968 the surface
was in good condition (Figure 43). Lateral cracks had developed at regular
intervals and at a few locations a longitudinal crack had developed along the
centerline.
58
KY 105, BRECKINRIDGE COUNTY
SP 14-813-3
Width: 18 feet
Plant and Paving Operations: The rock-asphalt aggregate was freshly quarried
material passing the 3/8-·inch sieve. Asphalt cement (PAC 7) was added to the
mix at a rate of 5.5 percent. Some difficulty was experienced with temperature
control and appeared to be the result of frequent shutdowns when trucks were
not available. A few loads of material out of the temperature tolerance
were rejected the first day surface mix was produced. The plant foreman indicated
that it was necessary to spend considerable effort in cleaning accumulations
of material from the plant, when it was shutdown, in order to operate properly.
60
The existing roadway surface was badly deformed and considerable
material was estimated for leveling. Leveling material overran the contract
quantities and a reduction was made in the surface course thickness to keep
the costs down. As a result, the surface course is very thin in some areas.
61
KY 54, DAVIESS-OHIO COUNTIES
SP 30-57, SP 92-44
Description: The Owensboro-Fordsville Road (KY 54) from 0.234 miles northwest
of Whitesville to the west city limits of Fordsville
Pay Quantities: (Based on estimate of October 27, 1967, not a final estimate)
62
freshly quarried ledge rock. Asphalt cement (PAC 5) was ~dded to the mix
at a rate of 5.5 percent--maintaining the .total bitumen content near 9.5 percent
Dow-Corning 200 fluid (silicone) was added to the asphalt cement at a rate of
one to two ounces per 5000 gallons of asphalt cement.
63
US 431, HcLEAN COUNTY
SP GROUP 15 (1967)
SP 75-202, SP 75-122
Description: The Central City-Owensboro Road (US 431) from the northeast city
limits of Island to the east city limits of Livermore
Pay Quantities: (Based on estimate of October 27, 1967, not a final estimate)
64
Plant and Paving Operations: The same plant and paving equipment were used on
this project and on the KY 54 project in Daviess-Ohio Counties. No problems
in plant or paving operations were reported.
65
Plant and Paving Operation!!: The same plant and paving equipment were used on
this project and on the KY 54 project in Daviess~Ohio Counties. No problems
in plant or paving operations were reported,
65
US 231, BUTLER COUNTY
SP 16-156, SF 16-296
Description: The Morganto"n-·Bovrling Green Road (US 231) from the old northwest
city limits of Morgantown to the \,rarren County line
RE:L Quantities: (Based on estimate of July 17, 1968, not a final estimate)
Plant Location: Gary Brothers Quarry on US 231 near the Warren County line
66
Thus this material was heated twic.e before mixing with asphalt cement. The
following test results t.rere obtained by District Maintenance:
Bitumen Conte.nt--4.8%
Finished Hot-Hix
Bitumen Content--8.8%
Performance: On July 7, 1968 an inspection was made and it was noted that the
overall condition was good. A slight bumpiness was noted, but it is anticipated
that this will smooth out under traffic. Approximately one mile of the 11.5
miles consisted of the heat·-treated rock asphalt (Figure 4 7). It is not
possible to distinguish this sec.tion from the remaining portion.
67
89
S~!fiS3H ~S3~ XHO~VHOHV!
· ,----"':0\i'·QNY - _ ·,-· ·'.;·..·.' · .~ ·. fl.0.'.- •~'
0
->'>""""___ ,
v~:::<!, 11.·.'.5.•.'..·••.\.•.•.•.••.·.·.·.l. '•
::cg ,-<'< ""'
:+4n ,;.'ffJ
••
s~1ai~H ~si.t·~Hi.ii ·,
30·~~ . , ...
SNOI~V!fiHV~
TABLE 1
Asphalt Unit
Date Content Stability Flow Weight Percent Void
Sampled (percent) (pounds) (0,01 inch) (1bs/cu ft) in Mix in Aggregate
126.6
6-13-68 9.0 1362
' 11.9 27 .2
70
,., ,.,.
..,
,.,, ,.,
..
"" ''" , ,....,
,.,,
,.,
,..
T'Ol
.....
... ,,,,
,.... ,,
,,
,., ""
,,
i:'OT
('CT
....
0'<0
,.,.
'"
'"
'" ~~:
"'
,., •m•••""l.!''''''"''
.......
,,....
...,.,
001 •• .,...
'"
....... "' '"" l9-8T-6
001 l9-SI-6
n "'
"' ~:i ;::g::
n 000
...
,..
,.,
,.,
,.,
''
,.,
...
,,·n "'
,,
00<
001
001
.......
l9·ot-•
,., ,., ,., ,, OOT
001
<9·!l·O
,_,,_,
...
"'" "'"'""" , ,...,
n: ,... ,,
..£'>9,. ,,.,....
re•
t'01
''OT
I'll
"' OOI
001
001
''"""V
,_,_,
,_,_,
I'OT '" 001 ,_,_ •
,., ,.,.
..,..,,.,.,... ,,, ...
.•,...,"''''"''"''"""
,......
'"
,.,
1'01 n
,.,
..,
o·n
•·n ...
,,.,
''" .. ,.
,.,. ,...
,..,
Z'60
6'88 ........
,... 001
001
001
001
.......
"-"-·
t9-ll-•
"'"
l'H 0'£8 ,.,. 001 001 ,_,_,
0'01
""
.., ,.,,., .. ,. ,.,.
'lH """''""'
,.., ;o "1'"''
,.,
,.,
,., ...,.,
1'01
<"01
,.,,
!'H ""
Z'lt
v·n
,.I.
,.,.
,.,.
1'06
,..,
0'" ,... ,,
o···
,.,.
,.,.
00<
'"
001
001
001
001
.......
"-.. -·
l9-n-•
,_,_,
'"'
,.,
''
...,.,,., ,.,
,.,
,.,, ,...
''"
,.,
....
•·u
,.,
""'""''''''""'
...
,,.,. 1'06 ,.,,
,.,.
....00!
OOI
001
''"""V
,_,_,
,.,
'' ,., ,.., ,.,. 1'l0 <'66 001 ,_,_,
('Ol
''" ...
, ,,.,,..., ,
~"''''"'""'"
... ,.,. 001 oot <9-0l-8
,.,. ,.,.
•lH p>qOJUJ4 10 •ld""S
,., ,.., 0"66
""""''"''""''
,., ,...
,.,
,.,
n ...,., ,.,
1'5<
,.,.
,.,,
,.,
0'08
,.,
...
,,., ,... ....,.,.,.,.,.,. ,,
"'
... ..
,.
tO-ot-9
,.,
,., ,.,
i'Ol
,.,. ,.,. ,.,.
,... ;:::
,.,. '" ,_.,_,
(9-0l-·
,., ,.,
''"' ,.,. ,... ,.,. o·,. "' ,,_.,_,
"' <9-9'-9
'"
,.., "lH ''"''"" JO "''""'
,... ,.,.
..... ,,,,,.,._,
,.,
""'"""OO:l'uuno-u""'"'" TOT
,.,. .... X>
,.,. ...,...
,.,
n
,.,
,.,
,.,
,..
,.,
,.,
•·m
,.,
>"01
::~1
,...
,."
,,...,.,
,.,,
,..,
1'00
,.,
>"10
,.,
..,
....,.,.
0'"
....
,.,.
••• 6
,.,.
,.,.
'"
000
000
000
"'
,., O'<l
,.., l'IO
,.,
"'" ,.,,
o··· '"
"'
''" 0'<0
... ...
000
··~ "'"''"" , , ,
,., ,.,
n;
''"'"""'" '"""" "''"" "'"" ,.,.
n: ,.,.
,.,. ...,...
''
,.,
,.,
,.,
...,.,,.,,., ,.,.. ,,
Z'H
l'<l
1'H
..,.,,
{'08
roo
0'61
n:
n•
,.,.
..,.
l'TO
1"•• 1'60
::::i:~:
,_,_n
"-H-n
.. .. 6'>t
, ,.,.,, ,,,..,
,.,
,.,
n
,.,
,., ,.,,
,.,
l'H
,..,
0""
',('""' ""'"" '"" '"
,.,.
""
,.,
,.,,
,.,
,.,,
,.,.
....,.,.
('16 ,, .,
000 .. ...
"-~<-•
,., ,., ,., ;::~;::
0'0>
,., ~:~
,., t'01
''" 0'" ,., "'
'" ••-•-or
,., ,., ''" ,.,
...,
''" ,.,.
0""
"'
,., ... ,
''"
... ;: ~; ,.,. 90-&l-6
"" 000
n
,., ,.,
., ,.,,,''".. ,..., ,
.., ,.,. ... 99-ll-6
,.,
''
,.,
,.,
,.,
,., ,.,
8'01 ,.,,
,., ,,...
,,.,,
..,
,.,.
6'00
0""
,.,.
001
oo1
.......
t9-u-•
,., ,., ,.,, 0'10
"" o·,.
001 ,_,_,
n ;·u
....
.,.,,..., , ... .... 1'" 001 ,_,_,
,.,
,., <'li ..,.,,.,,,, ·o;,.,., ,,., "'"" "' '"
,.,
,.,, ,.,, ,.,
0'61 ,... ,.,.
,.., ''"
.......
,... ,.,.
,., O'H
•·n
l't< ,_.,_,
"-n-s
,_,_,
,., •·n ,., ::~ 0''"
,., l'06
....
, ...
o· ..
US JlE
Barren-Hart Counties
4.57 12
7,061xl0 7
*2.32txlo7
US JlW
Warren County
KY 80 3.22 16
Adair-Metcalfe Counties
141,5
125,5
"
115
1.81 16
us 79 158.0 55
Todd County
K'<70
Barren County:
US 31E
Nelson County
**6,867x106
KY 105
Breckinridge County
*~*4. 97lxlO.ft
KY 54
Daviess-Ohio Counties 124.0 150+
4.00 15
126.5 83
1,59 30 100<-
1
2 ~:e:;::~~:n:tw~;:F ~b~~in~~ 'f~o:e~~ch
truck sampled,
**Viscosity test performed on a blend of bitumen
recovered from truck samples obtained on
)Specific Gravity at 77"F B1.054; Ash content ,.. 0,35% August 16 and 17, 1967,
4Percent Asphalt Extracted from 50-gram samplea of cold-feed material using; ***Vi!3cosity test performed on a blend of bitumen
Carbon Disulfide 4,05% recovered from hot-bin samples' obtained on
Benzene J. 92% August 25 and 28, 1967.
Carbon Tetrachloride 3.70%
~Viscosity test performed on combined bitumen recovered from all material sampled on June 20, 1967,
72
TABLE 5
Coefficient of Friction
Project Location Lane 1966 1967 1965 ADT
US 31W Hardin
Hardin-Meade Counties County Both 0.66 14670
us 41 Henderson
Henderson County County Both 0.60 5900
us68 Christian
Christian County County Both 0,62 2380
us 127 Russell
Russell County County Both 0,60 1130
us 79 Todd
Todd County County Both 0,64 1620
KY 70 Barren
Barren County County Both 0,61 1080
US 31E Nelson
Nelson County County Both 0.57 3660
KY 1827 Edmonson
Edmonson County County 0,72 0.64
(Nolin Dam Road)
74
APPENDIX C
SPECIAL PROVISIONS
FOR
CRUSHED BITUMINOUS SANDSTONE SURFACE
(KENTUCKY ROCK ASPHALT)
FOR
(Experimental)
I. DESCRIPTION
76
Page 2 of 3
II . MATERIALS
77
Page 3 of 3
c. Preoaratig.n._Qf_MJ.lS:t_'dJ~.'?...,.
(Art ..icle 306.3.3, as applicable--
excluding Paragraphs A and B thereof.)
The asphalt cement and the bi tumi.no'.ls t.ack rna t.er ial will be
measured in gallons as specified in Section 621.
V. BASIS OF PAYMENT
APPROVED-221~-t..~ /?th
~~····-·~&at~
A. NEISER
0"
P:ROoJECT MANAGE.IVJ.ENT ENGINEER
78
COMMONWEALTH OF KENTUCKY
DEPARTMENT OF HIGHWAYS
FOR
(Experimental)
I. DESCRIPTION
II. MATERIALS
79
Page 2 of 5
80
Page 3 of 5
c. Preparation of Mixture.
81
Page 4 of 5
82
Pa<je 5 of 5
I.
Maintenance and Protection. Maintenance and pro~ection shall
be in accordance with Article 306.3.10.
V. BASIS OF PAYMENT
Aftp ~/~<t~
A. 0. NEISER •
STATE HIGHWAY ENGINEER
83
COMMONWEALTH OF KENTUCKY
DEPARTMENT OF HIGHWAYS
FOR
I. DESCRIPTION
II. MATERIALS
84
Page 2 of 5
c. Preparation of Mixture.
87
Page 5 of 5
/
- ....·:.:) ; -
APPROVED____:j~f,.,·-''·-' / •".~'
' . ._.,i' .•-
/d ;>. / 7 b7
/ •...::-
88
· OVON dWVH .LVOS: ll:iiiGHV.LfiOW
GNV
aVOH 3HO.LS S,NGHHNfiW:iiG-WVa NI~ON
.LHOd:iiH
a
NOLIN DAN-DEHUNBRUN' S STORE ROAD
KY 728
The Nolin Dam Road, constructed during the summer and fall of 1965,
was the first hot--mix, rock-··asphalt surfacing project, An account of the
construction and performance through Harch 1966 has been reported (3).
The project involved construction of a lean rock-asphalt base (no added
petroleum asphalt) 3-1/2 inches thick and a hot--mixed, enriched, rock-
asphalt surface course 1·--1/2 inches thick placed on the existing traffic
bound surfacing.
The last previously reported performance inspection was made !1arcl1 23,
1966. At that time rather extensive cracking had occurred in the outer wheel
tracks. It was noted then that the cracking tended to be concentrated in
areas of poor subgrade support, primarily cut sections. The developer, Reynolds
and Associates, had sealed most of the cracked areas v-1ith a fine-,~graded rock
asphalt.
Further performance inspections were made in June and October 1966 and
in Narch and September 1967. Following is a discussion of the condition of
the surface and of the repairs made at the time of each inspection:
June 1966: Hany of the cracked areas (Figure 48) had broken up. The
Developer was then engaged in making repairs to the failed areas.
Repairs were made by removing the rock-asphalt base and surface courses
and a portion of the soft subgrade. The excavated areas was then filled
with crushed limestone to the level of the top of the base course.
Hot-mix rock asphalt was then used as the surfacing. These repairs were
generally too limited in extent and proved to be inadequate. Hany of
the patched areas deformed badly and additional failures occurred im-
mediately adjacent to the reparis.
October 1966: During the fall months, District Haintenance made temporary
repairs to the larger failed areas (Figure 49) by removing the hot-mix
surface, scarifying the balance of the base and allm•ing it to dry out,
and then applying No. 610 limestone aggregate to the level of the finished
surface. These repairs were made to keep the roadway in a reasonable
riding condition until more extensive repairs could be performed the
follmving cons true tion season.
90
Figure 48. Nolin Dam Road, June 14, 1966. Note the deformed and cracked
areas near the edges of the -pavement.
91
cold-mix surface course, consisting of No. 9 limestone and emulsion,
was then applied to bring the reparied area up to the level of the
surrounding surface. A chip seal was then placed on all of the roadway
surface which had not been repaired (Figure 51) • To allmv the cold mixes
ample time to cure~he repaired areas were not sealed. It is planned
to seal the full surface area during the 1968 construction season.
92
Figure 50. Nolin Dam Road, March 22, 1967. The broken sufracing was
removed and replaced wi.th limestone aggregate.
Figure 51. Nolin Dam Road, March 7, 1968. During the fall of 1967,
the failed areas were repaired with cold mix and a seal
coat was placed over the area Which was not repaired.
93
MOUTARDIER BOAT RANP ROAD
The Houtardier Boat Ramp Road was constructed in October 196L~ when a
lean rock-asphalt base (501f pounds per square yard) ~<as placed on the ne~<ly
constructed grade. The compacted base was immediately sealed with SS--lh
emulsion and fine--graded lean rock asphalt. A report on the construction
of this base and its performance through Harch 1966 has been made (3).
During the 1966 construction season, a Class I, Type A surfacing was placed
on the roadway by contract. An inspection was made of the surface in April
1967 and the roadway surface was in good condition. There was one small
area of cracking as shmm in Figure 52. An overall view of the roadway is
shown in Figure 53.
A recent inspection ,,;as made in l1arch 1968. The vmsternmost 0,1 mile
of the project was badly cracked and beginning to break up. In the remaining
0. 7 mile of the road~vay, minor rutting was observed and there was one limited
area of cracking.
94
Figure 52. Moutardier Boat Ramp Road, April 1967. This was
the only cracked area in the surface.
95