Renewable Integration Study - Aemo
Renewable Integration Study - Aemo
Renewable Integration Study - Aemo
Integration
Study:
Stage 1
report
April 2020
PURPOSE
AEMO publishes this Stage 1 report from its Renewable Integration Study to outline:
• System security limits that affect how much wind and solar PV generation can operate at any one time, and
what the limits are NEM-wide and for individual regions.
• How close NEM regions are to these security limits now, and how close they are expected to be by 2025.
• Actions that can overcome these barriers so the system can operate securely with higher penetrations of
wind and solar generation.
It is published as part of AEMO’s responsibilities under section 49(2) of the National Electricity Law.
DISCLAIMER
This document or the information in it may be subsequently updated or amended. This document does not
constitute legal or business advice, and should not be relied on as a substitute for obtaining detailed advice
about the National Electricity Law, the National Electricity Rules, or any other applicable laws, procedures or
policies. AEMO has made every reasonable effort to ensure the quality of the information in this document
but cannot guarantee its accuracy or completeness.
This publication does not include all of the information that an investor, participant or potential participant in
the National Electricity Market might require, and does not amount to a recommendation of any investment.
Anyone proposing to use the information in this publication (which includes information and forecasts from
third parties) should independently verify its accuracy, completeness and suitability for purpose, and obtain
independent and specific advice from appropriate experts.
Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants
involved in the preparation of this document:
• make no representation or warranty, express or implied, as to the currency, accuracy, reliability or
completeness of the information in this document; and
• are not liable (whether by reason of negligence or otherwise) for any statements or representations in this
document, or any omissions from it, or for any use or reliance on the information in it.
VERSION CONTROL
© 2020 Australian Energy Market Operator Limited. The material in this publication may be used in
accordance with the copyright permissions on AEMO’s website.
Executive summary
The Renewable Integration Study (RIS) is the first stage of a multi-year plan to maintain system security in a
future National Electricity Market (NEM) with a high share of renewable resources. AEMO’s findings and the
actions in this report reflect both its day-to-day experience operating the NEM power system, and the results
of extensive RIS modelling and analysis.
In its Integrated System Plan (ISP), AEMO identifies futures for the NEM that maximise consumer benefits at
the lowest system cost, while meeting reliability, security, and emissions expectations. Under every ISP
scenario, the NEM’s least-cost future features large increases in renewable generation – utility wind and solar
connected to the grid and distributed solar photovoltaics (DPV) installed by households and businesses – with
dispatchable generators, large-scale and distributed energy storage, demand side participation, and sector
coupling (such as with gas and transport).
This Stage 1 RIS report takes the ISP’s projections as given and investigates in detail the challenges in the
short term, to 2025, of maintaining power system security while operating this resource mix at very high
instantaneous penetrations1 of wind and solar generation. It recommends actions and reforms needed to
keep operating the NEM securely, now and as the power system transitions. AEMO looks forward to
engaging with stakeholders to refine and progress the recommended actions, including assessing the
potential roles of both existing and emerging technologies.
With this report, AEMO aims to provide foundational engineering perspectives for the ISP, Energy Security
Board (ESB), industry, market institutions, and policy-makers. The RIS’s technical perspectives will ideally
inform future investments, regulations, and market designs to securely operate the NEM power system with
very high instantaneous penetrations of wind and solar generation.
In summary, this Stage 1 RIS analysis finds that, in the next five years:
• The NEM power system will continue its significant transformation to world-leading levels of
renewable generation. This will test the boundaries of system security and current operational
experience.
• If the recommended actions are taken to address the regional and NEM-wide challenges identified,
the NEM could be operated securely with up to 75% instantaneous penetration of wind and solar 2.
• If, however, the recommended actions are not taken, the identified operational limits will constrain
the maximum instantaneous penetration of wind and solar to between 50% and 60% in the NEM.
Beyond 2025, AEMO has not identified any insurmountable reasons why the NEM cannot operate
securely at even higher levels of instantaneous wind and solar penetration, especially with ongoing
technological advancement worldwide.
Given the pace and complexity of change in the NEM, the RIS highlights the need for flexible market
and regulatory frameworks that can adapt swiftly and effectively as the power system evolves.
1
Instantaneous penetration of wind and solar is the half-hourly proportion of underlying demand that is met by wind and solar resources.
2
In recommending actions and highlighting positive potential outcomes, AEMO does not underestimate the extent of work that will be required to
successfully adapt the NEM. This includes the ongoing need for system limits that at times constrain the output of various generation sources. This study
also identified a number of uncharted operating conditions emerging in the NEM by 2025. AEMO will continue investigation and analysis to identify and
address additional limits and barriers that emerge.
3
AEMO’s October 2019 RIS report on how Australia compares with other international power systems is at https://www.aemo.com.au/energy-
systems/Major-publications/Renewable-Integration-Study-RIS.
4
Network congestion is when the network is not capable of securely transporting the output from one or several wind or solar resources.
System curtailment is when renewables are limited due to a need to maintain minimum levels of essential system services for system security.
Participant spill is when renewable generation removes itself from the market (self-curtails) due to market signals.
5
At https://aemo.com.au/-/media/files/electricity/nem/network_connections/west-murray/transforming-australias-energy-system--west-murray.pdf?la=
en&hash=ED13D8375B1E37626EEAFC86C59622EE.
6
For more information, see https://www.wa.gov.au/organisation/energy-policy-wa/energy-transformation-strategy.
Figure 1 Instantaneous penetration of wind and solar generation, actual in 2019 and forecast for 2025
under ISP Central and Step Change generation builds
Note: Penetration on this graph represent NEM half-hourly wind and solar generation divided by the underlying demand which includes
demand response, energy storage, and coupled sectors such as gas and the electrification of transport.
Identifying and quantifying existing and emerging limits, and actions to manage them
As the penetration of wind and solar on the system increases, operation of the system becomes significantly
more complex. The power system is being operated closer to its known limits more frequently, with
increasingly variable and uncertain supply and demand, and declines in system strength and inertia.
The knowledge, tools, and market frameworks of the past are becoming less effective, and operators must
adapt processes and tools, and train operators to be able to keep the system of the future secure.
The key system security challenges10 that are being, and will need to be, addressed as wind and solar
generation penetration continues to rise across all NEM regions are summarised in Table 1. The table also
contains a summary of recommended actions to address identified limits.
7
The NEM power system’s underlying demand (total demand met from all sources, including distributed resources) ranges from 16 to 35 GW.
8
See https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/future-grid/renewable-integration-study.
9
Central and other 2020 ISP scenario assumptions are at https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-
and-planning/scenarios-inputs-assumptions-methodologies-and-guidelines.
10
For definitions of terms used in this study, see AEMO’s Power System Requirements paper, at https://www.aemo.com.au/energy-systems/electricity/
national-electricity-market-nem/system-operations/future-grid.
• Understanding of the changing power system evolves. As part of its post-2025 market design program, the ESB is assessing market mechanisms
that increase certainty around system dispatch of energy and essential system services
• Requirements for system services change.
(inertia, system strength, minimum synchronous units, operating reserves, and flexibility)
• Technology evolves. as real time approaches. The ESB will recommend a high level design to the COAG Energy
Council by end of 2020 for implementation by 2025.
2020 In progress
The growth in wind and solar is increasing the complexity of 2.4 AEMO to develop a detailed proposal outlining requirements, timing, and method to
the system. This creates challenges for existing tools and achieve specified NEM high-speed monitoring (phasor measurement units) to cover more
processes used for system security analysis and assessment. points, allowing better visibility of performance of the system, and help operators to
Tools and processes used to model the system, assess outages, understand the changing power system.
and measure system performance are becoming increasingly
2020-25 In
computationally complex and more costly in time and resources. 2.5 AEMO to collaborate with industry and other world-leading power system operators
progress
to develop new operational capability, allowing better analysis of complex security
phenomena and optimisation for a power system with world-leading levels of renewable
generation (inverter-based, variable and decentralised), storage, and demand side
participation.
2020-21 New
System dispatchability is decreasing as invisible and 3.4 AEMO to collaborate with industry to:
uncontrolled DPV increases to levels not experienced
• Mandate minimum device level requirements to enable generation shedding
elsewhere globally. In 2019, South Australia operated for a
capabilities for new DPV installations in South Australia (other NEM regions and
period where 64% of the region’s demand was supplied by DPV;
Western Australia encouraged).
by 2025, all mainland NEM regions could be operating above
50% at times. • Establish regulatory arrangements for how distribution NSPs (DNSPs) and aggregators
could implement this as soon as possible.
• Investigate the need for updating the existing DPV fleet to comply with regional
generation shedding requirements.
2020-21 New
3.5 AEMO to collaborate with DNSPs to establish aggregated predictability or real-time
visibility requirements for DPV systems available for curtailment, and consistent real-time
SCADA visibility for all new commercial scale (> 100 kilowatt [kW]) systems.
NEM inertia levels could drop by 35%. Historically, NEM 4.2 AEMO to publish a detailed frequency control workplan covering tasks and 2020 New
mainland inertia has never been below 68,000 megawatt timeframes to:
seconds (MWs). By 2025, inertia could drop to as low as
• Revise ancillary service arrangements to ensure the required speed and volume of PFR
45,000 MWs. This will increase the required volume and/or
match the size of the Largest Credible Risk (LCR) and Frequency Operating Standard
speed of frequency sensitive reserve following a contingency
(FOS) containment requirements for the range of expected future operating conditions.
event, and the power system will operate in configurations
where the system dynamics are different to those experienced • Investigate the introduction of a system inertia safety net for the mainland NEM, under
today. system intact conditions. This minimum level safety net should be progressively revised
as operational experience is built and additional measures are put in place to ensure
DPV behaviour, inverter-based resources (IBR) behaviour,
system security. Investigation should include specifying the initial value and how the
and run-back schemes are making the system more complex.
safety net will be maintained.
These emerging issues will further exacerbate post-contingent
outcomes for credible and non-credible events. Non-credible • Investigate the effect of higher RoCoF on DPV, utility-scale generation, switched reserve
contingencies are expected to result in higher rate of change of providers, and protection relays used in various network functions. The result of this
frequency (RoCoF), the effect of which is not yet fully understood investigation will be a recommended system RoCoF limit, or set of RoCoF limits, in
for the NEM. addition to existing generator ride-though requirements. Investigation should include
assessment of the adequacy of Emergency Frequency Control Schemes (EFCS),
including Under Frequency Load Shedding (UFLS), under decreasing levels of inertia.
• Continue investigation into DPV penetration into UFLS load blocks.
• Apply appropriate limits to the total proportion of switched reserve. This is needed to
ensure there is a minimum amount of dynamic frequency control.
• Investigate appropriate regional contingency frequency control ancillary services (FCAS)
requirements, particularly for South Australia and Queensland.
• Update AEMO’s existing system frequency model to be able to predict post-contingent
frequency outcomes based on generating unit dispatch. Development of this model will
benefit from the capture of high-speed generator output and network quantities on a
routine or ongoing basis.
Stable voltage The NEM is at the international forefront of managing issues 5.1 AEMO to pursue opportunities to improve the minimum system strength framework 2020 In progress
waveform associated with low system strength; AEMO has so far and improve system strength coordination across the NEM, including:
(system strength) declared system strength gaps and worked with local
• AEMO to contribute latest findings and insights into ongoing ESB and AEMC reviews of
Ability to transmission NSPs (TNSPs) to address shortfalls in South
system strength frameworks.
maintain the Australia, Tasmania, Victoria, and Queensland. Localised system
voltage strength challenges are also creating increasing hurdles for • Following conclusion of the AEMC’s investigation into system strength frameworks in
amplitude, generators seeking to connect in weaker parts of the grid. the NEM, AEMO to assess the need for changes to the System Strength Requirements
waveform and Methodology and System Strength Impact Assessment Guidelines.
phase angle
under system • AEMO to progress planned actions (see Section 5.3.3) as part of the Final 2020 ISP.
normal and
contingent
conditions within
specifications
In progress
Resource The magnitude of peak ramps (upward/downward AEMO is investigating redeveloping its PASA systems (PD and ST) to better account for
adequacy fluctuations in supply/demand) is forecast to increase by system ramping requirements. See recommendation 2.2.
(managing 50% over the next five years as a result of increasing wind and
variability and solar penetration. Operators need to ensure there is adequate
uncertainty) system flexibility to cover increased variability across all times.
A sufficient
portfolio of 2020-21 New
energy There is a limit to the accuracy of deterministic forecasts of 6.1 AEMO to improve understanding of system uncertainty and risk, particularly during
resources to expected ramps, even using current best practice approaches. ramping events, by exploring:
balance supply Forecasting limitations increase uncertainty and the need for
• Trialling and implementing a ramping forecast and classification prototype.
and demand in greater ramping reserves.
every 5-minute • Deploying additional weather observation infrastructure that is fit for purpose for the
interval energy industry.
Ensuring sufficient flexible system resources are available to The ESB is exploring options for explicitly valuing flexibility and incorporating this into In progress
enable increased variability at times of high wind and solar scheduling and dispatch mechanisms. See recommendation 2.3.
penetration will become increasingly challenging. Times
characterised by low interconnector headroom (spare capacity) 6.2 Improve the reliability of information provided by participants (loads, and scheduled 2020-21 In progress
or ‘cold’ offline plant will be particularly difficult to manage. and semi-scheduled generation) to support security-constrained dispatch. The ESB is
coordinating several interim measures to improve the visibility of and confidence in
resources in the NEM, to ensure security can be maintained while new market
arrangements are developedB.
A. See http://www.coagenergycouncil.gov.au/sites/prod.energycouncil/files/ESB%20Post2025%20Directions%20Paper.pdf.
B. For more information on interim security measures, see http://www.coagenergycouncil.gov.au/interim-security-measures.
11
The zones in this figure are indicative only and have been aggregated up from regional limits (Queensland, New South Wales, South Australia, Tasmania,
Victoria).
12
This study also identified a number of uncharted operating conditions emerging in the NEM by 2025. AEMO will continue investigation and analysis to
identify and address additional limits and barriers that emerge.
Note: Penetration values on this graph represent non-overlapping half-hourly wind and solar generation divided by total underlying
demand across the NEM during the same half-hours. Actual 2019 penetration includes all curtailment; 2025 projections only include
network congestion.
Next steps
In recommending actions and highlighting positive potential outcomes, AEMO does not underestimate the
extent of work that will be required to successfully adapt the NEM.
This Stage 1 RIS has been a large undertaking and explored several critical power system security questions in
detail; however, its scope has been bound by the assumptions outlined throughout the report and
appendices. There are also several areas for further study arising as a result of the RIS findings. This means
there is a need for continued efforts on several fronts to build on these Stage 1 findings.
In addition, the NEM power system and market dynamics evolve daily, and a large body of work is already
underway across many organisations to explore different changes in the power system and energy markets.
Given the high level of complexity and inter-relatedness of power system security challenges, AEMO sees a
need to facilitate greater clarity among stakeholders regarding the priority focus as the generation mix
transitions.
Key next steps following the publication of this report include:
• An open and transparent stakeholder engagement process to discuss the findings and actions arising
from this report and priority focus areas for the future.
• Exploring the findings and insights from this work with regulatory bodies and policy-makers to help inform
ongoing reform processes. Given the pace and complexity of change in the NEM, the RIS highlights the
need for flexible market and regulatory frameworks that can adapt swiftly and effectively as our
understanding of the changing power system evolves.
• Incorporating relevant findings as part of the Final 2020 ISP.
• Undertaking identified actions to address limits.
• Scoping and commencing areas of further study, including but not limited to the resilience of a high
renewable future system to complex system events, and a study of the latest advancements in inverter
technology.
• Building on the Stage 1 RIS findings and subsequent stakeholder engagement, developing (by Q2 2021) a
roadmap for the secure transition to higher penetrations of wind and solar in the NEM, including key
study areas, actions, and reforms.
1. Introduction 18
1.1 Why AEMO is doing the Renewable Integration Study (RIS) 18
1.2 How the RIS scope was developed 20
1.3 Stage 1 scope 21
1.4 Report structure 24
2. System operation 25
2.1 How operators understand the power system 25
2.2 How the NEM power system is securely operated 27
2.3 Challenges to system operation 28
2.4 Operating the NEM with high renewable penetration 31
2.5 Actions to support system operation 36
3. Distributed solar PV 38
3.1 Increasing distributed solar PV 39
3.2 Impacts on the distribution network 39
3.3 Impacts on the bulk system 40
3.4 Actions to support integration of distributed solar PV 42
4. Managing frequency 44
4.1 Changing system conditions 44
4.2 Changing requirements for frequency sensitive reserve 45
4.3 Fast Frequency Response (FFR) 46
4.4 Managing new types of risk 47
4.5 Managing the transition to lower inertia 47
4.6 Actions to support frequency management 48
5. System strength 50
5.1 Current regulations 50
5.2 Changes to system strength 51
5.3 Managing system strength 53
5.4 Actions to support system strength 54
8. Next steps 67
8.1 Managing the transition 67
8.2 Future work 67
8.3 Implications for the Integrated System Plan 68
8.4 Stakeholder engagement 69
9. Reference resources 70
Abbreviations 74
Tables
Table 1 Managing power system requirements – summary of key challenges and actions 8
Table 2 Overview of RIS approach to studying impacts of increasing wind and solar
penetration in the NEM on power system requirements and operational pre-
requisites 22
Table 3 Dispatch and pre-dispatch 27
Table 4 Current inertia and system strength shortfalls in the NEM 29
Table 5 Challenges and actions – system operation 37
Table 6 Historical (2019) and projected (2025) maximum instantaneous penetration of DPV 39
Table 7 Summary of DPV integration issues experienced by DNSPs 40
Table 8 Challenges and actions – distributed solar PV 43
Table 9 Existing and proposed inertia limits 48
Table 10 Challenges and actions – frequency 49
Table 11 Challenges and actions – system strength 55
Table 12 Actions – variability and uncertainty 61
Table 13 RIS engagement activities and timeline 69
Table 14 Relevant AEMO publications 70
Figure 4 Installed wind and solar capacity in the NEM for 2019, with 2025 and 2040 forecasts from the Draft
2020 ISP Central and Step Change generation builds
Solar is split into the capacity of utility solar farms and the capacity of DPV systems, installed behind the meter on residential and commercial consumer
premises. Behind the meter battery includes both projected virtual power plants (VPPs) and passive batteries projected by the ISP. Utility storage includes
both utility-scale battery and pumped hydro.
13
AEMO, RIS International Review, October 2019, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-
Systems/2019/AEMO-RIS-International-Review-Oct-19.pdf.
14
At https://www.aemo.com.au/energy-systems/major-publications/integrated-system-plan-isp.
15
Throughout this report, the year refers to the financial year ending – for example, 2019 means the 2018-19 financial year.
Figure 5 Instantaneous penetration of wind and solar generation, actual in 2019 and forecast for 2025
under ISP Central and Step Change generation builds
Note: Penetration on this graph represent NEM half-hourly wind and solar generation divided by the underlying demand, which includes
demand response, energy storage, and coupled sectors such as electrification of gas and transport. Actual 2019 penetration includes all
lost energy; 2025 projections include network congestion but do not include system curtailment or participant spill.
This report explores the extent to which these outcomes might be achievable from a security perspective, and
the actions needed to enable them.
The findings from the RIS are being incorporated into AEMO’s Final 2020 ISP, ensuring the ISP presents a
future power system that will be operable.
16
For more information, see https://www.wa.gov.au/organisation/energy-policy-wa/energy-transformation-strategy.
17
At https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Power-system-requirements.pdf.
To maximise the value of the RIS to all stakeholders, AEMO considered the following factors when scoping
RIS Stage 1:
• Reviewing leading international experience in wind and solar integration – this culminated in the RIS
International Review published in October 201918.
• Where possible, prioritising the study of power system phenomena most likely to need managing in order
to operate the NEM at high penetrations of wind and solar generation.
• Prioritising areas of study that expand the available analysis on operating a high renewable NEM, noting
the volume of previous or concurrent investigations in the NEM19.
• Using the projected generation builds under Draft 2020 ISP scenarios developed in consultation with
industry.
• Choosing a target year for detailed analysis that strikes a reasonable balance between having the potential
for very high periods of wind and solar generation and not being too far into the future. AEMO chose
2025 as the horizon for this study because it is far enough to provide insights into future operating
patterns, and close enough for system conditions to be forecast with greater confidence based on existing
mechanisms and technologies.
Stage 1 of the RIS was established to be a technical analysis of system security limits NEM-wide and for NEM
regions. While it identifies recommended actions that would meet the system’s technical needs, it does not
investigate the costs of proposed actions or all the specific mechanisms that could be implemented. These
questions will be explored further as part of future work and other workstreams such as the ISP and the ESB’s
and Australian Energy Market Commission’s (AEMC’s) market reform processes.
18
AEMO, RIS International Review, October 2019, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-
Systems/2019/AEMO-RIS-International-Review-Oct-19.pdf.
19
See Chapter 9 in this report for relevant AEMO publications into the changing generation mix.
System operability – predictability and • Assessed how increasing wind and solar are impacting Chapter 2
dispatchability operability of the system, including the challenges of
Ability to forecast upcoming power system conditions, managing increasing uncertainty and interventions.
have confidence in how the system will perform, and
sufficient controls to manage dispatch and configure
power system services to maintain system security and
reliability
Integration of distributed solar PV (DPV) • Surveyed issues identified by distribution network Chapter 3 and
service providers (DNSPs) as levels of DPV increase. Appendix A
Balancing increasing levels of small, distributed PV
with power system requirements • Assessed bulk system limits for actual and 2025
projections of DPV penetration in each NEM region.
Frequency management • Assessed potential changes in online system inertia Chapter 4 and
under a range of plausible future dispatch Appendix B
Ability to set and maintain system frequency within
configurations
acceptable limits
• Analysed frequency control outcomes for different
combinations of inertia, primary frequency response,
load relief, and secondary risks.
Stable voltage waveform (system strength) • Compared historical synchronous machine dispatch Chapter 5
against potential 2025 dispatch outcomes.
Ability to maintain the voltage waveform and phase
angle under system normal and contingent conditions • Summarised parallel system strength work programs
assessing emerging fault level shortfalls, minimum
synchronous machine requirements, and local stability
challenges for wind and solar.
There are also several technical areas of high importance that are not being studied in the RIS, because
AEMO understands they are being evaluated in other programs of work and they do not relate to a system
curtailment limits on renewables during normal operating conditions. These include:
• More traditional power system limits and stability analyses 20 – given their extensive coverage in the ISP,
network planning processes, and generation connection studies, it was assumed that these traditional
limits would be manageable through existing processes, and would not pose regional or NEM-wide limits
to the penetration of wind and solar generation.
• Assessing system limitations at the local, sub-regional level, such as generator connection issues – these
are being, or will be, addressed in other projects and publications.
20
Traditional system limits that will continue to be assessed and managed via other processes include thermal limits, voltage stability, transient and
oscillatory stability, and local voltage management (management of pre and post contingent bus voltages).
21
The Reliability Standard, from the AEMC’s Reliability Panel, specifies that expected unserved energy (energy that cannot be supplied to meet consumer
demand because there is not enough available generation capacity, demand response, or network capability) should not exceed 0.002% of total energy
consumption in any NEM region in any financial year.
22
Study horizon refers to the period that is studied.
As outlined in chapters 3 to 6, increasingly variable and uncertain supply and demand, and declines in
system strength and inertia, have moved the system to its limits, reducing its resiliency and increasing the
risk to the system for complex events. The knowledge and tools operators have used in the past to
operate the system securely are now less effective and need to be adapted.
For example, intervention by AEMO has always been a part of operating a secure NEM, but where it was
used rarely in the past as a last resort to manage specific issues on the grid, it has now become
commonplace, especially in regions with higher shares of renewable generation (South Australia,
Tasmania, and Victoria). This RIS analysis projects that under the current market design the need for
interventions to address system security requirements will grow across all NEM regions.
Successfully managing the system’s increased uncertainty and operational complexity will require
different approaches and better co-ordination of all resources. The existing dispatch process for the NEM
was not designed for these new conditions, and the current reliance on operators to balance factors and
intervene is sub-optimal and unsustainable.
To manage the system of the future efficiently, operators will require:
• Improvements to existing frameworks, giving operators increased certainty around system conditions
that converge as real time approaches.
• Access to new and better sources of information to understand the changing system complexity.
• New operational processes, training, and tools to design and manage an increasingly complex system.
As the entity responsible for operation of the NEM, AEMO is committed to ensuring the system can operate
securely, reliably, and efficiently with increasing penetrations of wind and solar resources.
This chapter:
• Summarises AEMO’s understanding and experience of operating the current power system.
• Highlights the current challenges and actions that have been taken to adapt the system to securely
operate regions of the NEM with world-leading levels of renewables.
• Explores the actions required to accommodate the projected penetration of wind and solar across the
NEM, and ensure operational processes, tools and market reforms are in place for the continued secure
operation of the grid.
This chapter is a precursor to the remaining chapters of the report, which study the specifics of the changing
system and actions needed to manage these evolving system conditions.
23
See p. 4, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-Systems/2019/AEMO-RIS-International-
Review-Oct-19.pdf.
Pre-dispatch Dispatch
Resolution and timeframe 30-minute resolution out to the following trading day 5-minute resolution for the next five
minutes
Purpose • Provides market (including energy and FCAS) Used to run the market. Provides
information to participants to allow them to make instructions to generators (and scheduled
informed decisions. loads) on how much to produce (or
consume), subject to a security constrained
• Provides AEMO with information to allow it to fulfil
process.
its duties in relation to system reliability and security,
in accordance with the NER.
NEMDE is set up to ensure the system remains operating within its physical limits. Historically, these limits
have mainly been associated with keeping the system within its maximum physical limits, including loading
on the network and interchange between regions. It achieves this by providing instructions on the amount of
energy provided from each scheduled generator and the maximum amount of energy provided from each
semi--scheduled generator.
As the generation mix has changed, new emerging limits are predominantly associated with operating near
the system’s minimum physical limits. Examples include synchronous unit requirements to maintain fault
levels, inertia requirements, operating reserves, and limits associated with low levels of operational demand.
24
NEMDE is a central computer system that takes bid information, demand forecasts, network constraint information, and other information as input
variables, and every five minutes determines market spot prices and which combination of generators should be dispatched to meet demand for the next
5-minute period at the least cost.
25
In the case of thermal constraint equations only, there is a facility which can develop these constraint equations automatically in close to real time based
on current system conditions. This is currently only used when there are no appropriate constraints in the library.
26
See https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/system-operations/power-system-operation/power-system-
operating-procedures.
27
A 5-minute pre-dispatch schedule is also produced at a 5-minute resolution for an hour ahead, although this process is not currently required in the
National Electricity Rules (NER).
28
These and other operating procedures are outlined in AEMO, Power System Security Guidelines, SO_OP_3715, at https://www.aemo.com.au/energy-
systems/electricity/national-electricity-market-nem/system-operations/power-system-operation/power-system-operating-procedures.
29
Current RERT Guidelines (2019) are at https://www.aemc.gov.au/market-reviews-advice/review-reliability-and-emergency-reserve-trader-guidelines-2019.
South Australia Regional fault level shortfall Directions for system strength. Since Installation of high inertia
declared in October 2017. July 2017, directions have been in place synchronous condensers by
17% of the time. ElectraNet as South Australian TNSP
by 2021A.
Regional inertia shortfall Directions for inertia and FCAS required
declared in December 2018. under credible risk of islanding.
Victoria Inertia and fault level Hold points on NW Victoria generation Under study by AEMO as Victorian
shortfalls in West Murray to manage stability until system Jurisdictional planner.
declared in 2019. strength remediation is completeB.
Tasmania Regional inertia and fault TasNetworks has negotiated the provision of inertia network services and
level shortfalls declared in system strength services under contract from a provider within the Tasmanian
November 2019. region offering suitable synchronous condenser capabilities.
Queensland System strength shortfall Constraints for system strength are Under study by Powerlink, as the
declared in North currently implemented, requiring local TNSP, with system strength
Queensland in April 2020. minimum synchronous unit services to be implemented by
combinations and curtailing wind and 31 August 2021.
solar under certain conditions.
A. See https://www.electranet.com.au/what-we-do/projects/power-system-strength/.
B. See case study on increasing IBR in north-west Victoria at the end of Section 2.4.
Projecting shortfalls is a difficult process, because it is highly dependent on the behaviour of generators in the
energy market, which can change much faster than shortfalls can be declared and addressed.
Even if a shortfall is accurately projected, there are additional challenges:
• There is a lag between when a shortfall is identified and when it can be remediated. In the interim, before
solutions are contracted, temporary solutions – including additional use of directions – may be required to
manage the system.
• Under current market arrangements, these resources may not be dispatched efficiently:
– An operational tool and market mechanism are needed to schedule these services.
– Further co-ordination between markets is required where multiple providers are capable of providing
several services (such as energy, FCAS, and inertia services).
30
For more information about system strength, see AEMO, System Strength: System Strength in the NEM Explained, March 2020, at https://aemo.com.au/-
/media/files/electricity/nem/system-strength-explained.pdf?la=en.
31
See NER clause 5.20B.3 and 5.20B.4.
32
AEMO, RIS International Review, October 2019, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-
Systems/2019/AEMO-RIS-International-Review-Oct-19.pdf.
33
Note simulation run times are variable and are highly dependent on model development, complexity and the software/methodology used to run. These
estimates are based on the current tools used by AEMO, noting full system EMT models are early in their deployment.
2.4 Operating the NEM with high wind and solar penetration
As the system continues to change rapidly, there is a need to reconsider various aspects of system design and
operational tools to ensure operational processes, tools, and market reforms are in place for the continued
secure operation of the grid.
Successfully managing a power system with increased operational complexity will need more efficient
co-ordination of all resources. This will require better information-sharing across operators and participants,
and reduced uncertainty where possible so the right resources can be scheduled at the right time in an
efficient way.
To manage the system of the future efficiently, operators will require:
• Improvement to existing frameworks that give operators increased certainty around system conditions
that converge as real time approaches.
• Access to new and better sources of information to understand the changing system complexity.
• New operational processes, tools, and operator training to manage the changing system complexity.
This section provides examples of measures being used to keep the NEM operating securely now:
34
The summer operational period spans from November to March (inclusive). In summer, the power system must manage additional risk as it responds to
high consumer energy demand, increasing periods of high temperatures, and climatic events including bushfires and storms. To get the best capacity
from networks over this period, outages (including generation and transmission equipment) are minimised, where this does not increase any risk to future
reliability of equipment or present a safety issue. See AEMO’s Summer Readiness 2019-20 plan, at https://www.aemo.com.au/-/media/Files/Electricity/
NEM/System-Operations/Summer-2019-20-Readiness-Plan.pdf.
35
For example, in north-west Victoria, for generators connected to network assets undergoing maintenance there may be periods where they are curtailed
to manage system security. See https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Congestion-Information/2019/Planned-
outages-in-the-North-Western-VIC-and-South-West-NSW-transmission-network-industry-communique.pdf.
36
Every day, AEMO publishes the Pre-Dispatch Projected Assessment of System Adequacy (PD PASA) for the following day, and the Short-Term Projected
Assessment of System Adequacy (ST PASA) looking two to seven days ahead. The LOR assessment horizon is from the current time to the end of the
period covered by the most recently published ST PASA.
37
See AEMO’s Reserve Level Declaration Guidelines for more information, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_
Reliability/Power_System_Ops/Reserve-Level-Declaration-Guidelines.pdf.
38
The FUM was implemented in AEMOs production systems in February 2018.
39
AEMO’s Quarterly Energy Dynamics (QED) reports show the increasing proportion of time that units are being directed in South Australia and Victoria and
the increasing cost of these directions. This is particularly evident in the 2019 Q4 QED (pg. 25), at https://aemo.com.au/-/media/files/major-publications/
qed/2019/qed-q4-2019.pdf?la=en&hash=A46E0A510AE9F127B0A991B312C54460. For more information on trends in directions, see AEMO’s Quarterly
Energy Dynamics reports, at https://aemo.com.au/energy-systems/major-publications/quarterly-energy-dynamics-qed.
40
The number of hours represents the period of time a direction was effective in the NEM.
Separation event: at approximately 13:24, the collapse of several steel transmission towers on the Moorabool –
Mortlake and Moorabool – Haunted Gully 500 kilovolt (kV) lines resulted in the tripping of these lines and the
separation of South Australia from Victoria.
Managing the system on the day: manual intervention and additional monitoring by the control room and support
staff was required:
• Manual management of wind farm availability (reliability) – a doubling of dedicated staff was required to
manage the power system. The additional staff were required to actively identify wind sites at risk of de-rating,
monitor output from the sites, and contact plant operators for updated information if significant deviations
between actual output and expected availability occurred.
• Reliability and Emergency Reserve Trader (RERT)41 – AEMO dispatched up to 185 MW of RERT in Victoria and
134 MW in New South Wales between 15:30 and 21:30, involving activation of 15 contracts across both states, with
five of the contracts requiring pre-activation. An additional two contracts in New South Wales and one contract in
Victoria were pre-activated, but not activated in response to the LOR2 conditions.
• Other – AEMO issued one direction to keep non-scheduled wind farms offline to control flows on the Heywood
(Victoria – South Australia) interconnector.
Subsequent management of separation: in the 17 days following 31 January, while South Australia was operating as
an extended island42, significant manual intervention was required by the control room. The interventions included43:
• System strength (security) – AEMO issued 18 directions44 for synchronous generators to remain synchronised in
South Australia. This meant AEMO was intervening in the market 100% of the time between 1 February 2020 and
17 February 2020.
• FCAS – AEMO issued 25 directions for the provision of FCAS in South Australia – 15 directions to generators to be
synchronised to provide reserve, and 10 directions of batteries to 0 MW output and a specified state of charge so
they could provide raise and lower reserve and allow operators to re-secure the system within 30 minutes in the
event of a contingency.
• Reliability – AEMO issued two directions for generators in order to service essential loads in the area.
• Other – AEMO issued 25 directions to semi-scheduled and non-scheduled wind farms to disconnect or reduce
MW output (usually 0 MW).
41
RERT is an intervention mechanism under the NER that allows AEMO to contract for emergency reserves such as generation or demand response that are
not otherwise available in the market, as a safety net in the event that a critical shortfall in reserves is forecast.
42
The South Australia extended island consisted of the South Australia region and the elements of the Victorian network east of the Tarrone and Mortlake
substation, including the Alcoa Portland Smelter (APD).
43
Some directions were issued for both system strength and FCAS. A total of 65 directions was issued between 31 January 2020 and 17 February 2020.
44
One direction was issued at 21:00 on 31 January 2020, after the separation event.
An increasing penetration of wind and solar operating in the system 2.1 AEMO to identify and evaluate standard operational process, control room tools, and 2020 In progress
is pushing the system to minimum limits. The existing dispatch process operator training to operationalise intervention (directions/instructions) for system strength
for the NEM was not designed for managing minimum conditions and inertia services under the current framework.
(particularly managing the commitment of synchronous units to maintain
minimum levels of inertia and system strength). The current reliance on 2.2 AEMO to redevelop existing scheduling systems (Pre-Dispatch [PD] and Short Term [ST] 2020-22 In progress
operators to balance factors and intervene is sub-optimal as system PASA) to better account for system needs, including:
variability, uncertainty, and complexity increases. Without effective and
• Availability of essential system services, including inertia, system strength, and ramping
standardised operational process, tools, and training to schedule system
requirements.
strength and inertia services, the risk of human error grows, and the level
of intervention becomes increasingly unsustainable. • Catering for cross-regional sharing of reserves.
Further, the market design needs to adapt so all essential security and • Better modelling of new technologies, including VRE, batteries and DER (including demand
reliability services are provided efficiently, when required, and without response and VPPs).
operator intervention. Given the pace and complexity of change in the
2020-25 In progress
NEM, there is a need for flexible regulatory frameworks (particularly 2.3 Consistent with the outcomes of this study, the ESB considers that security constrained
technical standards and frameworks for sourcing system services) that can economic dispatch of energy-only is, by itself, no longer sufficient to maintain system
adapt swiftly and effectively as: security. The ESB considers that new system services need to be established and
remunerated and an ahead market is required to ensure system security going forwardA.
• Understanding of the changing power system evolves.
As part of its post-2025 market design program, the ESB is assessing market mechanisms
• Requirements for system services change.
that increase certainty around system dispatch of energy and essential system services
• Technology evolves. (inertia, system strength, minimum synchronous units, operating reserves, and flexibility) as
real time approaches. The ESB will recommend a high level design to the COAG Energy
Council by end of 2020 for implementation by 2025.
The growth in wind and solar is increasing the complexity of the 2.4 AEMO to develop a detailed proposal outlining requirements, timing, and method to 2020 In progress
system. This creates challenges for existing tools and processes used for achieve specified NEM high-speed monitoring (phasor measurement units) to cover more
system security analysis and assessment. Tools and processes used to points, allowing better visibility of performance of the system, and help operators to
model the system, assess outages, and measure system performance are understand the changing power system.
becoming increasingly computationally complex and more costly in time
and resources. 2.5 AEMO to collaborate with industry and other world-leading power system operators to 2020-25 In progress
develop new operational capability, allowing better analysis of complex security phenomena
and optimisation for a power system with world-leading levels of renewable generation
(inverter-based, variable and decentralised), storage, and demand side participation.
A. A. See http://www.coagenergycouncil.gov.au/sites/prod.energycouncil/files/ESB%20Post2025%20Directions%20Paper.pdf.
Australia has experienced strong growth in DPV generation over the last decade, with parts of the NEM
now at world-leading levels. AEMO expects this growth to continue over the next decade. Most DPV
systems in the NEM today operate in a passive manner – they are not subject to the same performance
requirements as large-scale sources and are not visible or controllable by distribution network service
providers (DNSPs) or AEMO, even under emergency conditions.
DNSPs have begun to experience technical challenges associated with increasing passive DPV
penetration, and have started to implement measures to improve hosting capacity.
At the bulk system level, the aggregated passive DPV fleet is impacting AEMO’s ability to securely operate
the South Australian region today, through:
• Increasing contingency sizes, associated with the potential mass disconnection of DPV systems
following plausible bulk system disturbances, eventually becoming unmanageably large, especially for
regions of the NEM that may operate as islands under some conditions.
• Ongoing reduction in the daytime system load profile, first impacting availability of the stable load
blocks necessary for the effective operation of critical emergency mechanisms in the daytime, and
eventually to the point of insufficient load to support minimum synchronous generation levels.
Under current DPV growth projections, without action, growing passive DPV generation will also impact
system operation in other NEM regions by 2025.
AEMO’s full analysis relating to the implications of increasing levels of DPV is in Appendix A.
DPV generation already exceeds the largest scheduled generator in the NEM today. There is already 9 GW of
DPV installed in the NEM today; by 2025, this is projected to increase to 12 GW in the Central scenario and
19 GW in the Step Change scenario.
Given the already high levels across the NEM, and expected growth into the future, this part of the RIS
considers the power system challenges associated with increasing levels of passive DPV generation. Better
integrating this fleet with the needs of the power system, through improved performance standards and
minimum levels of curtailability, will help to address some of these challenges.
Other forms of DER – such as storage and electric vehicle charging, and demand response – can also assist by
‘soaking up’ excess DPV generation in the daytime, but could also create their own system challenges if not
harnessed effectively. AEMO’s DER Program is considering the range of market and technical enablers for the
secure and efficient integration of DER within our energy systems 45. The ISP projections for these
technologies, as outlined in Section 1.1, have been included in the analysis.
45
For more information on AEMO’s DER Program and the different workstreams, see https://www.aemo.com.au/initiatives/major-programs/nem-
distributed-energy-resources-der-program.
Table 6 Historical (2019) and projected (2025) maximum instantaneous penetration of DPV
Maximum instantaneous DPV penetration (%) Historical (2019) Projected (2025, ISP scenario)
South Australia 64 68 85
Victoria 31 45 66
Queensland 30 45 57
Tasmania 12 14 21
AEMO has an ongoing program of work to better understand the implications of increasing levels of passive
DPV generation on the power system, with a current focus on South Australia47. Lessons from this work have
informed key actions to maintain system security in this region in the short term, and actions to better
integrate the DPV fleet with the future power system operation in other regions.
46
At https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-Systems/2019/AEMO-RIS-International-Review-Oct-
19.pdf.
47
For further information see, https://aemo.com.au/initiatives/major-programs/nem-distributed-energy-resources-der-program/operations
● indicates the DNSP has started to experience the issue in parts of their network or planning for it to arise under current DPV
projections. It does not provide any indication of materiality across the DNSP’s network.
Source: AEMO analysis of DNSP 2019 Annual Planning Reports, workshops with DNSPs in June 2019.
From the bulk system perspective, AEMO expects the growth in regional DPV generation to continue as
uptake continues to grow, and DNSPs implement such measures.
48
More detailed limits are provided and overlaid in Figure XX in Appendix A.
2020 New
Governance structures for the setting of DER technical performance 3.3 AEMO to collaborate with the ESB, Australian Energy Regulator (AER), AEMC, and industry to:
standards, and enforcement of these standards, are inadequate.
• Submit a rule change establishing the setting of minimum technical standards for DER in the NEM
Currently there is:
(with similar reforms to be proposed for Western Australia’s SWIS) covering aspects including power
• No formal pathway to ensure power system security and other industry system security, communication, interoperability, and cyber security requirements.
requirements are accounted for within technical standards set by
• Develop measures to improve compliance with new and existing technical performance standards
consensus.
and connection requirements for DPV systems, individual DER devices, and aggregations in the
• Inconsistent compliance with technical performance standards across NEM (and SWIS).
the DPV fleet today and a lack of clarity around enforcement.
2020-21 New
System dispatchability is decreasing as invisible and uncontrolled 3.4 AEMO to collaborate with industry to:
DPV increases to levels not experienced elsewhere globally. In 2019,
• Mandate minimum device level requirements to enable generation shedding capabilities for new
South Australia operated for a period where 64% of the region’s demand
DPV installations in South Australia (other NEM regions and Western Australia encouraged).
was supplied by DPV; by 2025, all mainland NEM regions could be
operating above 50% at times. • Establish regulatory arrangements for how DNSPs and aggregators could implement this as soon as
possible.
• Investigate the need for updating the existing DPV fleet to comply with regional generation
shedding requirementsA.
2020-21 New
3.5 AEMO to collaborate with DNSPs to establish aggregated predictability or real-time visibility
requirements for DPV systems available for curtailment, and consistent real-time SCADA visibility for
all new commercial scale (> 100 kilowatt [kW]) systems.
A. For the purposes of maintaining adequate levers for secure system operation in abnormal operating conditions during high DPV generation periods, AEMO’s work to date has found:
• Generation shedding capability as a “back-stop” measure is essential; it is required in addition to ongoing investment in storage and development of distributed markets for daily efficient market operation.
• When it is required, the necessary change in the supply-demand balance could be very large and increasing as DPV generation continues to grow.
• Harnessing load and storage flexibility may reduce the amount of DPV generation shedding necessary. However, given uncertainties in the availability of this flexibility in real time, this does not remove the
need for the generation shedding capability to be available in the first place
The contingency FCAS49 markets are responsible for ensuring the amount of frequency sensitive reserve
available can manage the trip of a single generating unit.
Since the introduction of the FCAS markets, the increase in the size of the largest generating unit –
coupled with a decline in system inertia50 and load relief – has changed the physical parameters
underpinning reserve management. The level of inertia is projected to decline further out to 2025. Under
the projected condition, more and/or faster frequency sensitive reserve will be needed.
No large power system currently operates without synchronous inertia, and a minimum level of
synchronous inertia will be needed in 2025. A staged approach to operating at lower inertia is
recommended, to progressively manage the expansion in the operating envelope of the system. This will
allow the system frequency control design to be adapted to the changing system, with capacity built in
advance of the requirement becoming evident on the system.
49
More information on how FCAS markets relate to power system requirements is at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_
Reliability/Power-system-requirements.pdf.
50
System inertia is provided by the aggregate rotating mass from rotating machines that are directly coupled to the grid. Inertial response acts to reduce the
Rate of Change of Frequency (RoCoF) following a disturbance. Under low RoCoF conditions, PFR has more time to respond.
51
Load relief is the change in load that occurs when system frequency changes. It results from the motor component of the load, which draws less power
when frequency is lower and more power when frequency is higher. As more motor load is connected through electronic interfaces, this beneficial system
property is declining.
52
PFR is when a generator measures the local frequency and adjusts its active power output in response. PFR is automatic; it is not driven by a centralised
system of control and begins immediately after a frequency change beyond a specified level is detected.
53
See https://www.aemc.gov.au/sites/default/files/2019-08/Rule%20Change%20Proposal%20-%20Mandatory%20Frequency%20Response.pdf.
54
See https://www.aemc.gov.au/sites/default/files/2019-08/Rule%20Change%20Proposal%20-%20Mandatory%20Frequency%20Response.pdf.
Figure 11 Inertia duration curves – historical (actual) and future range (forecast) of NEM mainland inertia
55
The forecast range indicates the range of forecast modelling output using a range of market dispatch assumptions out to 2025. The minimum extremity of
this range is from the Draft 2020 ISP Short Run Marginal Cost modelling, which can be expected to give a conservatively low inertia forecast. The
Minimum Units line represents the minimum inertia expected to be maintained through system strength requirements
56
See https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Ancillary_Services/Frequency-and-time-error-reports/2019/Update-
on-Contingency-FCAS-Aug-2019.pdf.
57
Modelling methodology and assumptions provided in Appendix B.
58
The static reserve requirement is the amount of active power required to replace the amount tripped less the expected load relief. This is the amount of 6-
second reserve currently procured through the FCAS market under normal conditions.
59
At https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/system-operations/ancillary-services/market-ancillary-services-
specification-and-fcas-verification-tool.
Figure 12 The 6-second reserve requirement for credible events (NEM mainland)
60
Switched FCAS providers are generally large or aggregated loads that can be partially or fully switched off in response to low frequency events.
System Credible trip Mainland: This report recommends investigating the implementation of an initial minimum inertia
intact of Largest safety net within range of the historical minimum inertia level in the mainland, with staged
Credible Risk reduction towards a minimum inertia available thorough system strength requirements
(single unit) (45,350 MWs).
Tasmania: Minimum threshold level of inertia, or secure level of inertia is always applicable.
System Non-credible Regional inertia and reserve levels to survive non-credible separations not generally defined.
intact separation These types of events are subject to periodic review through the Power System Frequency Risk
event Review (PSFRR).
System Credible or Defined as Minimum threshold level of inertia, calculated as per the Inertia Requirements and
intact protected Shortfalls Methodology.
risk of
separation Current values:
Islanded Credible trip Defined as Secure operating level of inertia calculated as per the Inertia Requirements and
region of Largest Shortfalls Methodology.
following Credible Risk
separation within Current values:
islanded
region Queensland 16,000 MWs
NEM inertia levels could drop by 35%. Historically, NEM 4.2 AEMO to publish a detailed frequency control workplan covering tasks and timeframes to: 2020 New
mainland inertia has never been below 68,000 MWs. By
• Revise ancillary service arrangements to ensure the required speed and volume of PFR match the size of the
2025, inertia could drop to as low as 45,000 MWs. This
LCR and FOS containment requirements for the range of expected future operating conditions
will increase the required volume and/or speed of
frequency sensitive reserve following a contingency event, • Investigate the introduction of a system inertia safety net for the mainland NEM, under system intact
and the power system will operate in configurations where conditions. This minimum level safety net should be progressively revised as operational experience is built and
the system dynamics are different to those experienced additional measures are put in place to ensure system security. Investigation should include specifying the initial
today. value and how the safety net will be maintained.
DPV behaviour, IBR behaviour, and run-back schemes • Investigate the effect of higher RoCoF on DPV, utility-scale generation, switched reserve providers, and
are making the system more complex. These emerging protection relays used in various network functions. The result of this investigation will be a recommended
issues will further exacerbate post-contingent outcomes for system RoCoF limit, or set of RoCoF limits, in addition to existing generator ride-though requirements.
credible and non-credible events. Non-credible Investigation should include assessment of the adequacy of EFCS, including UFLS, under decreasing levels of
contingencies are expected to result in higher RoCoF, the inertia.
effect of which is not yet fully understood for the NEM.
• Continue investigation into DPV penetration into UFLS load blocks.
• Apply appropriate limits to the total proportion of switched reserve. This is needed to ensure there is a
minimum amount of dynamic frequency control.
• Investigate appropriate regional contingency FCAS requirements, particularly for South Australia and
Queensland.
• Update AEMO’s existing system frequency model to be able to predict post-contingent frequency outcomes
based on generating unit dispatch. Development of this model will benefit from the capture of high-speed
generator output and network quantities on a routine or ongoing basis.
The NEM is at the international forefront of managing issues associated with low system strength, and
AEMO and local NSPs are adapting to operating in these low system strength conditions. These changes
create uncertainty about how the system could perform under certain operating scenarios.
AEMO has so far declared system strength gaps and worked with local TNSPs to address low system
strength in South Australia, Tasmania, Victoria, and Queensland. AEMO has been pioneering new
analytical techniques to simulate the complex interactions between IBR in areas with low system strength.
By 2025, this study forecasts that all NEM regions will be operating more often with a combination of low
numbers of synchronous machines and high levels of IBR online, both of which reduce available system
strength.
System strength is a complex concept, and an area of emerging understanding internationally61. Definitions
vary across jurisdictions, and continue to evolve as the international power system community’s collective
understanding of power system phenomena continues to grow.
AEMO sees system strength as the ability of the power system to maintain and control the voltage waveform
at any given location in the power system, both during steady state operation and following a disturbance.
System strength can be related to the available fault current at a specified location in the power system, with
higher fault current indicating higher system strength with greater ability to maintain the voltage waveform 62.
61
AEMO, RIS International Review, October 2019, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-
Systems/2019/AEMO-RIS-International-Review-Oct-19.pdf.
62
For more information, see AEMO, System Strength: System Strength in the NEM Explained, March 2020, at https://aemo.com.au/-/media/files/electricity/
nem/system-strength-explained.pdf?la=en.
63
At https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-Systems/2019/AEMO-RIS-International-Review-Oct-
19.pdf.
64
See https://aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/isp/2019/draft-2020-isp-appendices.pdf?la=en.
65
At https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/System-Security-Market-Frameworks-Review/2018/
System_Strength_Requirements_Methodology_PUBLISHED.pdf.
66
See https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/system-operations/system-security-market-frameworks-review.
67
See https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/congestion-information/transfer-limit-advice-system-strength.pdf?la=en.
68
2018 ISP, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Planning_and_Forecasting/ISP/2018/Integrated-System-Plan-2018_final.pdf.
69
Y Zhang, S Huang, J Schmall, J Conto, J Billo, E Rehman, “Evaluating System Strength for Large-Scale Wind Plant Integration”, PES General Meeting |
Conference & Exposition, 2014 IEEE.
70
See https://www.aemc.gov.au/rule-changes/managing-power-system-fault-levels.
71
AEMO, System Strength Impact Assessment Guidelines, at https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Security-and-
reliability/System-Strength-Impact-Assessment-Guidelines.
Note: Actual 2019 generation includes all lost energy; 2025 projections only include network congestion.
72
The first two units are scheduled to be installed by the end of 2020.
73
AEMO Direction Compensation Recovery Process, at https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-
nem/settlements-data/direction-compensation-recovery.
74
AEMO published the Draft 2020 ISP in December 2019. The Final 2020 ISP is expected to be published in mid-2020. https://aemo.com.au/en/energy-
systems/major-publications/integrated-system-plan-isp
The NEM is at the international forefront of managing issues associated with low 5.1 AEMO to pursue opportunities to improve the minimum system strength 2020 In progress
system strength; AEMO has so far declared system strength gaps and worked with framework and improve system strength coordination across the NEM, including:
local TNSPs to address shortfalls in South Australia, Tasmania, Victoria, and Queensland.
• AEMO to contribute latest findings and insights into ongoing ESB and AEMC
Localised system strength challenges are also creating increasing hurdles for generators
reviews of system strength frameworks.
seeking to connect in weaker parts of the grid.
• Following conclusion of the AEMC’s investigation into system strength
frameworks in the NEM, AEMO to assess the need for changes to the System
Strength Requirements Methodology and System Strength Impact Assessment
Guidelines.
• AEMO to progress planned actions (see Section 5.3.3) as part of the Final 2020
ISP.
This study indicates that variability and uncertainty driven by weather-dependent resources will keep
increasing to 2025. This increase is occurring on both the supply and the demand side (due to increased
utility wind and solar generation and the increased uptake of DPV).
To effectively integrate higher levels of variable renewable energy (VRE) while maintaining a secure and
reliable grid, the system needs access to adequate sources of flexibility that can respond to the constantly
varying supply-demand balance, as well as headroom to cover uncertainty.
While there is an increasing need for system flexibility under higher penetrations of VRE, there may be
less flexibility available when required in some regions of the NEM, due, for example, to synchronous
generation retirements, or displacement of online synchronous generation during high VRE periods.
These are complex new operating conditions. It is important to explore operational and market
enhancements that can help reduce uncertainty, fully utilise available system flexibility, and manage the
risks to secure supply.
AEMO’s full analysis relating to variability, uncertainty, and fleet flexibility is in Appendix C.
Historically, both demand and supply were relatively predictable. Today, as more VRE like wind and solar
generation is integrated into the grid, both supply and demand are more variable and harder to predict. This
increased variability and uncertainty changes the behaviour of the system, and operators need new controls
to keep the system operating reliably and securely.
75
A ramp is an upward or downward fluctuation in supply or demand over a defined time interval. VRE ramps refer to the net change in wind, utility solar,
and DPV. Ramps are used in this report to represent variability in the system.
76
See Appendix C for further details on the methodology used to produce the variability and uncertainty analysis.
77
Note that the largest 1% ramp across different technologies is not likely to occur simultaneously. Stacked together they represent the top 1% theoretical
ramp for a region if all VRE types had their 99th percentile ramp simultaneously.
Figure 15 NEM monthly top 1% of largest hourly ramps in VRE, actual 2015-19 and projected in 2025 under
Draft 2020 ISP Central generation build
The magnitude of hourly net demand79 ramps is projected to increase significantly out to 2025, with
variability in VRE outpacing underlying demand as the main driver of these ramps.
The net demand curves in Figure 16 highlight the increased system flexibility that will be required to respond
to both expected and unexpected changes in supply and demand.
The “duck curve” in Figure 16 has become familiar in the industry, with net demand falling in the middle of the
day and rising quickly in the evening. This figure highlights that in 2025 – compared to the experience of
2015-19 – evening ramps will be much larger than experienced historically, due to increased penetrations of
wind and solar.
78
The historical study period for this variability analysis is between January 2015 and April 2019.
79
Net demand is underlying demand net of VRE generation, that is, the demand that must be met by scheduled generation sources and not by wind or solar
(including utility solar and DPV).
Figure 16 NEM average winter net demand curves, actual 2015-19 and projected in 2025 under Draft 2020
ISP Central generation build
80
As shown in Figure 17, the 1-hour ahead forecast (yellow trace) has a similar shape to actual generation (purple trace), however it is offset (shifted to the
right) by one hour.
Figure 18 Summary of regional system flexibility to cover projected 30-minute, 1-hour, and 4-hour ramps
in 2025
Queensland
• Flexibility over shorter timeframes (30 minutes) may
be insufficient to manage variability and uncertainty
without curtailment or intervention. Additional New South Wales
system management may be required if there are
• The analysis projects New South Wales to have a
sufficient delays in activating fast start fleet in the
large reliance on local sources of flexibility
lead up to these short duration ramp events.
(particularly hydro), as modelling outcomes put New
• Behaviour of coal units at times of high VRE South Wales as a net importer of energy in 2025
penetration has the largest impact on meeting (particularly in periods of high VRE in adjoining
ramping requirements over 4 hours. regions).
• Adequate market signals are needed to encourage
South Australia local resources to provide flexibility when required.
• As synchronous generator requirements for system Additional system monitoring is also required for
strength are reduced, careful attention needs to be AEMO to assess ramping margins and operate the
paid to the way 4-hour ramps are managed following system to ensure security risks are managed.
prolonged operation without any local synchronous QLD
generation.
• Further work needs to be done to assess the factors
which influence flexibility in South Australia; for Victoria
example, interconnector constraints and headroom SA
management or new practices such as VRE pre- • Victoria is expected to have enough system flexibility
curtailment and other emerging sources of flexibility. NSW to manage projected levels of variability and
uncertainty, due to high levels of interconnection and
Tasmania local fast start capability.
Ensuring sufficient flexible system resources are available to enable increased The ESB is exploring options for explicitly valuing flexibility and incorporating this In progress
variability at times of high wind and solar penetration will become increasingly into scheduling and dispatch mechanisms. See action 2.3.
challenging. Times characterised by low interconnector headroom (spare capacity) or
‘cold’ offline plant will be particularly difficult to manage. 6.2 Improve the reliability of information provided by participants (loads, and 2020-21 In progress
scheduled and semi-scheduled generation) to support security-constrained
dispatch. The ESB is coordinating several interim measures to improve the visibility
of and confidence in resources in the NEM, to ensure security can be maintained
while new market arrangements are developedA.
This Stage 1 RIS analysis finds that, in the next five years:
• The NEM power system will continue its significant transformation to world-leading levels of
renewable generation. This will test the boundaries of system security and current operational
experience.
• If the recommended actions are taken to address the regional and NEM-wide challenges identified,
the NEM could be operated securely with up to 75% instantaneous penetration of wind and solar 81.
• If, however, the recommended actions are not taken, the identified operational limits will constrain the
maximum instantaneous penetration of wind and solar to between 50% and 60% in the NEM.
Looking beyond 2025, AEMO has not identified any insurmountable reasons why the NEM cannot
operate securely at even higher levels of wind and solar generation, especially with ongoing technological
advancement worldwide.
Given the pace and complexity of change in the NEM, the RIS highlights the need for flexible market and
regulatory frameworks that can adapt swiftly and effectively as the power system evolves.
81
In recommending actions and highlighting positive potential outcomes, AEMO does not underestimate the extent of work that will be required to
successfully adapt the NEM. This includes the ongoing need for system limits that at times constrain the output of various generation sources. This study
also identified a number of uncharted operating conditions emerging in the NEM by 2025. AEMO will continue investigation and analysis to identify and
address additional limits and barriers that emerge.
82
The zones in this figure are indicative only and have been aggregated up from regional limits (Queensland, New South Wales, South Australia, Tasmania,
and Victoria).
Note: Penetration values on this graph represent non-overlapping half-hourly wind and solar generation divided by total underlying
demand across the NEM during the same half-hours. Actual 2019 penetration includes all curtailment; 2025 projections only include
network congestion.
If recommended pre-emptive actions are taken to address the regional and NEM-wide technical
challenges identified in this study, the NEM could potentially be operated securely out to the beginning of
Zone C by 2025, with up to 75% of total generation coming from wind and solar resources at any time.
If recommended pre-emptive actions are not taken, the identified operational limits will bind. This would
constrain the output of wind and solar resources, limiting their maximum contribution at any time in the NEM
to between 50% and 60% of total generation.
Operation in Zone C, with up to as high as 100% of wind and solar generation operating securely at times, is
theoretically achievable in the future. This would, however, require more advanced methods of system
operation coupled with provision of essential system services to ensure adequate system flexibility, frequency,
and voltage management.
AEMO’s overarching objective is for the RIS to become an action plan that supports the secure transition
of the NEM power system. In recommending actions and highlighting positive potential outcomes, AEMO
does not underestimate the extent of work that will be required to successfully adapt the NEM.
Key next steps following the publication of this report include:
• An open and transparent stakeholder engagement process to discuss the findings and actions arising
from this report and priority focus areas for the future.
• Exploring the findings and insights from this work with regulatory bodies and policy-makers to help
inform ongoing reform processes.
• Incorporating relevant findings as part of the Final 2020 ISP.
• Undertaking identified actions to address limits.
• Scoping and commencing areas of further study, including but not limited to the resilience of a high
renewable future system to complex system events, and a study of the latest advancements in inverter
technology.
• Building on the Stage 1 RIS findings and subsequent stakeholder engagement, developing (by
Q2 2021) a roadmap for the secure transition to higher penetrations of wind and solar in the NEM,
including key study areas, actions, and reforms.
83
See p. 4, at https://www.aemo.com.au/-/media/Files/Electricity/NEM/Security_and_Reliability/Future-Energy-Systems/2019/AEMO-RIS-International-
Review-Oct-19.pdf.
Webinar(s) Inform stakeholders of the results and key insights. May 2020
• Recordings will be published on the RIS website.
Videoconference workshops Consult with stakeholders – open dialogue and discussion May-June
regarding matters of most interest, including but not limited 2020
• Workshops will be broken-down into discrete topics
to:
and/or industry groups to keep attendee numbers at
each workshop small enough to enable meaningful • Discussion and clarification about the methodology and
discussion and debate. results of the study.
• AEMO welcomes feedback and suggestions from • Discussion regarding the actions arising from this report
stakeholders regarding the workshop topics and and priority focus areas for the future.
structure they’d like to see.
• Exploring the relevance of findings and insights to
ongoing reform processes.
Information on the RIS, supplementary resources, and links to other related projects are available on the
AEMO website85.
For further information, feedback or suggestions on engagement activities, and lodgement of written
submissions, please contact AEMO’s Future Energy Systems team at FutureEnergy@aemo.com.au.
84
Advisory panel members are listed on pages 2 and 3.
85
At https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Security-and-reliability/Future-Energy-Systems/Renewable-Integration-Study.
AEMO has published other reports into the changing generation mix. A shortlist of relevant publications is
provided in Table 14.
Integrated System Prepared every two years to forecast a wide spectrum of interconnected 2018 ISP – July 2018
Plan (ISP) infrastructure and energy development scenarios and plans including
2020 ISP – draft
transmission, generation, gas pipelines and distributed energy resources. At
December 2019
https://www.aemo.com.au/energy-systems/major-publications/integrated-
system-plan-isp.
ISP Insights Published as required to provide a deep technical dive into select technologies NA
or projects and their potential impact on future NEM development. At
https://aemo.com.au/energy-systems/major-publications/integrated-system-
plan-isp/2020-integrated-system-plan-isp.
Electricity Statement Provides forecasts and analysis of technical and market data for the NEM for the NA
of Opportunities next 10 years. At https://aemo.com.au/energy-systems/electricity/national-
(ESOO) electricity-market-nem/nem-forecasting-and-planning/forecasting-and-
reliability/nem-electricity-statement-of-opportunities-esoo.
Energy Adequacy Quantifies the impact of potential energy constraints on expected levels of NA
Assessment unserved energy in the NEM for the next two years. At https://aemo.com.au/en/
Projection (EAAP) energy-systems/electricity/national-electricity-market-nem/nem-forecasting-
and-planning/forecasting-and-reliability/energy-adequacy-assessment-
projection-eaap.
Short term and Provides information on peak load forecasts, total available generation capacity, NA
Medium Term demand-side management capacity, any identified capacity shortfall of ancillary
Projected services, transmission outages, any security problems, fuel supply and logistics
Assessment of and any facility testing. MT PASA is published weekly for each week in the next
System Adequacy two years. ST PASA is published 2-hourly for each half hour for the next six
(ST PASA & MT PASA)
trading days. At https://aemo.com.au/en/energy-systems/electricity/national-
electricity-market-nem/data-nem/market-management-system-mms-
data/projected-assessment-of-system-adequacy-pasa.
Network Support and Assesses any requirements for NSCAS for network loading, voltage control, and NA
Control Ancillary transient and oscillatory stability ancillary services over the next five years that
Services Report are not currently being addressed by NSPs. At https://aemo.com.au/en/energy-
(NSCAS) systems/electricity/national-electricity-market-nem/system-operations/ancillary-
services/network-support-and-control-ancillary-services-procedures-and-
guidelines.
Summer Readiness Provides information on AEMO’s preparations for the forthcoming summer NA
report period, designed to minimise the risk of customer supply disruption in the NEM.
At https://aemo.com.au/energy-systems/electricity/national-electricity-market-
nem/system-operations/summer-operations-report.
All these appendices, providing detail on the analysis, limits and actions identified, are published separately
and are available at https://www.aemo.com.au/energy-systems/Major-publications/Renewable-Integration-
Study-RIS:
• Appendix A. Distributed solar PV.
• Appendix B. Frequency control.
• Appendix C. Variability and uncertainty.
GW Gigawatts
MW Megawatts
PV Photovoltaic
TAS Tasmania