Add Maths Sba 1
Add Maths Sba 1
Add Maths Sba 1
1
Table of Contents
Title 3
Purpose of Project 4
Mathematical Formulation 5
Problem Solution 7
Application of Solution 11
Conclusion 12
2
The Pipeline Problem
3
Purpose of Project
4
Mathematical Formulation
Each Contractor has a price for running the pipeline on land, R and
underwater, S.
5
The following are mathematical notations that will be used:
6
Problem Solution
Therefore CB = √ x 2+3600
Assuming that the straight shoreline runs along the line AB and the
pipeline leaves the shore at point C, we can derive:
dT
For stationary points dx =0
Sx
Therefore −R+ √ x2 +3600 = 0
Sx
R = √ x 2 +3600 (multiply by √ x 2+3600 )
x=
√ 3600 R ²
(S 2−R2 )
60 R
x = √ S ²−R ² where x is positive because it represents a distance.
60(4000)
Contractor 1: x = √5000²−4000²
240000
x= 3000
x = 80 km
CB = √ 6400❑+3600
CB = 100 km
T = $540,000.00
8
60(5000)
Contractor 2: x = √13000²−5000²
300000
x= 12000
x = 25 km
CB = √ 625+3600
CB = 65 km
T = $1,170,000.00
60(6000)
Contractor 2: x = √10000²−6000²
360000
x= 8000
x = 45 km
CB = √ 2025+3600
CB = 75km
T = $1,020,000.00
9
60(5000)
Contractor 4: x = √5000²−5000²
300000
x= 0
x = 0 km
Therefore CB = √ 02 +3600
CB = √ 3600
CB = 60 km
T = $750,000.00
10
Discussion
After evaluating the values of x for each Contractor and obtaining the
total costs of the project for each Contractor, we can determine the
appropriate Contractor to award the contract. This is the data
calculated:
11
Conclusion
The appropriate Contractor for the project was determined using
mathematical formulae.
12
Suggestions for future Analysis
13