Professional Documents
Culture Documents
Commissioning Construction Projects: T P M C
Commissioning Construction Projects: T P M C
Chapter 11
Commissioning
Construction Projects*
I
n order to insure that construction projects meet the specifica-
tion of the designers, it is critical that the project be commis-
sioned. The project manager should insure that this step has
not been overlooked when completing the project. All buildings
which are LED certified by the U.S. Green Building Council re-
quire “commissioning.” This chapter will highlight commission-
ing strategies that the project manager needs to know.
INITIATION OF A
RE-COMMISSIONING PROGRAM
Commissioning a new facility is very easy compared to re-
commissioning an old or existing building. For a new facility, the
design specifications are well documented. Mechanical and elec-
trical control points, as well as other as-built plans, are readily
available. The sequence of operation is well defined. To re-com-
mission an older facility you may lack some or most of these re-
sources. For that reason data collection is crucial. The following is
a suggested list of what you may need.
• Utility bills. Collect electric, natural gas, and any other en-
ergy bills. Contact the utilities and request a history of each
account for the past few years. Audit these bills and note any
spikes or gradual increases in consumption. An energy utili-
zation index (EUI) may be needed, especially if you have
similar facilities on the same campus. The EUI will provide
information on the total energy consumption of the facility
per square foot per degree days.
• Tour the facility. Visit all the mechanical and electrical rooms
and note their condition. Special attention should be paid to
air handler rooms. Note the condition of the air filters, drip
pans, dampers, valves, and coils, as well as the mechanical
room itself. Note any override of equipment. Holding the
outside air dampers open with a 2 × 4 or by a wire hanger is
not considered the best indoor air quality control measure.
• Indoor air quality test. An indoor air quality test was con-
ducted on all floors. All the readings were good.
• Cooling needs. The first week after the final two floors were
occupied, the “too hot” calls started coming when the outside
air temperature reached 90°F. The chiller was checked and
serviced and the cooling tower was cleaned. However, the
chilled water temperature was climbing even though the
chiller was running at 100 percent load. Conducting a load
test for the building reveled that another 20 tons of cooling
was needed to satisfy the cooling demand. A new chiller was
installed and the problem was corrected.
Re-commissioning Results of
Temple View Center Office Building
By uncovering and correcting the deficiencies, the goal of
improving tenant thermal comfort was achieved and in addition,
one significant lease agreement was extended. Other systems, like
the fire system, were re-commissioned but not included in this
chapter.
• Chilled water flow. The chilled water flow was too low to
the air handlers. The VFD that controlled the chilled water
circulating pumps was set too low. The chilled water flow
had been set low due to the vacancies caused by the HVAC
remodeling, Upon the completion of the remodeling and new
tenants, nobody remembered to increase the water flow. The
water flow was corrected.
CONCLUSION