Method Statement
Method Statement
Internal Project No
1 2 3 4
Document
Issue(Revision)
Date
Amended By
H&S CHECKED BY VICTOR MUEMA (H&S
SUPERVISOR)
DETAIL OF INITIAL DRAFT
AMENDMENT
SIGNATURE
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 3 of 21
Introduction
The project will involve the Supply, installation, Commissioning & Maintenance of a solar lit
murals at CENTRAL BANK EXTELCOM BUILDING
Scope of Work / Objectives.
The proposed works include: supply, installation of mounting structures, PV panels, inverters,
batteries, cabling, and inverter room construction.
supervisor, no matter
how minor and proper
treatment to be obtained
if required.
• Task specific PPE will be
required depending on the tasks,
as detailed below.
• The site shall be kept clean and
clear of unnecessary obstruction
(housekeeping)
• First aid kit boxes will be kept
at site office and a portable one
on site
• Pedestrian segregation to be
put in place as part of the works.
Storage
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 6 of 21
1. SOLAR PANELS
Procedure and Measures to be taken during offloading process;
• The distance between storage areas and the area the materials are to be used have been
identified (as shown in the image). The distance selected is the most appropriate and
convenient.
Unloading of all the material will take place ONLY in a designated area away from
other site operations and will be supervised by the site supervisor. This area will be
barricaded and marked using visible signage.
The offloading of the modules from the truck will be done by a forklift handled by a
qualified and certified personnel.
From the temporary storage area, the modules will be moved using a forklift to the
location where the scaffolding will be erected.
Only one module will be lifted at any given time. The process is explained in detail
under panel distribution.
When picking up items with a powered industrial truck, the following must be considered:
The material being ferried must be centered on the forks as close to the mast as
possible to minimize the potential for the truck tipping or the load falling.
Avoid overloading a lift truck because it impairs control and causes tipping over,
No extra weight will be placed on the rear of a counterbalanced forklift to avoid an
overload,
Appropriate signs showing unloading operations will be in place and visible
wherever appropriate.
Before loading the interior of the truck will be inspected for the following: trash,
loose objects and obstructions, holes, or weak floors.
Items which are stacked will be fastened properly to ensure they are stable and
cannot fall.
The height and speed limits from the storage area to roof will be observed at all
times on site.
Methodology
o Route shall be kept clear and free from obstructions.
o Visual safety check will be carried out by an employee of MEGAWATT POWER
&TELECOMMUNICATION LTD.
o The banksman shall ensure that no other person (or traffic), either public or site, are
within an unsafe distance of any lifted materials in the process of being moved.
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 9 of 21
o The forks will be inserted under the pallet of the rail boxes making sure they are
maintained in balanced position.
o When moving loose load with a forklift, the load will be tied using slings before
lifting.
o Only approved lifting slings suitable for the purpose will be used in lifting. The
weight of the load to be lifted will be taken into consideration in the selection of
slings. The sling shall be inspected for any damage.
o The unloading will be started from the top. The Load will be lifted upwards in a
horizontally aligned position. Make sure that lifting straps are equally tensioned
while lifting.
o The forklift driver shall, under no circumstances, move any Load until he has
checked that it is safe to do so from his banksman.
o On an uneven route, a low speed will be maintained so that the Load or the pallet of
accessories cannot move about on the fork.
o The trained driver will under no circumstances leave the forklift unattended for any
reason whilst the load remains suspended.
o All offloaded items will be stacked in accordance with the manufacturers’ Quality
procedures; the supervisor will ensure that each stack is stable and unlikely to
collapse.
Mitigation
a. There will proper planning of the work process to minimize any incidents
and accidents.
b. There will be strict adherence to good pedestrian/vehicle segregation
measures on site
c. Workers will be sensitized to always be alert and aware of what they are
doing.
d. Drivers and forklift operators will have to have proper training and be
physically fit.
e. There will be a checklist that will be used to guide the process of lifting
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 10 of 21
SCAFFOLDING.
Before using the scaffolding, the team will be properly inducted on its safe use.
The use of safety harness on the scaffolding will be mandatory.
The harness at all times will be properly hooked onto the scaffolding frame
The harness will be inspected daily before use.
Before use, the scaffolding will be thoroughly inspected to ensure that design of all
working platforms, their supporting structures and means of protection from falling
material or objects, to be used on this project must comply with the local
Construction Health and Safety & Welfare Regulations.
All working platforms, supporting structures and edge protection shall be erected
by competent personnel who possess the adequate training, knowledge and
experience.
Before Using the Scaffolding, a handover Certificate must be issued and tagged with
“SCAFFOLDING SAFE FOR USE” Signage.
Lights, or colored tapes, shall be used to segregate the scaffold area so that other
people within the premises are protected from accidentally injuring themselves or
destroying the scaffold.
The scaffolding shall be checked every morning to ensure it has not been interfered
with.
All Scaffolding shall be left in a manner to prevent unauthorized access and use at
the end of each Day. It must also be tagged with an “NO UNAUTHORIZED
PERSONNEL BEYOND THIS POINT” at ground Level.
Ladders are to be locked away or removed from site at the end of each working day.
A mandatory perimeter, properly reinforced anti-fall Edge protection must be done
before roof access can be granted to the installing team.
All Skylights within the Work area will be covered to prevent anyone from falling
down if accidentally stepped on
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 11 of 21
Since the area is surrounded by parking lot and heavy traffic as it is in town, there
will be banks man at all times to guide the forklift and truck operator to avoid any
form of accident or traffic delays.
PV modules are made of glass, and are therefore at risk of fracture or cracking. Care
of handling shall be a priority.
Any damaged modules shall be wrapped and repackaged to avoid any further
damage and risk of injury to persons. They shall be clearly marked as damaged and
returned to the storage area. The site manager shall be notified.
The modules are pre-wired with touch-proof connectors which isolate the current
and care shall be taken not to interfere with or expose the terminals.
Any suspected faulty modules shall be set aside for return.
PANEL DISTRUBUTION.
o PV modules shall remain in their packaging until they are Distributed using a
Forklift to the ground level of the Scaffolding.
o The forklift operator shall be assisted by a banks man in moving the panels
and also diverting traffic. Traffic signage must also be used to warn truck
drivers and other machinery operators of the works taking place.
o After safe positioning of the pellet on the ground, it will be unwrapped. This
will involve cutting of the straps using a hacksaw blade. The team doing this
will have to always wear hand gloves. The team will comprise of a minimum
number of 2 technicians.
o The modules will then be removed from the pellets in a systematic manner
starting by the topmost module to the bottom module.
o Each module will strictly be carried by at least a team of two technicians.
o The modules will be manually lifted on to the roof there will 2 at least 2
technicians at every working platform of the scaffolding. The modules will be
passed successively up the scaffolding to the roof top.
V. The team shall be getting toolbox talks with emphasis awkward positions and on
how to Place items to be lifted within the “power zone” i.e., close to the body,
between the mid-thigh and mid-chest of the person doing the lifting. This is the area
where the arms and back can lift the most with the least amount of effort.
VI. PV modules weigh approximately 23kg, but have a large wind uplift area and
therefore will be handled by two people. Works must discontinue in adverse
weather conditions.
All Packaging disposal shall be done on daily basis.
The support framework and modules will need to be manually handled;
protective gloves shall be used for this.
PV MODULE INSTALLATION.
a. Mounting rails shall be fixed on the Roof as per instructions on the Drawings.
With the aid of a String and a Tape measure to make sure that the Rail is
within the Mounting Zone of the Module.
b. The Rails will be mounted on the roof by Self drilling bolts using a portable.
c. The PV modules will then be mounted on the mounting Rails using mid and
end clamps depending on the position of the panel.
d. Torque values shall properly be observed during the exercise to avoid over
or under tightening the panels.
e. Gloves are to be worn by personnel whilst installing the mounting rails to
protect against sharp edges and hot/cold surfaces and final connections to
complete works.
f. Cloves should be worn when lifting and carrying modules to protect against
sharp edges and corners.
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 13 of 21
NB
No Panels shall be left on the Roof Un-mounted. All panels/Modules on the Roof must be
mounted to avoid being blown away by wind. At the end of each day, arrangements must be
done to return all loose panels back to the Store.
d. Modified edges of the Cable trays shall be filed to protect the Cables from
sharp edges which may puncture the cables or even the gloves of the
technicians hence exposing them to injuries.
e. Cable management shall be done in a way to protect the cables from stress
(i.e. ensure they are not trapped or trodden on) during installation as well as
during storage prior to installation.
f. Cable management shall be done with UV Rated Cable ties.
g. All cable terminations must be done on Dead Circuits at both ends before
connection to the modules is made to prevent the possibility of personnel
being exposed to bare live conductors.
h. DC connectors shall be kept as dry where possible.
i. As the modules are installed, they will be cabled up in series-connected
‘strings’. As each string is connected, a string voltage and polarity check will
be carried out to ensure that all connections are sound, and findings
recorded on a DC test sheet.
j. All DC cables shall be labelled at both ends with the string number.
k. All DC cables shall be tested and logged on test sheets.
First Aid:
Notices with First Aid procedures shall be displayed at all times at the site office. The name
of the site first aider at work and the location of the accident book and first aid kit shall also
be distributed within the site induction with notices again being displayed within
prominent positions. In the event of an injury:
If someone is seriously injured, we take the following steps.
1. Protect the area from hazards.
2. Prevent further injury to the casualty.
3. Administer first aid.
4. Call an ambulance or rescue unit.
5. Have someone direct the ambulance or rescue unit to the accident scene.
These control measures will be introduced after consultation with staff on site.
Permits required to complete the works
Daily Work Permits:
• Lifting works
• Roof PV installation
• Hot works.
Risk Assessment
HAZARD Person at Risk L S R L S R
Setting up of site Passers-by, 3 3 9 - Access to site should be restricted to authorized 2 2 4
Workers, personnel. All site areas to be kept free of any
Trespassers. article likely to cause a person to slip, trip or fall.
Site access and Passers-by, 3 4 12 - All persons on site to wear high visibility vest in 2 1 2
egress Workers, addition to other PPE specified.
Trespassers.
- All plant or vehicles only to be operated by
licensed operators and under the constant
supervision by a nominated member of the team
to avoid collisions.
-Cordon off working areas with barrier tapes
Further actions
Doc No: MPTCL – SO-002
MEGAWATT POWER &
TELECOMMUNICATION CO., LTD Rev: 03 Date: 2/10/2022
METHOD STATEMENT
Page 17 of 21
Further actions.
- In the event that it is necessary to work at
height on a roof adjacent to e.g. within a 3 meter
radius of a fume stack vent this should only be
undertaken via a permit to work. In the event
that a fume stack is less than 3 meters above the
primary roof surface workers must not go onto
the roof without the permission of their manager.
Roof access Workers. 2 3 8 - Roof access hatches pose openings that must be 1 2 3
hatches protected. The simplest approach to controlling
this hazard is to simply close the hatch cover
once on the roof. However, precautions shall be
taken to ensure that the cover will not latch in a
way that prohibits exit.