Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Bill of Quantities: Index

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 42

Bill of Quantities

The bill of quantities provided herewith were compiled from inputs obtained from a few
leading quantity surveying firms in Viet Nam. The information should be regarded as
indicative and for general guidance only. PMH makes no representation, expressed or
implied, with regard to the accuracy of the information herein and cannot accept any
responsibility or liability for any errors or omissions that may be made.

The bill of quantities include allowances for contractor’s overheads and profit and all
necessary labour, goods and materials, and plant & equipment costs unless stated
otherwise.

Index

1 Demolition and Alterations


2 Pilling and Diaphragm Wall

3 Excavation
4 Concrete Work

5 Brickwork and Blockwork

6 Roofing

7 Carpentry and Joinery

8 Ironmongery

9 Structural Steelwork
10 Metal Work
11 Wall Finishes
12 Ceiling Finishes
13 Floor Finishes
14 Plumbing
15 Glazing
16 Painting
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

I DEMOLITION AND ALTERATIONS


1 DEMOLITIONS

1.1 General Demolitions

Demolishing/clearing the site of all


structures/individual structures/ parts of structures
including make good affected surrounding areas to item
receive new finishes and carting debris off site

1.2 Temporary works

Providing, erecting and maintaining temporary work


for dealing with rainwater, temporary openings
including make good affected surrounding areas item
after clearing away temporary work

1.3 Shoring

Supplying, erecting and maintaining the shoring


including obtaining licences and paying fees, cutting
holes in the structure, providing all necessary nails,
screw, wedges, bolt, making good all work disturbed item
surrounding areas to reciece new finishes after
clearing away the shoring and debris off site

2 ALTERATIONS

Alteration works shall be described or grouped


item
according to location including make good

Provide for the protection to existing retained


item
structures and finishes

II PILLING & DIAPHRAGM WALL


1 MOBILIZATION & DEMOLISION

1.1 Pilling & diaphragm wall equipment

A Allow for provision and mobilization of all necessary


piling equipment, plant and tools and for their
transportation to the Site, handling and assembling, item
moving from pile to pile round the Site including all
necessary associated works

B Allow for demobilization and dismantling of all


necessary piling/diaphragm wall equipment plant,
and tools and for their transportation from the Site item
on the completion of the Works including all
necessary associated works

Page 2/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

1.1 Pilling & diaphragm wall equipment (Cont'd)

Allow for providing a working platform of suitable


size, strength and stability to permit operation of the item
boring plant,etc.

The Subcontractor is to make his own assessment


of the existing ground conditions and allow for the
provision of any temporary works that may be item
required to permit access and operation of
piling/diaphragm wall plant and equipment on the
site.

Allow for clearing the site of vegetation as required


item
to undertake the works.

1.2 Standing time

Standing time for all plant, equipment and labor in


excess three hours (the initial three hours shall be at
the Contractor own cost) due to suspension works hour
given in writing by the Engineer

2 BAKAU PILES

Supplying, transporting, handling, pitching as


60mm Diameter bakau pile No
80mm Diameter bakau pile No
100mm Diameter bakau pile No
120mm Diameter bakau pile No

Driving bakau pile to required levels


60mm Diameter bakau pile No
80mm Diameter bakau pile No
100mm Diameter bakau pile No
120mm Diameter bakau pile No

3 SPUN PILES/ PRECAST PILES

Supplying, transporting and handling spun


piles/precast piles as specified
300mm Diameter spun pile m
400mm Diameter spun pile m
450mm Diameter spun pile m
500mm Diameter spun pile m
600mm Diameter spun pile m

Driving in spun piles/pre-cast piles as specified


300mm Diameter spun pile m
400mm Diameter spun pile m
450mm Diameter spun pile m
500mm Diameter spun pile m

Page 3/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
600mm Diameter spun pile m

4 BORED PILES

4.1 Boring (Provisional)

Bore vertical pile hole through whatever soil strata


other than continuous solid rock as described
including all drilling and coring, installation and
extraction of temporary steel casings and linings:-
300mm Diameter bored pile m
400mm Diameter bored pile m
450mm Diameter bored pile m
500mm Diameter bored pile m
600mm Diameter bored pile m
Extra over for coring through rocks in whatever m
depth as described

4.2 Allow for bentonite slurry (Provisional)

Allow for bentonite slurry to bore holes (allowed to


full depth of bore).
to all bored piles  m3

4.3 Disposal of excavated spoil (Provisional)

Remove excavated spoil from the site and dispose


of in a legal tip (measured net - no allowance for
bulking).
to all bored piles m3

4.4 Filling (Provisional)

Back fill bored holes with selected materials


to all bored piles m3

4.5 Reinforced Concrete (Provisional)

Vibrated reinforced dry or termite concrete Grade


C35/45 as described:-
300mm Diameter bored pile m3
400mm Diameter bored pile m3
450mm Diameter bored pile m3
500mm Diameter bored pile m3
600mm Diameter bored pile m3

4.6 Reinforcement (Provisional)

Provide, fabricating and placing of high yield steel


bar reinforcement cage as described:-
300mm Diameter bored pile kg
400mm Diameter bored pile kg

Page 4/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
450mm Diameter bored pile kg
500mm Diameter bored pile kg
600mm Diameter bored pile kg

4.7 Cutting of piles

Cut and trim reinforced concrete cast-in-situ bored


piles at required cut-off levels and dispose surplus
length off site including all necessary excavation to
exposed steel bar reinforcement and cleaning,
straightening and bending projecting high yield steel
bar reinforcement to bond into reinforced concrete
pile cap.

300mm Diameter bored pile No


400mm Diameter bored pile No
450mm Diameter bored pile No
500mm Diameter bored pile No
600mm Diameter bored pile No

5 STEEL SHEET PILES

Supplying, transporting and handling steel sheet


piles/interlocking piles as specified
6000mm long x 400mm wide x 125mm high x13mm m2
thick (60kg/m)
6000mm long x 400mm wide x 170mm high x13mm m2
thick (76.1kg/m)
9000mm long x 400mm wide x 125mm high x13mm m2
thick (60kg/m)
9000mm long x 400mm wide x 170mm high x13mm m2
thick (76.1kg/m)
12000mm long x 400mm wide x 125mm high m2
x13mm thick (60kg/m)
12000mm long x 400mm wide x 170mm high m2
x13mm thick (76.1kg/m)

Pitching & driving steel sheet piles/interlocking piles


to required set and level
6000mm long x 400mm wide x 125mm high x13mm m2
thick (60kg/m)
6000mm long x 400mm wide x 170mm high x13mm m2
thick (76.1kg/m)
9000mm long x 400mm wide x 125mm high x13mm m2
thick (60kg/m)
9000mm long x 400mm wide x 170mm high x13mm m2
thick (76.1kg/m)
12000mm long x 400mm wide x 125mm high m2
x13mm thick (60kg/m)
12000mm long x 400mm wide x 170mm high m2
x13mm thick (76.1kg/m)

Page 5/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

5 STEEL SHEET PILES (CONT'D)

Supply and install corner piles, junction piles and


other special piles.
6000mm long x 400mm wide x 125mm high x13mm m
thick (60kg/m)
6000mm long x 400mm wide x 170mm high x13mm m
thick (76.1kg/m)
9000mm long x 400mm wide x 125mm high x13mm m
thick (60kg/m)
9000mm long x 400mm wide x 170mm high x13mm m
thick (76.1kg/m)
12000mm long x 400mm wide x 125mm high m
x13mm thick (60kg/m)
12000mm long x 400mm wide x 170mm high m
x13mm thick (76.1kg/m)

Apply two layer of anti-rust epoxy pain to the expose


steel sheet piles.
6000mm long x 400mm wide x 125mm high x13mm m2
thick (60kg/m)
6000mm long x 400mm wide x 170mm high x13mm m2
thick (76.1kg/m)
9000mm long x 400mm wide x 125mm high x13mm m2
thick (60kg/m)
9000mm long x 400mm wide x 170mm high x13mm m2
thick (76.1kg/m)
12000mm long x 400mm wide x 125mm high m2
x13mm thick (60kg/m)
12000mm long x 400mm wide x 170mm high m2
x13mm thick (76.1kg/m)

6 TESTING WORKD FOR TEST PILES

Test pile shall be measured in accordance with the


rule for the actual production or working piles

6.1 Working load test

Carry out working load test to completed bored


piles/spun piles including mobilization and
demobilization of plant, equipment, testing
instruments, all other accessories and all
submission test records and reports to the Employer
upon completion of the test

to…diameter bored piles/spun piles Ton

Page 6/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

6.2 Ultimade load test

Carry out ultimate load test to completed bored


piles/spun piles including mobilization and
demobilization of plant, equipment, testing
instruments, all other accessories and all
submission test records and reports to the Employer
upon completion of the test

to…diameter bored piles/spun piles Ton

7 TESTING WORKS

7.1 Koden Test

Carry out Koden Test to completed bored piles


including mobilization and demobilization of plant,
equipment, testing instruments, all other
accessories and all submission test records and
reports to the Employer.
300mm Diameter bored pile No
400mm Diameter bored pile No
450mm Diameter bored pile No
500mm Diameter bored pile No
600mm Diameter bored pile No

7.2 Access Tubes

Supply and Install testing access tube as per


specification through the concrete shaft; including
tape measurement, sleeve, all fixing against
displacement and any necessary rebar for fixing.
300mm Diameter bored pile m
400mm Diameter bored pile m
450mm Diameter bored pile m
500mm Diameter bored pile m
600mm Diameter bored pile m

7.3 Sonic Test

Carry out Sonic Test to completed bored piles


including mobilization and demobilization of plant,
equipment, testing instruments, all other
accessories and all submission test records and
reports to the Employer and subsequent all tube
shall be filled by non-shrink 15 MPa grout after
finishing the sonic test.
300mm Diameter bored pile No
400mm Diameter bored pile No
450mm Diameter bored pile No
500mm Diameter bored pile No
600mm Diameter bored pile No

7.4 Pile Integrity Test (PIT)

Page 7/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Carry out Pile Integrity Test to completed bored
piles including mobilization and demobilization of
plant, equipment, testing instruments, all other
accessories and all submission test records and
reports to the Employer
300mm Diameter bored pile No
400mm Diameter bored pile No
450mm Diameter bored pile No
500mm Diameter bored pile No
600mm Diameter bored pile No

7.5 Dynamic Load Test (PDA)

Provide all necessary plant, equipment, labor, and


all other accessories for high strain dynamic load
test using Pile Driving Analyzer (PDA) on selected
working bored pile by the  Engineer and to be
carried out by Specialist. Submit the test records
and reports to the Employer.

300mm Diameter bored pile No


400mm Diameter bored pile No
450mm Diameter bored pile No
500mm Diameter bored pile No
600mm Diameter bored pile No

8 DIAPHRAGM WALLS

8.1 Guide walls

Construction of the guide walls as specified m

8.2 Excavation for diapharagm wall

Excavate diapharagm wall panel form the level at


which the work of excavation is expected to begin
including additional excavation to accommodate
guide wall or to provide working space and disposal
of material off site
average 5-10m deep m3
average 10-15m deep m3
average 15-20m deep m3
average 20-25m deep m3
average 25-30m deep m3
exceed average 30mm deep m3

8.3 Allow for bentonite slurry (Provisional)

Allow for bentonite slurry to diaphragm wall (allowed


to full depth of panel).
to diaphragm wall  m3

Page 8/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
8.4 Trimming and cleaning

Trimming and cleaning the face of diaphragm wall m2


as specified

8.5 Stop ends

Supply, install and extraction stop-ends for m


diaphragm wall panel as specified

8 DIAPHRAGM WALLS (CONT'D)

8.6 Reinforced Concrete

Concrete in diaphragm wall (stated the wall m3


thickness and the specification of the concrete
grade)
Preparing the tops of wall and reinforcement to m
receive cappings ( stating the thickness)

8.7 Reinforcement

Mild steel bar reinforcement to diaphragm wall as kg


specfied

8.8 Formwork

Formwork to in-situ concrete including strutting as m2


spcified

8.9 Waterproof

Waterproof joints in diaphragm walls as specified item

III EXCAVATION
1 SITE CLEARANCE

1.1 Clear Site Vegetation

Clearing shrubs, bushes, undergrowth, grass,


rubbish and small trees not exceeding 600mm girth
at a height of 1.00m above ground and grubbing up
roots and disposal of materials off site
A generally m2 8.30 8.30 8.30 8.30

2 GENERAL EXCAVATION

Page 9/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

2.1 Oversite Excavation

Excavate over site, commencing from ground level,


to reduce level
A average 100mm deep m2 2.90 2.90 2.90 2.90
B average 200mm deep m2 3.80 3.80 3.80 3.80
C average 300mm deep m2 4.90 4.90 4.90 4.90
D exceed average 300mm deep m3 14.50 14.50 14.50 14.50

2.2 Pit/Trench Excavation

Excavate to form pit or trench, commencing from


reduced level
A ne 2.00m deep m3 26.30 26.30 26.30 26.30
B 2.00 - 4.00m deep m3 28.60 28.60 28.60 28.60
C 4.00 - 6.00m deep m3 31.00 31.00 31.00 31.00
D extra over for each 2.00m deep m3 4.60 4.60 4.60 4.60

2.3 Basement Excavation

Excavate to form basement, commencing from


reduced level
A ne 2.00m deep m3 23.60 23.60 23.60 23.60
B 2.00 - 4.00m deep m3 26.00 26.00 26.00 26.00
C 4.00 - 6.00m deep m3 28.30 28.30 28.30 28.30
D extra over for each 2.00m deep m3 2.70 2.70 2.70 2.70

2.4 Break Up Obstruction

Extra over excavation for breaking up obstruction


below ground level using mechanical means
A rock m3 98.30 98.30 98.30 98.30

2 GENERAL EXCAVATION (CONT'D)

2.5 Special strutting and shoring

Design, supply and installation of strutting and


shoring system during the basement excavation and
foundation work including all necessary connection,
jointing, welding,submission to Authorities, item
dismantle and removal upon completion of the
works and make good all affected works, to
Engineer's approval

Page 10/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
3 FILLING

3.1 Backfilling

Backfill around trench, column base, pile cap,


foundation, beam and pier hole
A excavated material obtained within the site m3 9.30 9.30 9.30 9.30
B earth filling obtained from contractor's own source m3 10.90 10.90 10.90 10.90

3.2 Filling and Forming Embankments

Deposit, spread, level, compact and consolidate in


layers of 150mm thick to make up levels
A excavated material obtained within the site m3 9.60 9.60 9.60 9.60
B earth filling obtained from contractor's own source m3 12.40 12.40 12.40 12.40

3.3 Hardcore and Aggregate

Spread, level, compact, ram and consolidate


A hardcore, including blinding with sand m3 51.30 51.30 51.30 51.30

4 DISPOSAL

4.1 Disposal of Water

Allow for keeping the Site and all excavation area item
free from all water by pumping or otherwise

4.2 Excavated Material

Remove excavated material off site


A to contractor's own dumping site m3 32.10 32.10 32.10 32.10

5 INSTRUMENTATION AND MONITORING

Maintenance and protection of all monitoring item


equipment including recording of data and reporting
throughout the duration of the Works

6 ANTI-TERMITE TREATMENT

Allow for anti-termite treatment to soil in contact with


item
the building structure as specified

IV CONCRETE WORK
1 IN-SITU CONCRETE

1.1 Lean/Mass Concrete

Lean or Mass concrete binding to any location


A grade 15 m3 202.30 202.30 202.00 200.30
B grade 20 m3 209.30 209.30 209.00 207.30

Page 11/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

1.2 Reinforced Concrete

Reinforced concrete to any location


A grade 25 m3 134.70 134.70 134.00 132.30
B grade 30 m3 138.10 136.30 133.90 132.60
C grade 35 m3 140.60 138.80 136.40 135.10
D grade 40 m3 143.40 141.50 139.10 137.90
E grade 50 m3 149.10 147.30 144.90 143.60
F Extra over for waterproofing additive m3 45.00 43.80 42.30 42.30

1.3 Green Concrete

Eco Green Concrete to any location


A 30 Eco Green Conc m3 144.80 144.80 144.20 144.20
B 35 Eco Green Conc m3 147.50 147.50 146.80 146.80
C 40 Eco Green Conc m3 150.20 150.20 149.50 149.50

2 REINFORCEMENT

2.1 Bar reinforcement

Mild steel bar reinforcement to any location


A 6 to 20mm diameter kg 1.30 1.30 1.30 1.30

High tensile steel bar reinforcement; to structure in


any location
B 10 to 13mm diameter kg 1.30 1.30 1.30 1.30
C 16 to 32mm diameter kg 1.30 1.30 1.30 1.30
D 40 to 50mm diameter kg 1.30 1.30 1.30 1.30

2.2 Fabric Reinforcement

Welded fabric reinforcement; well lapped (measured


net)
A Reference No A7 - 3.02kg/m2 m2 8.00 8.00 7.90 7.90
B Reference No A8 - 3.95kg/m2 m2 9.30 9.30 9.30 9.30
C Reference No A9 - 4.99kg/m2 m2 11.00 11.00 11.00 11.00
D Reference No A10 - 6.16kg/m2 m2 12.50 12.50 12.40 12.40
E Reference No A13 - 10.42kg/m2 m2 19.40 19.40 19.30 19.30
F Reference No B10 - 8.14kg/m2 m2 16.10 16.10 16.00 16.00
G Reference No B13 - 13.50kg/m2 m2 26.30 26.30 26.10 26.10
H Reference No D10 - 12.32kg/m2 m2 23.50 23.50 23.40 23.40
I Reference No D13 - 20.84kg/m2 m2 39.90 39.90 39.60 39.60

3 FORMWORK

3.1 Timber Formwork

Timber formwork to in-situ concrete including


strutting ne 3.50m high
A flat surface of suspended slab m2 43.40 42.60 42.60 42.60

Page 12/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
B vertical surface of pilecap, ground beam, etc. m2 43.90 43.10 43.10 43.10
C vertical surface of column, walls m2 44.30 43.50 43.50 43.50
D vertical curved surface of column, wall m2 50.50 49.80 49.80 49.80
E sides and soffits of beams m2 44.40 43.60 43.60 43.60
F slopping surfaces to soffit of slabs and staircases m2 44.90 44.40 44.40 44.40
G vertical edge for each 100mm high m 5.50 5.50 5.50 5.50

Extra over formwork for strutting exceeding 3.50m


H each 1.50m high m2 3.30 3.30 3.30 3.30

3.2 Metal Formwork

Metal formwork to in-situ concrete with strutting not


exceeding 3.50m high
A vertical surface m2 51.50 51.50 51.50 51.50
B vertical curved surface m2 57.20 57.20 57.20 57.20
C horizontal surface m2 52.20 52.20 52.20 52.20
D left in formwork to soffits of suspended slab m2 71.80 71.80 71.80 71.80

Extra over formwork for strutting exceeding 3.50m


E every successive 1.50m high m2 6.00 6.00 6.00 6.00

4 PRECAST CONCRETE COMPONENTS

4.1 Precast Concrete Components

Precast concrete components complete with steel


reinforcement, the whole hoisted, fixed and casted
in place including all labour and materials, formwork,
accessories and jointing
A column m3 1,093.30 1,093.30 1,093.30 1,093.30
B beam m3 953.30 953.30 953.30 953.30
C 100mm thick partition wall m2 89.30 89.30 89.30 89.30
D 100mm thick light weight partition wall m2 76.30 76.30 76.30 76.30

5 EXPANSION JOINTS

5.1 Joint Fillers

Compressible non-extruding bitumen impregnated


fibreboard to joint, including all necessary formwork
A 10mm thick m2 24.50 24.50 24.50 24.50
B 12mm thick m2 29.50 29.50 29.50 29.50
C 25mm thick m2 41.90 41.90 41.90 41.90

5.2 Joint Sealant

Polyurethane / polysulphide sealer squeezed into


A 25 x 15mm joint m 16.90 16.90 16.90 16.90
B 25 x 25mm joint m 21.60 21.60 21.60 21.60

Page 13/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

5.3 Prestressing Cables

Tendons to prestressed concrete complete with all


necessary fixing accessories and grouts
A 12.9mm tendon kg 5.60 5.60 5.60 5.60

6 WATERPROOFING

6.1 Damp Proof Membrane

Waterproofing sheet laid to top,side or underside of


concrete structure
A 0.6mm thick polyethylene moisture barrier m2 6.20 6.20 6.20 6.20
B 0.8mm thick polyethylene moisture barrier m2 9.40 9.40 9.40 9.40
C approved bituminous m2 25.20 25.20 25.20 25.20

6.2 Waterproofing System to Ground Slab / Basement

Bituminous waterproof membrane


A to vertical surfaces m2 24.30 24.30 24.30 24.30
B to horizontal surfaces m2 24.30 24.30 24.30 24.30

Homogeneous thermoplastic waterproof membrane


C to vertical surfaces m2 27.30 27.30 27.30 27.30
D to horizontal surfaces m2 27.30 27.30 27.30 27.30

Polyurethane waterproof membrane


E to vertical surfaces m2 29.70 29.70 29.70 29.70
F to horizontal surfaces m2 29.70 29.70 29.70 29.70

6.3 Waterproofing System to Interior/Exterior Wet


Areas

Cementitious waterproof coating


A to vertical surfaces m2 18.80 18.80 18.80 18.80
B to horizontal surfaces m2 18.80 18.80 18.80 18.80

Homogeneous thermoplastic waterproof membrane


C to vertical surfaces m2 30.00 30.00 30.00 30.00
D to horizontal surfaces m2 29.70 29.70 29.70 29.70

Acrylic waterproof membrane


E to vertical surfaces m2 21.50 21.50 21.50 21.50
F to horizontal surfaces m2 21.50 21.50 21.50 21.50

6.4 Waterproofing System to Water-retaining Structure

Cementitious waterproof coating

Page 14/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
A to vertical surfaces m2 18.30 18.30 18.30 18.30
B to horizontal surfaces m2 18.30 18.30 18.30 18.30

Polyurethane elastomeric waterproof membrane


C to vertical surfaces m2 24.50 24.50 24.50 24.50
D to horizontal surfaces m2 24.50 24.50 24.50 24.50

7 INTEGRATED FINISH

Power floated finish to concrete slab


A generally m2 4.90 4.90 4.90 4.90
B with non-metallic hardener; generally m2 16.10 16.10 16.10 16.10

V BRICKWORK AND BLOCKWORK


1 CLAY BRICKS

1.1 Common Brickwork

Common clay brick laid in cement mortar (1:4) with


approved plasticiser and mesh reinforcement at
every fourth course;
A 102.5mm thick m2 35.10 35.10 35.10 35.10
B 215mm thick m2 69.30 69.30 69.30 69.30

1.2 Facing Brickwork

First quality facing brick laid in cement mortar (1:4)


with approved plasticiser and mesh reinforcement at
every fourth course;
A 102.5mm thick m2 45.10 45.10 45.10 45.10
B 215mm thick m2 89.50 89.50 89.50 89.50

2 CONCRETE BLOCKS

2.1 Hollow Concrete Blockwork

Hollow concrete block laid in cement mortar (1:4)


with approved plasticiser and mesh reinforcement at
every fourth course;
A 90mm thick m2 29.00 29.00 29.00 29.00
B 190mm thick m2 57.30 57.30 57.30 57.30

2.2 Autoclaved Aerated Concrete Blockwork

Autoclaved aerated concrete block laid in cement


mortar (1:4) with approved plasticiser and mesh
reinforcement at every fourth course;
A 100mm thick m2 34.30 34.30 34.30 34.30
B 200mm thick m2 63.00 63.00 63.00 63.00

3 GLASS BLOCKS

Page 15/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

3.1 Glass Blockwork

Glass block laid in cement mortar (1:4) with


approved plasticiser and mesh reinforcement at
every fourth course;
A 80mm thick m2 286.30 286.30 286.30 286.30

VI ROOFING
1 TILE ROOFING

1.1 Clay Roof Tiles

Standard colour interlocking clay roof tiles laid to


slope not exceeding 30º (measured nett with no
allowance for laps); fixed to battens (measured
separately) according to manufacturer's
specifications and recommendations
A generally m2 57.90 57.90 57.90 57.90
B ridge or hip tiles m 42.80 42.80 42.80 42.80

1.2 Concrete Roof Tiles

Standard colour interlocking concrete roofing tile


laid to slope not exceeding 30º (measured nett with
no allowance for laps); fixed to battens (measured
separately) according to manufacturer's
specifications and recommendations
A generally m2 23.50 23.50 23.50 23.50
B ridge tile m 14.00 14.00 14.00 14.00

2 BUILT-UP ROOFING

2.1 Insitu Finishes

Cement and sand (1:3) screed with waterproofing


additive; finished with steel trowel to receive
waterproofing membrane (measured separately)
A 25mm (average) thick; finished to falls m2 17.60 17.60 17.60 17.60
B 50mm (average) thick; finished to falls m2 26.90 26.90 26.90 26.90
C add or deduct for each 10mm thickness m2 5.10 5.10 5.10 5.10

Cement and sand (1:3) screed finished with steel


trowel to receive waterproofing membrane
(measured separately)
D 25mm (average) thick; finished to falls m2 16.30 16.30 16.30 16.30

Page 16/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
E 50mm (average) thick; finished to falls m2 18.20 18.20 18.20 18.20
F add or deduct for each 10mm (average) thickness m2 3.80 3.80 3.80 3.80

2.2 Waterproofing Membranes

Preparing surfaces, priming, applying roof


waterproofing membrane in accordance to
manufacturer's recommendation on screeded bed
(measured separately)

Bituminous waterproof membrane


A to flat surface; finished to falls m2 25.20 25.20 25.20 25.20
B to vertical surface m2 25.20 25.20 25.20 25.20

2.2 Waterproofing Membranes (Cont'd)

Homogeneous thermoplastic waterproof membrane


C to flat surface; finished to falls m2 27.70 27.70 27.70 27.70
D to vertical surface m2 27.50 27.50 27.50 27.50

Polyurethane waterproof membrane


E to flat surface; finished to falls m2 29.20 29.20 29.20 29.20
F to vertical surface m2 29.20 29.20 29.20 29.20

2.3 Panel Roofing

50mm thick precast concrete slab in maximum


panel size not exceeding 1000 x 1000mm; complete
with 1 layer of BRC wire mesh, infilled joints with
approved PU sealant
A Concrete grade 20 to roof slabs; finished to falls m2 30.70 30.70 30.70 30.70
B Concrete grade 25 to roof slabs; finished to falls m2 34.30 34.30 34.30 34.30

3 METAL ROOFING

3.1 Steel Roofing

Corrugated steel roof covering complete with all


necessary fixing accessories; fixed to steel
structural framing (measured separately)
A 0.42mm thick; Zincalume Steel m2 27.50 27.50 27.50 27.50
B 0.48mm thick; Zincalume Steel m2 35.80 35.80 35.80 35.80
C 0.42mm thick; Colourbond Steel m2 32.50 32.50 32.50 32.50
D 0.48mm thick; Colourbond Steel m2 36.30 36.30 36.30 36.30

Curve corrugated steel roof covering complete with


all necessary fixing accessories; fixed to steel
structural framing (measured separately)
E 0.60mm thick; Zincalume Steel m2 51.20 51.20 51.20 51.20
F 0.80mm thick; Zincalume Steel m2 57.70 57.70 57.70 57.70

Page 17/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
G 0.60mm thick; Colourbond Steel m2 58.70 58.70 58.70 58.70
H 0.80mm thick; Colourbond Steel m2 65.20 65.20 65.20 65.20

4 RAINWATER GOODS

4.1 Flashings

0.61mm thick galvanised steel with Zincalume


coating (unpainted) metal flashing including fixing
A accessories
girth not exceeding 300mm girth m 14.30 14.30 14.30 14.30
B girth exceeding 300mm but n.e. 600mm girth m 26.50 26.50 26.50 26.50

1.0 mm thick galvanised steel with Zincalume


coating (unpainted) metal flushing including fixing
C accessories
girth not exceeding 300mm girth m 19.70 19.70 19.70 19.70
D girth exceeding 300mm but n.e. 600mm girth m 30.00 30.00 30.00 30.00

4.1 Flashings (Cont'd)

1mm thick colourbond metal flushing including fixing


accessories
E girth not exceeding 300mm girth m 21.20 21.20 21.20 21.20
F girth exceeding 300mm but n.e. 600mm girth m 32.80 32.80 32.80 32.80

2mm thick colourbond metal flushing including fixing


accessories
G girth not exceeding 300mm girth m 27.30 27.30 27.30 27.30
H girth exceeding 300mm but n.e. 600mm girth m 41.30 41.30 41.30 41.30

4.3 UPVC Downpipes

Unplasticied polyvinyl chloride rainwater pipes and


fittings; SS213 Class B; jointing in accordance to
manufacturer's recommendation

Pipes; casting inside reinforced concrete columns


A 100mm diameter m 42.50 42.50 42.50 42.50
B 150mm diameter m 54.90 54.90 54.90 54.90
C 200mm diameter m 67.10 67.10 67.10 67.10

Pipes; fixing to masonry walls; including brackets


D 100mm diameter m 43.00 43.00 43.00 43.00
E 150mm diameter m 55.10 55.10 55.10 55.10
F 200mm diameter m 67.10 67.10 67.10 67.10

Pipes; suspending from concrete soffits including


hangers
G 100mm diameter m 43.00 43.00 43.00 43.00
H 150mm diameter m 55.10 55.10 55.10 55.10
I 200mm diameter m 67.40 67.40 67.40 67.40

5 SUNDRIES

Page 18/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
5.1 Insulation

Insulation material to roof slabs; finished to falls


A 50mm thick fibreglass insulation, density 16 kg/m3 m2 7.50 7.50 7.50 7.50
B 25mm thick, ditto m2 5.70 5.70 5.70 5.70
C double-sided reinforced aluminum foil insulation m2 5.40 5.40 5.40 5.40
paper with 150mm laps
D 25mm thick extruded polystyrene insulation board of m2 9.90 9.90 9.90 9.90
density 32kg/m2
E 50mm thick, ditto m2 16.10 16.10 16.10 16.10

5.2 Wire Mesh

Wire mesh to roof space including dressing over


purlins (measured net)
A BRC Reference No 3315 (75 x 75 x 1.5mm m2 3.90 3.90 3.90 3.90
diameter)

5.3 Protection fleece

1 layer of approved geotextile fleece with side


lapped edges (measured nett); laid in accordance
with manufacturer's recommendation
A to roof slab; finished to falls m2 4.00 4.00 4.00 4.00

VII CARPENTRY AND JOINERY


1 CARCASSING

1.1 Structural Timber

Sawn timber in carpenter's works


A kapur m3 1,960.00 1,960.00 1,960.00 ###
B balau m3 2,193.30 2,193.30 2,193.30 ###
C kempas m3 1,486.70 1,486.70 1,486.70 ###
D chengal m3 2,873.30 2,873.30 2,873.30 ###

1.2 Timber Preservation

Extra over structural timber for pressure


impregnation with a suitable wood preservative to
an average dry salt retention of 5.6kg/m3 and
complying with SS 72 and treated in accordance
with SS CP 1
A generally m3 75.30 75.30 75.30 75.30

2 FRAMING

2.1 Roof Framing

Page 19/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Carpentry framing in roofs; complete with all
necessary fixing accessories
A 100 x 50mm tanalised kapur rafter m 21.00 21.00 21.00 21.00
B 150 x 50mm tanalised kapur rafter m 26.70 26.70 26.70 26.70

3 LININGS

3.1 Calcium Silicate Boards

Calcium silicate board reinforced with selected


fibres and fillers (Class 0) including pointing
A 6mm thick m2 23.40 23.40 23.40 23.40
B 9mm thick m2 32.40 32.40 32.40 32.40
C 12mm thick m2 34.40 34.40 34.40 34.40

3.2 Cement Building Boards

Cement building board including pointing


A 6mm thick m2 18.60 18.60 18.60 18.60
B 12mm thick m2 25.80 25.80 25.80 25.80

3.3 Gypsum Boards

Bare finish gypsum board including pointing


A 10mm thick m2 18.10 18.10 18.10 18.10
B 13mm thick m2 22.10 22.10 22.10 22.10

3.4 Plywoods

Non-waterproofed plywood complying with SS1


A 6mm thick m2 16.00 16.00 16.00 16.00
B 12mm thick m2 20.90 20.90 20.90 20.90
C 18mm thick m2 26.30 26.30 26.30 26.30
D 25mm thick m2 37.70 37.70 37.70 37.70

Waterproofed plywood type WBP


E 6mm thick m2 19.70 19.70 19.70 19.70
F 12mm thick m2 26.00 26.00 26.00 26.00
G 18mm thick m2 32.80 32.80 32.80 32.80
H 25mm thick m2 38.00 38.00 38.00 38.00

3.5 Laminated Plastics

Laminated plastic sheet to BS 3796 including


compatible adhesive
A 0.8mm thick Formica m2 24.20 24.20 24.20 24.20
B 0.8mm thick Print m2 21.20 21.20 21.20 21.20
C 1.0mm thick Formica m2 28.20 28.20 28.20 28.20

Page 20/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Laminated plastic sheet to BS 3796 including
compatible adhesive
D 1.0mm thick Print m2 23.10 23.10 23.10 23.10
E 1.2mm thick Print m2 26.20 26.20 26.20 26.20
F 1.3mm thick Print m2 26.20 26.20 26.20 26.20
G 1.3mm thick Formica m2 31.30 31.30 31.30 31.30

4 WALL INSULATION

4.1 Fibreglass Insulation

Supply and fix fibreglass insulation


A 50mm thick, 48 kg/m3 m2 22.90 22.90 22.90 22.90
B 75mm thick, 48 kg/m3 m2 29.10 29.10 29.10 29.10

4.2 Mineral Wool Insulation

Supply and fix mineral wool insulation


A 25mm thick, 48 kg/m3 m2 12.90 12.90 12.90 12.90
B 50mm thick, 48 kg/m3 m2 17.50 17.50 17.50 17.50
C 25mm thick, 80 kg/m3 m2 15.20 15.20 15.20 15.20

5 PANELLING

5.1 Timber Panelling

100mm wide tongued and grooved wrought


boarding fixed to battens (measured separately)
A 19mm thick kapur m2 44.70 44.70 44.70 44.70
B 25mm thick kapur m2 60.30 60.30 60.30 60.30
C 13mm thick chengal m2 47.50 47.50 47.50 47.50
D 19mm thick chengal m2 53.60 53.60 53.60 53.60
E 25mm thick chengal m2 119.80 119.80 119.80 119.80

5.2 Woodwool Slab Wall Panelling

Supply and fix woodwool slab to wall


A 50mm thick m2 17.90 17.90 17.90 17.90

6 FLOORING

6.1 Floor Boards

Page 21/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
100mm wide wrought plain edge floor board fixed to
bearers (measured separately)
A 19mm thick Indonesia teak m2 89.30 89.30 89.30 89.30
B 25mm thick Indonesia teak m2 107.00 107.00 107.00 107.00
C 19mm thick chengal m2 54.30 54.30 54.30 54.30
D 25mm thick chengal m2 65.00 65.00 65.00 65.00

100mm wide wrought tongued and grooved floor


board fixed to bearers (measured separately)
E 12mm thick Indonesia teak m2 88.50 88.50 88.50 88.50
F 19mm thick Indonesia teak m2 110.80 110.80 110.80 110.80
G 25mm thick Indonesia teak m2 132.70 132.70 132.70 132.70
H 19mm thick chengal m2 76.80 76.80 76.80 76.80
I 25mm thick chengal m2 88.10 88.10 88.10 88.10
J 20mm thick white oak m2 154.00 154.00 154.00 154.00

6.2 Parquet Flooring

Teak parquet flooring laid to approved pattern,


including levelling, spreading, filling, sanding,
cleaning and 3 coats of clear finish varnish; laid on
cement and sand screed (m/s)
A 12mm thick x 50mm wide x 300-400mm randon m2 55.90 55.90 55.90 55.90
length Indonesia teak
B 12mm thick x 50mm wide x 300-400mm randon m2 65.60 65.60 65.60 65.60
length Burmese teak

6.3 Timber Flooring

Teak strip flooring laid to approved pattern,


including levelling, spreading, filling, sanding,
cleaning and 3 coats of clear finish varnish; laid on
plywood backing (m/s)
A 12mm thick x 70mm wide x 400-1200mm randon m2 88.70 88.70 88.70 88.70
length Indonesia teak
B 12mm thick x 70mm wide x 400-1200mm randon m2 101.00 101.00 101.00 101.00
length Burmese teak
C Extra over for 9mm thick WBP plywood to underside m2 16.30 16.30 16.30 16.30
of teak strip flooring (m/s) laid on prepared screed
D (m/s)
Extra over for 9mm thick MR plywood to underside m2 19.30 19.30 19.30 19.30
of teak strip flooring (m/s) laid on prepared screed
(m/s)
7 TIMBER DOORS

7.1 Non Fire-rated Timber Doors; Kapur core

Page 22/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Solid core flush door faced both sides with timber
veneer; complete with hardwood lipping all round
vertical core strips glued and well cramped together
(including supply and installation of sub-frame,
frame / architrave and installation of ironmongery)
A overall size: 900 x 2100 x 38mm thick; single leaf No 613.30 613.30 613.30 613.30
B overall size: 900 x 2100 x 45mm thick; single leaf No 672.50 672.50 672.50 672.50

Hollow core flush door panel faced both sides with


timber veneer; complete with hardwood lipping all
round (including supply and installation of sub-
frame, frame / architrave and installation of
ironmongery)
C overall size: 900 x 2100 x 38mm thick; single leaf No 456.70 456.70 456.70 456.70
D overall size: 900 x 2100 x 45mm thick; single leaf No 522.50 522.50 522.50 522.50

7.2 Fire-rated Timber Doors

Fire-rated timber door panel faced both sides with


timber veneer; including supply and installation of
frame / architrave and installation of ironmongery
and all accessories to FSB requirements and PSB
testing and labelling

A 1/2 hour fire-rated single leaf door; to suit structural No 982.50 982.50 982.50 982.50
opening of 1040 x 2220mm high
B 1/2 hour fire-rated double leaf door; to suit structural No 1,433.30 1,433.30 1,433.30 1,433.30
opening of 1640 x 2220mm high
C 1 hour fire-rated single leaf door; to suit structural No 1,167.50 1,167.50 1,167.50 1,167.50
opening of 1040 x 2220mm high
D 1 hour fire-rated double leaf door; to suit structural No 1,721.30 1,721.30 1,721.30 1,721.30
opening of 1640 x 2220mm high
E 2 hour fire-rated single leaf door; to suit structural No 1,485.00 1,485.00 1,485.00 1,485.00
opening of 1040 x 2220mm high
F 2 hour fire-rated double leaf door; to suit structural No 2,141.70 2,141.70 2,141.70 2,141.70
opening of 1640 x 2220mm high

7.2 Fire-rated Timber Doors (Cont'd)

Fire-rated timber door panel faced both sides with


plywood in paint finish (measured separately);
including supply and installation of metal frame,
installation of ironmongery and accessories to FSB
requirements complete with PSB testing and
labelling
G 1/2 hour rated single leaf door; to suit structural No 930.00 930.00 930.00 930.00
opening of 1040 x 2220mm high

H 1/2 hour rated double leaf door; to suit structural No 1,376.70 1,376.70 1,376.70 1,376.70
opening of 1640 x 2220mm high

I 1 hour rated single leaf door; to suit structural No 1,106.70 1,106.70 1,106.70 1,106.70
opening of 1040 x 2220mm high

J 1 hour rated double leaf door; to suit structural No 1,661.70 1,661.70 1,661.70 1,661.70
opening of 1640 x 2220mm high

Page 23/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
K 2 hour rated single leaf door; to suit structural No 1,435.00 1,435.00 1,435.00 1,435.00
opening of 1040 x 2220mm high

L 2 hour rated double leaf door; to suit structural No 2,093.30 2,093.30 2,093.30 2,093.30
opening of 1640 x 2220mm high

INTERNAL WALLS

8 PARTITIONS

Drywall partition covered both sides with boards


complete with metal studs support, jointing and
finishing to give a flush seamless surface ready for
decoration
A 75mm thick walls with gypsum plasterboard on both m2 62.80 62.80 62.80 62.80
sides
B 75mm thick walls with fibrous plasterboard on both m2 71.70 71.70 71.70 71.70
sides
C 75mm thick walls with calcium silicate board on both m2 80.00 80.00 80.00 80.00
sides

One hour fire-rated drywall partition covered both


sides with boards complete with insulation, metal
studs support, jointing and finishing to give a flush
seamless surface ready for decoration

D 100mm thick walls with gypsum plasterboard on m2 82.00 82.00 82.00 82.00
both sides
E 100mm thick walls with fibrous plasterboard on both m2 91.30 91.30 91.30 91.30
sides
F 100mm thick walls with calcium silicate board on m2 99.70 99.70 99.70 99.70
both sides

8 PARTITIONS (CONT'D)

Acoustic drywall partition; achieving STC 48 rating,


covered both sides with boards complete with
insulation, metal studs support, jointing and finishing
to give a flush seamless surface ready for
decoration
G 100mm thick walls with gypsum plasterboard on m2 97.30 97.30 97.30 97.30
both sides
H 100mm thick walls with fibrous plasterboard on both m2 107.30 107.30 107.30 107.30
sides
I 100mm thick walls with calcium silicate board on m2 115.70 115.70 115.70 115.70
both sides

VIII IRONMONGERY

Page 24/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

1 Window Ironmongery

Supply and install window ironmongery including all


cutting, fitting, sinking, boring, morticing and the like
complete with matching screws as spcecified
hinges No
straps No
fasteners No
pulls No
openers No

2 Door Ironmongery

Supply and install door ironmongery including all


cutting, fitting, sinking, boring, morticing and the like
complete with matching screws as spcecified
hinges No
floor springs No
sliding No
folding No
overhead door gears No
locks No
latches No
catches No
bolt No
closers No
pad-locks No
push bars and plate No
pull bars and handles No
kickplates No

3 Sundry Ironmongery

Supply and install sundry ironmongery including all


cutting, fitting, sinking, boring, morticing and the like
complete with matching screws as spcecified
door stops No
shelf brackets No
coat hooks No
paper holders No
soap holders No
toothbrush No
glass racks No
shower curtain rails No
curtain rails No
towel rails No
handrails No
brackets No

Page 25/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
IX STRUCTURAL STEELWORK
1 Structural Steel

1.1 Mild Steel Members

Bolted and welded structural steel conforming to


EN10025 Grade S275 to building
A universal columns kg 5.10 5.10 5.00 5.00
B universal beams kg 5.10 5.10 5.00 5.00
C square or rectangular hollow sections kg 5.10 5.10 5.00 5.00
D circular hollow sections kg 5.10 5.10 5.00 5.00
E connection plates kg 5.10 5.10 5.00 5.00
F composite beam kg 5.10 5.10 5.00 5.00

1.2 Off-Site Surface Treatment

Surface treatment to structural steel members in


factory
A hot dip galvanising kg 1.10 1.10 1.10 1.10
B one coat of primer kg 0.50 0.50 0.50 0.50

1.3 Surface Treatment After Erection

Preparing and applying on structural steel surfaces


A one coat of red lead primer m2 2.60 2.60 2.60 2.60
B one coat of zinc chromate primer m2 2.70 2.70 2.70 2.70

X METAL WORK
1 ALUMINIUM WINDOWS AND DOORS

1.1 Aluminium Window Frames

Anodised aluminium section frames in single light,


complete with ironmongery, fixing straps, vinyl
weather strips including building-in and pointing
frame (glass measured separately)
A side-hunged window and casement frames m2 262.50 257.50 257.50 257.50
B top-hung window frame and sash m2 256.20 250.00 250.00 250.00
C sliding window frame and sash m2 237.80 231.60 231.60 231.60
D fixed panel window frame m2 219.90 214.90 214.90 214.90
E fixed louvred window frame including clips m2 323.30 323.30 323.30 323.30
F adjustable louvred window frame including clips m2 373.30 373.30 373.30 373.30

Page 26/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

1.1 Aluminium Window Frames

Powder coated aluminium section frames in single


light, complete with ironmongery, fixing straps, vinyl
weather strips including building-in and pointing
frame (glass measured separately)

G side-hunged window and casement frames m2 261.30 261.30 261.30 261.30


H top-hung window frame and sash m2 258.00 258.00 258.00 258.00
I sliding window frame and sash m2 243.00 243.00 243.00 243.00
J fixed panel window frame m2 213.00 213.00 213.00 213.00
K fixed louvred window frame including clips m2 330.00 330.00 330.00 330.00
L adjustable louvred window frame including clips m2 380.00 380.00 380.00 380.00

Flurocarbon coating aluminium section frames in


single light, complete with ironmongery, fixing
straps, vinyl weather strips including building-in and
pointing frame (glass measured separately)
M side-hunged window and casement frames m2 306.40 306.40 306.40 306.40
N top-hung window frame and sash m2 307.10 307.10 307.10 307.10
O sliding window frame and sash m2 290.00 290.00 290.00 290.00
P fixed panel window frame m2 258.70 258.70 258.70 258.70
Q fixed louvred window frame including clips m2 343.30 343.30 343.30 343.30
R adjustable louvred window frame including clips m2 410.00 410.00 410.00 410.00

1.2 Aluminium Louvre Window

Louvred blades with both ends fixed to metal clips,


in single light; complete with fixing accessories
A in anodised aluminium finish m2 330.00 330.00 330.00 330.00
B in aluminium flurocarbon finish m2 363.30 363.30 363.30 363.30

1.3 Aluminium Door Frames

Anodised aluminium section frames in single light,


complete with ironmongery, fixing straps, vinyl
weather strips including building-in and pointing
frame; with height not exceeding 3m high (glass
measured separately)

A side-hunged door and casement frames m2 280.00 280.00 280.00 280.00


B sliding door frame and sash m2 296.70 296.70 296.70 296.70
C fixed panel door frame m2 238.30 238.30 238.30 238.30

Powder coated aluminium section frames in single


light, complete with ironmongery, fixing straps, vinyl
weather strips including building-in and pointing
frame; with height not exceeding 3m high (glass
measured separately)
D side-hunged door and casement frames m2 283.30 283.30 283.30 283.30
E sliding door frame and sash m2 290.00 290.00 290.00 290.00
F fixed panel door frame m2 249.20 249.20 249.20 249.20

Page 27/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

2 Metal Cladding

2.1 Aluminium

Aluminium cladding panels complete with all


necessary fixing accessories
A 2mm thick panel in flurocarbon coated finish; m2 295.00 295.00 295.00 295.00
B generally
2mm thick panel in powder coated finish; generally m2 270.00 270.00 270.00 270.00

Perforated aluminium cladding panels complete with


all necessary fixing accessories
C 2mm thick panel in flurocarbon coated finish; m2 316.70 316.70 316.70 316.70
D generally
2mm thick panel in powder coated finish; generally m2 290.00 290.00 290.00 290.00

2.2 Stainless Steel

Stainless steel grade 316 cladding panels complete


with all necessary fixing accessories
A 2mm thick panel in mirror finish; generally m2 375.00 375.00 375.00 375.00
B 2mm thick panel in hairline finish; generally m2 375.00 375.00 375.00 375.00
C 2mm thick panel in 2B finish; generally m2 395.00 395.00 395.00 395.00

3 Metal Doors

3.1 Blast Door

Air tight blast door consist of door leaf, frame,


ironmongery, stainless steel ventilation sleeves
including fragmentation plate; coated with 1 coat of
cathodic electro deposition (CED) primer complete
with all fixing accessories and commissioning

A single leaf; size: 900 x 1900mm high no 1,133.30 1,133.30 1,133.30 1,133.30
B single leaf; size: 1000 x 2055mm high no 1,300.00 1,300.00 1,300.00 1,300.00

3.2 Refuse Hoppers and Refuse Chute Doors

1/2 hr fire rated air tight self-closing single leaf


refuse hopper complete with ironmongery, PSB
label and fixing accessories
A size: 450 x 350mm in aluminium finish no 276.70 276.70 276.70 276.70
B size: 450 x 350mm in stainless steel finish no 318.30 318.30 318.30 318.30

3.3 Roller Shutter

Manually operated roller shutter, in non-corrosive


aluminium finish; complete with ironmongery, PSB
label and fixing accessories
A non fire-rated; generally m2 300.00 300.00 300.00 300.00
B 1/2 hour fire-rated; generally m2 450.00 450.00 450.00 450.00

Page 28/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

3.3 Roller Shutter (Cont'd)

Electric motorised operated roller shutter, in non-


corrosive aluminium finish; complete with operating
gear, casing, ironmongery, PSB label and fixing
accessories
C non fire-rated; generally m2 510.00 510.00 510.00 510.00
D 1/2 hour fire-rated; generally m2 610.00 610.00 610.00 610.00

3.4 Fire-rated Metal Door

Single leaf metal flush door consisting of door leaf


and frames with primer finish, ironmongery and
fixing accessories to F.S.B. requirements and PSB
A labelling
1/2 hour fire-rated; generally m2 573.30 573.30 573.30 573.30
B 1 hour fire-rated; generally m2 660.00 660.00 660.00 660.00
C 2 hour fire-rated; generally m2 763.30 763.30 763.30 763.30

3.5 Non Fire-rated Metal Door

Metal flush door consisting of door leaf and frames,


complete with ironmongery and fixing accessories
A single leaf mild steel door with primer finish m2 546.70 546.70 546.70 546.70
B double leaves mild steel door with primer finish m2 530.00 530.00 530.00 530.00
C single leaf powder coated aluminium door m2 553.30 553.30 553.30 553.30
D double leaves powder coated aluminium door m2 583.30 583.30 583.30 583.30

4 RAILINGS

4.1 Stainless Steel

1100mm high x 12.76mm thick clear tempered


laminated glass railing complete with top railing;
glass framed in 'c' channel all round and fixed to
vertical support anchor embeded in concrete; the
whole constructed using stainless steel (grade 304)
flat bar in hairline finish

A horizontal balustrades m 830.00 830.00 830.00 830.00


B raking balustrades m 870.00 870.00 870.00 870.00

1000mm high stainless steel (grade 304) railing in


hairline finish constructed of top railing fixed on
vertical support anchor to concrete kerb (measured
separately); infill with vertical baluster welded to
horizontal rail at top and bottom; the whole
constructed using flat bar

C horizontal balustrades m 373.30 373.30 373.30 373.30


D raking balustrades m 396.70 396.70 396.70 396.70

Page 29/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

Stainless steel (grade 304) wall mounted tubular


railing in hairline finish welded to 'L' shape steel
bracket bolted onto wall
E horizontal balustrades m 108.30 108.30 108.30 108.30
F raking balustrades m 111.70 111.70 111.70 111.70

4.2 Mild Steel

1000mm high hot dipped galvanised mild steel


railing constructed of handrail fixed on vertical
support anchor to concrete kerb (measured
separately); infill with vertical balusters welded to
horizontal rail at top and bottom; the whole
constructed using flat bar
A horizontal balustrades m 150.00 150.00 150.00 150.00
B raking balustrades m 156.70 156.70 156.70 156.70

Hot dipped galvanised mild steel wall mounted


tubular railing welded to 'L' shape steel bracket
bolted onto wall
C horizontal balustrades m 64.30 64.30 64.30 64.30
D raking balustrades m 71.30 71.30 71.30 71.30

5 PROPRIETORY DEMOUNTABLE PARTITIONS

5.1 Proprietory Toilet Cubicle

Toilet cubicles complete with door and partition


constructed of solid phenolic core face both sides
with laminated plastic complete with aluminium
framing and nylon fixing accessories and
ironmongery
A Floor mounted system cubicl 1,063.30 1,063.30 1,063.30 1,063.30
e
B Ceiling hung system cubicl 1,201.70 1,201.70 1,201.70 1,201.70
e

XI FLOOR FINISHES
1 IN-SITU FINISHES

1.1 Plain Paving

Cement and sand (1:3) paving trowelled smooth


A average 25mm thick; generally m2 17.80 17.80 17.80 17.80
B average 30mm thick; generally m2 19.00 19.00 19.00 19.00
C average 38mm thick; generally m2 20.60 20.60 20.60 20.60
D average 50mm thick; generally m2 24.80 24.80 24.80 24.80
E add or deduct each 10mm thickness m2 1.80 1.80 1.80 1.80

1.2 Waterproofed Paving

Cement and sand (1:3) paving trowelled smooth


including approved waterproofing additive

Page 30/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
A average 25mm thick; generally m2 20.80 20.80 20.80 20.80
B average 30mm thick; generally m2 21.70 21.70 21.70 21.70
C average 38mm thick; generally m2 22.70 22.70 22.70 22.70
D average 50mm thick; generally m2 27.50 27.50 27.50 27.50

1.3 Hardened Paving

Cement and sand (1:3) paving trowelled smooth;


including approved light duty metallic hardener
(0.25kg of hardener per kg of cement)
A average 25mm thick; generally m2 20.50 20.50 20.50 20.50
B average 50mm thick; generally m2 22.80 22.80 22.80 22.80

Cement and sand (1:3) paving trowelled smooth;


including approved heavy duty metallic hardener
(0.5kg of hardener per kg of cement)
C average 25mm thick; generally m2 24.00 24.00 24.00 24.00
D average 50mm thick; generally m2 27.20 27.20 27.20 27.20

1.4 Liquid applied floor hardener

Supply and apply 3 coats of liquid applied hardener


to concrete surface
A to floor; generally m2 34.70 34.70 34.70 34.70

1.5 Anti-skid Coating

Supply and apply epoxy coatings to concrete


A to floor; generally m2 18.10 18.10 18.10 18.10

1.6 Granolithic Paving

Granolithic paving in cement, sand and granite


chippings (2:1:5) mortar to concrete surface;
including scrubbing to produce exposed aggregate
finish
A average 25mm thick; generally m2 38.50 38.50 38.50 38.50
B average 32mm thick; generally m2 39.80 39.80 39.80 39.80
C average 50mm thick; generally m2 47.70 47.70 47.70 47.70

1.7 Screed Bed

Cement and sand (1:3) screed to receive floor


finishes (measured separately)
A 13mm thick m2 13.00 13.00 13.00 13.00
B 20mm thick m2 14.70 14.70 14.70 14.70
C 25mm thick m2 15.70 15.70 15.70 15.70

Page 31/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
D 32mm thick m2 16.80 16.80 16.80 16.80
E 38mm thick m2 17.70 17.70 17.70 17.70
F 50mm thick m2 19.60 19.60 19.60 19.60
G add or deduct each 10mm thickness m2 1.70 1.70 1.70 1.70

2 CARPET FINISHES

2.1 Labour

Supply labour and compatible adhesive for laying


carpet; on smooth and levelled surface (measured
separately)

A carpet tile to floor; generally m2 8.40 8.40 8.40 8.40


B broadloom carpet to floor; generally m2 9.60 9.60 9.60 9.60
C Extra over for supply and install of foam rubber m2 2.80 2.80 2.80 2.80
underlay

3 VINYL FINISHES

3.1 Labour

Supply labour and compatible adhesive for laying


vinyl tiles; on smooth and levelled surface
(measured separately)
A to floor; generally m2 11.60 11.60 11.60 11.60

4 STONE FINISHES

4.1 Labour

Supply labour and compatible adhesive for laying


granite / marble slab including pointing with
coloured grout
A to floor; generally m2 66.50 66.50 66.50 66.50
B to skirting ne 150mm high, generally m 12.80 12.80 12.80 12.80
C to skirting 150-300mm high, generally m 17.30 17.30 17.30 17.30

5 TILE FINISHES

5.1 Labour

Supply labour and compatible adhesive for laying


ceramic / homogeneous / porecelain tiles including
pointing with coloured grout
A to floor; generally m2 34.70 34.70 34.70 34.70
B to skirting ne 150mm high, generally m 9.40 9.40 9.40 9.40
C to skirting 150-300mm high, generally m 12.40 12.40 12.40 12.40

Supply labour and compatible adhesive for laying


mosaic tiles including pointing with coloured grout
D to floor; generally m2 40.80 40.80 40.80 40.80
E to skirting ne 150mm high, generally m 11.00 11.00 11.00 11.00

Page 32/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
F to skirting 150-300mm high, generally m 15.80 15.80 15.80 15.80

6 BRICK / BLOCK PAVING

6.1 Interlocking Pavers

Supply and lay interlocking pavers complete with


matching colour pointing, interlocked together and
laid to patterns including levelling and compacting
sand bed
A 80mm thick brick paver to floor; generally m2 47.50 47.50 47.50 47.50
B 80mm thick concrete paver to floor; generally m2 56.80 56.80 56.80 56.80

7 GLASS BLOCKS

7.1 Glass Block Floors

Supply and lay standard glass blocks with


compactible adhesive including pointing with
coloured grout
A 95mm thick to floor; generally m2 344.30 344.30 344.30 344.30

8 RAISED FLOORING

8.1 Raised Floor System

Supply and install raised accessed floor system with


bare finish
A overall 150mm high m2 68.30 68.30 68.30 68.30
B overall 300mm high m2 90.00 90.00 90.00 90.00

9 SUNDRIES

9.1 Dividing Strip

Supply and fix 25mm high dividing strip to edge of


floor finish
A 2mm thick aluminium m 9.00 9.00 9.00 9.00
B 2mm thick stainless steel m 15.30 15.30 15.30 15.30

9.2 Tactile floor

Supply and install tactile tiles; on cement and sand


screed (measured separately)
A 300 x 300mm tactile tiles to floor; generally m2 114.10 114.10 114.10 114.10

XII WALL FINISHES


1 IN-SITU FINISHES

1.1 Smooth Finished Plaster

Page 33/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Plastering in cement and sand (1:4) mortar
plasticiser finished with a steel trowel to concrete or
brick surface
A 6mm thick; internal m2 12.30 12.30 12.30 12.30
B 13mm thick; internal m2 16.80 16.80 16.80 16.80
C 20mm thick; internal m2 20.60 20.60 20.60 20.60
D 20mm thick; external m2 21.80 21.80 21.80 21.80

1.2 Skim Coat Plaster

Skim coat plaster finished smooth to concrete


surfaces
A to wall/column, generally m2 10.20 10.20 10.20 10.20

1.3 Screed Backing

Cement and sand (1:3) screeded backing finished


with wood float to concrete or brick surface to
receive tiling (measured separately)
A 13mm thick; generally m2 15.60 15.60 15.60 15.60
B 20mm thick; generally m2 18.60 18.60 18.60 18.60

1.4 Aggregate Plaster

Granite aggregate plaster in cement and granite


chippings (1:2) mortar with plasticiser to concrete or
brick surface; including scrubbing to produce
exposed aggregate finish

A 20mm thick; generally m2 25.60 25.60 25.60 25.60


B 25mm thick; generally m2 26.70 26.70 26.70 26.70

2 TILE FINISHES

2.1 Labour

Supply labour and compatible adhesive for laying


ceramic / homogenous / porcelain tiles including
pointing with coloured grout
A to walls; generally m2 35.30 35.30 35.30 35.30

Supply labour and compatible adhesive for laying


mosaic tiles including pointing with coloured grout
B to walls; generally m2 40.60 40.60 40.60 40.60

3 STONE FINISHES

3.1 Labour

Page 34/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Supply labour and compatible adhesive for laying
granite / marble slabs including pointing with
coloured grout
A to walls; generally m2 71.00 70.50 70.50 70.50

Supply labour and compatible adhesive for laying


granite / marble slabs including mechanical fixing
and pointing with coloured grout

B to walls; generally m2 147.00 145.80 145.80 145.80

4 SHEET FINISHES

4.1 Labour

Supply labour and compatible adhesive for fixing


decorative fabric or vinyl paper including cutting
border strips, corners and motifs to profile
A to walls; generally m2 6.50 6.50 6.50 6.50

XIII CEILING FINISHES


1 IN-SITU FINISHES

1.1 Skim Coat Plaster

Skim coat plaster finished smooth to concrete


surfaces
A to ceiling, generally m2 9.10 9.10 9.10 9.10
B Extra over for every 1.5m high m2 1.60 1.60 1.60 1.60

2 SUSPENDED CEILINGS

2.1 Metal Framed Ceilings (Exposed Grid)

Ceiling board fixed to an appoved pattern on


exposed grid type suspended system and framing;
complete with concealed galvanised nails including
framing of board to all ends of grids along the
boundaries; not exceeding 3.5m high

A 600 x 600 x 15mm thick Mineral fibreboard, pre- m2 31.30 31.30 31.30 31.30
finished face pattern panels with a white paint finish
B 600 x 600 x 15mm thick Acoustical mineral m2 33.70 33.70 33.70 33.70
fibreboard, pre-finished face pattern panels with a
white paint finish
C 600 x 600 x 20mm thick Acoustical mineral m2 35.30 35.30 35.30 35.30
fibreboard, pre-finished face pattern panels with a
white paint finish
D 600 x 600 x 9mm thick calcium silicate board m2 35.50 35.50 35.50 35.50
E 600 x 600 x 13mm thick calcium silicate board m2 39.20 39.20 39.20 39.20
F 600 x 600 x 9mm thick cement board m2 35.20 35.20 35.20 35.20
G 600 x 600 x 12mm thick cement board m2 41.20 41.20 41.20 41.20
H 600 x 600 x 9mm thick fibrous gypsum board m2 32.20 32.20 32.20 32.20

Page 35/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
I 600 x 600 x 13mm thick fibrous gypsum board m2 34.80 34.80 34.80 34.80
J Extra over for every 1.5m high m2 2.00 2.00 2.00 2.00

2.2 Metal Framed Ceilings (Concealed Grid)

Ceiling board fixed to an approved pattern on


concealed type suspended system and framing;
jointing and finishing to give a flush seamless
surface ready to receive decoration; not exceeding
3.5m high
A 15mm thick acoustic fibreboard m2 39.00 39.00 39.00 39.00
B 20mm thick acoustic fibreboard m2 44.00 44.00 44.00 44.00
C 9mm thick fibrous gypsum board m2 30.70 30.70 30.70 30.70
D 12mm thick fibrous gypsum board m2 36.30 36.30 36.30 36.30
E 9mm thick moisture resistance fibrous gypsum m2 33.50 33.50 33.50 33.50
F board thick moisture resistance fibrous gypsum
12mm m2 35.70 35.70 35.70 35.70
G board
9mm thick calcium silicate board m2 36.80 36.80 36.80 36.80
H 13mm thick calcium silicate board m2 40.30 40.30 40.30 40.30
I 9mm thick cement building board m2 39.70 39.70 39.70 39.70
J Extra over for every 1.5m high m2 2.00 2.00 2.00 2.00

2.3 Metal Ceilings

Metal panel ceiling fixed to an approved pattern;


including metal sheet laid in proprietary system and
concealed supports; not exceeding 3.5m high
A Aluminium strip ceiling of ribs with baked enamel m2 80.00 80.00 80.00 80.00
finish fixed to suspended carrier rails 0.60mm thick x
100mm wide module
B Steel strip ceiling of ribs with baked enamel finish m2 65.50 65.50 65.50 65.50
fixed to suspended carrier rails 84mm wide module
C Aluminium perforated ceiling system fixed to m2 109.50 109.50 109.50 109.50
perforated clip-in system'
D Aluminium open cell ceiling system comprising U m2 100.50 100.50 100.50 100.50
shaped blades 9mm wide x 40mm thick and
suspension system, blade at 100mm
E Aluminium plank ceiling system fixed to perforated m2 95.00 95.00 95.00 95.00
clip-in system
F Extra over for every 1.5m high m2 2.50 2.50 2.50 2.50

XIV PLUMBING
The work in each different type of installation shall
be given separately under following or similarly
appproriate sub-heading
(i) Sanitary installation
(ii) Trade waste, acid or similar special installation
(iii) Cold water installation
(iv) Fire service installation
(v) Hot water installation
(vi) Gas installation

Page 36/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
(vii) Compressed air installation

XV GLAZING
1 STANDARD GLASS

1.1 In Panes

Obscured glass fixed to metal frame (m/s)


A 5mm thick m2 57.10 56.30 56.30 56.30
B 6mm thick m2 62.00 61.50 61.50 61.50

Clear float glass fixed to metal frame (m/s)


C 6mm thick m2 59.10 57.80 57.80 57.80
D 8mm thick m2 64.90 63.60 63.60 63.60
E 10mm thick m2 98.70 96.10 96.10 96.10
F 12mm thick m2 125.50 125.50 125.50 125.50

Tinted float glass fixed to metal frame (m/s)


G 5mm thick m2 38.00 37.30 37.30 37.30
H 6mm thick m2 51.60 50.60 50.60 50.60
I 8mm thick m2 72.10 70.60 70.60 70.60
J 10mm thick m2 136.70 134.00 134.00 134.00
K 12mm thick m2 158.60 155.30 155.30 155.30

Clear laminated tempered glass in metal frame (m/s)


L 12.76mm thick (6mm tempered + 0.76mm PVB + m2 175.00 175.00 175.00 175.00
6mm float)
M 17.9mm thick (8mm tempered + 1.9mm PVB + m2 235.00 235.00 235.00 235.00
8mm float)

Low emittance (Low-E) clear float glass to metal


frame (m/s)
N 6mm thick m2 90.70 90.70 90.70 90.70
O 8mm thick m2 110.70 110.70 110.70 110.70

Low emittance (Low-E) clear tempered glass to


metal frame (m/s)
P 6mm thick m2 105.80 105.80 105.80 105.80
Q 8mm thick m2 126.70 126.70 126.70 126.70

Clear tempered glass fixed onto metal frame (m/s)


R 12mm thick m2 205.30 205.30 205.30 205.30

Tinted wired glass fixed onto metal frame (m/s)


S 6mm thick m2 146.00 146.00 146.00 146.00

Page 37/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

1.2 In Louvres

Obscured glass with ends fixed to metal clips


A 100mm wide x 600mm long x 6mm thick No 3.10 3.10 3.10 3.10
B 150mm wide x 600mm long x 6mm thick No 4.20 4.20 4.20 4.20

Clear float glass with ends fixed to metal clips


C 100mm wide x 600mm long x 6mm thick No 3.10 3.10 3.10 3.10
D 150mm wide x 600mm long x 6mm thick No 3.70 3.70 3.70 3.70

Tinted float glass with ends fixed to metal clips


E 100mm wide x 600mm long x 6mm thick No 3.10 3.10 3.10 3.10
F 150mm wide x 600mm long x 6mm thick No 3.80 3.80 3.80 3.80

Tinted wired glass with ends fixed to metal clips


G 100mm wide x 600mm long x 6mm thick No 9.20 9.20 9.20 9.20
H 150mm wide x 600mm long x 6mm thick No 13.50 13.50 13.50 13.50

1.3 In Panels/Doors

Clear float toughened glass fixed to metal frame


A 6mm thick m2 95.30 95.30 95.30 95.30
B 8mm thick m2 117.20 117.20 117.20 117.20
C 10mm thick m2 142.60 142.60 142.60 142.60

Tinted float toughened glass fixed to metal frame


D 6mm thick m2 96.30 96.30 96.30 96.30
E 8mm thick m2 125.10 125.10 125.10 125.10
F 10mm thick m2 161.30 161.30 161.30 161.30

Low emittance (Low-E) clear float glass fixed to


metal frame (m/s)
G 6mm thick m2 91.70 91.70 91.70 91.70
H 8mm thick m2 111.30 111.30 111.30 111.30
I 10mm thick m2 136.30 136.30 136.30 136.30

2 SPECIAL GLASS

2.1 Mirrors

Frameless mirror glass with copper backing in


polished pencil edge; concealed fixing, plugging and
screwing to walls
A 6mm thick clear mirror m2 206.50 206.50 206.50 206.50
B 6mm thick tinted mirror m2 211.60 211.60 211.60 211.60

Beveling to straight edges including internal mitres


and scallops
C 8mm wide m 58.80 58.80 58.80 58.80
D 10mm wide m 65.50 65.50 65.50 65.50

Page 38/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
E 12mm wide m 73.10 73.10 73.10 73.10

2.1 Mirrors (Cont'd)

Aluminium framed mirror glass with copper backing;


concealed fixing, plugging and screwing to walls
F 6mm thick clear mirror m2 243.00 243.00 243.00 243.00
G 6mm thick tinted mirror m2 248.50 248.50 248.50 248.50

3 SHOWER SCREEN

Framed shower screen with clear tempered glass;


comprising one fixed panel and one swing door
complete with polished stainless steel L-shaped
handle, ironmongeries and all necessary fixing
accessories
A 8mm thick glazing m2 363.30 363.30 363.30 363.30
B 10mm thick glazing m2 385.00 385.00 385.00 385.00

Frameless clear tempered glass shower screen;


comprising one fixed panel and one swing door
complete with polished stainless steel L-shaped
handle, ironmongeries and all necessary fixing
accessories
C 10mm thick glazing m2 333.30 333.30 333.30 333.30
D 12mm thick glazing m2 383.30 383.30 383.30 383.30

XVI PAINTING
1 INTERNAL PAINTING

1.1 General Surfaces

Preparing, sealing, applying paint on plastered or


concrete surfaces
A one sealer coat and two finishing coats of acrylic m2 3.90 3.90 3.90 3.90
emulsion paint
B one sealer coat and two finishing coats of acrylic m2 4.20 4.20 4.20 4.20
elastomeric paint
C one sealer coat, one undercoat and two finishing m2 4.40 4.40 4.40 4.40
coats of acrylic emulsion paint
D one sealer coat, one undercoat and two finishing m2 5.20 5.20 5.20 5.20
coats of acrylic elastomeric paint
E one sealer coat, one texture coat and two finishing m2 9.00 9.00 9.00 9.00
coats of emulsion paint
F one sealer coat, one texture coat and two finishing m2 12.70 12.70 12.70 12.70
coats of acrylic elastomeric paint

1.2 Timber Surfaces

Page 39/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
Preparing, priming, applying paint on timber
A two coats of aluminium wood primer m2 7.30 7.30 7.30 7.30
B two coats of wood preservative painting m2 3.50 3.50 3.50 3.50
C two coats of stain and two coats of wax polish m2 7.50 7.50 7.50 7.50
D two coats of clear varnish m2 10.70 10.70 10.70 10.70
E one coat of aluminium wood primer, one undercoat m2 10.80 10.80 10.80 10.80
and two finishing coats of synthetic enamel paint
F one coat of stain and three coats of clear m2 11.80 11.80 11.80 11.80
G polyurethane
two coats staining, varnishing three coats of m2 13.50 13.50 13.50 13.50
translucent finish on wood

1.3 Metal Surfaces

Preparing, priming, applying paint on metal surfaces


A two coats of aluminium paint m2 4.20 4.20 4.20 4.20
B one undercoat and two finishing coats of synthetic m2 9.80 9.80 9.80 9.80
enamel paint
C one coat of zinc chromate primer, one alkyd resin m2 11.80 11.80 11.80 11.80
undercoat and two finishing coats of synthetic
enamel paint

1.4 Weldmesh Surfaces

Preparing, priming, applying paint on metal surfaces


(measured flat on one side)
A two coats of aluminium paint m2 9.80 9.80 9.80 9.80
B one undercoat and two finishing coats of synthetic m2 14.50 14.50 14.50 14.50
enamel paint
C one coat of zinc chromate primer, one alkyd resin m2 16.20 16.20 16.20 16.20
undercoat and two finishing coats of synthetic
enamel paint

1.5 Large Metal Pipe Surfaces

Preparing, priming, applying paint on large metal


A two coats of aluminium primer, one undercoat and m 4.00 4.00 4.00 4.00
two finishing coats of synthetic enamel paint
B two coats of zinc chromate primer, one undercoat m 3.90 3.90 3.90 3.90
and two finishing coats of synthetic enamel paint

1.6 Small Metal Pipe Surfaces

Preparing, priming, applying paint on small metal


pipes
A two coats of aluminium primer, one undercoat and m 3.10 3.10 3.10 3.10
two finishing coats of synthetic enamel paint

B two coats of zinc chromate primer, one undercoat m 3.20 3.20 3.20 3.20
and two finishing coats of synthetic enamel paint

1.7 Large UPVC Pipe Surfaces

Preparing, priming, applying paint on large uPVC

Page 40/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN
A one coat of polyvinyl acetate primer, one undercoat m 3.20 3.20 3.20 3.20
and two finishing coats of synthetic enamel paint

1.8 Small UPVC Pipe Surfaces

Preparing, priming, applying paint on small uPVC


pipes
A one coat of polyvinyl acetate primer, one undercoat m 2.60 2.60 2.60 2.60
and two finishing coats of synthetic enamel paint

1.9 Fire Protection

Supply and spray vermiculite to general surfaces


A 13mm thick m2 23.20 23.20 23.20 23.20
B 25mm thick m2 30.90 30.90 30.90 30.90
C 50mm thick m2 43.00 43.00 43.00 43.00

2 EXTERNAL PAINTING

2.1 General Surfaces

Preparing, sealing, applying paint on plastered or


concrete surfaces
A one sealer coat and two finishing coats of m2 5.80 5.80 5.80 5.80
weathershield emulsion paint
B one sealer coat and two finishing coats of acrylic m2 6.00 6.00 6.00 6.00
elastomeric paint
C one sealer coat, one texture coat and two finishing m2 9.20 9.20 9.20 9.20
coats of weathershield emulsion paint
D one sealer coat, one texture coat and two finishing m2 11.20 11.20 11.20 11.20
coats of acrylic elastomeric paint
E three coats of water based high build acrylic resin m2 12.50 12.50 12.50 12.50
texture coat incorporating natural granite chip c/w
clear top coat

2 EXTERNAL PAINTING (CONT'D)

2.1 General Surfaces (Cont'd)

Preparing, sealing, applying paint on fairface


mansory surfaces
F two coats of water repellant solution m2 4.30 4.30 4.30 4.30

3 GENERAL

3.1 Labour

Supply labour to prepare and apply paint on


A concrete or plastered surface m2 1.40 1.40 1.40 1.40
B timber surface m2 1.40 1.40 1.40 1.40
C metal surface m2 1.40 1.40 1.40 1.40
D large pipe surface m 1.40 1.40 1.40 1.40
E small pipe surface m 1.40 1.40 1.40 1.40

Page 41/42
Shedule of Works
Last Updated on 01 February 2021
[The data will be updated on a quarterly basis]

ITEM DESCRIPTION UNIT 2021Q1 2021Q2 2021Q3 2021Q4


MEAN MEAN MEAN MEAN

Page 42/42

You might also like