Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Add Maths Sba 1

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 13

The Pipeline Problem.

Additional Mathematics SBA – Differentiation


By: Ruchi Marajh

1
Table of Contents

Content Page No.

Title 3

Purpose of Project 4

Mathematical Formulation 5

Problem Solution 7

Application of Solution 11

Conclusion 12

2
The Pipeline Problem

Determining the cheapest route to transfer oil between Venezuela and


Trinidad through pipelines.

3
Purpose of Project

To use mathematical formulae to determine which contractor should


be awarded the contract to construct an oil pipeline from the shore of
Venezuela to Trinidad. Each contractor offers different prices.

4
Mathematical Formulation

Each Contractor has a price for running the pipeline on land, R and
underwater, S.

 Contractor 1: R = $4000 per km and S = $5000 per km


 Contractor 2: R = $5000 per km and S = $13000 per km
 Contractor 3: R = $6000 per km and S = $10000 per km
 Contractor 4: R = $5000 per km and S = $5000 per km

The total cost of the project will be represented by T.

5
The following are mathematical notations that will be used:

1. Pythagoras’ Theorem: Hypotenuse² = Adjacent² + Opposite²


2. Differentiation: Stationary points
3. Algebra

 Pythagoras’ Theorem will be used to obtain an equation for CB.


 Differentiation of stationary points will be used to find an
equation for x in terms of R and S.
 The algebra will be used to derive and solve these equations once
values are used.

6
Problem Solution

Using Pythagoras’ Theorem we can say that CB² = x² + 60².

Therefore CB = √ x 2+3600

Assuming that the straight shoreline runs along the line AB and the
pipeline leaves the shore at point C, we can derive:

T = R (90 – x) + S√ x 2+3600 , with R being the formula of the pipeline


running on land and S being the pipeline running underwater. The
total sum of money will be added up by all contractors in order to
get one final price.

Differentiating T with respect to x to find an equation for x in terms of


R and S.
dT Sx
=−R+ 2
dx √ x +3600

dT
For stationary points dx =0
Sx
Therefore −R+ √ x2 +3600 = 0

Sx
R = √ x 2 +3600 (multiply by √ x 2+3600 )

R √ x 2+3600 = Sx (square both sides)

R²(x² + 3600) = S²x²


7
R²x² + 3600R² = S²x²
S²x² - R²x² = 3600R²

X²(S²- R²) = 3600R²


3600 R ²
X² = ( S ²−R ²)

x=
√ 3600 R ²
(S 2−R2 )

60 R
x = √ S ²−R ² where x is positive because it represents a distance.

Because x varies with respect to R and S we have to insert the values of


R and S mentioned in the beginning from each Contractor to determine
the cheapest Contractor for the project.

60(4000)
Contractor 1: x = √5000²−4000²

240000
x= 3000

x = 80 km

Therefore CB = √ 802 +3600

CB = √ 6400❑+3600

CB = 100 km

Therefore T = 4000(90 – 80) + 5000(100)

T = $540,000.00

8
60(5000)
Contractor 2: x = √13000²−5000²

300000
x= 12000

x = 25 km

Therefore CB = √ 252 +3600

CB = √ 625+3600

CB = 65 km

Therefore T = 5000(90 – 25) + 13000(65)

T = $1,170,000.00

60(6000)
Contractor 2: x = √10000²−6000²

360000
x= 8000

x = 45 km

Therefore CB = √ 452 +3600

CB = √ 2025+3600

CB = 75km

Therefore T = 6000(90 – 45) + 10000(75)

T = $1,020,000.00

9
60(5000)
Contractor 4: x = √5000²−5000²

300000
x= 0

x = 0 km

Therefore CB = √ 02 +3600

CB = √ 3600

CB = 60 km

Therefore T = 5000(90 – 0) + 5000(60)

T = $750,000.00

10
Discussion
After evaluating the values of x for each Contractor and obtaining the
total costs of the project for each Contractor, we can determine the
appropriate Contractor to award the contract. This is the data
calculated:

Contractor Cost Price of Project


1 $540,000.00
2 $1,170,000.00
3 $1,020,000.00
4 $750,000.00

From the data we have determined that Contractor 1 should be


awarded the contract for the project because his total cost price was
the cheapest.

11
Conclusion
The appropriate Contractor for the project was determined using
mathematical formulae.

12
Suggestions for future Analysis

Differentiation can also be used to determine the outflow rate of oil


from the pipelines, given the dimensions of the pipelines.

Integration can be used to determine the volume of the pipelines.

13

You might also like