Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Traffic Management Plan (Part of Construction Method Statement)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

Site 

Reference 
Client Name 

Traffic Management Plan (part of Construction Method Statement)

Houghton Main TRRC


Peel Environmental Ltd
CRM.066.006.PL.R.002.
Octavia House Schools  

Contact Details: 
Enzygo Ltd.  tel: 0114 3215151 
Samuel House  email: barry.roberts@enzygo.com 
5 Fox Valley  www: enzygo.com 
Stocksbridge 
Sheffield 
S36 2AA 

Traffic Management Plan (part of Construction Method Statement) at 
Houghton Main TRRC, Great Houghton 

Project:  Traffic Management Plan (part of Construction Method Statement) at Houghton 
Main TRRC, Great Houghton 

For:  Peel Environmental Ltd 

Status:  Final  

Date:  March 2018  

Author:  Sarah Strauther – Senior Transport Planner 

Reviewer:  Barry Roberts BSc (Hons) IEng MICE MIHT – Director of Traffic & Transportation 

Approver:  Barry Roberts BSc (Hons) IEng MICE MIHT – Director of Traffic & Transportation 

Disclaimer: 
This report has been produced by Enzygo Limited within the terms of the contract with the client and taking account of 
the resources devoted to it by agreement with the client. 
We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above. 
This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom 
this report, or any part thereof, is made known.  Any such party relies on the report at their own risk. 

Enzygo Limited Registered in England No. 6525159 
Registered Office Stag House Chipping Wotton‐Under‐Edge Gloucestershire GL12 7AD
Contents 
Contents ........................................................................................................................................ i 
1.0  Introduction ........................................................................................................................ 1 
1.1  Background ....................................................................................................................... 1 
2.0  Overview of Construction Activity ....................................................................................... 2 
2.1  General .............................................................................................................................. 2 
2.2  Site Clearance .................................................................................................................... 2 
2.3  Remediation Works .......................................................................................................... 3 
2.4  Highway Access ................................................................................................................. 3 
2.5  Preparation Works ............................................................................................................ 4 
2.5  Construction Works .......................................................................................................... 4 
2.6  Soft Landscaping ............................................................................................................... 6 
2.7  Construction Programme .................................................................................................. 6 
3.0  Specific Measures................................................................................................................ 7 
3.1  General .............................................................................................................................. 7 
3.2  Health and Safety Requirements ...................................................................................... 7 
3.3  Site Security and Fencing .................................................................................................. 8 
3.4  Site Logistics ...................................................................................................................... 9 
3.5  Traffic Management ........................................................................................................ 10 
4.0  Construction Traffic and Deliveries .................................................................................... 12 
4.1  Construction Period and Contractor Liaison ................................................................... 12 
4.2  Vehicle Types and frequencies ....................................................................................... 13 
4.3  Abnormal Loads .............................................................................................................. 13 
4.4  Heavy Goods Vehicles (HGVs) ......................................................................................... 13 
4.5  Light Goods Vehicles ....................................................................................................... 14 
4.6  Loading/Unloading and Parking ...................................................................................... 14 
4.7  Parking ............................................................................................................................ 16 
4.8  Route to and from Site .................................................................................................... 16 
5.0  Pedestrian and Vehicle Controls ........................................................................................ 18 
5.1  Pedestrian Measures ...................................................................................................... 18 
5.2  Vehicle Controls .............................................................................................................. 18 
6.0  Signage and Lighting .......................................................................................................... 19 
6.1  Signage and Lighting ....................................................................................................... 19 

SHF.1268.001.R.TR.001 i March 2016 
 

Houghton Main TRRC TMP          March 2018 

1.0 Introduction 

1.1 Background 

1.1.1 Enzygo  has  been  instructed  by  Peel  Environmental  Ltd  to  prepare  a  Construction  Method 
Statement,  that  includes  issues  that  relating  to  Traffic  Management,  to  discharge  Planning 
Condition 9 as part of the existing planning consent (2015/0137).  This Traffic Management 
Plan should be read in conjunction with the Construction Method Statement.  

1.1.2 In terms of the Traffic Management requirements that Barnsley Metropolitan Borough Council 
(BMBC)  has  requested  these  are  outlined  in  the  BMBC  document  reference 
HDC/DC/2017/1726. 

1.1.3 Following  our  discussing  with  Peel  Environmental  Ltd  and  using  Enzygo’s  experience  of 
Renewable  Energy  Park  developments  this  document  will  aim  to  address  the  above  issues 
raised by BMBC; 

1.1.4 Enzygo’s  traffic  and  transportation  team  will  introduce  similar  traffic  management 
procedures, methods of management, communication techniques and monitoring methods 
experienced on similar renewable energy sites that we have worked on; 

1.1.5 Currently  the  Principal  Contractor  is  yet  to  be  appointed  and  additional  information  and 
refinement to this plan is expected from the Contractor.  Any amendments will be provided to 
the  Local  Planning  Authority  for  approval  prior  to  commencement  of  construction  of  the 
facility. 

1.1.6 In accordance with good practice this statement is being prepared at an early stage in the site 
development to allow it to be used to influence the detailed design and construction process. 

1.1.7 This Traffic Management Plan should be read in conjunction with the Construction Method 
Statement. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 
 

Houghton Main TRRC TMP          March 2018 

2.0 Overview of Construction Activity 

2.1 General 

2.1.1 The site currently comprises overgrown derelict land with shrub bushes and rough grassland. 
Access is from Houghton Main Colliery Roundabout to the south east of the site. An access 
spur is present on Houghton Main Colliery Roundabout, which will provide future access onto 
the site for construction traffic and subsequently for future site users. 

2.1.2 Proposed development works will involve the following: 
1 Clearance of existing vegetation, including trees and bushes; 
2 Construction of internal road system 
3 Reduced level excavation to sub‐formation level; 
4 Placement of piling mat; 
5 Substructure works to the buildings and plant; 
6 Construction of site drainage and services; 
7 Construction of the structures 
8 Construction of pavement and hardstanding areas; 
9 Landscaping; 
2.1.3 The proposed development is shown on Drawing CRM.066.006.GE.D.001 a copy of which is 
included in the Drawing Section of this document.   
2.1.4 More specific information is given for the three main stages of work are outlined below: 
  
2.2 Site Clearance 
2.2.1 Prior to any site clearance works being undertaken fencing it to be erected around retained 
trees to protect them in accordance with Planning Condition 7.  The fencing will be undertaken 
in accordance with approved plans. 
2.2.2 Prior  to  commencement  of  works  a  condition  survey  of  the  highways  to  be  used  by 
construction traffic will be undertaken in Accordance with Planning Condition 10. 
2.2.3 Site clearance will involve the felling of trees, which are not to be retained and grubbing out 
of shrubs and root balls. 
2.2.4 Areas of low vegetation such as grass and scrub will be subject to a soft strip using an excavator 
or dozer. 
2.2.5 Soils containing roots will be stockpiled on site awaiting suitable disposal off site. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 
 

Houghton Main TRRC TMP          March 2018 

2.2.6 Vegetation and timber will be temporarily stored on site awaiting removal for appropriate re‐
use or disposal. 

2.2.7 No demolition of structures is proposed. 

2.3 Remediation Works 

2.3.1 Ground investigations and risk assessments have been undertaken by Enzygo Ltd (Reference 
CRM.066.005.GE.R.001.A) in accordance with the requirements of Planning Conditions. 

2.3.2 The ground investigation identified no evidence of significant contamination on the site, with 
no specific requirements for remediation. 

2.3.3 A discovery strategy is included within the Contamination Assessment Report.   If unforeseen 
contamination is encountered during construction works such as localised spillage outside the 
areas  investigated  an  Environmental  consultant  will  be  available  on  a  ‘call  out’  basis  to 
undertake an assessment of risk.  If ‘unforeseen contamination’ is encountered the discovery 
strategy will be to remove the source as it is likely to be very limited in extent and the Local 
Planning Authority advised 

2.3.4 It is proposed that should contaminated soils be encountered requiring remediation that these 
are discarded directly off site to avoid the potential risk of cross contamination.  Where this is 
not feasible soils will be stockpiled on areas of hardstanding or on suitable membrane awaiting 
disposal. 

2.3.5 It is anticipated that this operation will require the use of a single tracked excavator and road 
vehicles  for  disposal.    The  excavation  of  contaminated  soils  will  be  monitored  by  an 
environmental consultant to minimise the volume of waste generated. 

2.3.6 Should  remediation  of  unforeseen  contamination  be  required  a  validation  report  will  be 
prepared  in  accordance  appropriate  guidance  and  in  liaison  with  regulators  and  with  the 
requirements of the Planning Conditions. 

2.4 Highway Access 

2.4.1 A highway access is to be constructed on to the site from the existing spur off the Houghton 
Main Colliery Roundabout in a north westerly direction.  The civil engineering access works 
comprise  an  extension  to  the  existing  roundabout  spur  that  includes  the  provision  of  new 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 
Houghton Main TRRC TMP    March 2018 

pavement construction up to the extent of the ASOS car park access and the access to the 
west.  It also extends south to the threshold point of the compound. 

2.4.2 The access works includes additional footpath construction, on both sides, along with kerbing 
proposals, new linear drainage, an uncontrolled crossing point, new speed limit signs on the 
approach and new thermoplastic lining.  The proposed access works have been submitted to 
BMBC to address conditions 5 and 7 referenced in HDC/DC/2017/1726. 

2.5 Preparation Works 

2.5.1  The site preparation works will comprise: 

 Bulk excavation down to sub‐formation level across the site.  This will be designed and
implemented in accordance with regulatory requirements. of Planning Condition 3.

 Existing  redundant  service  runs  and  old  foundations  will  be  excavated  in  accordance
with Series 200 of the Specification for Highway Works.  Where possible underground
obstructions will be crushed and processed on site for re‐use.

 Resultant voids will be backfilled with suitable granular fill, placed and compacted in
accordance with Series 600 of the Specification for Highway Works.

 The reduced level excavation will be raised to formation level using selected granular
materials.  Where possible secondary aggregate will be used, including processed site
won arisings.  The selected granular fill will comprise a piling mat below the proposed
building footprint and within the working area.  Areas of proposed hard standing outside
of  the  working  area  will  be  made  up  using  capping  material.    This  will  then  form  a
running layer for plant and equipment.

2.5 Construction Works 

2.5.1 Sub structure works to the proposed buildings will comprise the following: 

 Piling;

 Construction of pile caps; and,

 Construction of the ground floor slabs.

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 


Houghton Main TRRC TMP    March 2018 

2.5.2 Based on the findings of the ground investigation it is proposed that piled foundations are to 
be used.  Details of the piling works will be determined by the specialist contractor. The piling 
works  will  require  the  use  of  piling  rigs  with  support  crane  and  ancillary  plant,  including 
excavators and dumpers. 

2.5.3 Piles will be advanced from the top of the piling mat to the embedment depth.  When seated, 
the soils around the piles will be excavated to allow construction of the pile caps.  The concrete 
at  the  top  of  the  pile  will  be  broken  out  to  reveal  the  reinforcement.  This  will  then  be 
connected in to the reinforcement cage of the pile cap, temporary formwork installed and the 
concrete cast. 

2.5.4 Once the piles and pile caps are in place the floor slab will be constructed. 

2.5.5 Infrastructure  comprising  surface  and  foul  water,  gas  and  electricity  will  be  installed  and 
connected to service entry points within the ground floor slab.  

2.5.6 Appropriate attenuation will be constructed to the surface water drainage system to meet the 
requirements of Conditions 3 and 12. 

2.5.7 Foul  drainage  shall  be  designed  and  constructed  in  accordance  with  the  requirements  of 
Planning Condition 12. 

2.5.8 Areas of hardstanding will be constructed up to road base, together with temporary setting of 
manholes. 

2.5.9 The structures will be erected. The buildings are to comprise steel portal frame structures, 
which will be erected using a crane.  The crane will also be used place the roof, internal floors, 
staircases, ‘stack’ and hoist equipment to height, for placement within the buildings. 

2.5.10 Cladding to the structures will also be placed using a mobile crane. 

2.5.11 Following completion of the main structures, the wearing course can then be constructed on 
areas of hardstanding. The screed (power‐floated) will then be constructed to complete the 
ground floor slabs. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 


 

Houghton Main TRRC TMP          March 2018 

2.6 Soft Landscaping 

2.6.1 Areas  of  proposed  landscaping  will  be  constructed  in  accordance  with  landscape  plan  and 
management plan required under Planning Condition 15.  

2.6.2 Landscape works will be undertaken following the main construction phases. 

2.7 Construction Programme 

2.7.1 A  Construction  Programme  will  be  prepared  by  the  Principal  Contractor,  taking  account  of 
their  method  and  schedules  of  working.      The  construction  programme  will  incorporate  a 
critical  path  which  can  accommodate  incorporated  design,  co‐ordinated  trade  contractors 
design  and  design  reviews,  procurement,  equipment/materials  orders,  deliveries  and  site 
installation period as necessary. 

2.7.2 The construction programme will be monitored, tracked and updated on a regular basis and 
any corrective action applied as necessary. 

2.7.3 The construction programme will be used to identify times and periods of works, which may 
have  adverse  impact  on  neighbours.  Typically,  this  may  include  periods  of  more  noisy 
operations, such as piling.  By identifying these periods, the impact on neighbours can be more 
easily managed. 

 
 
 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 
 

Houghton Main TRRC TMP          March 2018 

3.0 Specific Measures 
3.1 General 

3.1.1 This section provides details of the measures proposed to address the specific items. 

3.1.2 As  part  of  the  site  management  process  it  is  proposed  that  the  Principal  Contractor,  in 
conjunction with the Client, will liaise on a regular basis with ASOS and its operator Expo, and 
the local residents/businesses regarding the progress of the construction works. In particular, 
it is proposed that the Construction Programme is used to identify critical stages of the works 
which, could cause potential nuisance to neighbours.  These typically include: 

 
1 Noisy operations such as piling; 
2 Periods of increased traffic such as major deliveries; 
3 Periods  where  there  is  a  greater  risk  of  mud  on  the  roads,  as  a  result  of  earthworks 
excavation. 
4 On  the  basis  of  the  terms  agreed  in  the  sale  contracts  by  both  Peel  and  ASOS,  the 
construction of the access road will be undertake by ASOS in order to ensure there is no 
disruption to the Fulfilment Centre arising during the peak months of business (November 
to January). 
 

3.1.3 The method of stakeholder engagement is yet to be finalised, though is likely to include: letter‐
drops to neighbours and a pre‐start meeting with local stakeholders. 

3.1.4 Contact details for the Site Agent will be included on the site hoarding, should members of the 
public  need  to  raise  concerns  of  complain  over  activities  being  undertaken.    Details  of  the 
client and Resident Engineer will also be included. Any complaints received will be relayed to 
the  Local  Planning  authority,  together  with  any  investigation  undertaken  and  mitigation 
measures proposed or implemented. 

3.2 Health and Safety Requirements 

3.2.1  Prior to the commencement of the works a Designers Risk Assessment and Pre‐Tender Health 
and  Safety  Plan  will  be  prepared  outlining  the  Health  and  Safety  issues  by  the  CDM  Co‐
ordinator (CDMc). 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 
Houghton Main TRRC TMP    March 2018 

3.2.2 The  appointed  Contractor  for  the  works  will  be  required  to  provide  a  Construction  Stage 
Health and Safety Plan and comprehensive supporting Method Statement for the works. 

3.2.3 As a general measure all working areas at the site will require fencing and appropriate signs 
to prevent access by unauthorised persons during the progression of deeper excavations or 
demolition works. 

3.2.4 All personnel will be inducted prior to gaining access to the site by the Principal Contractor.  
They will be informed of the specific site rules which apply.  In addition, all site staff operating 
without supervision by the Principal Contractor and all plant operators will be required to hold 
valid and appropriate CSCS cards. 

3.2.5 All trade contractors are obliged to provide safety policies, plans and method statements and 
will be interviewed, where appropriate, prior to placement of orders, on relevant aspects of 
health and safety.   

3.2.6 A ‘tool box talk’ will be provided to the Contractors and site staff by the Principal Contractor. 

3.2.7 Banksmen and Traffic Marshalls will be used where appropriate. 

3.3 Site Security and Fencing  

3.3.1 Due  to  the  nature  of  the  construction  works  it  is  proposed  that  plywood  hoarding  will  be 
constructed around the site boundary.  This will reduce potential risks associated with material 
migrating out of the site and reduce noise impact. 

3.3.2 The  existing  site  access  off  Houghton  Main  Colliery  Roundabout  will  be  retained  for 
construction traffic. Access and egress routes are shown on Drawing CRM.066.006.GE.D.001. 

3.3.3 The site access and internal haul road system will be linked to the existing access spur. 

3.3.4 Temporary site accommodation will be constructed adjacent to the site access and will provide 
security to the site.  This will be used to prevent members of the public accessing the site and 
to check vehicles entering and leaving the site. 

3.3.5 The site hoarding will include the names and contact details of the Principal Contractor, Client 
and  Engineer.    Details  of  any  decorative  displays  will  be  provided  to  the  Local  Planning 
Authority for approval in advance. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 


Houghton Main TRRC TMP    March 2018 

3.3.6 Details  of  any  specific  health  and  safety  requirements  such  as  the  use  of  PPE  and  site 
requirements, will also be included on the hoarding. 

3.4 Site Logistics  

3.4.1 A plan showing the proposed locations of site offices and compound is presented as Drawing 
CRM.066.006.GE.D.001. The key features are discussed below: 

 Temporary  site  accommodation  will  be  provided  by  the  Principal  Contractor,
comprising:  office  accommodation,  mess  facilities  and  welfare  facilities.  The
temporary accommodation is located adjacent to the site access so that it can also be
used for security;

 Car parking for site workers and visitors will be provided adjacent to the temporary
accommodation.

 Any  vehicles  showing  substantial  amounts  of  mud  and  dirt  will  be  required  to  be
cleaned using the Jet Wash facility and road sweepers will also be employed;

 The  proposed  sequence  of  construction  discussed  in  Section  2  should  limit  the
generation of mud and dirt.

 The  Contractors  Compound  will  be  constructed  on  hardstanding  comprising  either
tarmac or granular capping.  Vehicles using the Contractors Compound will not enter
the site and will not be required to use the wheel wash.

 The adjacent highway will be regularly inspected and if mud/debris is identified then
a road sweeper will be used to remove the material.

3.4.2 Areas of proposed storage for materials are shown on Drawing CRM.066.006.GE.D.001. This 
area will be used for loading and unloading of plant and materials. Materials will be stored 
within the building ready for the finishing trades once construction of the building has been 
completed. Where possible a ‘just in time’ delivery system will be used to minimise on‐site 
storage. This will be further developed by the appointed Principal Contractor. 

3.4.3 More vulnerable materials and equipment will be stored within the Contractor’s Compound.  

3.4.4 A  single  point  of  access  and  egress  is  proposed.    There  will  be  separation  on‐site  of 
construction plant and pedestrian access from the Contractor’s Compound to the construction 
site.  

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 


 

Houghton Main TRRC TMP          March 2018 

3.4.5 A circular route is proposed, where possible, for delivery vehicles to prevent vehicle crossing 
and to ensure that the wheel wash facilities are used. These will be kept separate from the 
working  area  of  the  plant.  The  internal  traffic  route  is  shown  on  Drawing 
CRM.066.006.GE.D.001.  A  specific  plan  will  be  developed  in  accordance  with  the  proposed 
Traffic Management procedures discussed later in this document. 

3.4.6 The working areas for plant and machinery on site will vary depending on the stage of the 
construction works. Suitable phasing plans will be determined by the Principal Contractor and 
the route for delivery vehicles will be amended as necessary. 

3.5 Traffic Management 

3.5.1 The works will comply with Regulation 36 (Traffic Routes) and Regulation 27 (Vehicles) of CDM 
2007 by providing a traffic management plan which will be displayed in the site office.  The 
objectives of the plan will ensure: 

 The safe and efficient working environment for all staff, visitors and contractors when 
on site; 

 To  ensure  visiting  traffic  and  deliveries  arriving  and  leaving  site  can  operate  within 
definitive areas; 

 Abnormal loads to be pre‐booked; 

 To  ensure  that  any  contractors  on  site  can  operate  their  workforce,  plant  and 
equipment in a safe and manageable environment.   

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

10 

 
Houghton Main TRRC TMP    March 2018 

3.5.2 The  plan  will  be  developed  by  the  Principal  Contractor  and  will  detail  specific  measures, 
including those outlined in the Site Locations Section and will include: 

 Speed restrictions;

 Traffic flow directions;

 Road crossing points;

 Turning circles;

 Wheel wash facilities; Pedestrian access and egress points;

 Site offices and compounds;

 Materials storage;

 Emergency assembly points.

3.5.3 The site entrance will be clearly signed to raise driver’s awareness to the site entrance.  The 
site will have adequate signage in accordance with Chapter 8 of the Traffic Signs Manual. 

3.5.4 A speed limit of 5mph will be applied on site vehicles when operating within the works.  All 
drivers will be notified of the limit with speed signs clearly displayed. 

3.5.5 To mitigate risks associated with plant and vehicles the following will also be used: 

 Pedestrian barriers at site entrance;

 Temporary crossings to direct pedestrians across road way away from conflict areas;

 Banksmen and Traffic Marshalls;

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

11 
 

Houghton Main TRRC TMP          March 2018 

4.0 Construction Traffic and Deliveries 
4.1 Construction Period and Contractor Liaison 

4.1.1 The predicted construction period for the construction of the new Renewable Energy Park, that 
will  comprise  of  a  Timber  Resource  Recovery  Centre  (TRRC)  and  associated  infrastructure,  is 
between approximately 30  months.  However, it should be noted that this contract period may 
fluctuate as the construction work progresses on site. 

4.1.2 It  should  be  noted  that  construction  works  will  be  limited  to  the  following  hours  unless 
otherwise agreed with the Local Planning Authority; 

 07:00 hours to 19:00 hours Monday to Friday; 

 07:00 hours to 13:00 hours on Saturday; 

 No working on Sundays or Bank Holidays 

There may be exceptional circumstances where work will be necessary outside of the hours 
set out above.  Any abnormal working hour requirements outside the proposed construction 
working hours will be notified in writing to the Local Planning Authority. 

4.1.3 The main construction phases of the TRRC will include the following, although timescales are 
currently unavailable for the main construction activities.  Indicative construction durations 
have been included below and will be firmed up once the contractor has been appointed.   

4.1.4 As the temporary ASOS car park is currently in use and has been temporarily ‘stoned up’ to 
approximate  levels it has  not yet  been confirmed when the permanent car park works will 
commence.  

4.1.5 The  details  of  the  personnel  who  will  be  responsible  for  supervising,  controlling  and 
monitoring vehicle movements to and from the site will be provide once the contractor has 
been confirmed.  The contractor will nominate an individual who will operate as a site security 
who will be responsible for ensuring all drivers sign in and out once they have visited the site.  
The site security staff will work alongside the site project manager who will ensure that the 
vehicle movements are supervised with site operatives assigned specific roles. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

12 

 
 

Houghton Main TRRC TMP          March 2018 

4.2 Vehicle Types and frequencies  

4.2.1 Peel Environmental Limited’s design team has experience in the delivery of similar Renewable 
Energy schemes and therefore an appreciation of the construction Information provided by 
design team has been used to inform this section. 

4.3 Abnormal Loads 

4.3.1 During the construction process, it may be necessary for the occasional abnormal load vehicles 
to transport components to the site. In advance of any such movements, the routing, timing 
and any specific traffic management requirements for such deliveries will be agreed in advance 
with the police and local highway authority. 

4.4 Heavy Goods Vehicles (HGVs) 

4.4.1 The construction period is anticipated to take approximately two and a half years. During 
this  period  there  will  be  trips  associated  with  the  arrivals  and  departures  of  construction 
staff,  and  with  the  delivery  of  parts  and  construction  materials.  Staff  trips  will  mainly  be 
made by cars, vans or minibuses, whilst deliveries of construction materials and equipment 
will mainly be made by HGVs. 

4.4.2 The construction phase includes the preparation of the site, including the installation of any 
required internal roads, erection of fencing, construction of the building and grid connection. 

4.4.3 The  Contractor  will  seek  to  limit  traffic  flows  during  the  road  network  peak  hours  and 
consideration will be given to any need for concrete pours requiring an intensification of HGV 
movements. 

4.4.4 A  maximum  of  up  to  200  construction  workers  are  anticipated  to  be  on  site  during  key 
milestones of the construction phase over a 24 – 30 month period.  A temporary construction 
compound will be provided to accommodate storage, parking for contractors and turning 
provision for HGVs. 

4.4.5 The  location  from  which  staff  will  travel  is  not  yet  known,  however  it  is  envisaged  that  a 
number of the non‐local workforce will stay in local accommodation and be transported to 
the site by minibuses to minimise the impact on the road network. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

13 

 
 

Houghton Main TRRC TMP          March 2018 

4.4.6 The construction period will include the use of HGVs to bring equipment onto the site and 
these operations will be strictly managed to ensure that vehicle movements are controlled 
and minimised. 

4.4.7 Construction  of  the  Renewable  Energy  Centre  is  unlikely  to  require  any 
equipment/components to be delivered by abnormal load vehicles. 

4.4.8 The majority of construction traffic movements will be generated from site operatives’ cars 
and light vans. Most construction machinery will be delivered to the site during the early 
stages of the build programme and will remain on‐site for most of its duration. 

4.4.9 The  materials  required  during  the  construction  of  the  facility  will  be  transported  by 
articulated vehicles with a maximum length of 16.5 metres.   

4.4.10 Generally, the flow of construction traffic would be spread evenly over the working day, with 
occasional peaks resulting from operational requirements for materials and stock‐piling on 
site.  At the peak of construction approximately 60 vehicles are predicted. 

4.5 Light Goods Vehicles 

4.5.1 In  addition  to  the  HGV  movements  there  will  also  be  a  small  number  of  construction 
movements associated with smaller vehicles, such as the collection of skips and the transport 
of construction workers. 

4.5.2 The number of construction staff on site will vary over the construction period depending on 
the activity that is taking place. The majority of staff will travel in crew buses, which will park 
on site during the day. 

4.5.3 In addition, there are expected to be a small number of managerial cars / vans. There will be 
sufficient parking space provided during construction to accommodate these vehicles and 
the unloading of delivery vehicles. 

4.6 Loading/Unloading and Parking 

4.6.1 GSDA drawing reference 1313 PL003 Revision A, that is in the drawing appendix to this report, 
shows the route of circulatory route of the site vehicles including the unloading and loading 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

14 

 
 

Houghton Main TRRC TMP          March 2018 

points within the site.  To confirm the vehicles will enter and exit via the western spur off the 
roundabout and will load up via the 2 No. loading access points on the west facing side of the 
reception  hall.    To  exit  the  vehicles  will  drive  around  the  west,  north  and  east  side  of  the 
process building and exit via the western roundabout spur onto the main network.  This route 
has been tracked on the drawing for a 16.5m legal length articulated HGV.  The construction 
vehicles will follow a similar route, particularly as the site work progresses. 
 
4.6.2 To ensure that any unloading or loading activities do not result in HGV’s reversing into the live 
carriageway  a  suitable  designed  part  of  the  site  will  assigned  to  accommodate  vehicles 
entering, turning and exiting in a forward gear.  The site is of a sufficient size to accommodate 
such  movements  along  with  the  aid  of  banksmen  who  will  be  readily  available  under  the 
supervision of the project manager. 
 
4.6.3 Any unloading or loading times associated with construction activities and deliveries will be 
deliberately planned to avoid the staff changeover times of the shifts.  At present ASOS employ 
approximately 4,000 staff across 3 shifts and each shift employs 3 rota’s of which at any one 
time there are only 2 rota’s on shift due to rest days.  As a result the maximum number of 
people onsite are as follows and any loading, unloading or construction activities will avoid the 
changeover periods of the following shifts; 
 
 AM Shift (07:00 – 15:00 hours) 
 PM Shift (15:00 – 23:00 hours) 
 Nights (23:00 – 07:00 hours) 

4.6.4 The  routes  shown  on  drawing  1313  PL003  Revision  A  show  that  the  majority  of  the  main 
pedestrian desire lines and walking routes are internal.  Any external walking routes, including 
the internal parking areas, are clearly separate from the HGV routes to avoid and potential 
vehicle/pedestrian conflict. 

4.6.5 To ensure delivery vehicles do not queue back onto the live carriageway, via the roundabout 
spur,  a  sufficient  length  of  internal  road  alongside  the  western  site  boundary  has  been 
designated  for  queuing  vehicles.    The  weighbridge  has  been  positioned  at  least  4  No. 
articulated vehicle lengths into the site (approximately 65 metres) that provides a sufficient 
internal queuing length and avoids vehicles queuing into the roundabout. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

15 

 
 

Houghton Main TRRC TMP          March 2018 

4.6.6 In terms of the construction vehicles they will follow a similar on site route to the operational 
traffic and as the construction activity ramps up the building lines and areas of ‘stoned up’ 
internal roads along with signage and banksmen will assist the drivers. 

4.7 Parking 

4.7.1 A parking area for construction vehicles will be signposted and clearly identifiable once the 
construction vehicles have entered the site.  The area that is designated as staff parking (see 
extract  below)  seems  to  be  a  practical  place  for  construction  vehicles  to  park  up  that  will 
encroach too much on the construction activity.  This area is large enough to accommodate a 
number  of  large  HGV’s  and  providing  they  are  parked  in  an  organised  manner,  via  the 
contractors banksmen. 

4.7.2 Internal parking arrangement will also be arranged with the contactor to ensure the staff also 
have a safe parking area that is segregated from the construction parking and vehicular routes.  
Although this area has yet to be confirmed there is a number of areas within the site that can 
accommodate the parking. 

4.8 Route to and from Site 

4.8.1 Although the route that the construction vehicles will take to the site has yet to be confirmed 
we have used our local knowledge of the area and the freight journey planner to predict what 
routes  the  HGV’s  and  abnormal  route  vehicles  will  take  to  reach  the  site.    To  avoid  any 
congested routes and potential torturous routes the HGV’s and abnormal loads will seek to 
avoid these area during the AM and PM peak periods. 

4.8.2 The diagram below shows how the vehicles are predicted to reach the site from the north and 
south.  The A1(M) is the main route that can be used for HGV’s and abnormal vehicles and the 
A635 Barnsley Road can then be used to access the site.  This involves passing through villages 
including Marr, Hickleton and along Goldthorpe bypass, although the roads in general are of a 
good vertical and horizontal alignment and suitable for HGV’s.  Any abnormal vehicles using 
this route should also be able to pass safely although it is still recommended that they inform 
the  local  police  authority  and  highway  authority.    There  are  a  number  of  laybys  that  are 
between the A1(M) and the site should the vehicles experience any difficulties, although this 
is unlikely.   

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

16 

 
 

Houghton Main TRRC TMP          March 2018 

Houghton Main TRRC Site 

 
[www.freightjourneyplanner.co.uk] 
4.8.3 The above route is considered to the safest for HGV’s and abnormal sized vehicles to reach 
the site.  

4.8.4 The above route plan, including a list of directions, will be issued to all contractors prior to 
any site activity commencing.  The site staff will have been briefed on the highway issues 
associated with the site and will be suitably trained to ensure that the vehicles are able to 
access and egress from the site in a safe manner. 

4.8.5 In terms of the internal haul road system and the predicted route that the vehicles will take 
this is shown in the extract in section 3.6 above.  Although the route may be subject to slight 
deviation the main buildings do dictate the route to an extent. 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

17 

 
 

Houghton Main TRRC TMP          March 2018 

5.0 Pedestrian and Vehicle Controls 
5.1 Pedestrian Measures 

5.1.1 The following measures will be put in place in order to protect pedestrians from construction 
vehicles; 
 The  provision  of  suitable  pedestrian  safety  barriers  along  with  clear  signage  and 
lighting to direct pedestrians away from the site activity; 

 Banksmen  who  will  be  positioned  at  the  site  entrance/exit  at  all  times  to  direct 
pedestrians away from the site and ensure safer entry for construction vehicles; 

 Temporary  footpaths  will  be  formed  and  signed  at  the  site  entrance  to  deter 
pedestrians  from  entering  the  site  or  encroaching  on  areas  that  are  subject  to 
construction activity; 

 The site will have tight security with CCTV camera’s, site security guards and suitable 
fencing to prevent pedestrians from entering the site that will ensure they are do not 
conflict with any vehicles. 

5.1.2  The above measures will protect pedestrians during times of deliveries and ensure that any 
potential risk of any conflict is minimised. 

5.2 Vehicle Controls 

5.2.1 To ensure that the deliveries are carried out in a safe manner the following controls will be 
enforced at the proposed development site; 
 The loading bay has been positioned and orientated to ensure the rear of the delivery 
vehicle opposes the main vehicle/pedestrian access; 

 Peel Environmental Ltd has a strict protocol that is followed by all delivery drivers and 
staff to ensure the risk of any conflict is minimised; 

 The  delivery  and  construction  vehicles  will  be  briefed  prior  to  arrival  at  the  site  to 
ensure they follow the correct route once they are approaching the site entrance 

 The contractor will time the deliveries and construction traffic activity during off peak 
periods to minimise any conflict with pedestrians, etc; 

 Double yellow lines and warning signs will be erected to prevent ill‐disciplined parking 
local to the site entrance; 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

18 

 
 

Houghton Main TRRC TMP          March 2018 

6.0 Signage and Lighting 

6.1 Signage and Lighting 

6.1.1 Lighting at the entrance to the TRRC and within the site will be provided to assist the delivery 
drivers  to  unload  in  a  safe  manner.    The  lighting  will  provide  clear  visibility  at  all  times, 
particularly during the dark winter periods, to ensure the vehicles can be loaded and unloaded 
in a safe manner.  
 
 
   

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

19 

 
 

Houghton Main TRRC TMP          March 2018 

APPENDIX 
 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

20 

 
NOTE

1. THIS DRAWING IS COPYRIGHT


GSDA LTD.

2. THE CONTRACTOR MUST


NOT SCALE FROM THE
DRAWING ALL DIMENSIONS
TO BE TAKEN FROM
DIMENSION STRINGS.

3. WHERE ANY DISCREPANCIES


ARE FOUND BETWEEN
DIMENSIONS THESE MUST
BE BROUGHT TO THE
ATTENTION OF THE
ARCHITECTS FOR
RESOLUTION.

4. WHERE DISCREPANCIES EXIST


BETWEEN REFERENCE OR
ASSEMBLY DRAWINGS &
DETAIL DRAWINGS, THE
LATTER TAKE PREFERENCE.

PARK SP
NORTH

RI
NG RO AD
KEY

Site boundary

Adjacent site

2.5m wide hedge/


tree line perimeter

For details of proposed


landscaping and planting
please refer to PL036-37

Fuel oil storage tank


and bund (double skin)

Standby generator Ash storage


silos

Di
smant
ledRai
l
way
Fire water tank

Fire water
pumps enclosure
a
M e
xLgl
ar
Ai
tu
ca
le
t e
dVhl
c
i 6
1
e(.m)
5 0%
13

Sub-Station
2 1
0%
ACCs 2 -2% Max Legal Articulated Vehicle (16.5m)
Condensers

Stack

Process
Building
13
Service
2
access -3%

Ctrl. Rm
Switchgear Room
First Floor

Service
Turbine Offices/ access
Workshop
ef

Reception
2
D

Hall 13

Car park

M
a
12 bays inc. 2x disabled

xL
eg
Out weighbridge

a
lA
rt
ic
ul
at
edV
0%

ehi
c
le(
Cycle shelter
Ma
xL

1
6
ega

.5
m)
lAr
ti
cul
at
ed
Ve

0%
hi
cl
e(
1
6.
5m

Manoeuvring
)

2 Loading -2%

Apron
access

06)
20
ar(
g
reC
a
2 8 0%

L
-1%
4%
Loading
Timber Resource access 13
4
Recovery Centre
A 150130 Issued for planning
9
2 -3%
HOUGHTON - 150123 Issued for planning

5 -14%
MAI
N
FOR INFORMATION
HGV access to
ea 2
r(0
06)
this elevation via 0%
0% C
a
Lg
r
COL
le(
6
1
(6
1
.5
.
m
5m
)) LI
ERY
2 no. roller shutters 8 td
e
dVe
h
V
eh
c
ic
i
e
l
a
le
t
4
M
a
Ma
xL
xL
eg
a
e
ga
A
lA
l
rt
c
r
i
tc
i
uu
a
l
GSDA
0%
0% ROUNDABOU GARRY STEWART DESIGN ASSOCIATES

T Highlands House, Office 101A, 165 The


Broadway, Wimbledon, London, SW19 1NE
In weighbridge T. 020 8544 8085

+ bypass lane 2 5
2

5 HOUGHTON MAIN REC


Access
Queuing - 2 x HGVs maintained PROJECT

Proposed Site Layout

DRAWING

1:500@A1
150130
1:1000@A3
SCALE DATE

0 50 100 150m El
ect
ri
ci
ty 1313_PL003 A GS

Gener
ati
ng
DWG. NO. REVISION CHECKED
 

You might also like