Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Michigan: United District Court District Division

Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.

1 Filed 01/18/22 Page 1 of 26

UNITED STATES DISTRICT COURT


WESTERN DISTRICT OF' MICHIGAN
SOUTHERN DIVISION

326 LAND COMPANY, LLC, a Michigan Case No. l:22-cv-45


limited liability company,
Honorable
Plaintiff,
COMPLAINT
v

CITY OF TRAVERSE CITY, a Michigan


Home Rule City and SHAWN WINTER, City
Planning Director,

Defendants.

James F. Scales (P40639)


Ross A. Leisman (P41923)
Mika Meyers PLC
Counsel for Plaintiff
900 Monroe Avenue, NW
Grand Rapids, MI49503
(616) 632-8000
jscales@mikame)'ers.com
rleisman@mikameyers. com

NATURE OF'CASE

1. This case involves the unlawful and unconstitutional taking of private property

rights from the owners of property in Traverse City, Michigan. This lawsuit was precipitated by

the issuance of a Stop Work Order by the City on November 18,2021, suspending the ongoing

construction of a residential condominium building taking place in compliance with a land use

permit issued by the City itself some four months prior to that time.

2. The financial impact of this action on the owners of this property is devastating.

As of November 18, 2021, the property owners had demolished a valuable existing office

1
0305093 I2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.2 Filed 01/18/22 Page 2 of 26

building, excavated for footings, entered into binding contracts and accepted deposits in an

amount over $3.6 million dollars for the sale of residential condominium units in the building,

and expended over $1.8 million dollars on design, demolition, and site preparation. All of this

was done in good faith reliance on a land use permit which had been issued in compliance with

provisions of the Traverse City Zoning Ordinance ("TCZO") regarding the measurement of

building height which had been in effect and uniformly applied for many years.

3. These vested rights were destroyed by City officials and staff (i) contrary to

policy adopted by the City Commission; (ii) unilaterally, without City staff having conducted

any investigation of the Project's status, (iii) without allowing any opportunity for input by the

property owner and (iv) predicated on a Circuit Court decision in a case concerning an unrelated

project, in which that Court specifically stated did not apply to other projects.

4. The illegality of this action is compounded because it was based upon the

application of an unlawful City Charter Amendment adopted by the voters in 2016 (known as

"Proposition 3") which deprives Plaintiff of rights guaranteed by the United States Constitution.

Proposition 3 (which Michigan's Attorney General opined was invalid before it was even
adopted) purports to make the construction of Plaintiff s building - which is permitted as a

matter of right under the TCZO - subject to a popular election. In that election, the voters of

Traverse City can act at their absolute whim and caprice, without any assurance that, or

standards to judge whether, the outcome of the vote has any relationship whatsoever to the public

health, safety, and welfare. There is no administrative remedy afforded for persons aggrieved of

its application.

5. The unconstitutional lack of a rational basis for Proposition 3 is obvious: The

Charter Amendment states that its purpose is to preserve the residential and historical character

2
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.3 Filed 01/18/22 Page 3 of 26

of the City, by requiring a vote of the electors to approve any building over 60 feet in height.

Yet a 100 foot tall building would be permitted if approved by the voters, while a 61 foot tall
building on the exact same site would be prohibited if rejected by the voters.

6. The Fourteenth Amendment protects all citizens from laws which have no relation

to a proper governmental purpose, by guaranteeing due process and equal protection of laws, and

the Fifth Amendment protects their property rights. The City of Traverse City, acting under

color of law violated these fundamental rights which are protected by the United States

constitution. 326 Land Company brings this action to redress the City's ongoing constitutional

violations and seeks declaratory and injunctive relief, along with costs, attorney fees, damages

and all other appropriate relief.

PARTIES, JURISDICTION AND VENUE

7. Plaintiff, 326 Land Company, LLC, is a Michigan limited liability company,

doing business in the City of Traverse City, Michigan (*326 Lahd";.

8. The Plaintiff is the owner of real property commonly known as 326 E. State

Street, located within the City of Traverse City, Michigan (the "Property").

9. Defendant, the City of Traverse City (the "City"), is incorporated as a Home Rule

City under Public Act279 of 1909.

10. Defendant Shawn Winter is the City Planning Director, the offltcial designated by

Chapter 1322 of the City Code, to issue land use permits and revoke, suspend or issue Stop Work

Orders to halt construction activities proceeding under a land use permit,

1 1. Mr. Winter is the official who in this capacity issued the Stop Work Order dated

November 18,2021.

12. This Court has original federal question jurisdiction over this action pursuant to

28 USC $133r.

03050931 ,
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.4 Filed 01/18/22 Page 4 of 26

13. This Complaint raises claims for deprivation of rights secured by the United

States Constitution, including the Fifth and Fourteenth Amendments thereof, which are

cognizable in this Court under 42 USC $1983.

14. This Complaint further requests declaratory relief as a result of the deprivation of

Plaintiff s rights as alleged in this Complaint, pursuant to 28 USC $2201.

15. This Court has supplemental jurisdiction over Plaintiff s state law claims pursuant

to 28 USC $1367. The claims under state law arise out of the same acts and conduct by

Defendants that give rise to Plaintiff s federal constitutional claims.

16. The federal claims alleged herein are not dependent on the State law claims.

17. The Property that is the subject to this action is located in, all Defendants reside

in, and all events giving rising to this action occured within the Western District of Michigan.

Venue is accordingly proper in this District and Division pursuant to 28 USC $1391(b).

GENERAL ALLEGATIONS

Location and lfisturical Zoning Regulation of the lleight of Buildings on this Property

18. The Property fronts upon State Street, located in downtown Traverse City. It is

immediately adjacent to the Park Place Hotel, a 142 foot tall building, and the Lofts, a building

60 feet in height measured to the deck of its flat roof, with elevator housing and mechanical

equipment extending above that height.

19. The Property is currently located in the City's C-4c. Regional Center District.

20. The Park Place Hotel abutting the Property to the west is also located in the C-4c

zoning district and the Lofts were conditionally rezoned specifically to permit a building of sixty

feet in height, plus mechanical equipment.

4
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.5 Filed 01/18/22 Page 5 of 26

21. From 1943 to 1999, the Property was located in azoning districtwhich allowed

buildings up to and exceeding 100 feet in height, subject to certain objective standards pertaining

to building setback and design,

22. Following a comprehensive revision of the Traverse City Zoning Ordinance

(TCZO") in 1999, a building with a height of 100 feet was still permitted on the property, but

subject to special approval if the building exceeded 60 feet in height, measured as provided by

theTCZO.

23. According to the TCZO, the height of building is measured as the vertical

distance from the grade to the highest point on a flat roof. TCZO, Section 1320.07.

24. The building approved by the City which is the subject of this suit is designed

with a flat roof, and accordingly height is measured to the highest point on the roof.

25. Since at least 1999 and still today, theTCZO has permitted an additional 15 feet

above the stated maximum height for "rooftop mechanical equipment or elevator shafts . . . ."

("rooftop appendage s") T CZQ, Sections I 3 6 8. 0 1 and 13 46.06.a

26. Buildings up to 60 feet in height measured to the surface of a flat roof with such

rooftop appendages above that have been permitted as a matter of right on the Property, without

any special land use or other discretionary approval on this Property since at least the 1999

TCZO revision.

27. Following the 1999 amendments, and still today, any building exceeding 60 feet

in height was designated a taller building, and a building of such additional height was permitted

only with special land use approval by the City Commission on recommendation of the Planning

Commission.

5
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.6 Filed 01/18/22 Page 6 of 26

28. The decision whether or not to approve a taller building is based in part upon

objective standards specific to "taller buildings" set forth in Sections 1364.01(b)(13) and

1364.08(13) of the TCZO.

29. That decision is also based on subjective discretionary standards described in

Section 1364.02 of the TCZO.

30. In reliance upon nearly 80 years of zoning regulations which allowed buildings of

a height of 100 feet, beginning in 2014 the Plaintiffs began preparing to construct a 10-story 100-

foot tall residential condominium building at 326 State Street.

The Genesis and Adoption of Proposition 3 (Despite its Rejection by the Michigan
Governor and Michigan Attorney General)

31. The City of Traverse City is a Home Rule City and has adopted a City Charter

pursuant to the Home Rule City Act ("HRA"), MCL II7.1, et seq.

32. Pursuant to MCL ll7.2l the City Charter may be amended by an initiatory
petition by the electors.

33. Beginning in2016, an initiatory petition regarding building height was circulated

for a ballot proposal to be presented to the City electors at the November 8, 2016 General

Election.

34. That petition was prompted by certain City residents' opposition to a ootaller

building" proposed to be constructed on the west side of downtown at 305 Front Street, not the

Plaintiff s proposed building at326 State Street.

35. The petition proposed that the following be added to Section 28, Chapter IV of

the City Charter:

It is hereby declared that buildings over 60 feet in height are generally


inconsistent with the residential and historical character of Traverse City.
Therefore, any proposal for construction of a building with a height above

6
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.7 Filed 01/18/22 Page 7 of 26

60 feet, shall not be approved by the City or City Commission, until after
the proposal is submitted to and approved by a majority of the City electors
at a regular election or at a special election.

36. The proposal, as eventually placed on the ballot, was and is generally referred to

o'Proposition 3,"
as and will be so identified in this Complaint.

37 . Pursuant to MCL lI7.2l(2) and MCL I17.22, proposed city charter amendments

are to be submitted to the office of the Michigan Attorney General and the Governor before

submission to the voters at an election. In practice, the Attorney General reviews the language

for the Governor.

38. In a letter dated April 28, 2016, the Attorney General, on behalf of the Governor,

objected to and rejected the proposed Proposition 3 language because it conflicted with state law.

The Attorney General opined that Proposition 3 conflicted with the Michigan Zoning Enabling

Act ("MZEA"), which authorizes the City Commission - not the City electors - to make special
land use and other zoning decisions (MCL 125.3502(l)), and further conflicted with the HRA

which prohibits a charter provision from conflicting with state law, i.e., the MZEA. MCL

rr7.36.

39. The Attorney General further refused to give approval for Proposition 3 because

the language of the proposed amendment failed to disclose that it conflicts with the MZEA. A

copy of the Attorney General and Governor's letters are attached as Exhibits A and B.

40. Notwithstanding the Attorney General's and the Governor's corresponding

rejection of the proposed language, the proposition was submitted to the City electors as

mandated by MCL 117.22.

4L At the November 8,2016 General Election, Proposition 3 was approved by a

majority of those voting.

7
0305093 l 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.8 Filed 01/18/22 Page 8 of 26

The City Commission Policy fmplementing Proposition 3

42. On April 24, 2017, the City Commission formally adopted an 'olmplementation

Policy for Charter $28 Building Height Restriction" (the "Proposition 3 Implementation

Policy"), attached as Exhibit C, which implemented the voter election requirement of Proposition

3 for buildings over 60 feet in height. The stated pu{pose of the policy was 'oto ensure
consistency and predictability in the administration of approvals related to building height as

required by" Proposition 3.

43. Section 3.c. of the Proposition 3 Implementation Policy provided that an election

would be required only if the building proposed required special land use or planned unit

development approval under the T CZO.

44. In the case of a taller building requiring special land use approval, Section 3.c.i.

provided that the election required by Proposition 3 would occur after the Planning

Commission's public hearing and recommendation, but before the City Commission's public

hearing and consideration ofapproval or denial.

45. Section 3.a. of the Proposition 3 Implementation Policy provides the following

method of measuring building height to determine if Proposition 3 is applicable:

Measurement: For pu{poses of determining whether the Charter provision is triggered by


a proposed building with a height above 60 feet, the methods of measuriJrg buildins
shall be fEmphasis added]

46. According to the Proposition 3 Implementation Policy, a building located in the

City's C-4c. Regional Center District with a flat roof at a height of 60 feet, with rooftop

appurtenances extending above that, would not be subject to an election pursuant to Proposition

J.

8
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.9 Filed 01/18/22 Page 9 of 26

The Plaintiffs First Lawsuit to Challenge Proposition 3


47. At the time Proposition 3 was adopted, Plaintiff had already worked for several

years and expended significant amounts of money for design and preparation for its l0-story

building proposal for the 326 State Street property under the special land use standards in the

TCZQ,

48. Because Proposition 3 would have a direct impact on the Plaintiffs proposed

building project, on January 5,2017, the Plaintiff filed a Complaint For Declaratory Ruling and

Order for Superintending Control in Grand Traverse County Circuit Court, challenging the

legality of Proposition 3.

49. On August 3,2017, the Circuit Court issued an Order dismissing the Plaintiffs

Complaint as not ripe for review without prejudice, requiring the Plaintiff to first seek voter

approval under Proposition 3.

50. The Plaintiff appealed that decision to the Michigan Court of Appeals, and on

September 27, 20t7, that Court issued an unpublished per curiam Opinion that affirmed the

Circuit Court's decision that the prior Plaintiff s Complaint was not ripe before submitting its 10-

story building to the voters for approval under Proposition 3.

The City Planning Staff and City Planning Commission Recommend Approval of 326
Land's I 0-Story Structure

51. Following the Court proceedings described immediately above, the Plaintiff

continued its effort to obtain approval of its lO-story project by following the Proposition 3

Implementation Policy which required a Planning Commission public hearing and

recommendation before the 1O-story building would be submitted to the voters under Proposition

J,

9
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.10 Filed 01/18/22 Page 10 of 26

52. Under Chapter 1364 of the City's Code, the City Planning Commission is

responsible for issuing a recommendation in favor of or against approval of a special land use

permit for a building over 60 feet in height.

53. On October 3,2017, following public hearing, the City Planning Commission

recommended approval of the Plaintiff s lO-story project.

The Voters Did Not Approve Plaintiffs |0-Story Building Proposal

54. Following the Planning Commission's recommendation for approval, and as

required by the Proposition 3 Implementation Policy, the Plaintiff requested that its proposal for

a l0-story building to be located at 326 State Street go before the Traverse City voters for

approval at the November 6,2018 regular election.

55. At the November 6,2018 regular election, the City voters did not approve the

building with 4,977 oNo" votes opposed to 3,242 "Yes" votes in favor.

The Plaintiffs Second Circuit Court Lawsuit

56. When the City voters did not approve the lO-story building, the issue of the

validity of Proposition 3 under State law became ripe and Plaintiff filed a lawsuit in the Circuit

Court on December 12,2018. That lawsuit sought an Order declaring thata special land use

application for a building exceeding 60 feet in height was to be decided solely by the City

Commission, as provided by the MZEA.

57. In response to several competing motions for summary disposition, the Circuit

Judge dismissed the Plaintiff s Lawsuit, holding that an approving vote under Proposition 3 was

required before the City Council could consider special land use approval for a building

exceeding 60 feet in height.

10
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.11 Filed 01/18/22 Page 11 of 26

The Plaintiff Made Signilicant Physical fmprovements to the Site and Substantial
Expenditures in Reliance on the Proposition 3Implementation Policy

58. Thereafter, Plaintiff made a decision to design and construct a five-story building

which would not require special land use approval.

59. In reliance upon the Proposition 3 Implementation Policy, in reliance upon the

foregoing sections of the TCZO, and in reliance upon the widespread adopted City policy of

measuring building height in such a manner to allow rooftop appendages above the maximum

stated height, the Plaintiff proceeded to design a five-story building known as Peninsula Place

with a flat roof at a height of not more than 60 feet, which included rooftop appendages above 60

feet on top of the fifth story.

60. These rooftop appendages included two stairway exit enclosures leading to a patio

on the roof, an enclosed structure housing elevator machinery, and an enclosure for mechanical

and electrical equipment.

6I. The rooftop appendages described in the previous allegation occupy an area of

approximately 489 square feet of the approximately 17 ,807 square feet of the total rooftop area,

or less than2.l5Vo of the rooftop area.

62. The placement of the rooftop appendages above a height of 60 feet pursuant to the

Proposition 3 Implementation Policy allowed a building with a flat roof at 60 feet in height

above grade, thus permitting the building to contain five stories, including four stories for

residential condominium units above ground level parking.

63. If the rooftop appendages were not allowed above a height of 60 feet, it would

result in the loss of one of the four residential floors from the building which was approved by

the July LUP.

1l
0305093 l 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.12 Filed 01/18/22 Page 12 of 26

64. The Plaintiff had already relied on the rooftop appendages placement above a

height of 60 feet in 2017 when it entered into a contract with a neighboring property to the

immediate east (where the five-story Lofts apartment building was ultimately constructed) to

extend its foundation 25 feet onto the Plaintiff s property and where a larger foundation was

constructed to support both the Plaintiff s proposed building and the neighboring building.

65. The Plaintiff relied on the rooftop appendages placement above 60 feet when it

designed the five-story building, paying its architects Alexander V. Bogaerts & Associates

$460,882.50 between November 2020 and September 2021.

66. The Plaintiff relied on the rooftop appendages placement above 60 feet by paying

engineering and structural costs in the amount of $104,360.07 between February 2021 and

November 1,2021.

67 . In July 2020 Plaintiff put the project out for bid by three competing construction

contractors and awarded the bid to REI Construction Consultants in October 2020.

68. The Plaintiff relied on the rooftop appendages placement above 60 feet when it

paid its construction contractor $518,855.04 between April 2021 andNovember 18,202I.

69. The Plaintiff relied on the rooftop appendages placement above 60 feet when it

paid down a building loan in the amount of $518,855.04 to its lender TCF National Bank on May

25,2021, in order to obtain a consent needed to commence construction.

70. The Plaintiff relied on the rooftop appendages placement above 60 feet when it

paid $240,926.84 for other costs related to the project.

The Plaintiff Relied to its Detriment on the Rooftop Appendages Placement above the Fifth
Story when it Entered into Purchase Contracts with Owners of Condominium Units in the
Project Building

71. The Plaintiff s Building Project consists of 42 individual residential condominium

units within the five-story building.

t2
0305093 I2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.13 Filed 01/18/22 Page 13 of 26

72. If the rooftop appendages were not allowed above a height of 60 feet, it would

effectively reduce the building from four to three stories for residential condominium units.

73. Due to the view of Grand Traverse Bay from the upper floors of Peninsula Place,

the units on those floors could be sold for an estimated 50Yo to 300% more than comparable

units on the second and third floors.

74. The Plaintiff has financed the initial design and construction of the Project

building by requiring the buyers of the residential condominium units to provide deposits over

the construction period as part ofthe buyers' purchase contracts.

75. By December 13, 2021, the Plaintiff had entered into building contracts to sell 21

condominium units, with a total purchase price of over $9.7 million.

76. By November 18, 202I, Plaintiff had received deposits from these purchasers in

the amount of $3,649,037.60.

77 . The Plaintiff has already utilized these deposits to fund over $1.8 million of costs

to demolish an existing structure, perform site preparation work, design and construct the

building project with respect to the costs and expenses identified in this Complaint.

The Plaintiff Initiates Construction of its Project Building

78. On July 20,2021 the Plaintiff obtained Land Use Permit PLU21-0112 ("July

LUP") which was based upon the City's review of a detailed set of site plans and architectural

drawings with a revised date as late July 2,2021identified as'oProjectNo. 2015-l13" prepared

by Alexander V. Bogaerts * Associates, P.C. ("Project Drawings").

79. The project architects were in regular contact with City planning and building

staff during the entire design process to assure that the Peninsula Place building, as designed,

would comply with the TCZO and Proposition 3 Implementation Policy and would not trigger

the requirements of a vote under Proposition 3.

tt
o3o5o93l ,.
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.14 Filed 01/18/22 Page 14 of 26

80. The Project Drawings showed a five-story building with a height of 60 feet with

several appendages on the roof top - such as mechanical equipment, elevator shafts, and stairway

exits - exceeding 60 feet.

81. The Project Drawings reflected the Plaintiff s reliance on the rooftop appendages

placement above 60 feet.

82. The Plaintiff s property at326 State Street had been occupied by lhe law office of

Running, Wise & Ford, PLC ("RWF"; for over 60 years. Two of the three principals of the

Plaintiff are members of the RWF law firm and were the owners of the company which owned

the former law office building property.

83. The law office building had a floor area of 5,120 square feet and was rated as

100% functional by the City's assessment records. According to the assessment records, the

building and land improvements were valued at approximately $350,000, not including land

value.

84. The Plaintiff relied on the July LUP allowing rooftop appendages to extend above

60 feet (and therefore allowing a five-story residential building) when it abated asbestos and tore

down this valuable building on August 2,2021 at a cost of approximately $120,000, and moved

the law office tenant to a new location.

85. The Plaintiff relied on the rooftop appendages placement above 60 feet and the

July LUP when it contracted with the firm of REI Construction Consultants to construct the

foundation of the Project Building.

86. As of November 3, 202I the Plaintiff had made non-refundable payments in the

amount of $478,759 to its construction contractor for demolition, excavation, and other physical

changes which had been made to the site.

t4
030s093 l 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.15 Filed 01/18/22 Page 15 of 26

87 . The Plaintiff incurred $49,51 I .00 in building permit fees for permits issued by the

City pursuant to the July LUP.

88. Prior to November 18,2021, the site was measured and excavated specifically in

preparation for installation of auger cast piles to provide a structural foundation designed for the

five-story building.

Ileight Order Resulting from Other Lawsuit


89. While Plaintiffls Project was proceeding, Innovo TC Hall, LLC ("Innovo")

applied for a land use permit to construct a five-story building in northwest downtown Traverse

City. The height of the Innovo building was subject to provisions of the TCZO which allowed

rooftop appendages above the maximum height of 60 feet in the zoning district in which that

building was located.

90. Save Our Downtown (.'SOD"), a public advocacy group that had originally

supported Proposition 3, filed a lawsuit in the Grand Traverse County Circuit Court to prevent

final zoning approval from being granted to Innovo's building ("Innovo Lawsuit").

91. That lawsuit did not name 326 Land as a party, nor challenge 326 Land's project

or permits.

92. SOD claimed that allowing rooftop appendages above a height of 60 feet without

a vote of the City electors violated Proposition 3's 60-foot height limitation.

93. Following a hearing on November 10, 2021, the Circuit Court entered a Judgment

Order dated November 18,2021, which held that the rooftop appendages on Innovo's building

were to be included in measuring building height for purposes of Proposition 3.

94. According to the transcript of the hearing on November 10, 282I, (pages 74'75)

the Judge issued the following ruling regarding other projects:

15
0305093 I2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.16 Filed 01/18/22 Page 16 of 26

Well, I guess it's alleged that there was -- could have been others -- specifically
4front, that were approved in violation of the 60-foot limit -- now, one of the
things requested in the complaint is directing the City to reverse any prior grant of
approval and/or permit for construclion of a building in excess qf 60 feet, To the
ts
those
oart of this case and I don't think we srant -- there's lots of reasons to
hen.nrrce lilre fnr evqrnnle the hrrildinotq qlreedw hrrilt' that that might not be
proper, but we can't do that without them being part of the case. Add an injunction
prohibiting the City from approving buildings in excess of 60 feet without a vote
of the public -- I'll grant that. fEmphases added]

95. The Circuit Court's ruling applied prospectively to new projects, but it did not

apply to prior grants of approval or permits for construction of buildings of 60 feet in height as

measured under the terms of the Proposition 3 Implementation Policy.

Stop Work Order fssued Against the Plaintiffs Building Project

96. On November 18, 202I, the same day that the Judgment Order was issued from

the Innovo lawsuit, the City's Planning Director, citing the Innovo Judgment Order, issued to the

Plaintiff a letter ("Stop Work Order") stating in part:

This letter is to inform you the approved residential development located at 326 E
State St. is no longer allowed to proceed as permitted. . .

The building in your development does in fact include such items that exceed a
height of60 feet and has not been approved by a vote ofthe electorate. Therefore,
the structural and foundation work approved under Land use Permit PLU2I-0112
is no longer valid and all associated work under that permit must cease and desist
immediately,

(Exhibit D).

97. Prior to the issuance of the Stop Work Order, no City official contacted the

Plaintiff and/or its representatives to make any inquiry into the facts alleged above with respect

to the Plaintiffs Project and with respect to the Plaintifls expenditures made, and physical

construction performed in reliance upon the July LUP, the Proposition 3 Implementation Policy,

the foregoing TCZO provisions cross-referenced by the Proposition 3 Implementation Policy,

I6
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.17 Filed 01/18/22 Page 17 of 26

and the City's long-standing zoning practice of allowing rooftop appendages to extend above the

standard height limitation (60 feet or otherwise).

98. The City's Stop Work Order did not comply with the Circuit Court's directives in

the Innovo Lawsuit, that it did not apply to any permit aheady issued.

The Plaintiffs Efforts to Mitigate its Damages


99. Because of a pre-existing arrangement with a specialized foundation contractor,

and other immediate commitments made prior to the Stop Work Order, 326Land did submit an

alternate plan drawing for the Project and received LUP PLUZI-}I7 3 on November 29,202I.

100. The plans for the building submitted after the Stop Work Order were modified on

an emergency basis to receive alternate land use approval to allow construction to continue while

making efforts to have the Stop Work Order rescinded.

101. These actions were taken by Plaintiff only to mitigate the Plaintiffs damages
associated with the Stop Work Order so that the construction work by contractors on site at that

time could continue.

I02. The building depicted on that substitute plan is not economically feasible and

differs from the building in which condominium units have already been sold.

COUNT I
Destruction of Vested Rights without Due Process or Compensation:
Sth Amendment and 14th Amendment, Section 1 of U.S, Constitution; 42 USC 51983

103. 326 Land hereby incorporates by reference all foregoing allegations of this

Complaint.

104. The due process clause of the l4thAmendment of the United States Constitution

provides that no person shall be deprived of property without the due process of law.

I7
030s093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.18 Filed 01/18/22 Page 18 of 26

105. Without regard to the validity of Proposition 3, or the Circuit Court decision in

the Innovo case, 326 Land justifiably relied in good faith on the TCZO, the Proposition 3
Implementation Policy and the July LUP issued by the City, which permitted a building with

rooftop appendages placement above 60 feet in height.

106. As alleged above, 326 Land undertook demolition and construction, made

expenditures, and entered into contracts with contractors and condominium owners in good faith

reliance on the TCZO pertaining to measurement of building height, the Proposition 3

Implementation Policy, and the July LUP.

I07. 326Land thereby acquired a vested and protected property interest in constructing

the building as proposed, including rooftop appendages above a height of 60 feet.

108. The City is estopped from issuing the Stop Work Order for construction as

approved by the July LUP.

109. The due process clause of the 14th Amendment protects against the deprivation of

a property interest without notice and an opportunity to be heard at a meaningful time and in a

meaningful manner,

110. The July LUP was revoked without prior notice or opportunity for 326Landto

present the reasons why it had acquired protected property interests in reliance on the July LUP.

11 1. Because Proposition 3 is not part of the TCZO or building codes, there is no

provision made for appeal to the Zoning Board of Appeals, Construction Board of Appeals, or

other quas i -j udi c ial administrative body,

ll2. The City Planning Director, Shawn Winter, was acting under color of law

according to authority granted to the Planning Director by Chapter 1322 of the TCZO.

18
0305093 l 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.19 Filed 01/18/22 Page 19 of 26

113. The City of Traverse City is acting under color of law by virtue of its

authorization to adopt and enforce its TCZO pursuant to the Michigan Zoning Enabling Act, and

the Charter amendment approved by its citizens.

ll4. The City of Traverse City and its Planning Director are each oopersons" within the

meaning of 42 USC $1983.

115. The City Planning Director violated 326Land's right to procedural due process.

116. The Fifth Amendment protects against the deprivation of property without

compensation.

II7. The revocation of the July LUP deprives 326Land of these valuable vested rights,

without payment of just compensation,

118. This violation of the due process clause of the 14th Amendment and just

compensation clause of the 5th Amendment are actionable under 42 USC $1983.

119. 326 Land is entitled to declaratory and injunctive relief, damages, costs and

attorney fees as provided by 42 USC 1988(b) and all other appropriate relief.

COUNT II
Substsntive Due Process * Deprivation of Property Rights by Procedare not Related to Public
Health, Safety and lYelfare

120. 326 Land hereby incorporates by reference all foregoing allegations of this

Complaint.

I2l. The due process clause of the l4th Amendment protects against the deprivation of

a property interest by an action under color of state law which has no rational basis in the

promotion of the public health, safety and welfare, or which advances such an interest but in a

manner which is unreasonable.

19
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.20 Filed 01/18/22 Page 20 of 26

122. As previously alleged, the TCZO permits, by right in this zoning district,

construction of a building as proposedby 326 Land and approved by the July LUP which has a

height of 60 feet, not including rooftop appendages which may extend 15 feet above that

elevation.

I23. The right to construct such a building is a property interest protected by the due

procgss clause.

I24. Proposition 3 was adopted under color of state law pursuant to the procedures of

Michigan's Home Rule Cities Act with the approval of the voters of the City of Traverse City.

125. The effect of Proposition 3 is that a building of a height which is otherwise


permitted by right by the TCZO without special land use approval will nevertheless be prohibited

ifnot approved by the voters, who are free to vote for or against such a proposal for any reason

whatsoever and are in no way bound to exercise their vote in a manner which bears a rational

relationship to the public health, safety and welfare.

126. The facial inationality of Proposition 3 is demonstrated by the fact that a 100 foot

tall building might be permitted if approved by the voters, while a 61 foot tall building on the

exact same site would be prohibited if rejected by the voters.

127. Requiring that a building which is otherwise permitted by right by the TCZO to

be subject to approval at the whim and caprice of the electors is per se a violation of 326 Land's

substantive and procedural due process rights.

I28. Proposition 3 violates substantive due process as applied to Plaintiff s building in

consideration of the minimal extent of the structures extending above the flat roof.

I29. This violation of the due process clause is actionable under 42 USC $1983.

20
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.21 Filed 01/18/22 Page 21 of 26

130. 326Land is entitled to declaratory and injunctive relief, costs and attorney fees as

allowed by 42 USC $1988(b) and all other appropriate relief.

COUNT III
Violation of Equal Protection - No Rational Busisfor Disparate Treatment
42 USC 51983; Mich. Const. 1963 Art I, $2

131. 326 Land hereby incorporates by reference all foregoing allegations of this

Complaint.

132. The equal protection clause of the 14th Amendment of the United States
Constitution provides that no person shall be deprived of the equal protection of the laws.

133. The equal protection clause of the United States Constitution protects persons

similarly situated from differential treatment by the goveilrment that has no rational basis.

I34. There are already existing in Traverse City buildings, including the adjacent Park

Place Hotel, Munson Hospital and Riverview Terrace, which exceed 100 feet in height, and

which have not been subject to Proposition 3.

135. In addition to these buildings, upon information and belief; there already exist in

Traverse City other buildings in the same or other zoning districts which exceed 60 feet in

height, including rooftop appendages at a level above 60 feet, and which have not been subject to

Proposition 3.

136. 326 Land has been denied the right to construct a building of a height identical to

or less than those existing in the City of Traverse City, unless approved by an election held

pursuant to Proposition 3.

I37. The effect of Proposition 3 is that identical proposed buildings exceeding 60 feet

in height might be approved or disapproved depending upon the results of a popular election.

2t
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.22 Filed 01/18/22 Page 22 of 26

138. Basing disparate treatment of identical or nearly identical buildings on the results

of an election does not satisff the equal protection requirement of a rational basis for

distinguishing between similarly situated persons or properties.

139. This violation of the equal protection clause is actionable under 42 USC $1983.
140. 326 Land is entitled to declaratory and injunctive relief, costs and attorney fees as

provided by 42 USC $1988(b) and all other appropriate relief.

COUNT IV
Dae Process - Deprivation of Property Rights by Unauthorized Revocation of July Land Use
Permit

14L 326 Land hereby incorporates by reference all foregoing allegations of this

Complaint.

142. The due process clause of the 14th Amendment protects citizens against the

deprivation of a property interest by an action taken under color of state law that is unauthorized

by law.

143. On April 24,2017, the Traverse City Commission adopted the Proposition 3

Implementation Policy by formal vote.

144. The Proposition 3 Implementation Policy has not been revoked or amended by the

City Commission.

I45. Proposition 3 did not speciff the manner in which building height is to be

measured for purposes of subjecting a building to a vote, so the Proposition 3 Implementation

Policy directed that the height of buildings for purposes of Proposition 3 was to be measured as

provided by the TCZO.

146. The Planning Director is bound to follow the Proposition 3 Implementation

Policy.

22
0305093 I2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.23 Filed 01/18/22 Page 23 of 26

147 . The July LUP for the 326 Building was issued in compliance with the Proposition

3 Implementation Policy.

148. The Proposition 3 Implementation Policy does not authorize revocation of a land

use permit issued in accordance with the Policy.

149. As previously alleged, in hip decision in the Innovo case Judge Power specifically

declined to make his injunction applicable to existing buildings or approvals.

150. The Planning Director's Stop Work Order was accordingly illegal and

unauthorized.

151. This unauthorized and illegal revocation in violation of the due process clause of

the 14th Amendment and is actionable under 42 USC $1983.

152. 326Land is entitled to declaratory and injunctive relief, costs and attorney fees as

allowed by 42 USC $1988(b) and all other appropriate relief.

COUNT V

Violation of Due process rights by Enforcement of Charter Provision which is Invalid under
State Law

153. 326 Land hereby incorporates by reference all foregoing allegations of this

Complaint.

154. Proposition 3, as applied by the City to the building proposed by 326 Land, has

the effect of nulliffing the provisions of the TCZO which permits such a building as a matter of

right, without the need for special land use or other approval.

155. The City of Traverse City is a creation of State law incorporated under the Home

ooNo
Rule City Act ("HRA"). According to Section 36 of the HRA: provision of any City

charter shall conflict with or contravene the provisions of any general law of the State." MCL

1r7.36.

23
0305093 I 2
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.24 Filed 01/18/22 Page 24 of 26

156. Section 4.i(c) of the HRA provides the City the authority to adopt the TCZO,

regulating the height and other characteristics of structures. MCL II7 .ai@).

I57. The City lacks authority to regulate the height of structures through a means other

than adoption and enforcement of the TCZO.

158. Proposition 3 as applied to a building permitted by right without special land use

approval is unlawful and invalid because it is contrary to State law.

159. Proposition 3 was adopted and is being enforced under color of law.

160. The action of the City and its Planning Director in revoking the July LUP in

reliance on this invalid Charter provision is a violation of 326 Land's constitutional due process

rights.

161. 326Land is entitled to declaratory and injunctive relief, costs and attorney fees as

provided by 42 USC $1988(b) and all other appropriate relief.

COUNT VI

Taking of Property in Violation of the Sth Amendment to the United States Constitution

162. 326 Land hereby incorporates by reference all foregoing allegations of this

Complaint.

163. A building with a flat roof surface height of approximately 60 feet, with an

additional allowance of 15 feet above that for rooftop appurtenances, could include four
residential stories, plus heating, ventilation, air conditioning and other equipment which is

customarily mounted on the roofs of such buildings.

164. If Plaintiff is prohibited from installing on its building any structure housing,

elevator equipment, stairways, HVAC equipment or similar necessary appurtenances above an

elevation of 60 feet, this will require re-design of the building to include only three residential

stories.

030s093r , 'o
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.25 Filed 01/18/22 Page 25 of 26

165. As applied to the 326 Land building, this would result in the loss of ten
condominium units on the top floor of the building, which are estimated to have a total sales

price for those ten units in excess of $ I I million. Net of construction costs for that top story, this

would result in damages in excess of $7 million.

166. In addition, a building re-designed to comply with the TCZO and Charter, as now
interpreted by the City, would be substantially different from the building for which purchase

reservations and deposits were rgceived, potentially allowing those purchasers te seek to revoke

their purchase agreements, gausing fuither financial loss.

167. As applied tq 326 Land, the application of Proposition 3 deprives 326Land of any

reasonable investment-backed expectation for use of its property.

168. As a result of that deprivation,326Land has suffered damages in an amount of $7

million or more.

RELIEF REQUESTED

THEREFORE, 326 Land Company, LLC respectfully requests this Court order and

award of the following relief:

A. A declaration that the expenditures and actions taken by 326 Land in good faith in

reliance on the July LUP conferred upon it vested rights which entitle it to

complete its building in accordance with the plans approved by the July LUP.

B. A declaration that the City Planning Director revoked the July LUP without legal

authorization to do so, in violation of the due process and vested property rights

of 326 Land,

C. An injunction ordering the Traverse City Planning Director to vacate the Stop

Work Order and permit the construction of the building in accordance with the

plans for which the July LUP had been issued.

03050931 , "
Case 1:22-cv-00045-PLM-PJG ECF No. 1, PageID.26 Filed 01/18/22 Page 26 of 26

D A declaration that Proposition 3 unconstitutionally deprives 326 Land of its

property rights without due process of law, and is invalid and unenforceable.

E. A declaration that Proposition 3 unconstitutionally deprives 326 Land of its right

to equal protection of the laws, and is invalid and unenforceable.

F. Damages for the unconstitutional taking of its property.

G Costs and attorney fees as provided by 42 USC $1988(b).

Respectfully submitted,

MIKA MEYERS prc


Counsel for Plaintiff

Dated: January l% ,zozz By:


F. (P4063e)
Ross A. Leisman (P41923
900 Monroe Avenue, NW
Grand Rapids, MI49503

26
0305093 I 2

You might also like