GM CSR Training

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

GM Customer Specific

Requirement Overview
GM Customer Specific Requirements
There’s 3 basic requirements to follow:

GM IATF 16949 Customer Specific


Requirements

Global Supplier Quality Manual

BIQS (Quality Performance Metrics and


Quality Management Assessment)
IATF 16949 Customer Specific
Requirements
 A manual that includes additional requirements of GM for IATF 16949,
 This document can refer to additional GM Global Procedures and Instructions that
must also be implemented into the LF QMS.

Relevant Requirements:
 7.5.3.2.1 Record retention (GMW15920)/ electronic traceability.
 Section 8.3 Design Process (GMW15049, RPN in PFMEA)
 Section 8.4 Supplier Control process (Change control, PTR)
 Section 8.5 Manufacturing process (BIQS)
 9.1 Customer Satisfaction (New Business Hold, BIQS Requirements, Control
Shipping II)
 9.2 Internal Audits (LPAs, CQIs)
 10. Problem Solving, error proofing and CI. (Fast Response)
Global Supplier Quality Manual

 Divided in APQP and Current Process


 The APQP section defines GM’s global product quality planning requirements
to develop and implement an APQP process.
 The Current section defines the standardized work around processes to
protect GM plants.

Relevant Requirements:
 Explains roles and responsibilities of Supplier and GM in the APQP Process.
 Supplier APQP readiness valves
 Quality Performance Metrics (BIQS Level required)
 PPAP (SQMS)
 Special Conditions: CSI, CSII, BIQS Requirements, NBH
BIQS (Quality Performance Requirements and Quality
Management Assessment)
Built In Quality Supply based (BIQS) is an advanced level of implementation of a robust
Manufacturing System that helps to achieve not only key business results, but First Time Quality as
well. Is aligned with GM Global Manufacturing System (GMS) , IATF16949 standard and with
Customer Specific Requirements (CSR), BIQS is formed by two elements:

Quality Performance Requirements: GM 1927 30 Quality Management Gap


Supplier must comply with an annual Assessment: an assessment consisting
criteria released by GM for Quality of 30 elements of the GM manufacturing
Performance; this is given in BIQS Levels system. Actually, there's no minimum
where the minimum requirement is BIQS score to approve and is used as part of
level 3 GM CSR

Actions and Controls to assure


product quality since
manufacturing point.
BIQS (Quality Performance Requirements)

GM
Excellence
Award

Minimum
BIQS Level
required
BIQS (Quality Management Assessment)
Assessment of 30 Elements of the GM Manufacturing system (GM’s Philosophy), all related to IATF clauses and GM CSR

No. Element No. Element


1 Maintenance 16 Standardization / Standardized Work
2 Training 17 Repair / Rework / Teardown
3 Supply Chain Management 18 Alarm and Escalation
4 Process Failure Mode and Effect Analysis Non-Conforming Material / Material
19 Identification
5 Process Capability
20 Team Problem Solving
6 Visual Standards and Controls
21 Andon System
7 Visual standards
Inspection Gate /Verification station/Final
8 Error proofing / Detection Verification 22 Inspection
9 Bypass / Deviation Management Production meeting/Fast Response (Visual
10 Gauge Calibration and MSA 23 mgmt. manufactura)
11 Process Control Plan PFMEA-PCP-SW 24 Quality Focused Checks
12 Process Control Plan Implemented 25 Feedback / Feed forward
13 Process Change Control 26 Re-PFMEA Risk Reduction
14 Change Control - PTR 27 Contamination control
15 Layered Process Audits 28 FIFO and Material handling (traceability)
29 Shipping Approved Packaging
30 Safety
GM CSR 9.1.2.1 Customer Satisfaction

Organizations shall achieve and maintain BIQS Level of 3, 4 or 5. The organization whose BIQS Level falls below
Level 3 shall notify its Certification Body within 5 business days after falling below the stated requirement. The
Certification Body shall issue a major non-conformance against IATF 16949:2016, clause 9.1.2.1, when they
are notified (or discover) the organization is at a BIQS Level 1 or 2.
NOTE 1: Two conditions where a major non-conformance is not required for BIQS level < 3 are:
- BIQS Level 0 – With no production receipts nor any quality SPPS records in the last 12 months; or
- Not yet nor previously certified to IATF 16949
NOTE 2: The GM system Sourceability Report will indicate a BIQS Level of 1 or 2 for those organizations not
meeting the BIQS requirements.
If the organization failed to notify their Certification Body, the Certification Body shall also issue a minor non-
conformance against IATF 16949:2016, clause 9.1.2.1.
The Certification Body must conduct an on-site special audit per the IATF Rules to close out the non-
conformance.