General Formula
General Formula
General Formula
3 Concrete C- 20 Mechanical mix Cement = 320 kgs (6.4bags) Sand = 718 kgs (0.39 m3)
Mix ratio 1:2:4 Gravel = 1755 kgs (0.78m3) Water = 110 liters
5 Concrete C- 7 Hand mix Cement = 153 kgs (3.06bags) Sand = 704 kgs
Mix ratio 1:3.5:8 (0.38 m3)
Gravel = 1966 kgs (0.87 m3) Water = 92 liters
Calculating Material for Masonry
Basic Data
For one meter cube masonry work
- Sub Structure (foundation wall) =1m3 of stone/m3
- Super structure (semi-dressed) =1.25m3 of stone/m3
- Super structure (dressed) =1.5m3 of stone/m3
A. Stone Masonry
a) 50cm thick basaltic or equivalent foundation wall bedded in cement mortar 1:4
1. Stone = 1m3/m3
2. Mortar = 0.4 m3/m3
2.1 Cement = 150 kgs/m3
2.2 Sand = 0.42m3 /m3
b) 50cm thick roughly dressed super-structure stone wall bedded in cement mortar
1:4
1. Stone = 1.25 m3/m3
2. Mortar = 0.4m3/m3
2.1 Cement = 150 kgs/m3
2.2 Sand = 0.42m3/m3
c) 40cm thick dressed super structure stone wall bedded in cement mortar 1:4
1. Stone = 1.50m3/m3
2. Mortar = 0.40m3/m3
2.1 Cement = 150kgs/m3 2.2 Sand = 0.42m3/m3
B. Brick Masonry for Super-structure
a. ½ brick wall bedded in compo- mortar 1:2:9 both sides left for plastering
1. Brick with 5% wastage = 58 pcs/m2
2. Compo-mortar (10mm joints) = 0.0353m3/m2
15% wastage
2.1 Cement = 5kgs/m2
2.2 Lime = 14kgs/m2
2.3 Sand = 0.034m3/m2
b. One brick wall bedded in compo-mortar 1:2:9 both sides left for plastering.
1. Brick with 5% wastage = 115pcs/m2
2. Compo-mortar with 15% wastage =0.085m3/m2 (10mm joints)
2.1 Cement = 12.5kgs/m2
2.2 Lime =34kg/m2
2.3 Sand =0.081m3 /m2
C. Hollow Block Masonry for Super-Structure
a) 10cm thick hollow concrete block wall bedded in cement mortar 1:4
1. Hollow block with 5% wastage = 13 pcs/m2
2. Mortar 10mm joints 20% wastage = 0.0135m3/m2
2.2 Cement = 5 kgs/m2
2.2 Sand = 0.014m3/m2
b) 15cm thick hollow concrete block wall bedded in cement mortar 1:4. 1.Hollow block with 5% wastage =1
2.Mortar 10mm joints 20% wastage = 0.020m3/m2
2.1 Cement =7.5kgs/m2
2.2 Sand = 0.022m3/m2
c) 20cm thick Hollow concrete block wall bedded in cement mortar 1:4
1. Hollow block with 5% wastage = 13pcs/m2
2. Mortar 10mm joints 20% wastage = 0.027m3/m2
2.1 Cement =10kgs/m2
2.1 Sand = 0.028m3/m2
III. Mortar
Assuming 25% Shrinkage
5% Wastage
a) Cement Mortar
Item Type of Work Material required to produce 1m3
mortar
1 Cement Mortar 1:3 Cement = 460kgs
Sand = 0.99m3
2 Cement Mortar 1:4 Cement = 308kgs
Sand = 1.05m3
3 Cement Mortar 1:5 Cement = 306kgs
Sand = 1.10m3
4 Cement Mortar 1:6 Cement = 263kgs
Sand = 1.13m3
b) Compo-Mortar
Assuming 20% Shrinkage
5% Wastage
Item Type of Work Material Required to produce 1m3
Compo-Mortar
1 Compo-mortar1:1:6 Cement = 221 kgs
Lime = 300 kgs
Sand = 0.95m3
2 Compo-mortar 1:2:9 Cement = 147 kgs
Lime = 399 kgs
Sand = 0.95m3
3 Compo-mortar ½: 1:3 Cement = 195 kgs
Lime = 528 kgs
Sand = 0.89m3
Light Weight Screed
Assuming - 25% Shrinkage
5% Wastage
Item Type of Work Material required to produce 1m3
mortar
1 Cement Pumice 1:6 Cement = 263 kgs
Pumice = 1.13m3
2 Cement Pumice 1:8 Cement = 205 kgs
Pumice = 1.17m3
IV. Roofing
A. Roofing out of corrugated Iron sheet Nailed on wooden truss
a) Roof covering up to 150 Slope
1. Roofing Sheet =1.38m2/corrugated Iron Sheet
2. Washer = 10pcs/Iron Sheet
3. Dome Headed nail = 10pcs/Iron Sheet
b) Roof ridge 33cm wide
1. Covering of 2m length = 5pcs/9ml
2. Dome headed nail = 0.05 kgs/ml
c) Valley covers
1. Covering of 2m length = 5 pcs/9ml
2. Nails 6cm = 0.006kgs/ml
d) Gutter
1. Gutter with 2% wastage = 1.02mts/ml
2. Lead
3. Acid
4. Screws (fixers) = 3pcs/ml
5. Metal Brackets = 3pcs/ml
e) Down pipe
1. Down pipe = 9pcs/10ml
2. Metal Brackets = 2pcs/ml
3.Nut & Belt for metal brakes
(fixers) = 4pcs/ml
f) Fascia board
1. Fascia board with 10% wastage = 1.10mt/ml
2. Nails = 0.007kgs/ml
B) Roofing out of corrugated Asbestos on wooden Truss
a) Roof Covering for up to 200 slope
1. Roof covering = 2.25m/Asbestos Sheet
2. “J” hooks = 12pcs/Asbestos Sheet
3. Washer = 12pcs/ Asbestos Sheet
b) Roof ridge up to 200 slope
1. Covering = 2.25m2/ Asbestos Sheet
2. “J” hooks = 12pcs/ Asbestos Sheet
3. Washer = 12pcs/ Asbestos Sheet
c) Gutter
1. Gutter
2. “J” hooks
3. Washer
C) Roofing out of EGA Sheet on Steel truss
a) Roof Covering
“J” hooks
b) Roof ridge
1. Covering
2. “J” hooks
c) Valley Covers
1. Covering
2. “J” hooks
d) Gutter with 2% wastage
1. Gutter = 1.02pcs/ml
2. Metal Brackets = 2pcs/ml
3. Fixers = 4pcs/ml
e) Down pipe
1. Down pipe = 9pcs/10ml
2. Metal Brackets =2pcs/ml
3. Fixers =4pcs/ml
f) Roofing nails
1kg=105 pcs 1pkg 3kgs 315pcs
V. Carpentry & Joinery
a) Eucalyptus truss for span up to 10m
1. 10-12 cm Upper and Lower Eucalyptus
wood truss members with 50% wastage = 1.5mt/ml
2 Nails = 0.04kgs/ml
3 Band/Iron = 0.12kgs/ml
4 8-10 cm vertical & diagonal truss members
With 60% wastage = 1.6m/ml
5 Nails = 0.06kgs/ml
6 Band Iron = 0.17kgs/ml
b) Truss out of 5x10cm & 15cm wood up to 10m span
1 5x10cm Zigba wood upper member in truss
with 15% wastage = 1.15mt/ml
2 Nails = 0.03 kgs/ml
3 Band Iron = 0.10kgs/ml
2 5x10cm Zigba wood diagonal & Vertical
member with 20% wastage = 1.20mt/ml
2 2x2.5x15cm zigba wood = 2.30mts/ml
Lower member with 15% wastage
4 Nails = 0.04kgs/ml
5 Band Iron = 0.20kgs/ml
c) Truss out of 2.5 x 15cm zigba wood
1 2(2.5 x 15cm) Zigba wood upper & lower
member with 15% wastage = 2.30mts/ml
2 Nails = 0.03kgs/ml
3 Band Iron = 0.10kgs/ml
2 2 x 2.5 x 15cm diagonal & vertical
member with 20% wastage = 2.40mts/ml
3 Nails = 0.04kgs/ml
5 Band Iron = 0.20kgs/ml
d) Purlin
1. 06 – 8cm eucalyptus wood purl in with
40% wastage =1.40mts/ml
2 Nails = 0.025 kgs/ml
2 5 x 7 zigba wood purl in with 20%
wastage = 1.20mts/ml
3 Nails = 0.15kgs/ml
e) Fascia Board
1. Zigba or Tid wood with 15%
Wastage = 1.15mts/ml
2. Nails = 0.10kgs/ml
f) Door & window frame
1. Wood with 15% wastage = 1.15mts/ml
2. Nails = 0.05kgs/ml
g) Cheap wood ceiling nailed on 4 x 5 zigba
wood battens placed at c/c 41 cm.
1 4 x 5 cm zigba wood battens with
15% wastage = 4.6mts/m2
3 Nails = 0.08kgs/m2
c) Hollow block wall pointed with cement mortar 1:3 with 10%
Wastage per 10 square meters.
1. Mortar = 0.02m3/10m2 = 0.002m3/m2
1.1 Cement = 9.19kgs = 0.919 kg
1.2 Sand = 0.02m3 = 0.002 m3
d) Brick wall
1 Mortar = 0.03m3/10m2 = 0.003m3/m2
1.1 Cement = 11.04kgs = 1.104 kgs
1.2 Sand = 0.03m3 = 0.003m3
e) Stone wall pointed with cement mortar 1:4 with 12% wastage
Per 10 square meters.
1. Mortar = 0.06m3/10m2 = 0.006m3/m2
1.1 Cement = 22.08kgs = 2.208 kgs
1.2 Sand = 0.06m3 = 0.006m3
f) Hollow block wall pointed with mortar 1:4 with 10% wastage
Per 10 square meters.
1 Mortar = 0.02m3/10m2 = 0.002m3/m2
1.1 Cement = 7.36kgs = 0.736 kg
1.2 Sand = 0.02m3 = 0.002m2
VII. Plastering
a) Cement Mortar plaster on walls per 10 square meters.
Proportion 12mm thick with 15mm thick 15% 20mm thick 12% 25mm thick 10%
of cement 20% wastage wastage mortar = wastage Mortar= wastage
mortar Mortar= 0.144m3 0.172m3 0.22m3 mortar=0.25m3
Cement Sand (m3) Cement Sand Cement Sand Cement Sand
(kgs) (kgs) (m3) (kgs) (m3) (kgs) (m3)
1:3 66.15 0.14 79.10 0.17 102.90 0.22 114.84 0.25
X.A. Flooring
= 1pcs/500m2
3 Brusher for plastic paint
40 x 140mm
4. Sand paper = 0.01m2/m2
5. Gypsum = 0.03kg/m2
b. 3 coats of plastic emulsion paint to internal newly plastered surface.
1. Priming coat to fill the process of the surface to prepare smooth base for 1st
paint coat.
1.1 Stucco =50.0 grams/m2
1.2 Animal or vinavil glue =12.5grams/m2
2. 1st coat = 0.07 lit/m2
3. 2nd coat = 0.06 lit/m2
4. 3rd coat final coat = 0.05 lit/m2
5. Gypsum = 0.03 kgs/m2
6. Sand paper = 0.01 m2/m2
7. Brush 140 x 40mm = 1pcs/500m2
c) 2 coat of plastic emulsion paint to external newly plastered surface.
1 Priming coat = 62.5gram/m2
1.1 stucco = 0.50grams/m2
1.2 Animal or vinavil glue = 12.5grams/m2
2 1st coat = 0.08lit/m2
3 2nd coat = 0.07lit/m2
4 Sand paper = 0.01m2/m2
5 Brush 140 x 40mn = 1pcs/500m2
6 Cement mortar = 0.02kgs/m2
d) 3 coats of plastic emulsion paint to external newly plastered surface
1. Priming coat = 62.5 gram/m2
1.1 stucco = 50grams/m2
1.2 Animal or vinavil glue = 12.5 grams/m2
2. 1st coat = 0.08 lit/m2
3. 2md coat = 0.07 lit/m2
4. 3rd coat = 0.06 lit/m2
5. Sand paper = 0.01m2/m2
6. Brush 140 x 40 mm = 1pcs/500m2
7. Cement mortar = 0.02kgs/m2
e) 2 coats of plastic emulsion to external rendered surface.
1. 1st coat = 0.13lit/m2
2. 2nd coat = 0.11 lit/m2
3. Brush 140 x 40m = 1pcs/m2
f) 3 coats plastic emulsion paint to external rendered surface
1. 1st coat = 0.13 lit/m2
2. 2nd coat = 0.11 lit/m2
3. 3rd coat = 0.01lit/m2
4. Brush 140 x 40m = 1pcs/500m2
g) 2 coats of synthetic enamel paint to wooden surface.
1. 1st coat =0.06lit/m2
2. 2nd coat =0.05litm2
3. Solvent (thinner) for 1st and 2nd coat =0.5 lit/gall
4. Brush 4” or 5” =1pcs/200m2
5. Stucco =0.05kgs/m2
6. Sand paper =0.007m2/m2
h) 3 coats of synthetic enamel point to wooden surface.
1. 1st coat = 0.06lit/m2
2. 2nd coat = 0.05lit/m2
3. 3rd coat = 0.04lit/m2
4. Solvent (thinner) for 1st and 2nd coat = 0.5lit/gall
5. Brush = 1pcs /200m2
6. (Stucco) Knotting = 0.05kgs/m2
7. Sand paper =0.007m2/m2
i) 2 coats of varnish or lurker paint to wooden surface
1. 1st coat =0.06lit/m2
2. 2nd coat =0.05lit/m2
3. Brush =1pcs/200m2
4. Stucco (Knotting) = 0.05kgs/m2
5. Sand paper =0.007m2/m2
j) Cement paint to porous smooth surface
1. Cement paint =0.5lit/m2
2. Brush =1pcs/200m2
k) Cement paint to porous rough surface
1. Cement Paint =1.25lit/m2
2. Brush =1pcs/200m2
l) 3 coats of plastic emulsion paint to chip wood ceiling.
1. Priming coat = 62.5grams/m2
1.1 Stucco = 50.0grams/m2
1.2 Vinavil or animal glue = 12.5grams/m2
2. 1st coat plastic emulsion paint = 0.5lit/gall
3. Knotting
3.1 Stucco =0.05kgs/m2
3.2 Gypsum =0.04kgs/m2
4. 2nd coat =0.08lit/m2
5. 3rd coat = 0.07lit/m2
6. Sand paper = 0.007m2/m2
7. Brush 140 x 40mm = 1pcs/400m2
m) 3 coats of synthetic enamel paint to steel surface.
1. Priming coat (anti-rust) = 0.04lit/m2
Wastage = 0.42kgs/m2
2. Two coats of bitumen with 5% wastage =1.58kgs/m2
2. Conduits 13mm = ml
3. Conduits 14mm = ml
4. Conduits 19mm = ml
5. Conduits 20mm = ml
6. Conduits 23mm = ml
7. Conduits 25mm = ml
8. Conduits 29mm = ml
9. Conduits 35mm = ml
10. Conduits 42mm = ml
11. Conduits 50mm = ml
b) Electrical Junction Boxes
1. Switch boxes 0.65 mm = pcs
2. Junction boxes 0.85 mm = pcs
Junction boxes 100 x 100mm = pcs
Junction boxes 100 x 150mm = pcs
Junction boxes 100 x 300mm = pcs
3. Water proof junction boxes 70mm = pcs
c.) Wires & cables
c-1 Electrical Wires Rigid
1. Single rigid Wire 1 x 1mm2 = ml
2. Single rigid Wire 1 x 1.5mm2 = ml
3. Single rigid Wire 1 x 2mm2 = ml
4. Single rigid Wire 1 x 2.5mm2 = ml
5. Single rigid Wire 1 x 4mm2 = ml
6. Single rigid Wire 1 x 6.3mm2 = ml
7. Single rigid Wire 1 x 8mm2 = ml
c-2. Electrical Wires Flexible.
1. Single Flexible Wire 1 x 1mm2 = ml
2. Single Flexible Wire 1 x 1.5mm2 = ml
3. Single Flexible Wire 1 x 2mm2 = ml
4. Single Flexible Wire 1 x 2.5mm2 = ml
5. Single Flexible Wire 1 x 4mm2 = ml
6. Single Flexible Wire 1 x 8 mm2 = ml
7. Single Flexible Wire 1 x 10mm2 = ml
8. Single Flexible Wire 1 x 16mm2 = ml
9. Single Flexible Wire 1 x 25mm2 = ml
c-3. Flat Wire
1. Twin Wire 2 x 0.25mm2 = ml
2. Twin Wire 2 x 0.35mm2 = ml
3. Twin Wire 2 x 0.50mm2 = ml
4. Twin Wire 2 x 0.80mm2 = ml
5. Twin Wire 2 x 2.00mm2 = ml
6. Twin Wire 2 x 2.5mm2 = ml
c-4. Telephone Wire
1.Telephone Wire 2 x 0.50mm2 = ml
2. Telephone Wire 2 x 0.80mm2 = ml
3. Telephone Wire 2 x 1.00mm2 = ml
c-5. Round flexible rubber cables
1.Rubber 2 cores cable 2 x 0.50mm2 = ml
2. Rubber 2 cores cable 2 x 0.80mm2 = ml
3. Rubber 2 cores cable 2 x 1.00mm2 = ml
4. Rubber 2 cores cable 2 x 1.5mm2 = ml
5. Rubber 2 cores cable 2 x 2.0mm2 = ml
6. Rubber 2 cores cable 2 x 2.5mm2 = ml
7. Rubber 2 cores cable 2 x 6.0mm2 = ml
8. Rubber 2 cores cable 3 x 0.8mm2 = ml
9. Rubber 2 cores cable 3 x 1.0mm2 = ml
10. Rubber 2 cores cable 3 x 1.5mm2 = ml
11. Rubber 2 cores cable 3 x 2.00mm2 = ml
12. Rubber 2 cores cable 3 x 2.5mm2 = ml
13. Rubber 2 cores cable 3 x 4mm2 = ml
14. Rubber 2 cores cable 3 x 6.3mm2 = ml
15. Rubber 2 cores cable 4 x 1.5mm2 = ml
16. Rubber 2 cores cable 4 x 2.0mm2 = ml
17. Rubber 2 cores cable 4 x 2.5mm2 = ml
18. Rubber 2 cores cable 4 x 4.0mm2 = ml
19. Rubber 2 cores cable 4 x 6.3mm2 = ml c-6. Flat Rigid Cable
1. Rigid 2 cores cable 2 x 0.50mm2 = ml
2. Rigid 2 cores cable 2 x 0.80mm2 = ml
3. Rigid 2 cores cable 2 x 1.0mm2 = ml
4. Rigid 2 cores cable 2 x 1.60mm2 = ml
5. Rigid 2 cores cable 2x 2.0mm2 = ml
6. Rigid 2 cores cable 2 x 2.5mm2 = ml
7. Rigid 2 cores cable 2 x 4 mm2 = ml
8. Rigid 2 cores cable 2 x 6.3mm2 = ml
9. Rigid 2 cores cable 2 x 8mm2 = ml
10. Rigid 2 cores cable 2x 10mm2 = ml
c-7. Round Rigid Cable
1 Round Cable 3 cores 3 x 0.50mm2 = ml
2. Round Cable 3 cores 3 x 0.80mm2 = ml
3. Round Cable 3 cores 3 x 1.00mm2 = ml
4. Round Cable 3 cores 3 x 1.60mm2 = ml
5. Round Cable 3 cores 3 x 2.0mm2 = ml
6. Round Cable 3 cores 3 x 2.5mm2 = ml
7.Round Cable 3 cores 3 x 4mm2 = ml
8. Round Cable 3 cores 3 x 6.3mm2 = ml
9. Round Cable 3 cores 4 x 1.6mm2 = ml
10. Round Cable 3 cores 4 x 2.5mm2 = ml
11. Round Cable 3 cores 4 x 4mm2 = ml
12. Round Cable 3 cores 4 x 6mm2 = ml
d) Line terminal
1. Line terminal 05mm = pcs
2. Line terminal 06.5mm = pcs
3. Line terminal 08mm = pcs
4. Line terminal 09mm = pcs
e) Switch
e-1) Flush Mounted
1. Flush mounting normal switches = pcs
2. Flush mounting two way switches = pcs
3. Flush mounting double two way = pcs
4. Flush mounting two way + two way + tow switches = pcs
5. Flush mounting two way switches + boll push = pcs
e-2) Surface mounted
1. Surface mounted switches = pcs
2. Surface mounting two switches = pcs
3. Surface mounting double switches = pcs
e-3) Main Switch
1. Main Switch single pole = pcs
2. Main Switch double pole = pcs
3. Main Switch three pole = pcs
f) Sockets
f.1) Surface Mounting socket
1. Surface mounting socket 10A + ground
2. Surface mounting socket 2x15A + ground
3. Surface mounting socket 2x15A
f.2) Flush mounting socket
1. Flush mounting normal socket 10A = pcs
2. Flush mounting normal socket 10A + ground = pcs
3. Flush mounting normal socket 15A + ground = pcs
f.3) Heavy duty rubber socket
1. Heavy duty rubber socket 2 x 10A+G = pcs
2. Heavy duty rubber socket 2 x 15A+G = pcs
3. Heavy duty rubber socket 3x 15A+G = pcs
g) Bell Push
g-1) Surface mounted
1. Surface mounting bell push 10Amp = pcs
###
3.4 Hollow Block Masonry
Wall for plastering
4 Roofing Work
40m2 12min/m2
4.1 Leaf covering (G.C.I) 1C+2D.L 8hr
4.2 Ridge cover 1C+2D.L 8hr 70ml 7min/ml
4.3 Valley cover 1C+2D.L 8hr 70ml 7min/ml
4.4 Gutter fixing 1C+2D.L 8hr 30ml 16min/ml
Joining eucalyptus truss
upto 10m span on ground 1C+2D.L 8hr 4truss 2hr/truss
4.6 Down pipe fixing 1C+2D.L 8hr 40ml 12min/ml
4.7 Truss erecting 1C+2D.L 8hr 15tress 32min/tress
4.8 Fixing corrugated 1C+2D.L 8hr
asbestos 25m2 19min/m2
4.9 Fixing EGA sheet joining 1C+2D.L 8hr 30m2 16min/m2
4.10 Joining Zigba Truss up to
10m span on ground 1C+2D.L 8hr 3tress 2.66hr/tr
4.11 Zigba truss erecting 1C+8D.L 8hr 15tress 32min/tru
4.12 Fascia board fixing 1C+2D.L 8hr 70ml 7min/ml
5. Joinery - Work
5.1 Leaf covering (G.C.I) 1C+2D.L 8hr 3pcs 2.66hr/pos
5.2 Ridge cover 1C+2D.L 8hr 4pcs 2hr/pos
5.3 Valley cover 1C+2D.L 8hr 10m2 48min/m2
5.4 Gutter fixing 1C+2D.L 8hr 10m2 48min/m2
5.5 Joining eucalyptus truss 1C+2D.L 8hr
up to 10m span on ground 13m2 48min/m2
6. Metal Work
6.1 Metal door fixing 1W+2D.L 8hr 3pcs 2.66hr/pcs
6.2 Metal Window fixing 1W+2D.L 8hr 4pcs 2hr/pcs
6.3 French Window fixing 1W+2D.L 8hr 2pcs 4hr/pcs
7. Plastering & Pointing
7.1 1st cost plastering 1P+2D.L 8hr 35m2 14min/m2
7.2 2nd cost plastering 1P+2D.L 8hr 10m2 48min/m2
7.3 3rd cost plastering 1P+2D.L 8hr 14m2 34min/m2
7.4 Pointing on stone Wall
7.5 Pointing on brick wall 1P+2D.L 8hr 8m2 4hr/m2
7.6 Pointing on Hollow block 1P+2D.L 8hr 14m2 34min/m2
7.7 Pointing on dressed stone 1P+2D.L 8hr 12m2 40min/m2
7.8 Rendering 1P+2D.L 8hr 20m2 24min/m2
8. Flooring
8.1 Cement Screed 1M+2D.L 8hr 14m2 34min/m2
8.2 Cement tile fixing 1M+2D.L 8hr 10m2 48min/m2
8.3 Plastic tile fixing 1M+2D.L 8hr 17m2 48min/m2
8.4 Par - quet flooring 1M+2D.L 8hr 15m2 32min/m2
8.5 Wooden flooring 1C+2D.L 8hr 8m2 1hr/m2
8.6 Ceramic wall tile 1M+2D.L 8hr 7m2 1.14hrn/m2
8.7 Plastic tile skirting 1M+2D.L 8hr 40ml 12min/ml
8.8 Cement tile skirting 1M+2D.L 8hr 12ml 40min/m2
8.9 Marble slate flooring 1M+2D.L 8hr 12ml 40min/m2
8.10 Marble slate skirting 1M+2D.L 8hr 16ml 30min/m2
8.11 Fixing pre-cat window sill 1M+2D.L 8hr 10ml 48min/ml
8.12 Fixing un pre-cast window sill 1M+2D.L 8hr 6ml 1.33min/ml
9. Glazing
9.1 Cutting 1G+2D.L 8hr 8hr 50m2 10min/m2
9.2 Fixing 1G+2D.L 20m2 24min/m2
10. Painting
a) Plastic paint
b) Synthetic paint
10.6 Plastered wall surface in 1p + ID1 8hr
3 coats 25m2 19min/m2
Calculating Unit Prices (Analysis of Rates)
In ordinary type of building the cost of materials is about 60% & labor 40% of the total
cost of the whole building.
Materials: - Walling material 25% cement 13% steel 10% timber 12%
Labor: - Excavation 1% mason 25% carpenters 12% smith 2%
The cost of separate items of works may be roughly as follows as percentage of the total cost
of the building for a single storey building.
Excavation …………………………………………………… 1%
Concrete in Foundation ……………………………………… 2% Foundation wall up to plinth ………………………
Flooring……………………………………………………….. 6%
Joinery………………………………………………………… 15%
Internal Finishes……………………………………………….. 6%
External………………………………………………………… 3% Water Supply & Sanitary work……………………
100%
For the purpose of calculating unit prices the details about all the operations involved in
carrying out the work should be available, the quantities of materials required and their costs
should be known and the number of different categories of laborers required and the capacity doing work per laborer
The rates of particular item of work depend on the following:-
- Specifications of work and materials, quality of materials proportion of mortar method of
constructional operation.
- Quantities of materials and their rates, number of different types of laborer and their rates.
- Location of the site of work and its distance from the sources of materials and their rates.
- Profits overhead expenses & miscellaneous of contractor.
Material Cost – include
- The first cost (cost of origin)
- Cost of transport
- Taxes etc.
Labor Cost
Varies from place to place. In bigger cities where standard of living is high &
specialized and experienced labor is higher than small towns and country sides.
Transportation
In the country if transportation of material is to be done the rate is on highway (as
0.02049 cents/kg/km on rural road (0.04 cent/kg/km).
Profit - Contractors are allowed to get a net profit of 6 - 8%
Overhead cost & Miscellaneous
These include general office expenses, rents taxes, Supervision and other costs, which are indirect expenses and not p
The analysis of rates of different items of work is the summation of cost of material,
cost of labor, transportation, profit & overhead cost and miscellaneous.
PRODUCTION RATE FOR BUILDING CONSTRUCTION
Item Type of activity Unit CREW FORMATION
No Labor Equipment
1 5cm thick lean concrete (c- 7) m3 1 Forman 1 mixer
2 mason
45 D/L
2 Concrete C-15 m3 1 Forman 1Mixer
2 mason 1 Vibrator
45 D/L
3 C-25 concrete for footing m3 1 Forman 1 Mixer
2 mason 1 Vibrator
45 D/L
4 C-25 concrete for column m3 1 Forman 1 Mixer
2 mason 2 Vibrator
25 D/L
5 C-25 concrete for Grade Beam m3 1Forman 2 mason 1 Mixer
45 D/L 2 Vibrator
TRANSPORT COST
To transport cement from Addis Ababa - Kebridehar
Type of Vehicle - Truck (N3) with trailer Capacity of truck - 200 qts/trip
Average speed of truck - 40km/hr Total distance to cover - 1035 kms
Time taken to arrive - 1035 = 25.8 = 26 hr = 3.25 days 40
7 days round trip
Rental rate of truck with fuel and wage (Rental rate x day) hour/ day = (86 x 7) 8 = 4816 birr/trip
Fuel Expense = 1035 x 2 (it covers 1.5 km/liter)
1.5
= 1389 - Fuel cost/liter (1.46 Birr/liter)
= 1380 x 1.46
= 2014.80 birr
Driver wage.
a. Driver salary = 420 x 7 = 113 birr
26
= 20 birr x 7 = 140 birr
∑= 253 birr
b. Assistant salary = 180 x 7 = 63 birr
26
= 18 x 7 = 126 birr
∑= 189 birr
= 253 + 189 = 442 birr
Loading and unloading = (20 cents/qts)
= 2(200 x 0.20) = 80 birr/qts
Storage cost = (0.02 x 200) 10 days = 40 birr
Total transport cost = 4816 + 2014 .80 + 442 + 80 + 40 = 7392.80 /round trip
= 7392.80 birr = 36.96 birr 37 birr /qts/trip 200 qts
cost of cement = 41 birr/qt
Material + Transport cost
= 41 birr + 37 birr
= 78 birr/qts
ITEM TYPE OF WORKS QUANTITIE
1. Natural stone masonry for foundation 400mm thick hard basaltic stone masonry
foundation wall bedded in cement mortar 1:4 in full joints
a. Basaltic stone =0.53m3/m2
a. 25 m3/m3 x 0.40m x 1.05 waste
b. Mortar 0.34m3/m3 x 0.40 x 1.05 waste = 0.14m3/m2
c. Cement = 0.392 qts/m2
2. Ditto but one side roughly dressed and left for pointing
a. Basaltic stone :-
1.35m3/m3 x 0.40m x 1.05 waste = 0.56 m3/m2
b. Mortar
34m3/m3 x 0.40m x 1.05 waste = 0.14m3/m2
e. Sand = 0.02m3/m2
4. Ditto but 250mm thick
a. Brick = 115.4 pcs/m2
b. Mortar (with 15% waste) Cement = 0.062 m3/m2
c. Lime = 0.07 qts/m2
d. Sand = 0.11 qts/m2
e. = 0.05 m3/m2
5
Covering capacity of paint etc on various applied hand m2 covered by 1 lit
Special aluminum priming coat on planed timber 20
Lead Priming wat coat on planed timber 12
First a coat of all paint after priming 16
Second coat 18
Third coat 22
First coat of oil paint on previously painter timber 18
Second coat 20
Oil glass paint applied as a finishing coat 24
Under coat for enamel 20
Enamel on prepared surface – first coat 14
Enamel on prepared surface – second coat 18
Flat finish for varnish 22
Varnish on prepared surface – first coat 16
Varnish on prepared surface – second coat 20
Stain applied to planed timber 10
Stain applied to unwrought timber 10
Priming coat on brick or stucco 8
Priming coat 1 concrete, compo or stone 10
Priming coat on plaster 18
First coat oil paint after priming 12
Oil glass paint applied as a finishing coat 18
Priming coat on smooth iron 20
Priming coat 1 concrete, compo or stone 10
Priming coat on plaster 18
First coat oil paint after priming 12
Oil glass paint applied as a finishing coat 18
Priming coat on smooth iron 20
Priming coat on slightly rusted iron 14
Priming coat rust – pitted iron 10
First coat often priming 20
Second coat after priming 24
Description Paint required in KGS
m2
Area of ceiling = 192.54m2
192.54 x 1.05 = 65 pcs of 8mm chip wood 1.25 x 2.50
c. Beams:-
4cm Nails per chip wood =65 x 80pc = 9.52kg
546 pcs
- 6 cm nails = 50 pcs 1 ml
- 12 cm nails = 6 – 8 pcs ml (stiffening)
1 gallon of paint = 4 kilograms = 4 liters
7 meters band iron = 1 kilogram
1 gallon of plant covers = 15m2
EGA sheet max length 400cm x 80.6cm
- side cover lapping 1.5 3cm Front and rear
400 – 0.20 = 380 cm
806 – 0.3 = 776 ½ cm
3.8 x 0.776 - 2.95m2
EGA sheet + 9 400 x 8.6cm Cover an area 2.95m 2
###
200 – 20
1.80 x .776
EGA 500/0.6m width - 0.63m
Length 5m
ith 5% wastage = 13 pcs/m 2
viders placed at c/c 70cm.
m of its height covered with sheet metal & dividers placed at c/c 60cm.
x30 = 12pcs/m2
h ………………………………… 5% Walling (super structure)……………………………………… 25% Roofing……………
oing work per laborer and their wages per day should be known.
ect expenses and not productive expenses on the job. And this is about 5 - 10%
Hourly
Output
2.25m3
2.25m3
2.25m3
0.75m3
1.75m3
2.50m3
1.50m3
2.00m2
0.60m2
0.50m2
5% Roofing………………………………………………………… 20%