AACE International AACE-PSP

Planning & Scheduling Professional (PSP) Exam


AACE International AACE-PSP Dumps Available Here
at:
https://www.certification-questions.com/aace-international-exam/aace-psp-dumps.html

Enrolling now you will get access to 120 questions in a unique set of
AACE-PSP dumps

Question 1
Which of the following project planning situations is the most frequent contributor to cost
overruns?

Options:

A. lack of detailed planning for operational start-up

B. Insufficient planning for change management

C. Inappropriate definition of work breakdown structure

D. Inadequate definition of scope at the estimate (budget) stage

Answer: D

Question 2
Project delays are best analyzed

Options:

A. After either the contractor or the owner acknowledges ^responsibility for the delay.

B. Contemporaneously with the delay.

C. By an expert after the project is finished when complete records are available and the impact is

known.

D. Late in the project.

Answer: C

https://www.certification-questions.com
AACE International AACE-PSP

Question 3
If a cost estimate assumes that 240 hours will be expended on a given activity, and the
projected crew size expected to perform that activity is 5 personnel working and 8-hour workday,
what is the calculated duration for the activity?

Options:

A. 8 days

B. 6 days

C. 4 days

D. 5 days

Answer: B

Question 4
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a
single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the
minimum number of tower cranes that should be used for the above described column pours?

Options:

https://www.certification-questions.com
AACE International AACE-PSP

A. 2 cranes

B. 1 crane

C. 4 cranes

D. 3 cranes

Answer: A

Question 5
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish
date for Activity 2002?

https://www.certification-questions.com
AACE International AACE-PSP

https://www.certification-questions.com
AACE International AACE-PSP

Options:

A. 09-28-01.

B. 09-08-01.

C. 09-15-01.

D. 09-18-01.

Answer: B

Question 6
Midway through the project you received an executed change order for this project, adding
thirty-three days to the contract for weather delays. In its simplest form, how would your next
project update display the changed condition?

https://www.certification-questions.com
AACE International AACE-PSP

https://www.certification-questions.com
AACE International AACE-PSP

Options:

A. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000,
and

tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000,
and

tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000,
and

tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Answer: C

Question 7
Determine the driving activity for Activity 10001.

https://www.certification-questions.com
AACE International AACE-PSP

https://www.certification-questions.com
AACE International AACE-PSP

Options:

A. Activity 11001.

B. Activity 10002.

C. Activity 9005.

D. There is no driving activity for Activity 10001 in the backward pass.

Answer: B

Question 8
If Activity E's duration changes to 4 months, what is the overall duration of the project.

https://www.certification-questions.com
AACE International AACE-PSP

Options:

A. 19 months.

B. 20 months.

C. 22 months.

D. 21 months.

Answer: B

Question 9
Determine the correct formula and date for the late start for the Activity 11001:

https://www.certification-questions.com
AACE International AACE-PSP

https://www.certification-questions.com
AACE International AACE-PSP

https://www.certification-questions.com
AACE International AACE-PSP

Options:

A. LF.1001 + DUR.10001 -> 01-14-04.

B. LF.11001 - Dur.11001 -> 01-16-04.

C. LF.11001 - 27 days + 1 day -> 01-14- 04.

D. LF.10001 + 1 day -> 01-16-04.

Answer: D

Question 10
What method would be the best way to determine the most likely as-built critical path of a
project that is underway, and the schedule of which has been partially progressed?

Options:

A. Use the progressed portion of the critical path of all the updates previous to the current update.

B. Use the progressed portion of the critical path of the baseline schedule.

C. Interview the project personnel for their perceptions and opinions because the schedule is
usually

inadequate.

D. Use the forward-looking critical path of the most current updates.

Answer: D

Would you like to see more? Don't miss our AACE-PSP