Ce 446
Ce 446
Ce 446
progress.
What is PERT?
PERT is a Program Evaluation and Review Technique. PERT/CPM Project Requirements
Presidential Decree 1594
What is CPM? “The program of work shall include, among other things, estimates of the work
CPM is the Critical Path Method. items, quantities, costs and a PERT/CPM network of the project activities… in the
preparation of the bidding documents, the government shall make and estimate
PERT and CPM? the actual number of working days required to complete the project through
These are networks developed independently in the latter part of the 1950s. PERT/CPM analysis of the project activities and corrected for holidays and
Techniques used for planning and coordinating large-scale projects. weekends.”
The use of PERT began in 1958 to speed up the Polaris Missile project.
PERT/CPM Project Requirements
Developers of CPM Memorandum Circular 153 (Ferdinand E. Marcos Jan 27, 1968)
J.E Kelly of the Remington Rand Corp.
M.R. Walker of Du Pont Gantt Chart (Bar Type)
PERT/CPM Network
PERT vs. CPM
PERT/CPM Project Requirements
Project Evaluation and <Meaning> Critical Path Method is a Section 6 of RA 5979
Review Technique is a Project Management - requires application of PERT/CPM technique to all projects with an estimated
technique used to plan and technique which plans and cost of P100,000 or more
control large scale projects. controls complex but routine
projects. With the use of PERT/CPM, the project manager can obtain:
Event-Oriented <Orientation> Activity-Oriented 1. The graphical display of project activities.
Probabilistic <Activities> Deterministic 2. An estimate of how long the project lasts.
Time <Focus> Time and Cost Trade off 3. Determine which activities are the most critical to timely project completion.
Three times estimates <Estimates> One time estimate
4. Determine how long any activity can be delayed without lengthening the
High precision time <Suitable for> Reasonable time estimate
project.
estimate
Non-repetitive activities <Nature of Repetitive Activities
Three Phases of PERT/CPM
Job>
Research and Development <Usage> Construction Projects Planning
Projects Scheduling
Control-monitor
PERT/CPM
Control tool for defining the parts of the construction job and putting them Planning
together in a network form. Planning is defined as determining the relationship between the work operation
Only serves the project manager to see the whole picture of the entire job. and the sequence in which they are to be performed.
The Critical Path Method (CPM) offers the solution through a systematic 7. By performing the work personally, one obtains intimate first-hand knowledge
approach. The specific information provided by the CPM is enumerated as of the job and gain insight and details of anticipated problems.
follows:
1. Pinpoints particular focal work operations...
2. Provides means of speeding up a project without excessive cost for overtime. Scheduling
3. Gives time leeway or float available for each of the non-critical work Scheduling is defined as the process of translating the arrow diagram into time
operations. table of calendar days. This is done by the day date table converting working
4. Establishes time boundaries for operations with possibilities of change… days into calendar days which permits the inclusion of weekends, holidays,
5. PERT/CPM indicates the earliest starting date for each work operation and weather, and other time lost.
sub-contracts for the supply and delivery of materials.
6. Shows the most advantageous scheduling for all operations. The PERT/CPM schedule shows the relationships between the operations and
7. Offers a means of assessing the effect on the overall project variations in one the leeway limitations.
operation such as change orders.
8. Offers a means of rescheduling the operations but still to be completed at the The PERT/CPM diagram should be updated periodically to account for:
least increase in cost. 1. Time discrepancies
9. With the critical path schedule as revised to reflect the change order, any 2. Deliveries
claim if any, for additional payment will be understood both by the owner and 3. Weather
the contractor. 4. Change Orders
10. In case of serious delay due to weather, late material, or equipment delivery, 5. Unexpected events or conditions
the network can be revised at that stage and new computation is made to Updating of the diagram is based on the number of days the project is out of
determine the new critical operation if any, and revised float times are schedule.
determined for the non-critical operations. Controlling and Monitoring
Flexibility and updated re-computations brought about by changing conditions
are the keys to successful network programming.
In any project construction undertakings, planning is the most important
consideration which includes: 1. The contractor is supplied with a time status report showing the overall status
1. Gather all the necessary input data to make the PERT/CPM work. of the project in general and in particular.
2. Planning phase is the main work of the contractor for being familiar and 2. The contractor is provided with revised schedules that reflect the actual work
knowledgeable of his costing methods of doing business. conditions and the project status.
3. The contractor can seek assistance for the accomplishment of his work 3. The contractor is supplied with cost status reports showing how much money
particularly the gathering of data, but his basic responsibility on this matter is being disbursed for what type of expenses.
cannot be delegated to any outsider group. 4. The contractor should be supplied with those reports as frequently as desired
4. The contractor has a complete perception, experiences, resources, and or required to maintain control over the project.
interest in getting the project done in the best possible time and cost.
5. The planning stages give the contractor a “Dry Run” on the construction of the In Planning Phase, there are five inputs that can be obtained:
project. 1. A network diagram defining the activities in the project.
6. If the contractor wants an effective approach and use of the construction 2. The duration of activities.
management, he must do it himself. 3. Cost estimates of the activities for monitoring cost, cash flow requirements.
4. Resource estimates THE NETWORK FUNDAMENTALS
5. Trade indicators (responsibility) for activity grouping.
Network Conventions Use of Network or Precedence Diagram
- main features of PERT/CPM
From the Schedule Phase, there are four outputs that can be obtained: - key in solving typical problems
1. The schedule of activities in the network shows the following: - clearly indicate which of the activities must be performed independently with
a. The Critical Activities each other
b. The Earliest Start date for each activity
c. The Earliest Finish date for each activity
d. The Latest Start date for each activity Network/Precedence Diagram
e. The Latest Finish date for each activity - composed of Arrows and Nodes
f. The Float refers to the amount of extra time available for an
activity
2. A Bar Chart or a Time Scaled Network Two Slightly Different Conventions for Making Network Diagram
3. A Resource Analysis
4. A Cash Requirement
PRINCIPLE No. 3
The network (arrow diagram) does not describe time relationships but rather
dependency relationships.
PRINCIPLE No. 4 Activities can either be:
That the network (arrow diagram) is hardly ever done by a single person. a. By their endpoints, such as 1-2; 2-4; etc.
b. By letter assigned to an arrow, such as a,b,c, etc.
- an accomplishment of the schedule is influenced by several numbers of people
who have something to do with the project and should be consulted when
making the network
ACTIVITY
-work operations required to complete a task or some cases, a segment of a DUMMY ACTIVITY
task. - actual work between events - an arrow or a network showing the dependent relationship
between two activities
- does not represent actual work efforts and do not consume
time
- may be used in the network to distinguish between two or
more parallel activities
DURATION OF AN ACTIVITY
- the time it takes an activity to be finished
EVENTS
- the normal time duration of a task
- a point signifying the beginning or end of one or more activities
- the span of time from:
- denotes the completion of all preceding or predecessor activities and the
a. Early Start to its Early Finish
beginning of one or more succeeding activities
b. Late Start to its Late Finish
PATH - a sequence of activities that leads from the starting node to the finishing
node
The EVENT is indicated on the network as any form of geological symbol with a
number written for identification.
Note:
a. Numbering the events follows the construction of the network
b. No two events shall have the same identification number
c. For this reason, one or more dummy activities may be used in a network a.) Path 1-2-4-6
b.) Path 1-3-5-6
PATH Comments:
1. The length of time of any path can be determined by adding the expected PLANNING - is where the logical sequence of the job is to be performed.
time of the activities along the path. Considerations:
2. The path ith the longest time, catches management interset because it 1. Logic sequence must be correct
governs the project completion time. 2. All phases of work should appear
3. In short, the expected duration of a project is equal to the expected time of 3. Scope of work is correctly interpreted
the longest path
4. If there are delays along the longest path, naturally there is also a Resources: Time, Manpower, Equipment, Money, and Facility
corresponding delay in project completion time.
5. Therefore any attempt to shorten the project completion time must PLANNING OBJECTIVES
concentrate on the longest sequence of activities because of its relation to the 1. Represent graphically and properly sequence of the job.
completion time. 2. Establish a medium for estimating resources necessary for each job.
6. The longest path is the critical path and its activities are called critical 3. Available sequential arrangement of jobs, accurate estimate of resources, and
activities. alternative plan.
7. Paths that are shorter than the critical path may experience some delay but
may not affect the overall project completion time as long the ultimate path SCHEDULING
time does not exceed the length of the critical path. -secondary to planning.
8. The allowable slippage for any path is called path slack or float time. It -it is the process of allocating calendar dates to jobs based on the approved plan.
indicates the difference between the length of a given path and the length of the
critical path.
9. The critical path then has a zero slack or float. DEFINITION OF TERMS
Critical Path - longest route in the network of activities representing the project.
RULES IN NUMBERING EVENTS IN A NETWORK DIAGRAM
1. All events should be numbered starting from left to right. Critical Activities – activities along the critical path.
2. No event should be lower than the number of events preceding it (left or right
direction). Earliest Event - it is the earliest time an event can happen sometimes called
3. Event number shall increase from left to right. Earliest Event Time or Early Event Time.
4. Events should be numbered from top to bottom. Similarly, increasing should Numerically equal to the longest path of activities.
be consistent from top to bottom or from bottom to top.
Earliest Start - is always equal to the earliest event at the beginning of an arrow
which is called i-node and the point of an arrow is called j-node.
THE NETWORK DIAGRAM i-node j-node
Network Diagrams are a graphical portrayal of the activities and events of a Early Start - not the point in time that the activity will be over, but the earliest
project. time that it can occur. The first day after physical assumption of activity.
• They show how each activity relates to others in the project, the sequence of
activities, and the need to perform some tasks before others. Earliest Finish - is equal to its Earliest Start plus its duration of time.
EF = ES + Duration or EF = Early Event + Duration
Latest Finish - is activity cannot be later than the latest time of its j-node.
LS + D = LF or LS = LF – D
Total Float/Activity Total Slack - the span of time an activity can be delayed
after its earliest start time
LS – EF = Total Float or LS + D = (ES + D) or LS – ES = Total Float
Free Float - is the span of time activity can be delayed after its early start.
FF = ES - (ES + D)
Independent Float - is that portion of the activities Free Float that would remain
if all its preceding activities used up all their float
I.F. = ES - (LF - D)
When the result is negative, means there is no independent float.
I.F. = 0
4. As a determiner:
The engineer must act as a mediator to help the parties towards agreement in 4. Schedule of Work
issues such as claims for reimbursement of costs or extension of time Establish a clear notice to proceed date, a construction start date, and date of
completion, and be sure to differentiate between calendar days and workdays. It
5. Issuance of instructions and variations is also wise to include in the contract that you are not responsible for delays
Include: issuance of additional or modified drawings, actions in relation to caused by the property owner in obtaining the required permits, easements, and
defective works, issuance of clarifications, giving approval, and ordering approvals, or for delays as the result of bad weather. Make sure to account for
variations. lead times from your suppliers, and if there are change orders, be sure to
document any additional time they will require.
It's important for parties entering into any significant economic transaction to
have written contracts. This is especially true for construction projects which 5. Authority
are, by their nature, complicated. A contract on a construction project sets With so many moving parts, it can become difficult to establish who has
forth the parties' obligations to each other and determines how risks will be authority to make decisions during a construction project. This is why it is
shared or divided on the project. important to make clear who has the authority to make legally binding decisions
before project initiation. This simple element of the contract can save a lot of
headaches and confusion during the project.
These five essential elements of a construction contract can result in major
vulnerabilities if overlooked:
Contracts are an important part of the process of any construction project.
1. Full Name, Address, and Signatures of Both Parties
A construction contract such as a JCT or NEC Contract provides important
Though this may sound obvious, this commonly overlooked element of
protection for Main Contractors, Subcontractors, and Building Employers and is
construction contracts is required to make the contract legally binding. Without
vital in preventing disputes. Primarily the contract safeguards against payments
the proper information or appropriate signatures on all required documents, it
will be difficult to get the contract to hold up in court. and guarantees adequate work, but if a dispute arises, construction contracts
can also dictate how the parties move forward to resolve the issue. Simon
2. Scope of Work Dunkling, Director at Arbicon ADR Ltd, Construction Dispute Experts, explains
the importance of using a properly drafted written contract for construction
Although this is an element that is often included in most construction contracts,
many individuals tend to overlook the necessity for details. This area of the projects and the negative impact if the correct terms are not included.
contract should, in great detail, explain the services to be provided, including a
description of materials, quality, grade, schedule of work, and other Contracts:
specifications pertinent to the construction of the property. The following are the various types of contracts, for the execution of civil
engineering works:
1. Item rate contract
2. Percentage rate contract
3. Lumpsum contract quantity of work to be done within a given period.
4. Labour contract
5. Materials supply contract 7. Cost plus percentage rate contract:
6. Piece-Work agreement In tendering for work on a “Cost Plus" basis, the contractor is paid the actual
7. Cost plus percentage rate contract cost of the work, plus an agreed percentage, in addition, to allow for profit.
8. Cost plus fixed fee contract
9. Cost plus fluctuating fee contract 8. Cost plus fixed fee contract:
10.Target contract In this type of contract, the contractor is paid by the owner an agreed lump-sum
amount over and above the actual cost of work.
1. Item rate contract:
For this contract, contractors are required to quote rates for individual items of 9. Cost plus Fluctuating Fee contract:
work on the basis of the schedule of quantities furnished by the client's In this type of contract, the contractor is paid by the owner the actual cost of
department. construction plus an amount of fee inversely variable according to the increase
or decrease of the estimated cost agreed first by both the parties.
2. Percentage rate contract:
In this form of contract, the client's department draws up the schedule of items 10. Target Contract: This is the type of contract where the contractor is paid on a
according to the description of items sanctioned in the estimate with quantities, cost-plus percentage of work performed under this contract. In addition, he
rates, units, and amounts shown therein. receives a percentage plus or minus on savings or excess effected against either
a prior agreed estimate of total cost or a target value arrived at by measuring
3. Lump sum contract: the work on completion and valuing at prior agreed rates.
In this form of contract, contractors are required to quote a fixed sum (lumpsum
amount) for the execution of work complete in all respects i.e., according to the JCT contracts facilitate the process of constructing buildings. In simple terms,
drawings, design, and specifications supplied to them with the tender within the contracts set out the responsibilities of all parties within the construction
specified time. process and their obligations, so it is clear as to what work needs to be done,
who is doing it, when are they doing it by, and for how much.
4. Labour contract:
This is a contract where the contractor quotes rates for the item work exclusive JCT is the UK’s leading producer of standard forms of contract, which work on
of the elements of materials that are supplied by the client's Department. the principle of adapting established benchmark provisions to suit a wide range
of projects.
5. Materials supply contract:
In this form of contract, the contractors have to offer their rates for supply of
the required quantity of materials, inclusive of all local taxes, carriage, and
delivery charges of materials to the specified site within the time fixed in the
A specification is a specific description of a particular subject. An engineering
tender.
specification contains a detailed description of all workmanship and materials
which are required to complete an engineering project in accordance with its
6. Piece-Work agreement:
drawings and details.
As the name signifies the piece-work agreement, it is that for which only a rate is
agreed upon without reference to the total quantity of work to be done or the
Purpose of Specification: General condition
It includes all parts of the construction that shall be finished with first-class
1. The cost of a unit quantity of work is governed by its specification. workmanship to the fullest talent and meaning of the plans and the
2. work is carried out according to its specification and the contractor is paid Specifications, and to the full satisfaction of the designing Architect and the
for the same. Any change in specification changes the tendered rate. Project Owners.
3. The necessity of specification is to verify and check the strength of materials
for a work involved in a project. Clearing the site
4. Specification is an essential contract document and is required for The construction site must be leveled to a reasonable grade in accordance with
Arbitration or court cases.
the specifications. Plans, garbage, roots, and other perishable objects should be
5. Specification is necessary to specify the equipments, tools, and plants to be
removed.
engaged for work and thus enables to procure them beforehand.
The Major Elements of Organizational Structures Management is a Function- the function of getting things done through the
1. Distribution of Functions- the functions to be performed, the groupings of efforts of others. It is the application of authority and the assumption of
functions, and the vertical and horizontal task relationships among functions responsibility.
2. Vertical and Horizontal Authority Relationships- who is the authority to do Management Concept
what 1. Management to be effective must be systematic- things can be done better by
3. Communication and Decision Processes- the manner in which formal decisions means of the plan of action
are made and by whom
4. Policies- the decision, rules, or guidelines established
2. Management to be successful must be scientific- by the application of the 3. Willing to delegate and share with his subordinates the credit of a job well
scientific method to the study and analysis of the operations of a particular job, done
me have discovered the best-known methods of performing the operation 4. Trains and develops his men to prepare them to assume delegated work
3. Management must be humanistic- human being preferably should be led by 5. Knows how to control and plan his time 6. Institutes control for effective
goals they accept as justifiable, worthy, and fair to all concerned performance
Executive Functions
Management Structures Managers do not do the actual work of an organization. His specific functions
The primary objective of management structure is to facilitate the coordination are:
and control over the activities of the company 1. to Plan
2. to Organize
3. to Direct
The line of responsibility works in two ways: 4. to Control
1. From the executive to the supervisor down to the workers under his
jurisdiction and conversely Planning
2. From the workers to those who are in authority over him the job of making things happen that would otherwise not occur
Executive Leadership The shortage of capable people in leadership and supervision is one of the
Executive Leadership is the bridge between objective and result. Success is the biggest difficulties encountered by companies, and this may be due to:
result of good management and the responsibility for management is vested 1. Lack of incentive
primarily on the manager. He is the fellow who gets things done through the 2. Inadequate or ineffective recruitment of those possessing potential leadership
efforts of others. He is the leader of the organization, and a good leader usually ability
makes a good manager. 3. Insufficient training of present and potential supervisory personnel
What is an Order? Asking for Volunteers- the leader explains what is to be done and asks for
Order- is a specific message conveyed by a leader to a follower for the purpose volunteers to do it.
of influencing the follower to take the desired action. Orders are either verbal or
written. You should ask for volunteers for:
1. Jobs that are dangerous or disagreeable
When to use verbal orders? 2. For extra heavy work
1. When the order is simple and the message can be clearly heard 3. For jobs that require overtime
2. When privacy is important 4. When you want a skilled worker to do a special unskilled job
3. When the follower is intelligent and reliable
4. When a demonstration is involved
Direct Order or Command- this is the last alternative. 2. When privacy is important
3. When the follower is intelligent and reliable
You should only use it under the following circumstances: 4. When a demonstration is involved
1. In case of danger or extreme urgency
2. When haste is important When to have written order?
3. With lazy and indifferent workers, chronic objectors 1. When precise figures or complicated details are involved
4. For careless workers 2. When orders must be passed to someone else
5. When all methods have failed repeatedly 3. When the workers involved are slow to understand and forgetful
4. When you want to hold the receiver strictly accountable
Guiding Principles on How to Phrase Orders Effectively 5. When a particular sequence must be followed exactly
6. When a notice board can be suitable used
Orders should be: 7. When you are quoting general instructions on higher authority
1. Clear- phrase it in simple terms and repeat anything that might be forgotten 8. When a record is desirable, perhaps the order may need to be referred to in
or misunderstood the future
2. Complete- answer all the questions who, what, when, where, and why Knowledge Workers and Manual Workers
3. Concise- make it short enough for the receiver to be able to repeat it
4. Acceptable- ensure that the receiver sees it as justified, practical, tactful, Manual Worker- needs only efficiency, that is, the ability to do things right
challenging, and accompanied by sufficient authority rather than the ability to get the right things done. The manual work can always
be judged in terms of quantity and quality of a definable and discrete
Always remember that every order has three meanings: accomplishment.
1. The meaning you think you convey
2. The meaning you do convey, directly and by implication Knowledge Worker- does not produce a thing, instead, he produces good ideas,
3. The meaning the receiver thinks you convey information, and concepts. He is a specialist.
The goal in evaluating the time cost-trade-off is to identify a plan that will
minimize the amount of direct and indirect project costs. This will aid the
Example 1 Path 1-3-4-5-6 (C-D-E-F) = 26 days
From the following data, develop an optimum time cost plan assuming that the
indirect cost is P10,000 3. Rank Critical Path from lowest Crashing Cost
Activity Normal Time Crash Time Cost per day to Critical Path Activity Cost per day to Available
Crash Crash Days/Crash Limit
A 8 8 (Normal Time-
B 12 10 P6,000 Crash Time)
C 7 6 P2,000 1-3-4-5-6 C 2,000 1
D 6 2 P6,000 E 4,500 2
E 9 7 P4,500 D 6,000 4
F 4 2 P7,000 F 7,000 2
Table-1
4. Start shortening the project one day at a time from Activity with lowest
Crashing Cost: Activity C
5. Crashing Activity C by 1 day: = 26 – 1 = 25 days
6. Crashing Activity E (Crashing next activity with least cost per day to
crash): 25 - 1 = 24days
SOLUTION:
1. Find the length of the activities in each path
Path 1-2-5-6 (A-B-F) = 8+12+4 = 24 days
Path 1-3-4-5-6 (C-D-E-F) =7+6+9+4 = 26 days *
This step is essential, and one of the most crucial in the construction
process.
ROUGH ESTIMATE - This is an estimate where you’re just looking to get in the
ballpark range for a project. PRELIMINARY ESTIMATE - Created when a project’s deliverables are about
halfway defined, a preliminary estimate uses somewhat detailed scope
information to incorporate unit costs.
BID ESTIMATE
For the contractor, a bid estimate submitted to the owner either for
competitive bidding or negotiation consists of direct construction cost
including field supervision, plus a mark up to cover general overhead
profits. The direct cost of construction for bid estimates is usually
delivered from a combination of the following approach:
-Subcontractor Quotations
-Quantity Takeoffs
WHAT IS A COST ESTIMATE? -Construction Procedures
INDIRECT COST
Indirect costs are expenses of items that are not allocated directly for
specific construction activities. These are called overhead costs.
Examples of project overhead expenditures are:
-Quality Control
-Security Costs
-Utilities
-Administrative Costs
-Temporary Structures
-Legal Fees & Permits Labor Cost
- An important value that finance and accounting professionals calculate to
CONSTRUCTION COST ESTIMATION TECHNIQUE determine the direct and indirect price that a company pays for labor.
- The total of wages, benefits, and payroll taxes paid to and for all employees.
ANALOGOUS ESTIMATION - Analogous estimating draws from a purpose-built
archive of historical project data, often specific to an organization. - Construction cost percentage ranges from 20%-30% and will still increase
depending on some conditions.
Equipment Cost
3 Labor Classification: Formulas
General workers / casual workers Total capital cost per hour = (equipment’s sale price x percent sale tax + life loan
Skilled labor financing) / total life expectancy of the equipment in motor-hours
Foreman/supervisor *Add the annual cost for licensing, insurance, and taxes
METHODOLOGY STAGE
The last and final stage is the methodology stage, which is broken up
COMMONLY USED VALUE TECHNIQUES into eight phases which is called the Job Plan. Each step involves critical
analysis and elimination to come to a solid understanding of what
VALUE MANAGEMENT (VM) - The full range of value techniques alternatives are going to be best.
available. It is a higher-order title and is not linked to a particular
project stage at which the value technique may be applied. VALUE METHODOLOGY
VALUE PLANNING (VP) - Value techniques applied during the planning A systematic process used by a multidisciplinary team to improve the
phases of a project. value of projects through the analysis of functions.
VALUE ENGINEERING (VE) - Value techniques applied during the design Value methodology is applied using a process known as the "Job Plan".
or ‘engineering phases of a project. The purpose of the Job Plan is to guide the Value Study Team through
the process of identifying and focusing on key project functions in order
VALUE ANALYSIS (VA) - Value techniques applied retrospectively to to create new alternates that will result in value improvements.
completed projects to analyze or audit the project’s performance.
JOB PLAN
The purpose of the Job Plan is to guide the Value Study Team through the
VALUE ENGINEERING STAGES process of identifying and focusing on key project functions in order to create
new alternates that will result in value improvements. The Job Plan consists of
PLANNING STAGE the following sequential phases:
-Is the earliest aspect of development and is an important part of maintaining
solid communication in construction projects
-Defining key goals, objectives, and criteria for the project
-Functional analysis of the facility
-Review of all utility and material options
-A projected budget for the project
-Ideation of alternative and sustainable solutions
4. EVALUATION (ANALYSIS) PHASE - Check the Functionality vs Cost
- Process to select those alternates that offer the potential for value
improvement while delivering the project's function.
5. DEVELOPMENT PHASE
- Develops the selected ideas into alternatives (or proposals) with a sufficient
level of documentation to allow.
6. PRESENTATION PHASE
- The Value Team Leader develops a report and/or presentation that documents
and conveys the adequacy of the alternative(s) developed by the team and the
THE SIX-STEP JOB PLAN associated value improvement opportunity.
1. INFORMATION PHASE
- Open space no neighboring structure
- Facade is made of fully tempered glass capable of resisting wind load ELEMENT OF VALUE ENGINEERING
- It cost four (4) times more than ordinary glass. Selection
Value engineering need not be applied to everything. The areas selected are
2. FUNCTION ANALYSIS PHASE those which should yield the greatest results for the suitable least time and
- Functionality effort and with the minimum risk.
- Cost involves
- Maintenance cost Information
An essential ingredient and time must be allowed for the relevant costs,
3. SPECULATION (CREATIVE) PHASE - To cut the cost but to gain the same specifications and requirements to be collected, analyzed, and prepared ready
result. for the use of the designer or team.
- Use secondary gauge by reducing the size of glass panels, this is by introducing
narrowed frame to avoid hindering the view. Analysis
- Re-configuring the facade such as inclined surface to reduce wind load - The analysis of information takes two basic forms in value engineering: Cost
concentration. forms of Analysis and Functional Analysis.
- Propose a roof deck using lightweight concrete to minimize the cost of Cost Analysis - is the most usual preliminary to selecting and fixing the
upgrading the foundation. scope of a study.
Functional Analysis - require an accurate definition of the functions
performed by the subject under investigation.
The collective purpose of the committee would be to review progress and to
direct and guide the value engineering program to achieve greater profitability
in the short and long term.
Teamwork
The element of teamwork in value engineering is not intended as a substitute for
individual skills. The effectiveness of value engineering teamwork results from
using the people Combining who are normally concerned with the product and
concentrating their skills collective abilities and experience.
Procedure
The procedures used in value engineering saves time have been devised with a
view to controlling and concentrating the scarce resources in skills and
knowledge, in the most effective manner.
Attitudes
The positive attitudes which proper training and guidance can bring about at the
operating level must be a reflection of similar attitudes from senior
management.
IMPLICATIONS
The management team must fully understand the implications of the
introduction of value engineering into their business. This means that it should
be a seek explanation of the technique and its potential.
RESOURCES
Management must be prepared to make a small but adequate investment for
the high returns which are obtainable from value engineering. They will need
other resources to service the operation and introduce certain minor
administrative changes.
STEERING COMMITTEE